QUENCORO
NDICE
1. 2. 4. 5. 6. 7. 8. 9.
ANTECEDENTES ..................................................................................................3 OBJETIVO ..............................................................................................................3 INFORMACIN ESTADSTICA DE LA DEMANDA ...........................................4 PROYECCIN DE LA DEMANDA .......................................................................8 ALTERNATIVA SOLUCIN ................................................................................11 ESQUEMA DE PROTECCIONES ......................................................................12 CARACTERSTICAS DEL TRANSFORMADOR T58-1621 ............................13 TENSIN DE OPERACIN EN LAS BARRAS DE 10.5kV DE LA SUBESTACIN QUENCORO ............................................................................14
ANEXOS: Anexo 1: Cronograma del proyecto Anexo 2: Presupuesto del Proyecto Anexo 3: Simulaciones de Flujo de Carga
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
1.
ANTECEDENTES
En la subestacin Quencoro opera un transformador de 132/34,5/10,5 kV, 10/3/7 MVA y desde aqu se suministra parte de la energa que requiere la ciudad de Cusco. En esta subestacin las demandas, en sus diferentes niveles de tensin, se han incrementado significativamente en los ltimos aos, debido al crecimiento actual de la economa del pas y del turismo. En septiembre de 2008 hubo una redistribucin de carga en la subestacin de Dolorespata por parte de Electro Sur Este, con lo cual disminuy la sobrecarga del transformador. En septiembre de 2008, REP mediante su estudio Plan de expansin del sistema de transmisin de REP 2008-2016, entre otros proyectos, recomend la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV para que opere conectado en paralelo con el transformador actual (T47-131), con la finalidad de atender la demanda y el crecimiento futuro de las cargas atendidas desde la subestacin Quencoro. La ampliacin de la capacidad de transformacin de esta subestacin forma parte del proyecto de Ampliacin 5 que se encuentra en la etapa de anteproyecto.
2.
OBJETIVO
Estudiar una alternativa de solucin provisional para poder atender la demanda y el crecimiento futuro de las cargas atendidas desde la subestacin Quencoro, en el muy corto plazo, mientras se implemente la solucin definitiva que consiste en la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV conectado en paralelo con el transformador actual (T47-131).
3.
DESCRIPCIN DE LA SUBESTACIN
La subestacin Quencoro ubicada en la ciudad del Cusco es una instalacin conformada por un transformador de 10 MVA. Este transformador de 3 devanados, se encuentran operando con regulacin automtica bajo carga en el lado primario. Las caractersticas tcnicas de este transformador se detallan a continuacin: Cuadro N 1: Caractersticas Tcnicas de los Trafos de la SE Quencoro
Tensin Nominal ( kV) Potencia Nominal (MVA) Primario Secundario Terciario Primario Secundario Terciario Tipo Primario Secundario Terciario 132 34.5 10.5 10 3 7 BCA 8x1.25 0 0 YNyn0d11
Pg. 3
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Esta subestacin se encuentra conectada al SEIN en el nivel de 138 kV, con tres lneas de transmisin: L.T. Quencoro Tintaya. L.T. Quencoro Dolorespata. L.T. Quencoro Machupicchu La carga de esta subestacin se encuentran en el nivel de 34.5kV (carga rural de Urcos) y la ciudad de Cuzco se encuentra atendida desde el devanado de 10 kV, que es el devanado que presenta sobrecarga. Se puede indicar que la carga de 10 kV de Quencoro no se podra atender desde el transformador ubicado en Dolorespata, debido a que ya est sobrecargado. En el rea se encuentra el transformador de SEDA Cuzco cuya carga corresponde al Plan Maestro Agua Potable y que hasta agosto 2009 ha estado atendindose desde el T47-131, sobrecargando a este transformador. Grfico N 1: Diagrama Unifilar SE Quencoro
4.
Pg. 4
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Tabla1.
