Вы находитесь на странице: 1из 17

TRASLADO DEL TRANSFORMADOR DE RESERVA 30/30/5/25 MVA, 138/60/22.9/10 KV DE LA S.E. JULIACA A LA S.E.

QUENCORO

GERENCIA DE OPERACIN DEL SISTEMA - REP DEPARTAMENTO DE ANLISIS OPERATIVO

Lima, Octubre de 2009

PROYECTO TRASLADO DEL TRANSFORNMADOR DE

DE S.E. JULIACA A S.E. QUENCORO

NDICE

1. 2. 4. 5. 6. 7. 8. 9.

ANTECEDENTES ..................................................................................................3 OBJETIVO ..............................................................................................................3 INFORMACIN ESTADSTICA DE LA DEMANDA ...........................................4 PROYECCIN DE LA DEMANDA .......................................................................8 ALTERNATIVA SOLUCIN ................................................................................11 ESQUEMA DE PROTECCIONES ......................................................................12 CARACTERSTICAS DEL TRANSFORMADOR T58-1621 ............................13 TENSIN DE OPERACIN EN LAS BARRAS DE 10.5kV DE LA SUBESTACIN QUENCORO ............................................................................14

10. SIMULACIONES DE FLUJO DE CARGA .........................................................15 11. CONCLUSIONES ................................................................................................16

ANEXOS: Anexo 1: Cronograma del proyecto Anexo 2: Presupuesto del Proyecto Anexo 3: Simulaciones de Flujo de Carga

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

1.

ANTECEDENTES
En la subestacin Quencoro opera un transformador de 132/34,5/10,5 kV, 10/3/7 MVA y desde aqu se suministra parte de la energa que requiere la ciudad de Cusco. En esta subestacin las demandas, en sus diferentes niveles de tensin, se han incrementado significativamente en los ltimos aos, debido al crecimiento actual de la economa del pas y del turismo. En septiembre de 2008 hubo una redistribucin de carga en la subestacin de Dolorespata por parte de Electro Sur Este, con lo cual disminuy la sobrecarga del transformador. En septiembre de 2008, REP mediante su estudio Plan de expansin del sistema de transmisin de REP 2008-2016, entre otros proyectos, recomend la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV para que opere conectado en paralelo con el transformador actual (T47-131), con la finalidad de atender la demanda y el crecimiento futuro de las cargas atendidas desde la subestacin Quencoro. La ampliacin de la capacidad de transformacin de esta subestacin forma parte del proyecto de Ampliacin 5 que se encuentra en la etapa de anteproyecto.

2.

OBJETIVO
Estudiar una alternativa de solucin provisional para poder atender la demanda y el crecimiento futuro de las cargas atendidas desde la subestacin Quencoro, en el muy corto plazo, mientras se implemente la solucin definitiva que consiste en la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV conectado en paralelo con el transformador actual (T47-131).

3.

DESCRIPCIN DE LA SUBESTACIN
La subestacin Quencoro ubicada en la ciudad del Cusco es una instalacin conformada por un transformador de 10 MVA. Este transformador de 3 devanados, se encuentran operando con regulacin automtica bajo carga en el lado primario. Las caractersticas tcnicas de este transformador se detallan a continuacin: Cuadro N 1: Caractersticas Tcnicas de los Trafos de la SE Quencoro
Tensin Nominal ( kV) Potencia Nominal (MVA) Primario Secundario Terciario Primario Secundario Terciario Tipo Primario Secundario Terciario 132 34.5 10.5 10 3 7 BCA 8x1.25 0 0 YNyn0d11
Pg. 3

Regulacin (%) Grupo de Conexin


Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Esta subestacin se encuentra conectada al SEIN en el nivel de 138 kV, con tres lneas de transmisin: L.T. Quencoro Tintaya. L.T. Quencoro Dolorespata. L.T. Quencoro Machupicchu La carga de esta subestacin se encuentran en el nivel de 34.5kV (carga rural de Urcos) y la ciudad de Cuzco se encuentra atendida desde el devanado de 10 kV, que es el devanado que presenta sobrecarga. Se puede indicar que la carga de 10 kV de Quencoro no se podra atender desde el transformador ubicado en Dolorespata, debido a que ya est sobrecargado. En el rea se encuentra el transformador de SEDA Cuzco cuya carga corresponde al Plan Maestro Agua Potable y que hasta agosto 2009 ha estado atendindose desde el T47-131, sobrecargando a este transformador. Grfico N 1: Diagrama Unifilar SE Quencoro

4.

