Академический Документы
Профессиональный Документы
Культура Документы
SL.No
1 2 3 4
100MVA, 220/110/11kV Power Transformers 20MVA, 110/33kV Power Transformer 10MVA, 110/33kV Power Transformer Current transformer
Rating
Numbers
2 1 1 36 48 12 33 6 6 3 3 7 16 5 11 34 75 11 6 15 5
Potential transformer
7 8
5. Check earth connection for proper contact 4. 11 kV Switchgears 1. Clean the breakers, panels and bus bars thoroughly, clean insulators with CTC or Petrol 2. Check II values of the bus bars and individuals, breakers between phases and earth 3. Check operation of breakers on local remote through relay and corresponding annunciation 4. Check and lubricate operating mechanism wherever necessary 5. Tighten the terminal connection of all auxiliary circuit and wiring 6. Check all earth connections between the panel and electrodes for tightness and check the contact resistance of earth connection. 7. Replace oil in MOCBs as recommended by supplier, check oil condition in BOCBs and replace if necessary 8. Check contact travel, contact erosion in MOCBs and BOCBs 9. Check 11 kV CTs and PTs connections 5. Isolator 1. Check jump connection and replace PG clamps, if necessary 2. Check the alignment of isolator 3. Cleaning and applying petroleum jelly to contacts 6. GOS-HR fuses Station yard Earthing 1. Check clean and grease the GOS and check contacts for erosion, clean insulator 2. Check operation for proper closing of the insulator 3. Check the fuses and renew the same wherever HR fuses are provided 4. Check the earth resistance of earthing mat and all individual earthing if any, the resistance should be within the prescribed limit, otherwise action should be taken to Bering the same to within limit immediately as it is very important aspect for the safety of the equipment in any station.
TABLE.2: Maintenance Schedule for Oil-Filled Power Transformers
Review equipment ratings Preventive maintenance
IV.MAINTENANCE SCHEDULE Maintenance schedule is categorized into daily, weekly, monthly, quarterly and yearly maintenance schedules. Maintenance for 1. Power transformer (100 MVA, 20MVA, 10MVA) 1. Check and re-condition of silica jelly. 2. Check the working cooling fans, pumps 3. Release gas from BH relay 4. Clean the bushing, radiator, body etc., 5. Check earthing connection 6. Check jump connections 7. Check OLTC motor drive and control panel i) Lubricate bearing and cleaning ii) Check the gear box oil level iii) Check operation of limit switch, sequence switch with transformer in off conditions iv) Check gasket joints for oil leakage 2. HT Circuit breakers 1. Clean the porcelains 2. Check the connections for loose contact 3. Check tripping through relays 4. Check the wiring for loose contact 5. IR valves, oil level for MOCB;s 6. Vermin Proofing of control box 7. Check annunciation scheme 8. Lubricate moving/link mechanisms wherever recommended by manufacturer 9. Replacement of Oil (in case of MOCB;s) 3. HT: CTs, PTs & Lightning arresters. 1. Clean the porcelain and metal body 2. Check connection both primary and secondary for tightness 3. Check oil level 4. Take IR values
Maintenance or Test
Transformer physical inspection Bushings visual inspection Bushings - check oil level Bushings cleaning Transformer and bushings Doble test Transformer and bushings infrared scan Insulating oil - DGA, physical, and chemical tests Leakage reactance, Turns Ratio tests, SFRA test Cooling fans inspect and test Oil pumps and motors - inspect and test Heat exchangers inspect Conservator and bladder - inspect
5 years As Per manufacturers recommendations Annually Quarterly and 3-5 years Weekly 3-5 years 3-5 years (6 months to 1 year for suspect bushings) Annually Annually after first year of operation If problems are indicated by other tests Annually Annually Annually 3-5 years
Recommended Interval
3 Top oil and winding thermometers Oil level indicator operation Pressure relief device Sudden pressure relay Buchholz relay Inspect foundation, rails, trucks Annually inspect and infrared scan 3-5 years calibrate 3-5 years Annually inspect and perform function test 3-5 years check oil leaks Annually inspect and perform function test 3-5 years test per manufacturers recommendations Annually inspect and perform function test 3-5 years
Maintenance or Test
Review equipment rating Visual inspection with binoculars Clean insulator and check connections Doble test (power frequency dielectric loss, direct current [DC] insulation resistance, power factor) Replace all silicon carbide arresters with metal oxide varistor type Infrared scan
5 years Quarterly to semiannually 3-6 years Ambient dependent 3-6 years Ambient dependent As soon as possible Annually
Recommended Interval
Maintenance or Test
Record gas pressure and temperature, compare with tolerances Record operations counter Visual inspection Check foundation, grounds, paint Check external screws, bolts, electrical terminals tight Contact resistance test, power factor insulation test, motion analyzer, trip test, moisture test on gas Verify operation and calibration of temperature and pressure switches and gauges Check lube points, heater operation, tightness of terminals, linkages screws, bolts; latch, linkage, operating mechanism adjustments Overhaul breaker with new seals, contacts, nozzles Overhaul disconnect, grounding, and breaking switches Gas cart maintenance
Recommended Interval
instruction
Monthly Monthly, annually,5 years 5 years Annually 5 years, if manufacturer 5 years 5 years required by
Maintenance or Test
Recommended Interval
Maintenance or Test
Review equipment ratings External visual inspection, Check and tighten connections, Check and clean enclosures Hipot (to ground and between phases) or Doble Infrared scan, while loaded if possible