10.49 2009 2.42 2.66 2.53 2.50 2.60 2.72 2.58 2.31
2.72 2009 6.88 6.68 7.89 7.73 7.46 7.21 7.39 7.01
7.89
De los cuadros anteriores podemos observar que en el 2009 se present una sobrecarga de 11.27% en el devanado de 10 kV y de 4.9% en el devanado de 132 kV; as mismo, que la tasa de crecimiento promedio de la mxima demanda de la subestacin en el periodo de 2004 - 2008 fue de 2.18 %.
Pg. 5
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Grfico N 2: Evolucin Histrica de la Mxima Demanda de Potencia de la Subestacin Quencoro Periodo 2003 2008
12.0 10.0 8.0 MVA 6.0 4.0 2.0 0.0 2003 2004 2005 Ao Mxima Pot Nominal 2006 2007 2008
De los cuadros anteriores, observamos que en el ao 2008, la mxima demanda del devanado de 132 kV del transformador T47-131 de la subestacin fue 10.86 MVA, que representa una sobrecarga de 8.6%. En el 2009, como se mencion se ha llegado a una carga de 10.49 MVA (4.9% de sobrecarga del devanado de 132 kV); esto a pesar que se ha redistribuido las cargas hacia Dolorespata y la puesta en servicio del transformador de SEDA Cuzco. La situacin es ms complicada en el devanado de 10.5 kV del transformador, ya que la mxima demanda en el 2008 fue 8 MVA (sobrecarga de 14.3%) y de 7.89 MVA en lo que va del 2009 (12.7% de sobrecarga, registrado el 29 de marzo a las 19:30 horas). A continuacin se muestra el Diagrama de Carga del da de mxima demanda en los devanados de 132 y 10.5 kV de Quencoro y las mximas demandas diarias medidas durante el 2009. Grfico N 3: Diagrama de Carga en 132 kV del da de Mxima Demanda 2009
12.0
10.0
8.0
MVA
6.0
4.0
2.0
0.0
12:15:00 a.m. 01:00:00 a.m. 01:45:00 a.m. 02:30:00 a.m. 03:15:00 a.m. 04:00:00 a.m. 04:45:00 a.m. 05:30:00 a.m. 06:15:00 a.m. 07:00:00 a.m. 07:45:00 a.m. 08:30:00 a.m. 09:15:00 a.m. 10:00:00 a.m. 10:45:00 a.m. 11:30:00 a.m. 12:15:00 p.m. 01:00:00 p.m. 01:45:00 p.m. 02:30:00 p.m. 03:15:00 p.m. 04:00:00 p.m. 04:45:00 p.m. 05:30:00 p.m. 06:15:00 p.m. 07:00:00 p.m. 07:45:00 p.m. 08:30:00 p.m. 09:15:00 p.m. 10:00:00 p.m. 10:45:00 p.m. 11:30:00 p.m.
Horas
Pg. 6
Revisin : 1 Fecha: oct. 2009 Proyecto Traslado transformador de S.E Juliaca a S.E. Quencoro Pg. 7
Horas
10.0
12.0
MVA 0.0
12:15:00 a.m. 01:00:00 a.m. 01:45:00 a.m. 02:30:00 a.m. 03:15:00 a.m. 04:00:00 a.m. 04:45:00 a.m. 05:30:00 a.m. 06:15:00 a.m. 07:00:00 a.m. 07:45:00 a.m. 08:30:00 a.m. 09:15:00 a.m. 10:00:00 a.m. 10:45:00 a.m. 11:30:00 a.m. 12:15:00 p.m. 01:00:00 p.m. 01:45:00 p.m. 02:30:00 p.m. 03:15:00 p.m. 04:00:00 p.m. 04:45:00 p.m. 05:30:00 p.m. 06:15:00 p.m. 07:00:00 p.m. 07:45:00 p.m. 08:30:00 p.m. 09:15:00 p.m. 10:00:00 p.m. 10:45:00 p.m. 11:30:00 p.m.
