Академический Документы
Профессиональный Документы
Культура Документы
ABSTRACT
Electricity is a widely used entity by each human being though it is divided by
different types of consumers. It is used by each and every consumer daily like
a breath. Without electricity our life will be in dark. To provide electricity up to
our doors each & every component of a power system is working very efficiently
& continuously. If there is malfunctioning at any stage of operation of a power
system component, our switchgear is always ready to repair it again & present that
component for our service. Load dispatch center is a coordinating agency for
state electricity boards for ensuring a mechanism for safe and secure grid
operation. Load dispatch center is an important links between generation and
transmission, which co-ordinates the power requirements of consumers
of electricity. Load Dispatch center which is the nerve of our power system is
used to perform various functions. This paper explains the details of LDC, its
functions, its importance in a power system & its future scenario as it is a very
important factor of a power system. Terms and Keyword used:
1. INTRODUCTION
Power sector is reforming day by day to give us the uninterrupted & continuous
supply up to our homes. No. of new equipments are coming forth for fulfilling the above
purpose along with the simulation studies like load flow, economic load dispatch, control
units, tariff measurements etc.Power sector is a key infrastructure sector & is the
backbone of Indian economy. Installed power generation capacity in India has grown to
87 times since independence.Until 1980s Indian power sector was in growth phase
with many achievements to its credit. But by late 1980s almost all SEBs (state electricity
board) started showing signs of financial technical & governance failure. But after the
mergence of private companies SEBs were restructured with financial support like IPPs
(independent power producers).Before knowing about Load dispatch center it is
important to know about what is about electricity and how the electricity is
related with countries economy.Today electricity plays a key role in a society. In house,
offices, factories or farms electricity powers so many gadgets. It is the most
versatile form of commercial energy & it has been a key input to economic growth in turn
improving quality of life. It can be economically transported over long distances & easily
converted to heal, light, or shaft power. It does work for us, cannot be seen, heard, smelt
but still it is always with us without polluting the atmosphere.
The Indian Power System was demarcated in early sixties in five regions for
the purpose of planning, development and operation with a view to optimally utilize
the unevenly Distributed power resource in the country, as well as to achieve
economy, reliability and Security of supply. Five Regional Electricity Boards, viz.,
Northern, Southern, Eastern, Western and North-Eastern were constituted to ensure
integrated operation of regional grids formed with progressive interconnection of
contiguous state power systems. Five Regional Load Dispatch Centers were also set up to
coordinate the operations of the Regional girds in real time. The regional grids were
strengthened with the establishment of large thermal, hydro and nuclear stations in
the Central Sector in which the states of the concerned region have shares. Central
Sector transmission system was constructed for Evacuation of power from these central
projects to the beneficiary states. The contiguous Regions have also been
interconnected through AC and HVDC back-to-back systems with the ultimate objective
of achieving a National Grid. Eastern & Northern-Eastern Regions operate in synchronous
mode while other regions operate independently and exchange power asynchronously
through HVDC back to back systems or through AC lines in radial mode.
Power system
Network of generating stations, substations, and power lines is called as power system
It spans a large area. It has a 5 major blocks which are efficient in transforming power to
End user.
Electrical power production is the very important part of the complete electrical power
system. Once it is produced it must be distributed to location where it will be used.
Controlling of power is done by using no. of devices and equipments. To convert it to
different forms particular types of loads are used and the last block is for
measurement of energy without which control & conversion is difficult. Power system may
be a huge or a small network.eg. a small generating station operating on a waterfall
at the edge of village with power lines running to village square from where they
branch off to village homes a small power system or a system like Niagara falls. The whole
power system also uses different devices for different functions like data loggers,
data acquisition devices, SCADA, security monitoring systems etc. monitoring of power
quality is another issue which decides the thing that whether the provided power is of
harmonic free or not.
Loads which are creating harmonics are many so the harmonic mitigation is of utmost
importance. Hence quality monitoring is essential. For this purpose many computer
based measurement & automation products aid scientists and engineers in research,
design, valid production testing and field monitoring of industrial power sectors. Other
things like data transmission logging, acquisition, receiving, and economic load Dispatch,
load forecasting and load allocation is also important for power system.
NECESSITY/OBJECTIVES:
To Provide Secure operation and Control of the Power System in the
country leading to GRID DISCIPLINE.
To provide
consumers.
