SIX SIGMA BLACK BELT PROJECT REPORT

MANAGING & ENHANCING QUALITY OF IT OPERATIONS BY REDUCING THE UNPLANNED DOWNTIME

HAKEEMURREHMAN 27022012 Lahore, Pakistan SUPERVISOR: DR. NADEEM SHAFIQ BUTT

THIS PROJECT REPORT IS PART OF THE REQURMENT FOR THE

SIX SIGMA BLACK BELT COURSE

ORGANISED BY

PIQC INSTITUTE OF UALITY AND SINGAPORE QUALITY INSTITUTE


SIX SIGMA (BLACK BELT)PROJECT Page 1

TABLE OF CONTENTS
Sr. No. 1 Topic DEFINE PHASE Project Charter Deployment Process Flow Diagram SIPOC Diagram KPIs and KPOs MEASURE PHASE Measurement System Analysis (MSA) Line Chart (Month Wise Downtime) Pie Chart (Category Wise Downtime) Pareto Analysis (Category Wise Downtime) Cause & Effect Diagram (Downtime) Pie Chart Country Wise Downtime City Wise Downtime Bar Chart Shift Wise Average Downtime Gender Wise Average Downtime Qualification Wise Downtime Experience Wise Downtime Age Wise Downtime Multiple Bar Chart Country & City Wise Downtime Qualification & Experience Wise Downtime Age & Experience Wise Downtime Probability Plot Current Sigma Level Calculation ANALYSIS PHASE Testing of Hypothesis IMPROVE PHASE Design of Experiment CONTROL PHASE Process Failure Mode & Effect Analysis Control Charts Page No. 3 4 5 5 8 9 10 12 13 13 14 14 14 15 16 16 17 17 17 18 18 18 19 20 21 33 34 42 43 59

SIX SIGMA (BLACK BELT)PROJECT

Page 2

DEFINE PHASE
DEFINE PHASE: Project Charter Process Flow Diagram SIPOC Diagram KPIs & KPOs

SIX SIGMA (BLACK BELT)PROJECT

Page 3

PROJECT CHARTER:
PROJECT TITLE: BUSINESS CASE: Managing & Enhancing Quality of It Operations By Reducing The Unplanned Downtime

Last year (from February to August, 2011) due to the different issues in the IT operations and development company faces unplanned downtime which causes the loss of revenue, reputation and customers. By considering these issues the overall losses are approximately Average Rs. 23981100 per month (Average Downtime per month X Average Cost (Human Resource) per Minute X 7 Months). By reducing above said losses by 30%, we will be able to save approximately average Rs.7194330 per month. PROBLEM Managing quality by controlling and improving processes of identified major downtime STATEMENT: categories which are causing 45% of total down time. OBJECTIVE: METRICS: Reduction in %age downtime up to 30% of the total downtime. Primary Metric = Downtime (%) = (Total Downtime / Secondary Metric = % Yield Total Production Time) * 100

PROJECT IT Operations & Development SCOPE: BEFORE IMPROVEMENT MONTHLY DOWNTIME :

Month wise Total Downtime


10000 Total Downtime 8000 6000 4000 2000 0 Total Feb 8079 Mar 6961 Apr 7047 May 6263 Jun 6559 Jul 5405 Aug 6645

AFTER IMPROVEMENT MONTHLY DOWNTIME :

Month Wise Total Downtime


10000 8000 6000 4000 2000 0 Total Downtime

Feb Mar Apr May Jun

Jul Aug Sep Oct Nov Dec

Total Downtime 8079 6961 7047 6263 6559 5405 6645 5430 4355 2122 2276

Schedule:
ID Task Name Start Finish Duration 1 2 3 4 5 Define Measure Analyze Improve Control 10/17/2011 10/31/2011 11/21/2011 12/12/2011 1/30/2012 10/28/2011 11/18/2011 12/9/2011 1/27/2012 2/17/2012 10d 15d 15d 35d 15d

Oct 2011

Nov 2011

Dec 2011 1/1

Jan 2012 8/1 15/1 22/1 29/1

Feb 2012 5/2 12/2

23/10 30/10 6/11 13/11 20/11 27/11 4/12 11/12 18/12 25/12

SIX SIGMA (BLACK BELT)PROJECT

Page 4

DEPLOYMENT PROCESS FLOW DIAGRAM:


Process Flow Diagram; IT Operations and Development

Client Services

Request to Create New Campaign

Document that contains requirements for new campaign No

Request to Load the Leads

Data which Need to be Loaded

Request to update the filter

Analyze Performance

Satisfied with Performance

Yes

Inform Client

Development Team

Develop Campaign Script

Approval for Script Deployment

No

Update Script

Develop Query to Load the Leads

Develop Filter for Leads Selection No

DBA Team

Correct format Yes

Yes

Load the Leads

Perform Database Maintanance

Perform Leads Scrubbing

Operations Dialer Team Team

Deploy Script

Apply Filter

Update Filter

Analyze Current System and Request Maintainance

Reboot Dialers

Change Dialing Parameters

Login Agents No

Getting Leads

Yes

Start Dialing

Report any Production Impacting Issue

Help Desk

Open the Bridge

Get Required Teams on the Bridge

Record Downtime

Provide Downtime Details to Concerned Person

NT Admin Team

Have Login Rights

Give Rights to the Agents

Perform System Maintainance

Assign/Unassign Machine

GNOC

Set Rules to Access the Network

Monitor Network Traffic

Perform Maintenance Activity of Telco Lines with Career

Analyse Network Health in Case of Issues

SIPOC DIAGRAM:

