Learning Program (CLP) Brain Storming Topic Serial No -1 Dear All, The below is a brain storming issue to power plant engineers. Pls look into the below problem being faced in a CPP. You are requested to explore the causes and the repercussions of this problem. A 27 MW CPP, and we are having a Variable Pressure Deaerator with maximum pressure of 5.8 Kg/Sq.cm and temp of 160 Deg.C. Whenever, there is a load throw of 6-7 MW (from 27 to 21 MW), the feed pump discharge pressure reduces and thereby the pumping is not taking place.