Both State and Central Govt. responsible for development & management of
this sector
State Electricity Boards (SEBs)/STU responsible for development of intrastate transmission system
POWERGRID the Central Transmission Utility for development of interstate & inter-regional system
Power distribution responsibility is with State Govt. and Private owned
utilities
3 levels for Grid management system namely State, Regional & National
1,300MW
1,35,000MW
16th EPS*
750
Peak Demand
155,000
195,000
71,000
8.2%
13%
Transmission Network:
Synchronous Grid interconnecting four(4) regions of 90 GW capacity
geographically spread over 2.6 million sq. kms.
South(SR) is asynchronously connected
MW Capacity
NER-ER
1,850
ER-NR
2,500
ER-SR
1,200
ER-WR
1,650
SR-WR
1,200
WR-NR
900
2,000
To ensure the integrated operation of the power system in the Northern Region.
Monitoring of system parameters and system security.
Daily scheduling and operational planning.
Facilitating bilateral and inter-regional exchanges of power.
Analysis of tripping/disturbances and facilitating immediate remedial measures.
System studies, planning and contingency analysis.
Augmentation of telemetry, computing and communication facilities.
Computation of energy despatch and drawal values using SEMs.
Load generation balance and quality of supply
Maintenance scheduling of generating units and transmission lines
Economic load dispatch
Grid discipline
Load forecasting or demand estimation
System security and islanding facility
Black start preparedness
Energy distribution and load pattern study
Communication and SCADA management
Event analysis and preventive measures
Coordination with neighbor grids
Public relations and consumer interaction
Both Fixed and Variable charge was payable as per energy drawal
Inadequacies:
Non-utilization of Utilities Surplus Power
No incentive for Maximization of own/ IPP/captive generation
within a State as the cost of power paid is based on pooled rate of
ISGS stations.
No effective commercial mechanism for pricing deviations from
schedule.
Dumping of surplus power at High Freq
Forced Backing down/ Reserve Shut down
Deemed generation for backing down
Non-utilization of embedded IPP/Licensee surplus Power.
Administrative problems and no commercial arrangements for
utilization of this power. Any surplus remains unutilized.
Non-utilization of Pumped Storage Scheme
No commercial mechanism to draw cheap off peak power for
pumping. Bhira PSS/Kadamkadai is not being utilized in the
pumping mode.
Inability to Despatch Generation according to Grid requirement.
Generation of Licensees cannot be despatched as per Grid
requirements due to commercial problems.
Curtailment of Bilateral Transactions due to Grid Indiscipline.
Overdrawing State(s) deliberately increase drawls and cause
frequency to dip below 48.5 Hz so that inter-regional transactions
are terminated.
Absence of Merit Order Operation
As payments are based on drawls and not on shares/schedules,
fixed cost are not perceived as sunk costs.
Inherent Disadvantage:
No incentives for generators /utilities to respond to dispatch orders for
issues like frequency control
No Incentive for helping the grid
No disincentive for hurting the grid
No signal to generators to match availability with system needs
Did not promote Grid Discipline
No signal for trading of power.
Ultimate Effect:
Grid Indiscipline Low Frequency during peak
High Frequency during off peak
Control Instructions
Subjective decisions
Not based on overall economy
Perpetual Operational & Commercial Dispute amongst Utilities/Central
Generators
Poor Supply quality to consumers/industries
Damage to equipments
Shifting of Industries/Investments
pool-Option
C
Increase in Trading Opportunities & Harnessing of Captive
Generation
ABT (self controlled mechanism)
A. Capacity charges
Proportionate to entitlements (not actual
drawals)
Full recovery at target availability (not PLF)
Incentives linked to Availability (80%) and PLF
(77%)
Incentives half of per KWh fixed charges at target
availability / capped at 21 p/u.
B. Energy charges
Payable for schedules (not as per actual drawals)
C. Unscheduled Interchange
Payable for deviations from schedules
Linked to average frequency for 15 minute time
block (graph enclosed)
0.0
@ 8 paisa / .02 Hz
@ 18 paisa / .02 Hz
Below 49.02 Hz
1000
UI RATE Vs FREQUENCY
12.00
10.00
Rupees
8.00
6.00
4.00
2.00
0.00
49.00 49.16 49.32 49.48 49.64 49.80 49.96 50.12 50.28 50.44
Frequency
The term Availability Tariff, particularly in the Indian context, stands for a
rational tariff structure for power supply from generating stations, on a
contracted basis.