INFORMACIN ESTADSTICA DE LA DEMANDA


La subestacin Quencoro est conformado por un transformador, tal como se describi anteriormente y la subestacin atiende cargas conectadas en las barras de 34.5 y 10 kV. A continuacin se muestra el cuadro resumen de la demanda histrica de la subestacin, para el periodo 2004 2008, por devanado.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 4

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Tabla1.

Registro de contadores de energa de los devanados del transformador en MVA


REGISTRO DE CONTADORES EN DEVANADO 132 kV (MVA) Pot Nominal 2004 2005 2006 2007 2008 Ene 10 7.26 7.44 8.25 9.27 10.60 Feb 10 7.09 7.36 8.47 10.11 10.55 Mar 10 8.17 7.66 8.64 8.40 9.95 Abr 10 8.58 7.81 8.83 8.50 10.33 May 10 9.11 8.07 8.65 8.60 10.25 Jun 10 7.32 7.94 8.69 10.07 10.35 Jul 10 7.76 8.26 9.11 10.26 10.69 Ago 10 7.53 8.18 9.03 10.79 10.42 Sep 10 7.55 8.47 10.39 10.91 10.86 Oct 10 7.44 8.40 9.38 10.91 9.32 Nov 10 7.39 8.32 9.71 10.88 9.69 Dic 10 7.92 8.62 10.17 10.86 9.67 Mxima 9.11 8.62 10.39 10.91 10.86 MES REGISTRO DE CONTADORES EN DEVANADO 34.5 kV (MVA) Pot Nominal 2004 2005 2006 2007 2008 Ene 3 1.34 1.35 1.61 2.29 2.29 Feb 3 1.35 1.45 1.64 2.41 2.82 Mar 3 1.43 1.51 1.63 2.49 2.17 Abr 3 1.44 1.57 1.74 2.58 2.19 May 3 1.48 1.60 1.92 2.60 2.16 Jun 3 1.41 1.60 2.02 2.72 2.24 Jul 3 1.51 1.62 2.11 2.59 2.29 Ago 3 1.50 1.64 2.72 2.62 2.05 Sep 3 1.45 1.65 2.34 2.71 2.57 Oct 3 1.49 1.65 2.34 2.69 2.54 Nov 3 1.45 1.58 2.35 2.59 2.92 Dic 3 1.41 1.62 2.48 2.66 2.46 Mxima 1.51 1.65 2.72 2.72 2.92 REGISTRO DE CONTADORES EN DEVANADO 10.5 kV (MVA) Pot Nominal 2004 2005 2006 2007 2008 Ene 7 5.63 5.84 6.37 6.56 7.76 Feb 7 5.45 5.75 6.53 7.18 7.99 Mar 7 6.36 5.89 6.64 5.57 7.40 Abr 7 6.80 5.97 6.71 5.67 7.75 May 7 7.34 6.18 6.56 5.66 7.66 Jun 7 5.64 6.06 6.41 6.91 7.65 Jul 7 5.89 6.29 6.53 7.22 7.98 Ago 7 5.83 6.31 6.55 7.73 7.69 Sep 7 5.83 6.50 7.48 7.73 8.00 Oct 7 5.90 6.40 6.55 7.90 6.85 Nov 7 5.74 6.40 7.02 7.95 6.74 Dic 7 6.19 6.62 7.76 7.84 7.03 Mxima 7.34 6.62 7.76 7.95 8.00 2009 9.21 9.28 10.49 10.27 10.01 9.96 10.08 9.67

10.49 2009 2.42 2.66 2.53 2.50 2.60 2.72 2.58 2.31

2.72 2009 6.88 6.68 7.89 7.73 7.46 7.21 7.39 7.01

7.89

De los cuadros anteriores podemos observar que en el 2009 se present una sobrecarga de 11.27% en el devanado de 10 kV y de 4.9% en el devanado de 132 kV; as mismo, que la tasa de crecimiento promedio de la mxima demanda de la subestacin en el periodo de 2004 - 2008 fue de 2.18 %.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 5