SUPPLIER
Development Team Operations Team Strategy Analyst

INPUT
Dialing Filter Dialing Criteria Email

PROCESS
APPLY FILTER
Operations team requests filter update

OUTPUT
Correct Leads Enough Leads Available

CUSTOMER
Operations Team Agents

Development team develops the filter

Dialer team implements the filter and checks the leads count

Dialer team provide the updated leads count and filter to development team

SIX SIGMA (BLACK BELT)PROJECT

Page 5

SUPPLIER
NT Admin

INPUT
Credentials with the rights to reboot

PROCESS
Reboot Dialer
Dialer team analyst stops the controller

OUTPUT

CUSTOMER

Analyst stops the CTIEngine and Dialogic

Controller up Dialer Team and running Agents CTI Engine up and running Dialogic up and running

Restart the machine

Once machine is backup restart the dialogic

Restart the CTIEngine and Controller applications

Dialer is ready for production

SUPPLIER
Client Client Services Team

INPUT
Client Requirements Client's Approval Client Services Approval

PROCESS
UPDATE SCRIPT
Client services requests a change in script

OUTPUT
Correct Script With Updated Information

CUSTOMER
Agents Client Services Operations Manager Developer

Developer makes changes in the script

Script is tested on test server

Developer sends the script to Dialer Team for deployment in production

Dialer Team deploys the script after getting appropriate approvals

SIX SIGMA (BLACK BELT)PROJECT

Page 6

SUPPLIER
Client Services Strategy Analyst

INPUT
Previous Dialing Data New Strategy

PROCESS
CHANGE DAILING PARAMETERS
Client Services/Strategy Analyst request change in parameters

OUTPUT
Target Strategy Met Dialing with New Parameters

CUSTOMER
Strategy Analyst Client Services Team

Dialer Team analyst implements the strategy

Dialer Team supervisor verifies that the change has been implemented correctly

Dialer Team inform the requestor that change has been implemented

SUPPLIER
Client Services Client

INPUT
Lead files

PROCESS
LEADS LOADING
Operations team requests filter update

OUTPUT
New Leads

CUSTOMER
Operations Team Client Services Dialer Team

Development team develops the filter

Dialer team implements the filter and checks the leads count Dialer team provide the updated leads count and filter to development team

SUPPLIER
NT Admins Dialer Team

INPUT
X-ten NT login credentials Agent application login credentials

PROCESS
LOGIN AGENTS
Agent starts soft phone

OUTPUT
Agent Application Campaign Loaded

CUSTOMER
Agents

Agent logs into terminal server using his credentials

Agents starts agent application and login Once agent is logged into agent application he logs into the campaign Required campaign is loaded and agent starts dialing

SIX SIGMA (BLACK BELT)PROJECT

Page 7

SUPPLIER
Machine Owner

INPUT
Required approvals Required machine information

PROCESS
MAINTENANCE
Dialer Team request field support to perform maintenance

OUTPUT
Machine up and running

CUSTOMER
Dialer Team NT Admin

Field support team performs the maintenance and restarts the machine

Dialer Team restarts the appropriate applications

KPIs and KPOs:


KPIs Month Gender Qualification Experience Country City Shift X X1 X2 X3 X4 X5 X6 X7 KPOs Downtime Y Y1

SIX SIGMA (BLACK BELT)PROJECT

Page 8

MEASURE PHASE
MEASURE PHASE:

Measurement System Analysis Line Chart Pie Chart Pareto Chart Cause & Effect Diagram Bar Chart Multiple Bar Chart Probability Plot Current Sigma Level

SIX SIGMA (BLACK BELT)PROJECT

Page 9

Process performance is measured in terms of downtime per month. This time is measured from the clock and noted on an Excel sheet. Different cases of intervals were provided to operators to evaluate those intervals as Good or Bad. While conducting study, Downtime 60 minutes as good and others as bad. After that operators performance was put in Minitab-16 and Measurement System Analysis for Attribute data was analyzed. Results as shown below:

MEASUREMENT SYSTEM ANALYSIS:


According to AIAG 10% overall error rate is acceptable in measurement system. Below report indicating that our Measurement system has acceptance up to 93.3%. Hence our Measurement system is acceptable.
Attribute Agreement Analysis for Results Summary Report
Is the overall % accuracy acceptable? < 50% 100% Misclassification Rates Overall error rate Good rated Bad Bad rated Good Mixed ratings (same item rated both ways) 6.7% 10.0% 3.3% 13.3%

No
93.3% The appraisals of the test items correctly matched the standard 93.3% of the time.

Yes

% Accuracy by Appraiser 120


100.0 85.0

Comments Consider the following when assessing how the measurement system can be improved: -- Low accuracy rates: Low rates for some appraisers may indicate a need for additional training for those appraisers. Low rates for all appraisers may indicate more systematic problems, such as poor operating definitions, poor training, or incorrect standards. -- High misclassification rates: May indicate that either too many Good items are being rejected, or too many Bad items are being passed on to the consumer (or both). -- High percentage of mixed ratings: May indicate items in the study were borderline cases between Good and Bad, thus very difficult to assess.