0.0
2.0
4.0
6.0
8.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
01/01/2009 08/01/2009 15/01/2009 22/01/2009 29/01/2009 05/02/2009 12/02/2009 19/02/2009 26/02/2009 05/03/2009 12/03/2009 19/03/2009 26/03/2009 02/04/2009
09/04/2009 16/04/2009 23/04/2009 30/04/2009 07/05/2009 14/05/2009 21/05/2009 28/05/2009 04/06/2009 11/06/2009 18/06/2009 25/06/2009 02/07/2009 09/07/2009 16/07/2009 23/07/2009 30/07/2009 06/08/2009 13/08/2009 20/08/2009 27/08/2009
Fecha: 05.oct.09
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
8.0
7.0
6.0
5.0
4.0
3.0
2.0
1.0
0.0 01/01/2009 08/01/2009 15/01/2009 22/01/2009 29/01/2009 05/02/2009 12/02/2009 19/02/2009 26/02/2009 05/03/2009 12/03/2009 19/03/2009 26/03/2009 02/04/2009 09/04/2009 16/04/2009 23/04/2009 30/04/2009 07/05/2009 14/05/2009 21/05/2009 28/05/2009 04/06/2009 11/06/2009 18/06/2009 25/06/2009 02/07/2009 09/07/2009 16/07/2009 23/07/2009 30/07/2009 06/08/2009 13/08/2009 20/08/2009 27/08/2009
NOMINAL
5.
PROYECCIN DE LA DEMANDA
Con la informacin de contadores se calcula la proyeccin de la demanda total de la subestacin hasta el 2011. Tabla2. Proyecciones de demanda en MVA. Periodo 2009-2011.
PROYECCIONES DE DEMANDA (MVA) DEVANADO 132kV 2004 2005 2006 2007 2008 7.26 7.44 8.25 9.27 10.60 7.09 7.36 8.47 10.11 10.55 8.17 7.66 8.64 8.40 9.95 8.58 7.81 8.83 8.50 10.33 9.11 8.07 8.65 8.60 10.25 7.32 7.94 8.69 10.07 10.35 7.76 8.26 9.11 10.26 10.69 7.53 8.18 9.03 10.79 10.42 7.55 8.47 10.39 10.91 10.86 7.44 8.40 9.38 10.91 9.32 7.39 8.32 9.71 10.88 9.69 7.92 8.62 10.17 10.86 9.67 9.11 8.62 10.39 10.91 10.86
MES Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima
Pot Nominal 10 10 10 10 10 10 10 10 10 10 10 10
2009 10.50 10.69 10.84 10.72 10.90 10.54 10.93 10.88 11.29 10.93 10.87 11.17 11.29
2010 11.09 11.28 11.44 11.31 11.49 11.11 11.52 11.47 11.90 11.52 11.45 11.77 11.90
2011 11.67 11.87 12.04 11.90 12.09 11.69 12.11 12.06 12.50 12.10 12.03 12.36 12.50
Pg. 8
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
PROYECCIONES DE DEMANDA (MVA) DEVANADO 34.5 kV 2004 2005 2006 2007 2008 1.34 1.35 1.61 2.29 2.29 1.35 1.45 1.64 2.41 2.82 1.43 1.51 1.63 2.49 2.17 1.44 1.57 1.74 2.58 2.19 1.48 1.60 1.92 2.60 2.16 1.41 1.60 2.02 2.72 2.24 1.51 1.62 2.11 2.59 2.29 1.50 1.64 2.72 2.62 2.05 1.45 1.65 2.34 2.71 2.57 1.49 1.65 2.34 2.69 2.54 1.45 1.58 2.35 2.59 2.92 1.41 1.62 2.48 2.66 2.46 1.51 1.65 2.72 2.72 2.92 PROYECCIONES DE DEMANDA (MVA) DEVANADO 10.5 kV 2004 2005 2006 2007 2008 5.63 5.84 6.37 6.56 7.76 5.45 5.75 6.53 7.18 7.99 6.36 5.89 6.64 5.57 7.40 6.80 5.97 6.71 5.67 7.75 7.34 6.18 6.56 5.66 7.66 5.64 6.06 6.41 6.91 7.65 5.89 6.29 6.53 7.22 7.98 5.83 6.31 6.55 7.73 7.69 5.83 6.50 7.48 7.73 8.00 5.90 6.40 6.55 7.90 6.85 5.74 6.40 7.02 7.95 6.74 6.19 6.62 7.76 7.84 7.03 7.34 6.62 7.76 7.95 8.00