The Indian version of Availability Tariff comprises of three components: (a)
capacity charge, towards reimbursement of the fixed cost of the plant, linked to
the plant's declared capacity to supply MWs, (b) energy charge, to reimburse
the fuel cost for scheduled generation, and (c) a payment for deviations from
schedule, at a rate dependent on system conditions. The last component would
be negative (indicating a payment by the generator for the deviation) in case
the power plant is delivering less power than scheduled.
OPEN ACCESS
Availability Tariff is primarily meant for long-term supply from generating
stations on a contractual basis and is not directly applicable for transactions
under open access and wheeling provisions in the Electricity Act,
2003. However, its third component (UI) has a great relevance. Open access
and wheeling generally involve two parties, one supplying a certain quantum
of power to the other through the regional / State grid. Any such
transaction involves a number of parties, and disputes could arise in
scheduling, energy accounting and commercial settlement, unless an
appropriate framework is in place.
Capacity
Market
Ancillary
Market
PX 2008
Open
Access 2004
ABT 2002-03
IEGCFeb.2000
DEFINITIONS:
Section 2(47) of Electricity Act 2003
Open Access means the non-discriminatory provision for the use of transmission lines or
distribution system or associated facilities with such lines or system by any licensee, or
consumer, or a person engaged in generation in accordance with the regulations specified
by the Appropriate Commission
Bilateral transaction means a transaction for exchange of energy (MWh)
between a specified buyer and a specified seller, directly or through a trading
licensee or discovered at power exchange through anonymous bidding, from a
specified point of injection to a specified point of drawl for a fixed or varying
quantum of power (MW) for any time period during a month.
Short-term open access means open access for a period up to one (1) month at
one time.
RLDC will check if connectivity with CTU/ ISTS or STU system (as the case may be) is
established, necessary metering, protection, communication are in place, transfer
capability upto the CTU network for power flow of the quantum of injection/drawl
applied for is available on the date of application and whether the applicant has
undertaken to abide by the Central Electricity Authority (Technical Standards for
Connectivity to the Grid) Regulations, 2007.
Application to be submitted to::
Application Contents
SUBMISSION OF APPLICATION:
SLDC concurrance
RLDC concurrance
ADVANCE SCHEDULING:
Separate Application
Last date for submission ( -10 / -5 / 0 days prior to end of current month MO
for transaction in M1, M2, M3)
Congestion Information to Applicant next day 12:00 Hrs (Day 2)-FormatIV(Congestion information-Advance scheduling)
e-Bidding Procedure:
period of congestion
Bid Price
In addition to Open Access Transmission charges
- Multiples of Rs. 10/ MWh . ( Min. Rs. 10/MWh)
FIRST-COME-FIRST-SERVED BASIS:
Scope
Applications received within 3 days prior to the day of Scheduling and up to 15:00
Hrs. of the day immediately preceding the day of scheduling shall be treated as
same priority
SCHEDULING OF
CONTINGENCY:
BILATERAL
TRANSACTION
IN
To be considered after 1500 hrs of the day immediately preceding the day of
scheduling
REVISON OF SCHEDULE:
Accepted schedule for Day-Ahead & Contingency transaction shall not be revised or
cancelled.
Example:
Applicant has been scheduled for 10 days from 21st day of a month to
30th day of a month for 100 MW on round the clock basis (i.e. for 2400
MWh per day). If this Applicant, on or before 18th day of that month,
submits request for revision of schedule to 50MW on round the clock
basis (i.e.1200 MWh per day), the revised schedule will get implemented
from the beginning of the transactions (i.e. 21st day of the month). The
Applicant shall pay the Transmission Charges for 2400 MWh per day for
the period from 21st to22nd day of the month. Whereas for the period
from 23rd day to 30th day of the month, Transmission Charges shall be
payable for 1200MWh per day.
However, if the Applicant requests for such revision on 20th day of the month,
his request will be implemented from 23rd day of the month. He shall pay
Transmission charges for 2400 MWh per day for 2 days i.e. from 23rd to 24th
day of the month and for the remaining period he shall pay the Transmission
Charges based on 1200MWh per day.
Simple interest at the rate of 0.04 % for each day of default from the Due
Date of Payment
GENERAL CONDITIONS:
Entities which are making Application for the first time must submit the OneTime information as per enclosed format (FORMAT-VIII: Registration Form) to
the concerned nodal RLDC.