100

95.0

93.3%

80

60

40

20

Hassan Rauf

Fahad Javaid

Najeeb Rehma

SIX SIGMA (BLACK BELT)PROJECT

Page 10

Overall Error Rate = 6.7%

Attribute Agreement Analysis for Results Misclassification Report


Most Frequently Misclassified Items

% Good rated Bad Item 1 Item 5 Item 2 Item 7 Item 9 0 10 20 30 Item 3 Item 4 Item 6 Item 8 Item 10 0 10

% Bad rated Good

20

30

Appraiser Misclassification Rates


% Good rated Bad % Bad rated Good % Rated both ways

Hassan Rauf

Hassan Rauf

Hassan Rauf

Fahad Javaid

Fahad Javaid

Fahad Javaid

Najeeb Rehma 0 15 30

Najeeb Rehma 0 15 30

Najeeb Rehma 0 15 30

Attribute Agreement Analysis for Results Accuracy Report


All graphs show 95% confidence intervals for accuracy rates. Intervals that do not overlap are likely to be different.
% by Appraiser Hassan Rauf Hassan Rauf % by Appraiser and Standard Good

Fahad Javaid

Najeeb Rehma 40 60 80 100

Fahad Javaid

% by Standard Good Bad 40 60 80 % by Trial 100 Hassan Rauf Najeeb Rehma Bad

Fahad Javaid

Najeeb Rehma

40

60

80

100

40

60

80

100

SIX SIGMA (BLACK BELT)PROJECT

Page 11

Attribute Agreement Analysis for Results Report Card


Check Mix of Items Accuracy and Error Rates Status Description It is good practice to have a fairly balanced mix of Good and Bad items. Your data shows that you have 50% Good items and 50% Bad items. If you have a small percentage of items of one type, you reduce your ability to assess how well the appraisers rate that type of item. The accuracy and error rates are calculated across all appraisals. Suppose you test 10 items, 5 Good and 5 Bad, and three appraisers test each item twice for a total of 60 appraisals (10 x 3 x 2 = 60). To calculate the error rates for Good items, you would have 30 appraisals (5 x 3 x 2); for Bad items you would have 30 (5 x 3 x 2). To calculate the error for items rated both ways, you would have 30 values (10 items x 3 appraisers = 30). The accuracy and error rates are: Accuracy= 93.3% Error= 6.7% Good rated Bad= 10.0% Bad rated Good= 3.3% Rated both ways= 13.3%

i i

LINE CHART:
9000 8000 Total Downtime 7000 6000 5000 4000 3000 2000 1000 0 Total Feb 8079 Mar 6961 Apr 7047 May 6263 Jun 6559 Jul 5405 Aug 6645

Month wise Total Downtime

Above line chart and descriptive statistics shows last seven months trend of the total production downtime on monthly basis.

SIX SIGMA (BLACK BELT)PROJECT

Page 12

PIE CHART:

Category Wise Downtime


Windows server 4% Change Error 11% Unknown 25% Client Related 4% Database 1% Dialer Hardware 3% Dialer Software 12% Telco 6% Software 3% Service Provider 0% Procedure Error 12%

Facilities 10%

Maintenance 1%

Network Network Hardware 4% 4%

From pie chart of category wise production downtime we can clearly observe that unknown was the largest downtime category with the share of 25% of total downtime. Dialer Software and Procedure Error were the second largest downtime category with 12% share of each catagory. Overall, we have a clear picture of percentage of downtime associated with each root cause category through pie chart.

PARETO ANALYSIS:
Category Vs Downtime
50000 40000 100 80 60 40 20 0

Downtime

20000 10000 0

Root Cause Category

r e ies ro w ar lit Er Er no tw ci f k e ge Fa So ur Un an ed er al Ch oc Di Pr n

Downtime Percent Cum %

r k e ed lc o or ar he at w Te tw Ot el rd Ne tR Ha en k i r Cl wo et N 11661 5465 5379 5237 4652 2842 2066 2043 1933 5681 24.8 11.6 11.5 11.2 9.9 6.1 4.4 4.4 4.1 12.1 24.8 36.5 47.9 59.1 69.0 75.0 79.4 83.8 87.9 100.0

r ro

SIX SIGMA (BLACK BELT)PROJECT

Page 13

Percent

30000

After constructing the Pareto chart of downtime of causes it was observed that out of remaining 14 categories (except Unknown) only 4 were responsible for a downtime of 44.2%. Procedure error and Dialer software proved to be the first and second largest category of downtime which was responsible for an 11.6% and 11.5% of the total downtime respectively. Change error caused 11.2% while facilities caused around 9.9% of total downtime. From above information, main four major categories identified which are Change Error, Procedure Error, Facilities Failure and Dialer Software. These four categories alone were responsible for 44.2% of total downtime. By managing these four categories we can considerably increase the quality by reducing unplanned downtime.