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Grfico N 2: Evolucin Histrica de la Mxima Demanda de Potencia de la Subestacin Quencoro Periodo 2003 2008
12.0 10.0 8.0 MVA 6.0 4.0 2.0 0.0 2003 2004 2005 Ao Mxima Pot Nominal 2006 2007 2008

De los cuadros anteriores, observamos que en el ao 2008, la mxima demanda del devanado de 132 kV del transformador T47-131 de la subestacin fue 10.86 MVA, que representa una sobrecarga de 8.6%. En el 2009, como se mencion se ha llegado a una carga de 10.49 MVA (4.9% de sobrecarga del devanado de 132 kV); esto a pesar que se ha redistribuido las cargas hacia Dolorespata y la puesta en servicio del transformador de SEDA Cuzco. La situacin es ms complicada en el devanado de 10.5 kV del transformador, ya que la mxima demanda en el 2008 fue 8 MVA (sobrecarga de 14.3%) y de 7.89 MVA en lo que va del 2009 (12.7% de sobrecarga, registrado el 29 de marzo a las 19:30 horas). A continuacin se muestra el Diagrama de Carga del da de mxima demanda en los devanados de 132 y 10.5 kV de Quencoro y las mximas demandas diarias medidas durante el 2009. Grfico N 3: Diagrama de Carga en 132 kV del da de Mxima Demanda 2009
12.0

10.0

8.0

MVA

6.0

4.0

2.0

0.0
12:15:00 a.m. 01:00:00 a.m. 01:45:00 a.m. 02:30:00 a.m. 03:15:00 a.m. 04:00:00 a.m. 04:45:00 a.m. 05:30:00 a.m. 06:15:00 a.m. 07:00:00 a.m. 07:45:00 a.m. 08:30:00 a.m. 09:15:00 a.m. 10:00:00 a.m. 10:45:00 a.m. 11:30:00 a.m. 12:15:00 p.m. 01:00:00 p.m. 01:45:00 p.m. 02:30:00 p.m. 03:15:00 p.m. 04:00:00 p.m. 04:45:00 p.m. 05:30:00 p.m. 06:15:00 p.m. 07:00:00 p.m. 07:45:00 p.m. 08:30:00 p.m. 09:15:00 p.m. 10:00:00 p.m. 10:45:00 p.m. 11:30:00 p.m.

Horas

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 6

Revisin : 1 Fecha: oct. 2009 Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro Pg. 7
Horas

Grfico N 4: Diagrama de mximas demandas diarias en 132 kV durante el 2009

10.0

12.0

MVA 0.0
12:15:00 a.m. 01:00:00 a.m. 01:45:00 a.m. 02:30:00 a.m. 03:15:00 a.m. 04:00:00 a.m. 04:45:00 a.m. 05:30:00 a.m. 06:15:00 a.m. 07:00:00 a.m. 07:45:00 a.m. 08:30:00 a.m. 09:15:00 a.m. 10:00:00 a.m. 10:45:00 a.m. 11:30:00 a.m. 12:15:00 p.m. 01:00:00 p.m. 01:45:00 p.m. 02:30:00 p.m. 03:15:00 p.m. 04:00:00 p.m. 04:45:00 p.m. 05:30:00 p.m. 06:15:00 p.m. 07:00:00 p.m. 07:45:00 p.m. 08:30:00 p.m. 09:15:00 p.m. 10:00:00 p.m. 10:45:00 p.m. 11:30:00 p.m.

0.0

2.0

4.0

6.0

8.0

Grfico N 5: Diagrama de Carga en 10.5 kV del da de Mxima Demanda 2009

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

01/01/2009 08/01/2009 15/01/2009 22/01/2009 29/01/2009 05/02/2009 12/02/2009 19/02/2009 26/02/2009 05/03/2009 12/03/2009 19/03/2009 26/03/2009 02/04/2009

PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

DEPARTAMENTO DE ANLISIS OPERATIVO

GERENCIA DE OPERACIN DEL SISTEMA

Mximas diarias (MVA) NOMINAL

09/04/2009 16/04/2009 23/04/2009 30/04/2009 07/05/2009 14/05/2009 21/05/2009 28/05/2009 04/06/2009 11/06/2009 18/06/2009 25/06/2009 02/07/2009 09/07/2009 16/07/2009 23/07/2009 30/07/2009 06/08/2009 13/08/2009 20/08/2009 27/08/2009

Fecha: 05.oct.09

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Grfico N 6: Diagrama de mximas demandas diarias en 10.5 kV durante el 2009


