Вы находитесь на странице: 1из 3

MUHAMMAD ZAHIN BIN BASRI AD090269 CHAPTER 2 QUESTION NO 8 8.

The cost to relocate 3 different machines to several locations is shown in Table 7. Using assignment technique, calculate the optimum relocation cost. (20 marks) Table 7 : Relocation Cost To New Locations Location A $800 $500 $500 Location B $1,100 $1,600 $1,000 Location C $1,200 $1,300 $2,300 Location D $1,000 $800 $1,500

Machine X Machine Y Machine Z

a) To balance the problem, we add a dummy row (machine) with zero location cost to each location.

Location Machine Machine X Machine Y Machine Z Dummy

Location A $800 $500 $500 0

Location B $1,100 $1,600 $1,000 0

Location C $1,200 $1,300 $2,300 0

Location D $1,000 $800 $1,500 0

b) Subtract smallest number in each row and cover zeroes (column subtraction will give the same numbers and there fore is not necessary)

Location Machine Machine X Machine Y Machine X Dummy

Location A 0 0 0 0

Location B 300 1,000 500 0

Location C 400 800 1,800 0

Location D 200 300 1,000 0

c) Subtract smallest uncovered number (200), add it to each square where two lines intersect, and cover all zeroes.

Location Machine Machine X Machine Y Machine Z Dummy

Location A 0 0 0 200

Location B 100 900 300 0

Location C 200 600 1,600 0

Location D 0 100 800 0

d) Subtract smallest uncovered number (100), add it to each squares where two lines intersect, and cover all zeroes.

Location Machine Machine X Machine Y Machine Z Dummy

Location A 0 0 0 300

Location B 0 800 200 0

Location C 100 500 1,500 0

Location D 0 100 800 100

e) Subtract smallest uncovered number (100), add it to each squares where two lines intersect, and cover all zeroes.

Location Machine Machine X Machine Y Machine Z Dummy

Location A 100 0 0 400

Location B 0 700 100 0

Location C 100 400 1,400 0

Location D 0 0 700 100

f) Since it takes four lines to cover all zeroes, and optimal assignment can be made at zero squares. We assign

(1) Dummy (no one) to Location C (2) Machine X to Location B (3) Machine Y to Location D (4) Machine Z to Location A

Cost = $0 + $500 + $800 + $1,100 = $2,400

Вам также может понравиться