CAUSE & EFFECT DIAGRAM:


Below cause & effect diagram indicating that there are number of root causes which are responsible for downtime in the system. Four major causes (i.e.: Procedure Error, Facilities Error, Change Error and Dialer Software Failure) are considered to identify the root causes.
Procedure Error
Agents logging into wrong machine Proper login information was not provided Procedure misunderstanding System crash Lack of Education Not clearly defined Procedure wrongly followed Inexperienced technician Virus attack Antivirus was not installed Some malicious software installed Poor Maintenance System upgrade is costly Maintenance performed on wrong time Misunderstanding of timings Virus database was not updated Too much load Incompatibility after system upgrade Earthquake Natural disaster Flood Fire Hardware failure

Facilities Failure

Storm

Documentation not available Not considered important Not upgraded Trainings not arranged Lack of job knowledge Not enough trained resource

Too much load Load unbalancing Software crash Not thoroughly tested Incompatibility with other components Unhandled exception QA not performed before release New version needs to be released immediately Parameters were not double checked Wrong parameters applied Lack of education/training Lack of experience/knowledge

Downtime
Change implemented wrongly Lack of communication between stakeholders Change was misunderstood Lack of automation Resistance to change Tools are considered unimportant Resources are busy in other tasks

Resources not available to develop customized tools Lack of ownership Change manager/implementer not properly defined Technology failed during change Current system does not support upgrade Change was not properly tested Campaign needs to go live on short notice Not good enough testing environment Lack of time

Dialer Software Failure

Change Error

PIE CHARTS:
4% 1%

Country Wise Downtime


0% Pakistan Philippines Senegal 95% United States of America

SIX SIGMA (BLACK BELT)PROJECT

Page 14

From pie chart of Country wise downtime we can clearly observe that Pakistan was the largest downtime country with the share of 95% of total downtime.

City Wise Downtime


Manila 0% Pittsburg Bend Beckley 2% 1% 0% Dakar 1% King of Prussia 1% Charlston 0%

Karachi 10%

Lahore 85%

From pie chart of City wise downtime we can clearly observe that Lahore was the largest downtime city with the share of 85% of the total downtime. BAR CHARTS:

70.00 Average Downtime 60.00 50.00 40.00 30.00 20.00 10.00 0.00 Total

Shift wise Average Downtime

Evening 58.94

Morning 56.94

Night 39.95

Above bar chart indicates that average downtime occurs in the evening and morning shifts are much higher than the night shift.

SIX SIGMA (BLACK BELT)PROJECT

Page 15

Gender Wise Average Downtime


60.00 50.00 Average Downtime 40.00 30.00 20.00 10.00 0.00 Total Female 39.79 Male 50.28

Above bar chart indicates that average downtime occurs due to male is more than female.

Qualification Wise Total Downtime


14000 Total Downtime 12000 10000 8000 6000 4000 2000 0 A BBIT Levels 4985 142 5145 132

BCE 156 2

BCS 6827 144

BEE 1704 59

BIS

BIT

BT

MCS 86 2

MIS 420 1

MT 5389 104

Sum of Downtime Count of Downtime

3289 11470 7488 52 190 117

Legend:
A Levels A-Levels BBIT Bachelors in Business and Information Technology BCE Bachelors in Computer Engineering BCS Bachelors in Computer Science BEE Bachelors in Electrical Engineering BIS Bachelors in Information Systems BIT Bachelors in Information Technology BT Bachelors in Telecommunication MCS Masters in Computer Science MIS Masters in Information Systems MISS Masters in Information Systems Security MT Masters in Telecommunication Due to lesser counts in few categories regarding the downtime bar chart used to high light major responsible qualification levels. So, most of the downtime are due to Graduate (i.e.: BIT, BT and BCS). SIX SIGMA (BLACK BELT)PROJECT Page 16

Experience Wise Total Downtime


18000 16000 14000 12000 10000 8000 6000 4000 2000 0 Sum of Downtime Count of Downtime Total Downtime

2-3 15236 334

4-5 16884 291

6-7 10967 230

8-9 3033 74

10-11 809 15

12-14 30 1

Above bar chart indicates that the lesser experience persons are more responsible for downtime.

Age Wise Total Downtime


25000 Total Downtime 20000 15000 10000 5000 0 Sum of Downtime Count of Downtime 28-29 8664 198 30-31 20699 459 32-33 7833 120 34-35 2647 50 36-37 3954 50 38-39 1702 43 40-41 651 10 50-51 457 8 54-55 352 7

Above bar chart indicates that the people having less than 34 years age are more responsible for downtime. MULTIPLE BAR CHARTS:

Country & City Wise Total Downtime


45000 40000 35000 30000 25000 20000 15000 10000 5000 0 Karachi Lahore Pakistan Sum of Downtime Count of Downtime 4668 93 40016 808 Manila Dakar Beckley Bend Total Downtime

Charlst King of Pittsbur on Prussia g 58 1 352 7 877 9

PhilippinesSenegal 195 2 451 16 92 5

United States of America 250 4

SIX SIGMA (BLACK BELT)PROJECT

Page 17

Above multiplebar chart indicates that the most of downtime occurs in Lahore, Pakistan.

Qualification & Expereince Wise Total Downtime


6000 5000 4000 3000 2000 1000 0 Total Downtime

4-5

8-9

6-7

2-3

6-7

8-9

4-5

2-3

4-5

6-7

8-9

2-3

2-3

4-5

8-9

2-3

4-5

2-3

4-5

6-7

4-5

4-5 10-11

10-11

A Levels

BBIT

BCE

BCS

BEE BIS BIT Qualification & Experience

BT

MCS MIS MT

Above multiplebar chart indicates that the most of downtime occurs due to lesser experience and having Graduate (i.e.: BIT, BT, BCS) qualification.