9.0

8.0

7.0

6.0

5.0

4.0

3.0

2.0

1.0

0.0 01/01/2009 08/01/2009 15/01/2009 22/01/2009 29/01/2009 05/02/2009 12/02/2009 19/02/2009 26/02/2009 05/03/2009 12/03/2009 19/03/2009 26/03/2009 02/04/2009 09/04/2009 16/04/2009 23/04/2009 30/04/2009 07/05/2009 14/05/2009 21/05/2009 28/05/2009 04/06/2009 11/06/2009 18/06/2009 25/06/2009 02/07/2009 09/07/2009 16/07/2009 23/07/2009 30/07/2009 06/08/2009 13/08/2009 20/08/2009 27/08/2009

Mximas diarias (MVA)

NOMINAL

5.

PROYECCIN DE LA DEMANDA
Con la informacin de contadores se calcula la proyeccin de la demanda total de la subestacin hasta el 2011. Tabla2. Proyecciones de demanda en MVA. Periodo 2009-2011.
PROYECCIONES DE DEMANDA (MVA) DEVANADO 132kV 2004 2005 2006 2007 2008 7.26 7.44 8.25 9.27 10.60 7.09 7.36 8.47 10.11 10.55 8.17 7.66 8.64 8.40 9.95 8.58 7.81 8.83 8.50 10.33 9.11 8.07 8.65 8.60 10.25 7.32 7.94 8.69 10.07 10.35 7.76 8.26 9.11 10.26 10.69 7.53 8.18 9.03 10.79 10.42 7.55 8.47 10.39 10.91 10.86 7.44 8.40 9.38 10.91 9.32 7.39 8.32 9.71 10.88 9.69 7.92 8.62 10.17 10.86 9.67 9.11 8.62 10.39 10.91 10.86

MES Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima

Pot Nominal 10 10 10 10 10 10 10 10 10 10 10 10

2009 10.50 10.69 10.84 10.72 10.90 10.54 10.93 10.88 11.29 10.93 10.87 11.17 11.29

2010 11.09 11.28 11.44 11.31 11.49 11.11 11.52 11.47 11.90 11.52 11.45 11.77 11.90

2011 11.67 11.87 12.04 11.90 12.09 11.69 12.11 12.06 12.50 12.10 12.03 12.36 12.50

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 8

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
PROYECCIONES DE DEMANDA (MVA) DEVANADO 34.5 kV 2004 2005 2006 2007 2008 1.34 1.35 1.61 2.29 2.29 1.35 1.45 1.64 2.41 2.82 1.43 1.51 1.63 2.49 2.17 1.44 1.57 1.74 2.58 2.19 1.48 1.60 1.92 2.60 2.16 1.41 1.60 2.02 2.72 2.24 1.51 1.62 2.11 2.59 2.29 1.50 1.64 2.72 2.62 2.05 1.45 1.65 2.34 2.71 2.57 1.49 1.65 2.34 2.69 2.54 1.45 1.58 2.35 2.59 2.92 1.41 1.62 2.48 2.66 2.46 1.51 1.65 2.72 2.72 2.92 PROYECCIONES DE DEMANDA (MVA) DEVANADO 10.5 kV 2004 2005 2006 2007 2008 5.63 5.84 6.37 6.56 7.76 5.45 5.75 6.53 7.18 7.99 6.36 5.89 6.64 5.57 7.40 6.80 5.97 6.71 5.67 7.75 7.34 6.18 6.56 5.66 7.66 5.64 6.06 6.41 6.91 7.65 5.89 6.29 6.53 7.22 7.98 5.83 6.31 6.55 7.73 7.69 5.83 6.50 7.48 7.73 8.00 5.90 6.40 6.55 7.90 6.85 5.74 6.40 7.02 7.95 6.74 6.19 6.62 7.76 7.84 7.03 7.34 6.62 7.76 7.95 8.00