Fecha: 05.oct.09
Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima
Pot Nominal 3 3 3 3 3 3 3 3 3 3 3 3
2009 2.62 2.80 2.72 2.79 2.85 2.89 2.93 3.05 3.05 3.04 3.05 2.99 3.05
2010 2.90 3.10 3.00 3.08 3.15 3.19 3.23 3.36 3.35 3.34 3.35 3.28 3.36
2011 3.18 3.40 3.29 3.37 3.44 3.49 3.53 3.66 3.66 3.64 3.65 3.57 3.66
MVA Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic Mxima
Pot Nominal 7 7 7 7 7 7 7 7 7 7 7 7
2009 7.57 7.71 7.53 7.77 7.91 7.66 7.94 7.98 8.31 7.87 7.92 8.30 8.31
2010 7.95 8.10 7.91 8.16 8.30 8.04 8.33 8.37 8.71 8.26 8.31 8.70 8.71
2011 8.33 8.49 8.28 8.55 8.69 8.42 8.73 8.76 9.12 8.64 8.69 9.10 9.12
12 2003 10 2004 2005 8 2006 2007 2008 6 2009 2010 4 2011 Pot. Nom. 2
MVA
0
Ene
Feb
Mar
Abr
May
Jun
Jul
Ago
Sep
Oct
Nov
Dic
Mes
Pg. 9
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
3.5
3.0 2.5
2004 2005 2006 2007 2008 2009 2010 2011 Pot. Nom.
MVA
2.0
1.5
1.0 0.5
0.0 Ene Feb Mar Abr May Jun Mes Jul Ago Sep Oct Nov Dic
5 4 3 2 1 0
Ene Feb Mar Abr May Jun Jul Ago Sep Oct Nov Dic
Mes
Pg. 10
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Se observa que durante el ao se presentaran sobrecargas mayores a las histricas por lo que si se aceptara estos niveles de sobrecarga sera riesgosa la operacin del transformador, por lo ser necesario tomar acciones para solucionar esta situacin operativa de sobrecargas.
6.
ALTERNATIVA DE SOLUCIN
Se plantea la utilizacin provisional del transformador de reserva de REP, que lo tenemos en Juliaca, para alimentar toda la carga de 10.5 kV; el T47-131 quedara alimentando la carga de la barra de 34.5 kV. El diagrama unifilar del proyecto sera el siguiente:
Pg. 11
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Se ha verificado en campo que el transformador de reserva se ubicar al lado de la lnea Quencoro Tintaya (L-1005) de 138 kV, lugar donde hay espacio suficiente. En la barra de 10 kV, existen disponible 02 celdas libres, una de estas se conectara el transformador de reserva de 30 MVA. El interruptor IN-1410 operara abierto. El equipamiento necesario ser el siguiente: EQUIPAMIENTO EN 138 KV: Se implementara un (01) interruptor de 138 kV. Implementar un (01) seccionador de barras. Implementar tres (03) Pararrayos Se utilizar los transformadores de corriente incorporados en los bujes, para la proteccin diferencial y sobrecorriente del transformador.
EQUIPAMIENTO EN 10KV: Se implementar un juego de 3 pararrayos de 10 kV, y cable y terminales de 10 kV, la distancia del transformador de reserva hacia la celda de reserva de 10 kV, aproximado de 60 m. Se utilizar los transformadores de corriente incorporados en los bujes, para la proteccin diferencial y sobrecorriente del transformador.