Age & Expereince Wise Total Downtime


Total Downtime 14000 12000 10000 8000 6000 4000 2000 0

8-9

2-3

4-5

2-3

4-5

6-7

2-3

4-5

6-7

8-9

2-3

4-5

6-7

2-3

4-5

8-9

2-3

4-5

8-9

12-14

12-14

28-29

30-31

32-33

3637 Age & Experience

34-35

38-39

40-41

50- 5451 55

Probability Plot of Downtime


Normal 99.99
Mean StDev N AD P-Value 49.69 62.08 945 82.236 <0.005

99 95

Percent

80 50 20 5 1

0.01

-200

-100

100

200 300 Downtime

400

500

600

700

Above probability plot of the overall downtime for all root cause categories indicating a non normal distribution because the p-values for the Anderson-Darling test are less than 0.05 SIX SIGMA (BLACK BELT)PROJECT Page 18

10-11

4-5

MEASURING THE CURRENT PROCESS SIGMA LEVEL: Root Cause Downtime Root Cause Categories Categories (Minutes per Year) Dialer Software 5379 Procedure Error Dialer Hardware 1431 Network Hardware Network 2043 Database Windows Server 1685 Telecommunication (Telco) Facilities 4652 Software Client Related 2066 Service Provider Maintenance 491 Unknown/Other TOTAL Change Error 5237

Downtime (Minutes per Year) 5465 1933 677 2842 1257 140 11661 46959

COST OF DOWNTIME: Total Production time (Minutes) per Month = 15 hours X 60 Minutes X 26 Days = 23400 Average Down Time (Minutes) per Month = 6708 Average Cost per minute (Human Resources) = Rs. 3575 Average down time Cost / month = Rs. 23981100 SIGMA LEVEL CALCULATIONS: LAST SEVEN MONTH STUDY: Total Downtime (Minutes) = 46959 Total Production Time (Minutes) = 163800 Opportunity per Unit = 1 DPU (Defects / Unit) = 46959 / 163800 = 0.2867 DPO (Defects/opportunity) = 46959 / (163800 X 1) =0.2867 Yield = 1 DPO = 1 0.2867 = 0.7133 DPMO = 286685 (defects/million opportunity) Sigma Level = 2.06 (Using M.S. Excel) CONCLUSION: From above said investigations it is concluded that most of the downtime occurs in Lahore, Pakistan. On average in evening and morning shift downtime occurs more than night shift and male are more responsible than female for this downtime. Persons having lesser experience and having graduate level qualification (i.e: BIT, BT, BCS) are more responsible than others.

SIX SIGMA (BLACK BELT)PROJECT

Page 19

ANALYZE PHASE
ANALYSIS PHASE: Testing of Hypothesis

SIX SIGMA (BLACK BELT)PROJECT

Page 20

One-Way ANOVA for Downtime by Country Diagnostic Report


Distribution of Data Compare the location and spread. Data in Worksheet Order Investigate outliers (marked in red).
Pakistan

Pakistan

500 250 0

Philippines

Philippines

500 250 0

Senegal

Senegal

500 250 0

United State

United State

500 250 0 0 250 500

SIX SIGMA (BLACK BELT)PROJECT

Page 21

One-Way ANOVA for Downtime by Country Summary Report


Do the means differ? 0 0.05 0.1 > 0.5 # 1 2 3 4 Sample Senegal Pakistan United State Philippines Which means differ? Differs from

Yes
P = 0.076 Differences among the means are not significant (p > 0.05).

No

None Identified

Means Comparison Chart

Senegal

Comments Pakistan You cannot conclude that there are differences among the means at the 0.05 level of significance.

United State

Philippines

-400

-200

200

400

The result of the above test shows that County is an insignificant factor as the Pvalue is more than 0.05.

SIX SIGMA (BLACK BELT)PROJECT

Page 22

The result of the above test shows that City is an insignificant factor as the Pvalue is more than 0.05.

SIX SIGMA (BLACK BELT)PROJECT

Page 23

One-Way ANOVA for Downtime by Shift Diagnostic Report


Distribution of Data Compare the location and spread.
Evening

Data in Worksheet Order Investigate outliers (marked in red).


Evening

500

250

Morning

0
Morning

500

250

Night

0
Night

500

250

0 0 100 200 300 400 500 600

One-Way ANOVA for Downtime by Shift Summary Report


Do the means differ? 0 0.05 0.1 > 0.5 # 1 2 3 Sample Night Evening Morning Which means differ? Differs from 2 1

Yes
P = 0.000 Differences among the means are significant (p < 0.05).

No

Means Comparison Chart Red intervals that do not overlap differ.

Night Comments You can conclude that there are differences among the means at the 0.05 level of significance. Use the Comparison Chart to identify means that differ. Red intervals that do not overlap indicate means that differ from each other. Consider the size of the differences to determine if they have practical implications.

Evening

Morning

40

60

80

SIX SIGMA (BLACK BELT)PROJECT

Page 24

The result of the above test shows that shift is a significant factor as the Pvalue is less than 0.05.

2-Sample t Test for the Mean of Downtime (Male and Female) Diagnostic Report
Data in Worksheet Order Investigate outliers (marked in red).
Downtime (Ma Downtime (Fe

500

250

0 1 90 179 268 357 446 535 624 713 802 891 1 6 11 16 21 26 31 36 41 46 51

Power W hat is the chance of detecting a difference? < 40% 60% 90% 100%

What difference can you detect with your sample sizes of 892 and 53? Difference 14.433 16.495 18.907 22.253 Power 60.0 70.0 80.0 90.0

14.433 22.253 For alpha = 0.05 and sample sizes = 892, 53: If the true mean of Downtime (Ma was 14.433 greater than Downtime (Fe, you would have a 60% chance of detecting the difference. If Downtime (Ma was 22.253 greater than Downtime (Fe, you would have a 90% chance.