Fecha: 05.oct.09

Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima

Pot Nominal 3 3 3 3 3 3 3 3 3 3 3 3

2009 2.62 2.80 2.72 2.79 2.85 2.89 2.93 3.05 3.05 3.04 3.05 2.99 3.05

2010 2.90 3.10 3.00 3.08 3.15 3.19 3.23 3.36 3.35 3.34 3.35 3.28 3.36

2011 3.18 3.40 3.29 3.37 3.44 3.49 3.53 3.66 3.66 3.64 3.65 3.57 3.66

MVA Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima

Pot Nominal 7 7 7 7 7 7 7 7 7 7 7 7

2009 7.57 7.71 7.53 7.77 7.91 7.66 7.94 7.98 8.31 7.87 7.92 8.30 8.31

2010 7.95 8.10 7.91 8.16 8.30 8.04 8.33 8.37 8.71 8.26 8.31 8.70 8.71

2011 8.33 8.49 8.28 8.55 8.69 8.42 8.73 8.76 9.12 8.64 8.69 9.10 9.12

Grfico N 7: Proyeccin de demanda devanado 138 kV (2009 2011)


Demanda - Quencoro 132kV
14

12 2003 10 2004 2005 8 2006 2007 2008 6 2009 2010 4 2011 Pot. Nom. 2

MVA
0

Ene

Feb

Mar

Abr

May

Jun

Jul

Ago

Sep

Oct

Nov

Dic

Mes

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 9

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Grfico N 8: Proyeccin de demanda devanado 34.5 kV (2009 2011)

Demanda - Quencoro 34.5kV


4.0

3.5

3.0 2.5

2004 2005 2006 2007 2008 2009 2010 2011 Pot. Nom.

MVA

2.0

1.5

1.0 0.5

0.0 Ene Feb Mar Abr May Jun Mes Jul Ago Sep Oct Nov Dic

Grfico N 9: Proyeccin de demanda devanado 34.5 kV (2009 2011)


Demanda - Quencoro 10.5kV
10 9 8 7 6
MVA 2004 2005 2006 2007 2008 2009 2010 2011 Pot. Nom.

5 4 3 2 1 0
Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic

Mes

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 10

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Se observa que durante el ao se presentaran sobrecargas mayores a las histricas por lo que si se aceptara estos niveles de sobrecarga sera riesgosa la operacin del transformador, por lo ser necesario tomar acciones para solucionar esta situacin operativa de sobrecargas.

6.

ALTERNATIVA DE SOLUCIN
Se plantea la utilizacin provisional del transformador de reserva de REP, que lo tenemos en Juliaca, para alimentar toda la carga de 10.5 kV; el T47-131 quedara alimentando la carga de la barra de 34.5 kV. El diagrama unifilar del proyecto sera el siguiente:

Grfico 10: Diagrama unifilar del proyecto

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 11

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Se ha verificado en campo que el transformador de reserva se ubicar al lado de la lnea Quencoro Tintaya (L-1005) de 138 kV, lugar donde hay espacio suficiente. En la barra de 10 kV, existen disponible 02 celdas libres, una de estas se conectara el transformador de reserva de 30 MVA. El interruptor IN-1410 operara abierto. El equipamiento necesario ser el siguiente: EQUIPAMIENTO EN 138 KV: Se implementara un (01) interruptor de 138 kV. Implementar un (01) seccionador de barras. Implementar tres (03) Pararrayos Se utilizar los transformadores de corriente incorporados en los bujes, para la proteccin diferencial y sobrecorriente del transformador.

EQUIPAMIENTO EN 10KV: Se implementar un juego de 3 pararrayos de 10 kV, y cable y terminales de 10 kV, la distancia del transformador de reserva hacia la celda de reserva de 10 kV, aproximado de 60 m. Se utilizar los transformadores de corriente incorporados en los bujes, para la proteccin diferencial y sobrecorriente del transformador.

7.

ESQUEMA DE PROTECCIONES
El sistema de proteccin del transformador de potencia est formada por: Protecciones Mecnicas. El transformador de potencia tiene las siguientes protecciones mecnicas con umbrales de alarma y disparo. Buchholz: Alarma y disparo Sobrepresin: Disparo Temperatura de aceite: Alarma y disparo Temperatura de devanado: Alarma y disparo Nivel de aceite: Alarma y disparo Flujo: Alarma y disparo Los disparos de las protecciones mecnicas hacia los interruptores sern a travs de un rel de disparo y bloqueo, el cual tendr la posibilidad de reseteo local y remoto. Las alarmas preventivas y de disparo sern implementadas en el SCADA para la supervisin remota. Protecciones Elctricas. El transformador de potencia debe ser protegida por las siguientes protecciones elctricas.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 12

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

1 rel diferencial de transformador (87T) como proteccin principal, para proteger ante fallas internas. Los disparos sern a travs del rel de disparo y bloqueo utilizado para las protecciones mecnicas. 1 rel de sobrecorriente (51) para cada lado del transformador como proteccin de respaldo a la proteccin principal y a las protecciones de los alimentadores. Los disparos sern directamente a su interruptor del lado del transformador en el que se encuentra conectado el rel. Si el rel diferencial cuenta con la funcin de sobrecorriente para cada lado del transformador no ser necesario un rel adicional como respaldo. El siguiente esquema unifilar es el resumen del sistema de proteccin del transformador de potencia.