7.
ESQUEMA DE PROTECCIONES
El sistema de proteccin del transformador de potencia est formada por: Protecciones Mecnicas. El transformador de potencia tiene las siguientes protecciones mecnicas con umbrales de alarma y disparo. Buchholz: Alarma y disparo Sobrepresin: Disparo Temperatura de aceite: Alarma y disparo Temperatura de devanado: Alarma y disparo Nivel de aceite: Alarma y disparo Flujo: Alarma y disparo Los disparos de las protecciones mecnicas hacia los interruptores sern a travs de un rel de disparo y bloqueo, el cual tendr la posibilidad de reseteo local y remoto. Las alarmas preventivas y de disparo sern implementadas en el SCADA para la supervisin remota. Protecciones Elctricas. El transformador de potencia debe ser protegida por las siguientes protecciones elctricas.
Pg. 12
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
1 rel diferencial de transformador (87T) como proteccin principal, para proteger ante fallas internas. Los disparos sern a travs del rel de disparo y bloqueo utilizado para las protecciones mecnicas. 1 rel de sobrecorriente (51) para cada lado del transformador como proteccin de respaldo a la proteccin principal y a las protecciones de los alimentadores. Los disparos sern directamente a su interruptor del lado del transformador en el que se encuentra conectado el rel. Si el rel diferencial cuenta con la funcin de sobrecorriente para cada lado del transformador no ser necesario un rel adicional como respaldo. El siguiente esquema unifilar es el resumen del sistema de proteccin del transformador de potencia.
138k V
51/51 N 87T
34,5k V
51/51N
10,5 KV
8.
Pg. 13
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
9.
12
10
8 kV
0
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m a. a. a. a. p. p. p. p. a. p. p. p. a. a. a. a. a. a. a. a. p. p. p. p. p. p. a. a. a. p. p. p. 00 :00 :0 0 :00 :00 :0 0 :0 0 :00 :00 :0 0 :00 :00 :0 0 :00 :00 :00 :00 :00 :00 :00 :00 :0 0 :00 :00 :0 0 :00 :00 :0 0 :0 0 :00 :00 :00 0 5 5 0 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 0 5 5: 5 0 5 0 0 :1 1:0 1:4 2:3 3 :1 4:0 4:4 5:3 6:1 7:0 7:4 8:3 9:1 0:0 0:4 1 :3 2 :1 1:0 1:4 2 :3 3:1 4:0 4:4 5:3 6:1 7:0 7:4 8:3 9:1 0:0 0:4 1 :3 12 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1
Horas
La tensin operacin de la barra de 10.5 kV de Quencoro se encuentra entre 10.4 kV y 10.9 kV estas tensiones de operacin representan en el cuarto devanado del transformador de reserva una tensin de 1.04 pu y 1.09 pu
Revisin : 1 Fecha: oct. 2009
Pg. 14
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Con la operacin del transformador reserva se podr atender la carga de la empresa de distribucin ELSE sin restriccin de suministro o traslados de carga a la subestacin Dolorespata de EGEMSA. Durante el 2010 la carga del transformador estar entre el 29.6% y 33.4% respecto de su potencia nominal de 25 MVA y el transformador T47-131 solo atender la carga de la barra de 34.5 kV, as la carga del transformador T47-131 estar entre 67.3% y 81%. Las tensiones en el devanado del 10 kV del transformador de reserva estarn entre 1.03 pu y 1.05 pu, asimismo se puede apreciar en el cuadro N 11 que la posicin de los TAP varia entre -8 y -10 teniendo holgura para regular tensin en la barra de 10.5 kV. Las simulaciones de flujo de carga se muestran en el anexo N 01. Cuadro N 3: Tensiones y posicin del TAP en el tra nsformador T1-261 en el 2010
Escenario Mxima Avenida 2010 Media Avenida 2010 Mnima Avenida 2010 Mxima Estiaje 2010 Media Estiaje 2010 Mnima Estiaje 2010 Barra 138kV 137.3 139.6 140.52 137.59 139.10 139.79 Barra 10.5KV/pu 10.36/0.99 10.30/0.99 10.51/1.00 10.51/1.00 10.46/1.00 10.44/0.99 Dev 10 kV Reserva/pu 10.36/1.04 10.30/1.03 10.51/1.05 10.51/1.05 10.46/1.05 10.44/1.04 TAP Reserva -9 -8 -8 -10 -9 -8
Pg. 15
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Avenida 2011
En la temporada de avenida del 2010 tambin se tendr holgura para atender la carga de ELSE, se espera tener una mxima carga de 34.6% respecto de 25 MVA en el transformador T1-261, asimismo el transformador T47-131 tendr una carga mxima del 81%.