Power is a function of the sample sizes and the standard deviations. To detect a difference smaller than 18.907, consider increasing the sample sizes.

SIX SIGMA (BLACK BELT)PROJECT

Page 25

2-Sample t Test for the Mean of Downtime (Male and Female) Summary Report
Mean Test Is Downtime (Ma greater than Downtime (Fe? 0 0.05 0.1 > 0.5 Statistics Sample size Mean 90% CI Standard deviation Difference between means* 90% CI Downtime (Ma 892 50.280 (46.83, 53.73) 62.571 Downtime (Fe 53 39.792 (27.699, 51.886) 52.573

Yes
P = 0.084 The mean of Downtime (Ma is not significantly greater than the mean of Downtime (Fe (p > 0.05).

No

10.488 (-2.0710, 23.047)

* The difference is defined as Downtime (Ma - Downtime (Fe. 90% CI for the Difference Does the interval include zero? Comments 0 5 10 15 20 -- Test: There is not enough evidence to conclude that the mean of Downtime (Ma is greater than Downtime (Fe at the 0.05 level of significance. -- CI: Quantifies the uncertainty associated with estimating the difference from sample data. You can be 90% confident that the true difference is between -2.0710 and 23.047. -- Distribution of Data: Compare the location and means of samples. Look for unusual data before interpreting the results of the test.

Distribution of Data Compare the data and means of the samples.


Downtime (Ma

Downtime (Fe

-100

100

200

300

400

500

600

SIX SIGMA (BLACK BELT)PROJECT

Page 26

One-Way ANOVA for Downtime by Qualification Power Report


Power What is the chance of detecting a difference? < 40% 60% 90% 100%
What difference can you detect with your sample sizes? Difference Power 23.539 126.15 139.35 150.83 159.82 3.5 60.0 70.0 80.0 90.0 - 60.0 - 100.0 - 100.0 - 100.0 - 100.0

23.539 159.82 Based on your samples and alpha level (0.05), you have at least a 90% chance of detecting a difference of 159.82, and at most a 60% chance of detecting a difference of 23.539.

Power is a function of the sample sizes and the standard deviations. To detect differences smaller than 150.83, consider increasing the sample sizes.

Statistics Qualification A Levels Bachelors _2 Bachelors _3 Bachelors _4 Bachelors _5 Bachelors _6 Bachelors _7 Bachelors _8 Masters in_9 Masters in_1 Sample Size 142 132 2 144 58 52 190 117 2 104 Mean 35.106 38.977 78 47.410 29.034 63.25 60.368 64 43 51.817 Standard Deviation 43.816 41.490 56.569 51.121 38.518 66.703 75.072 82.220 18.385 57.211 Individual 95% CI for Mean (27.836, 42.375) (31.833, 46.121) (-430.25, 586.25) (38.989, 55.831) (18.907, 39.162) (44.680, 81.820) (49.625, 71.112) (48.945, 79.055) (-122.18, 208.18) (40.691, 62.943)

One-Way ANOVA for Downtime by Qualification Summary Report


Do the means differ? 0 0.05 0.1 > 0.5 # 1 2 3 4 5 6 7 8 9 10 Sample Bachelors _5 A Levels Bachelors _2 Bachelors _4 Masters in_1 Bachelors _7 Bachelors _8 Bachelors _6 Masters in_9 Bachelors _3 Which means differ? Differs from 6 6 7 7

Yes
P = 0.016 Differences among the means are significant (p < 0.05).

No

Means Comparison Chart Red intervals that do not overlap differ. Bachelors _5 A Levels Bachelors _2 Bachelors _4 Masters in_1 Bachelors _7 Bachelors _8 Bachelors _6 Masters in_9 Bachelors _3 -100 0 100 200 300

1 1

2 2

Comments You can conclude that there are differences among the means at the 0.05 level of significance. Use the Comparison Chart to identify means that differ. Red intervals that do not overlap indicate means that differ from each other. Consider the size of the differences to determine if they have practical implications.

SIX SIGMA (BLACK BELT)PROJECT

Page 27

The result of the above test shows that qualification is a significant factor as the Pvalue is less than 0.05.

SIX SIGMA (BLACK BELT)PROJECT

Page 28

One-Way ANOVA for Downtime by Age Diagnostic Report


Distribution of Data Compare the location and spread. 28 29 30
0 500
28

Data in Worksheet Order Investigate outliers (marked in red).


29 30

250

31
500

31

32

33

32
250

33
0

35
500

35

36

38

36
250

38
0

40
500

40

50

55

50
250

55
0

250

500

One-Way ANOVA for Downtime by Age Summary Report


Do the means differ? 0 0.05 0.1 > 0.5 # 1 2 3 4 5 6 7 8 9 10 11 12 Sample 40 30 28 38 35 29 32 31 55 36 50 33 Which means differ? Differs from 7 8 10 10 10 10

Yes
P = 0.000 Differences among the means are significant (p < 0.05).