138k V

51/51 N 87T

T58-131 138/60/22.9/10.5kV 30/30/5/25 MVA

T47-131 138/34.5/10.5kV 10/3/7 MVA

34,5k V

51/51N

10,5 KV

Grfico 11: Esquema de Protecciones

8.

CARACTERSTICAS DEL TRANSFORMADOR T58-1621


Las caractersticas tcnicas del transformador de reserva de Juliaca se muestran en el cuadro N se resalta que la tensin de nominal del cuarto devanado es es 10 9, KV.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 13

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Cuadro N 1: Datos de placa del transformador reser va de Juliaca


Datos Tcnicos Potencia Tensin Frecuencia Enfriamiento Grupo de Conexin Nmero de fases Impedancia de cortocircuito: AT/MT AT/BT AT/BT2 MT/BT2 Prdidas de Cortocircuito: AT/MT AT/BT AT/BT2 MT/BT2 Posiciones de TAP TAPS AT T1-261 30/30/5/25 MVA 138/60/22.9/10 KV 60 Hz OFAF2 YNyn0yn0d5 3 10.16% 4.16% 15.29% 5.3% 131.95 kW 12.74 kW 105.91 kW 84.71 kW -14/10 1.25%

9.

TENSIN DE OPERACIN EN LAS BARRAS DE 10.5kV DE LA SUBESTACIN QUENCORO


Grfico N 15: Perfil de tensiones de la barra de Quencoro 10.5 kV Ene-Ago 2009
14

12

10

8 kV

0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m a. a. a. a. p. p. p. p. a. p. p. p. a. a. a. a. a. a. a. a. p. p. p. p. p. p. a. a. a. p. p. p. 00 :00 :0 0 :00 :00 :0 0 :0 0 :00 :00 :0 0 :00 :00 :0 0 :00 :00 :00 :00 :00 :00 :00 :00 :0 0 :00 :00 :0 0 :00 :00 :0 0 :0 0 :00 :00 :00 0 5 5 0 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 5: 5 0 5 0 0 :1 1:0 1:4 2:3 3 :1 4:0 4:4 5:3 6:1 7:0 7:4 8:3 9:1 0:0 0:4 1 :3 2 :1 1:0 1:4 2 :3 3:1 4:0 4:4 5:3 6:1 7:0 7:4 8:3 9:1 0:0 0:4 1 :3 12 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1

Horas

La tensin operacin de la barra de 10.5 kV de Quencoro se encuentra entre 10.4 kV y 10.9 kV estas tensiones de operacin representan en el cuarto devanado del transformador de reserva una tensin de 1.04 pu y 1.09 pu
Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 14

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

10. SIMULACIONES DE FLUJO DE CARGA Avenida y Estiaje 2010


Cuadro N 2: Carga de los transformadores T47-131 y TR-Reserva en el 2010
Escenario Mxima Avenida 2010 Media Avenida 2010 Mnima Avenida 2010 Mxima Estiaje 2010 Media Estiaje 2010 Mnima Estiaje 2010 Tr-RESERVA (MVA) 8.35 7.55 7.10 8.66 8.18 7.42 % Carga RESERVA 33.4 30.2 28.4 34.6 32.7 29.6 T47-131 (MVA) 2.22 2.00 1.95 2.43 2.02 2.03 % Carga T47-131 74.0 66.6 65.0 81.0 67.3 67.6