5 years Annually
Recommended Interval
10 to 15 years or 4,000 to 10,000 operations (more frequent if high current operation) 15 years or 5,000 to 10,000 operations Per manufacturers manuals instruction
TABLE.8: Maintenance Schedule of Batteries Maintenance or Test Visual inspection Battery float voltage Cell float voltage Specific gravity Temperature Connection resistance Capacity testing Safety equipment inspection Battery monitoring system Recommended Interval Monthly Shift (charger meter)Monthly overall battery voltage with digital meter compare with charger meter Monthly, pilot cells with digital meter Quarterly, all cells Monthly, pilot cells Quarterly, 10 percent (%) of cells Annually, all cells Monthly (pilot cell) ,Quarterly (10% of all cells) Annually, all connections 5 years, annually if capacity less than 90% Monthly, test all wash devices and inspect all safety equipment According to manufacturers recommendations
TABLE.4: Maintenance Schedule for Relays and Protection Circuits Maintenance or Test
Fault/load study and recalculate settings Electro-mechanical relays Calibration and functional testing Solid-state relays Calibration and functional testing Microprocessor relays calibration and functional testing Protection circuit functional test, including lockout relays Check red light lit for lockout relay and circuit breaker coil continuity Lockout relays Cleaning and lubrication 5 years
Recommended Interval
Upon commissioning and every 2 years Upon commissioning 1 year after commissioning and every 3 years Upon commissioning 1 year after commissioning and every 8-10 years Immediately upon installation and/or upon any changes in wiring and every 3-6 years Daily 5Years
TABLE.9: Maintenance Schedule Battery Chargers Maintenance or Test Preventive maintenance Recommended Interval Dependent on charger type manufacturers recommendations and
4 TABLE 10: MW/h load on incoming, outgoing lines, 100MVA Power transformer and Allotted by ALDC. On 4th July 2011
Hour
8 9 10 11 12 13 14 15 16 17 18 19 20
132 142 150 126 130 142 162 140 144 152 134 118 116
TABLE. 11: peak and min load on 100MVA 220/110 kV power transformer
1/7/11 2/7/11 3/7/11 4/7/11 5/7/11 6/7/11 7/7/11 8/7/11 9/7/11 10/7/11 11/7/11 12/7/11 13/7/11 14/7/11 15/7/11
Peak load in MW
86 96 80 72 60 62 54 50 52 60 78 88 66 58 60
Minimum load in MW
62 54 46 44 38 36 36 32 30 38 44 42 34 26 26 Fig.2: MW load on 220 kV outgoing line V/s time in hours
K V Max
110KV Mi n Max
11KV Min
1/7/11 2/7/11 3/7/11 4/7/11 5/7/11 6/7/11 7/7/11 8/7/11 9/7/11 10/7/11 11/7/11 12/7/11 13/7/11 14/7/11 15/7/11
215 220 219 220 220 220 220 220 220 218 220 215 220 224 220
198 190 202 205 208 210 200 205 200 198 190 190 190 208 198
114 112 113 112 114 115 114 115 114 112 115 113 114 115 115
100 100 104 105 106 108 108 104 101 100 99 100 102 108 100
11.4 11.5 11.5 11.5 11.6 11.6 11.6 11.8 11.6 11.4 11.6 11.5 11.6 12 11.5
10.8 10.8 10.9 10.8 10.8 10.9 10.9 10.5 10.6 10.8 10.8 10.6 10.7 10.8 10.8
V. CONCLUSION Planned maintenance schedule keeps the substation equipment in proper working condition to provide maximum reliability, flexibility in operation, continuity of service with reduce down time and reduce the cost of operation and maintenance. Planned maintenance schedule which includes daily, weekly, monthly, half yearly, yearly checks based on the manufacturers recommendation which increases working time as well as life of the equipment. Establishing the substation near to the load centers minimize the transmission and distribution losses and it possible to supply quality power to consumer with competitive prices. The good design of a substation should provide a high level of service continuity, provision for further expansion, flexibility of operation and low initial and ultimate costs. VI. REFERENCES [1] FIST volume 4-1B revised November 2005. [2] KPTCL training institute, Study material on training programme on maintenance. [3] KPTCL annual report 2010. [4] S. Rao, Text bookTesting commissioning operation & maintenance of electrical equipments [5] Website: www.kptcl.com. [6] Website: www.kpcl.com. VII. BIOGRAPHY
Chavan P.L: was born in Bagalkot, Karnataka state,India,on July 13,1985.He received B.E. degree in Electrical and Electronics engineering from visheshwaraya technological university, Belgaum, in 2009.worked as a faculty in SRVR polytechnic Guledagudd. He is presently persuing master degree in power and energy systems, in Basaveshwar Engineering College, Bagalkot, Karnataka, India. Proff. G. Suchitra: was born in Bagalkot, Karnataka,India on 10 may,1960.She obtained B.E. Electrical degree from Karnataka university dharwad. M.Tech from Bangalore University in 1990 and persuing Ph.d in Basaveshwar Engineering College, Bagalkot. Presently working as faculty in department of Electrical and Electronics at Basaveshwar Engineering college, Bagalkot, Karnataka,India. Dr. Suresh. H. Jangamshetti: (S'88, M'90, SM'97) was born in Bijapur, Karnataka, India on May 28, 1963. He obtained his B.E (Electrical) degree from Karnataka University Dharwad in 1985 and M.Tech. (Power Systems) & Ph.D (Wind Energy Systems) from IIT Kharagpur in 1989 & 2000 respectively. His areas of interest include Wind-Solar Energy Systems, Energy Conservation, Computer Applications to Power System and FACTS He won the "Outstanding IEEE Student Branch Counsellor" award for the year 1996(R10) and 2010 (IEEE Bangalore Section) at Basaveshwar Engineering College, Bagalkot, Karnataka, India. He was Fulbright-Nehru Visiting Lecture Fellow at Michigan Technological University, Houghton MI USA during Fall 2011. He is working as Professor in the department of E&E at Basaveshwar Engineering College, Bagalkot.