No

Means Comparison Chart Red intervals that do not overlap differ. 40 30 28 38 35 29 32 31 55 36 50 33 -100 0 100 200 300

1 1 1 2 3 4

Comments You can conclude that there are differences among the means at the 0.05 level of significance. Use the Comparison Chart to identify means that differ. Red intervals that do not overlap indicate means that differ from each other. Consider the size of the differences to determine if they have practical implications.

SIX SIGMA (BLACK BELT)PROJECT

Page 29

The result of the above test shows that age is a significant factor as the Pvalue is less than 0.05.

SIX SIGMA (BLACK BELT)PROJECT

Page 30

One-Way ANOVA for Downtime by Experience Diagnostic Report


Distribution of Data Compare the location and spread.
2

Data in Worksheet Order Investigate outliers (marked in red).


3 4

2
500

3
250

4
0
5 6 7

5
500

6
250

7
0
8 9 10

8
500

9
250

10
0

250

500

One-Way ANOVA for Downtime by Experience Summary Report


Do the means differ? 0 0.05 0.1 > 0.5 # 1 2 3 4 5 6 7 8 9 Sample 8 7 2 3 6 4 10 5 9 Which means differ? Differs from 9 9 9 9 9 9 9 1 2 3 4 5 6 7

Yes
P = 0.000 Differences among the means are significant (p < 0.05).

No

Means Comparison Chart Red intervals that do not overlap differ. 8 7 2 3 6 4 10 5 9 0 40 80 120 160

Comments You can conclude that there are differences among the means at the 0.05 level of significance. Use the Comparison Chart to identify means that differ. Red intervals that do not overlap indicate means that differ from each other. Consider the size of the differences to determine if they have practical implications.

SIX SIGMA (BLACK BELT)PROJECT

Page 31

The result of the above test shows that experience is a significant factor as the Pvalue is less than 0.05.

CONCLUSIONS: Testing of Hypothesis indicating that the few Key Input Variables (KPIs) are became significant like Shift, Qualification, Experience and Age. In Improve phase, further experimentation will be done by considering following significant factors that is Shift, Qualification, and Experience. While age is a significant factor but its a noise factor thats why not considered it further.

SIX SIGMA (BLACK BELT)PROJECT

Page 32

IMPROVE PHASE
IMPROVE PHASE:

Design of Experiment

SIX SIGMA (BLACK BELT)PROJECT

Page 33

Summary for Downtime


A nderson-Darling N ormality Test A -S quared P -V alue M ean S tDev V ariance S kew ness Kurtosis N M inimum 1st Q uartile M edian 3rd Q uartile M aximum 90.34 85.76 9 5 % C onfidence Inter vals
Mean Median 80 100 120 140 160 180

0.33 0.483 132.81 79.71 6353.23 0.040952 -0.641979 16 10.00 55.00 135.00 180.00 280.00 175.29 180.00 123.36

50

100

150

200

250

300

95% C onfidence Interv al for M ean 95% C onfidence Interv al for M edian 95% C onfidence Interv al for S tDev 58.88

Graphical summary of the response clears that the data generated (i.e.: response) against the Design of Experiments is normally distributed and hence the assumption of the normality is fulfilled.

SIX SIGMA (BLACK BELT)PROJECT

Page 34

Normal Plot of the Standardized Effects


(response is Downtime, Alpha = 0.05)
99 Effect Ty pe Not Significant Significant
F actor A B C N ame S hift Q ualification E xperience

95 90 80

Percent

70 60 50 40 30 20 10 5 B BC

-8

-6

-4 -2 Standardized Effect

SIX SIGMA (BLACK BELT)PROJECT

Page 35

Pareto Chart of the Standardized Effects


(response is Downtime, Alpha = 0.05) 2.306 B BC C
F actor A B C N ame S hift Q ualification E xperience

Term

ABC AC AB A 0 1 2 3 4 5 Standardized Effect 6 7 8

Residual Plots for Downtime


Normal Probability Plot
99 90 50 10 1 -50 -25 0 25 Residual 50 50

Versus Fits

Residual

Percent

25 0 -25 -50 0 50 100 150 Fitted Value 200

Histogram
6.0
Mean StDev N -4.44089E-15 24.31 16

Versus Order
50

Frequency

Residual
-40 -20 0 20 Residual 40

4.5 3.0 1.5 0.0

25 0 -25 -50
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Observation Order

SIX SIGMA (BLACK BELT)PROJECT

Page 36

Main Effects Plot for Downtime


Data Means
Shift Qualification

200 150 100

Mean

50 Night 200 150 100 50 2 14 Experience Evening A-Levels Maters

Main effect plots of shift, qualification & experience shows that the most dominating factor is the qualification. As it gives visible variation in the downtime required for the reducing the unplanned downtime.

Cube Plot (data means) for Downtime


15.0 37.5

105.0 Maters

115.0

Qualification

230.0

185.0 14 Experience 2

165.0 A-Levels Night Shift

210.0 Evening

Cube plot for downtime shows the optimum conditions for the desired results. If minimum unplanned downtime is required than organization must work with the combination of Night shift, Master Qualification, and 14 year of experience (means maximum experience). SIX SIGMA (BLACK BELT)PROJECT Page 37

RESPONSE OPTIMIZATION:
Shift Evening Night Night Qualific Maters Maters A-Levels Experien 14.0 [14.0] 2.0

Optimal High D Cur 1.0000 Low

Composite Desirability 1.0000

Downtime Minimum y = 15.0 d = 1.0000

When optimizer is run for the goal of minimum downtime evaluation, it gives minimum downtime which is 15 minutes.