Con la operacin del transformador reserva se podr atender la carga de la empresa de distribucin ELSE sin restriccin de suministro o traslados de carga a la subestacin Dolorespata de EGEMSA. Durante el 2010 la carga del transformador estar entre el 29.6% y 33.4% respecto de su potencia nominal de 25 MVA y el transformador T47-131 solo atender la carga de la barra de 34.5 kV, as la carga del transformador T47-131 estar entre 67.3% y 81%. Las tensiones en el devanado del 10 kV del transformador de reserva estarn entre 1.03 pu y 1.05 pu, asimismo se puede apreciar en el cuadro N 11 que la posicin de los TAP varia entre -8 y -10 teniendo holgura para regular tensin en la barra de 10.5 kV. Las simulaciones de flujo de carga se muestran en el anexo N 01. Cuadro N 3: Tensiones y posicin del TAP en el tra nsformador T1-261 en el 2010
Escenario Mxima Avenida 2010 Media Avenida 2010 Mnima Avenida 2010 Mxima Estiaje 2010 Media Estiaje 2010 Mnima Estiaje 2010 Barra 138kV 137.3 139.6 140.52 137.59 139.10 139.79 Barra 10.5KV/pu 10.36/0.99 10.30/0.99 10.51/1.00 10.51/1.00 10.46/1.00 10.44/0.99 Dev 10 kV Reserva/pu 10.36/1.04 10.30/1.03 10.51/1.05 10.51/1.05 10.46/1.05 10.44/1.04 TAP Reserva -9 -8 -8 -10 -9 -8

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 15

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Avenida 2011
En la temporada de avenida del 2010 tambin se tendr holgura para atender la carga de ELSE, se espera tener una mxima carga de 34.6% respecto de 25 MVA en el transformador T1-261, asimismo el transformador T47-131 tendr una carga mxima del 81%.
Cuadro N 4: Carga del transformador T1-261 en el 2 011
Escenario Mxima Avenida 2011 Media Avenida 2011 Mnima Avenida 2011 Tr-RESERVA (MVA) 8.66 8.50 7.32 % Carga RESERVA 34.6 34.0 29.3 T47-131 (MVA) 2.43 2.22 2.11 % Carga T47-131 81.0 74.0 70.3

Las tensiones en la barra de 10.5KV se encuentra entre 1.00 pu y 1.02 pu mientras que el devanado de 10 kV del transformador de reserva estar entre 1.05 pu y 1.06 pu, las variaciones de TAP estarn entre -7 y -9 y se tendr todava margen de reserva para regular la tensin. Las simulaciones de flujo de carga se muestran en el anexo N 01
Cuadro N 5: Tensiones y posicin del TAP en el tra nsformador T1-261 en el 2011
Escenario Mxima Avenida 2011 Media Avenida 2011 Mnima Avenida 2011 Barra 138kV 137.1 139.1 144.4 Barra 10.5KV/pu 10.51/1.00 10.46/1.00 10.66/1.02 Dev 10 kV Reserva/pu 10.51/1.05 10.46/1.05 10.66/1.06 TAP Reserva -9 -9 -7

11. CONCLUSIONES
La alternativa estudiada permite atender la demanda y su crecimiento como una solucin provisional en el corto plazo; mientras se implemente la solucin definitiva que consiste en la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV conectado en paralelo con el transformador actual (T47-131). Cabe mencionar que si bien resuelve los problemas de atencin de la demanda, esta configuracin representa una baja seguridad operativa en toda la zona sur de 138 kV, debido a que en casos falle un transformador de esta zona, la reposicin del servicio se ver afectado por no contar con el transformador de reserva de REP disponible. En este sentido, es de aplicacin el DS. 059-2009-EM del 22 de agosto de 2009 que modific el D.S. 015-2009-EM, para las subestaciones del Sur. Se logra operar y atender la carga de ELSE con el transformador de reserva; sin embargo, es necesario tener en consideracin que el grupo de conexin del transformador de reserva en el devanado de 10 kV es diferente al grupo de conexin del transformador T47-131 para el mismo nivel de tensin, por lo que ELSE no podr hacer transferencias de carga en caliente, desde la subestacin Dolorespata.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 16

GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO

Fecha: 05.oct.09

Esta configuracin provisional ser necesaria hasta que se culmine la instalacin del segundo transformador de potencia recomendado con el Plan de Expansin de REP 2008-2016 como solucin definitiva. Se recomienda implementar la alternativa estudiada que consiste en el traslado del transformador de potencia de reserva de REP de S.E. Juliaca hacia S.E. Quencoro.

Revisin : 1 Fecha: oct. 2009

Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro

Pg. 17

Вам также может понравиться