Cuadro N 4: Carga del transformador T1-261 en el 2 011
Escenario Mxima Avenida 2011 Media Avenida 2011 Mnima Avenida 2011 Tr-RESERVA (MVA) 8.66 8.50 7.32 % Carga RESERVA 34.6 34.0 29.3 T47-131 (MVA) 2.43 2.22 2.11 % Carga T47-131 81.0 74.0 70.3
Las tensiones en la barra de 10.5KV se encuentra entre 1.00 pu y 1.02 pu mientras que el devanado de 10 kV del transformador de reserva estar entre 1.05 pu y 1.06 pu, las variaciones de TAP estarn entre -7 y -9 y se tendr todava margen de reserva para regular la tensin. Las simulaciones de flujo de carga se muestran en el anexo N 01
Cuadro N 5: Tensiones y posicin del TAP en el tra nsformador T1-261 en el 2011
Escenario Mxima Avenida 2011 Media Avenida 2011 Mnima Avenida 2011 Barra 138kV 137.1 139.1 144.4 Barra 10.5KV/pu 10.51/1.00 10.46/1.00 10.66/1.02 Dev 10 kV Reserva/pu 10.51/1.05 10.46/1.05 10.66/1.06 TAP Reserva -9 -9 -7
11. CONCLUSIONES
La alternativa estudiada permite atender la demanda y su crecimiento como una solucin provisional en el corto plazo; mientras se implemente la solucin definitiva que consiste en la instalacin de un segundo transformador de 25/7.5/17.5 MVA, 132/34.5/10.5 kV conectado en paralelo con el transformador actual (T47-131). Cabe mencionar que si bien resuelve los problemas de atencin de la demanda, esta configuracin representa una baja seguridad operativa en toda la zona sur de 138 kV, debido a que en casos falle un transformador de esta zona, la reposicin del servicio se ver afectado por no contar con el transformador de reserva de REP disponible. En este sentido, es de aplicacin el DS. 059-2009-EM del 22 de agosto de 2009 que modific el D.S. 015-2009-EM, para las subestaciones del Sur. Se logra operar y atender la carga de ELSE con el transformador de reserva; sin embargo, es necesario tener en consideracin que el grupo de conexin del transformador de reserva en el devanado de 10 kV es diferente al grupo de conexin del transformador T47-131 para el mismo nivel de tensin, por lo que ELSE no podr hacer transferencias de carga en caliente, desde la subestacin Dolorespata.
Pg. 16
GERENCIA DE OPERACIN DEL SISTEMA DEPARTAMENTO DE ANLISIS OPERATIVO PROYECTO TRASLADO DEL TRANSFORNMADOR DE S.E. JULIACA A S.E. QUENCORO
Fecha: 05.oct.09
Esta configuracin provisional ser necesaria hasta que se culmine la instalacin del segundo transformador de potencia recomendado con el Plan de Expansin de REP 2008-2016 como solucin definitiva. Se recomienda implementar la alternativa estudiada que consiste en el traslado del transformador de potencia de reserva de REP de S.E. Juliaca hacia S.E. Quencoro.
Pg. 17