Any amendment/modification
fresh Application
summarily rejected
The Applicant shall abide by the provisions of The Electricity Act, 2003, Indian
Electricity Grid Code and CERC Regulations, as amended from time to time
Role of SLDC:
1) As per the Electricity Act, 2003, the State Load Dispatch Centre (SLDC) shall be the apex
body to ensure integrated operation of the power system in a State.
2) SLDC shall exercise supervision and control over the intra-State transmission system.
3)SLDC will be responsible for carrying out real time operations for grid control and
dispatch of electricity within the State through secure and economic operation of the State
grid in accordance with the Grid Standards and the State Grid Code.
4) The SLDC shall comply with the directions of the RLDC.SLDC shall keep accounts of the
quantity of electricity transmitted through the State grid.
for
6.FUTURE SCENARIO
GW
800
700
600
500
400
300
200
100
0
778
575
107135
220
158
306
226
425
323
592
437
Pead Demand
Installed Capacity
NR
FATEHPUR
GORAKHPUR
AURAIYA
KANKROLI
RAPP
BALIA
MUZAFFARPUR
AGRA
PATNA
KOTA
MALANPUR
ZERDA
NAGDA
GWALIOR
UJJAIN
SAHU
PURI
500
MW
VINDHYACHAL
KORBA
WR POOLING
SIPAT
RAIPUR
WR
CHANDRAPUR
KOLHAPUR
PONDA
1000
MW
1000
MW
BIRPARA
SILIGURI
BARH
B'SHARIFF
NABI NAGAR
GAYA
MALDA
SASARAM
ER
DEHRI
BUDHIPADAR
RANCHI
ROURKELA
TALCHER
BALIMELA
1000
MW
GAZUWAKA
NARENDRAU.SILERU
BELGAUM
NAGJHARI
SR
Time Line
NER
SALAKATI
BONGAIGAON
The main things are make load dispatch center operations more complex than earlier
years are changes in system network, growth in consumer population, mix of fuel used etc.
also problems related to security , integration of various grids, forces the load dispatcher to
attain new dimensions. Load dispatch center has to handle and face no. of problems
regarding the electricity changes. In earlier days the methods used to communicate
oral instruction and manual intervention were somewhat unreliable in critical
situations.And this thing make necessary to adopt the new methods and
1)techniques like automatic control on generating units as well as important load centers.
This is for effective and timely control to avoid the major occurances of black out.This
aspect will also require the foolproof arrangement of reliable interlocks and back up
protection to ensure safe grid working.
2)Also the transmission switchyard will be properly equipped and no interference of
local staff except the experts.
3)Control actions taken by load dispatcher can not be bypassed.
4)The remote control of generation should be done through the governor controls to
improve generation. In recent years it is done by the automatic governor control.
Economic dispatch
Adaptive islanding
Self-healing
Establishment of Power Exchange
7.CONCLUSION:
Day by day the technology is changing , new trends are emerging which are definitely
beneficial for utility side, power players and consumers too. In early days communication
was done by the telephones only. All the changes, information transfer, fault data,
generation and demand side requirement and all other data transfer depends upon the
means which were not adequate but somehow it was very difficult to keep the records
of all the above said things second to second as in many cases some information may
gets lost.
Hence a new technique named SCADA originates which helping the power sector a lot
by taking the form of load dispatch center. A real-time expert system now dergoing
considerable fault case for restoration guidance. The progress so far indicates a hopeful
future for a quick and accurate fault restoration support system. The system will
continue to be thoroughly tested in the field until it can be introduced into practical
service.
Also
automation
in communication process gives quick information and
response and all this happens at Load dispatch center.Hence this presentation conclude
that Load dispatch center is a very important and most useful factor of a power sector
in all sense.
CONTENT
S.NO
1
2
3
4
5
6
7
8
9 (i)
(ii)
10
11
12
13
14
TOPIC
ABSTRACT
INTRODUCTION
EFFECT OF ECONOMY ON POWER SECTOR
POWER SYSTEM AND ITS FUNCTIONS
LOAD DISPATCH CENTER
NORTHERN REGIONAL LOAD DESPATCH CENTER
Significance of Unscheduled Interchange
Availability Based Tariff
OPEN ACCESS
Short-Term Open Access in Inter-State
Transmission
(Bilateral Transaction)
ROLE Of SLDC
USE OF SCADA IN LOAD DESPATCH CENTER
FUTURE SCENARIO
Grid Management outlook
CONCLUSION