SIX SIGMA (BLACK BELT)PROJECT

Page 38

Probability Plot of Downtime


Normal
99 Mean StDev N AD P-Value 132.8 79.71 16 0.328 0.483

95 90 80

Percent

70 60 50 40 30 20 10 5

-100

100 Downtime

200

300

Test for Equal Variances for Downtime


Shift Night Qualification A-Levels Experience 2 14 Maters 2 14 Evening A-Levels 2 14 Maters 2 14 0 5000 10000 15000 20000 95% Bonferroni Confidence Intervals for StDevs
Bartlett's Test Test Statistic P-Value 11.06 0.136

SIX SIGMA (BLACK BELT)PROJECT

Page 39

Pareto Chart of Root Cause Catagories Before Improvement


50000 40000 100 80 60 40 20

Downtime

20000 10000 0

Root Cause Category

r r s e ro ro wn ar itie Er Er no c il ftw k e re Fa So Un ng du ler ha ce a C o Di Pr

k e d lc o or te ar Te tw ela dw r R Ne Ha nt lie rk C o tw Ne

r he Ot

Downtime Percent Cum %

11661 5465 5379 5237 4652 2842 2066 2043 1933 5681 24.8 11.6 11.5 11.2 9.9 6.1 4.4 4.4 4.1 12.1 24.8 36.5 47.9 59.1 69.0 75.0 79.4 83.8 87.9 100.0

Pareto Chart of Root Cause Catagories After Improvement


20000 100 80 60 40 5000 0 20 0

Total Downtime

15000 10000

Root Cause Catagories

r o n rk ted are ver are or re ties er are he r ro rr Telc wa r ow two a ili w Er ovid ftw Ot el se o ftw e E kn e rd rd Fac e r R o s r P N a S Un ng Ha nt r H dow du ice rS a k e e ie e al Ch or rv Cl oc al Win Di Pr tw Se Di Ne Total Downtime 3258 1759 1503 1198 1180 1175 1106 1089 1025 1005 967 965 960 1703 Percent 17 9 8 6 6 6 6 6 5 5 5 5 5 9 Cum % 17 27 35 41 47 53 59 65 70 76 81 86 91 100

Month Wise Total Downtime (After Improvement "Sep. to Dec.")


9000 8000 7000 6000 5000 4000 3000 2000 1000 0 Total Downtime

Feb

Mar 6961

Apr 7047

May 6263

Jun 6559

Jul 5405

Aug 6645

Sep 5430

Oct 4355

Nov 2122

Dec 2276

Total Downtime 8079

SIX SIGMA (BLACK BELT)PROJECT

Page 40

Percent

Percent

30000

SIGMA LEVEL CALCULATIONS (AFTER IMPROVEMENT): FOUR MONTH STUDY: Total Downtime (Minutes) = 14183 Total Production Time (Minutes) = 93600 Opportunity per Unit = 1 DPU (Defects / Unit) = 14183 / 93600 = 0.1515 DPO (Defects/opportunity) = 14183 / (93600 X 1) = 0.1515 Yield = 1 DPO = 1 0.1515 = 0.8485 DPMO = 151528 (defects/million opportunity) Sigma Level = 2.53 (Using M.S. Excel) SIGMA LEVEL BEFORE THE IMPROVEMENT 2.06 AFTER THE IMPROVEMENT 2.53

CONCLUSIONS: With new suggested combination provided by the Design of Experiment; the overall system performance is improved as shown in the above sigma level calculation.

SIX SIGMA (BLACK BELT)PROJECT

Page 41

CONTROL PHASE
CONTROL PHASE:

Process Failure Mode & Effect Analysis Control Charts

SIX SIGMA (BLACK BELT)PROJECT

Page 42

Process Failure Mode and Effect Analysis: CHANGE ERROR


Process Function / Requirement Apply Filter Potential Failure Mode Leads never get buffered Potential Effects of Failure High wait time Potential Causes / Mechanisms of Failure Applied wrong filter Wrong filter was provided Current Process Controls Filter is just overviewed to find out any kind of error No process controls available RPN Recommended Actions Check the filter in database and get the leads count before actually applying it Double check the filter with developer and with Ops manager to discuss the result of implementation and avoid requesting filter change himself Always ask the requester if change is only for one day or its for until further notice O Responsibility Jawad Hassan (Analyst Systems and Production) D S 8

120

144

Wrong leads gets buffered

Agents talking to wrong customers

Import date of leads not updated Part of filter missing while applying

196

Zeeshan Jamil (Supervisor Systems and Production)

168

Filter reverted to old one

Agents getting wrong leads

Applied for only one day instead of until further notice 4 6 Current tasks finished

Usually asked from OPS team if change is only for one day or for until further notice No process controls available Normally developers mentions in which database to

Ali Gohar (Analyst Systems and Production)

144

54

Leads Loading

Loaded to wrong database

Agent in downtime waiting for leads

Wrong information provided by developer

32

Tasks audit should be performed every month Always get a confirmation from dialer team and developer

Afriaz Cheema (Manager Systems and Production) Hammad Haasan (Database Administrator)

SIX SIGMA (BLACK BELT)PROJECT

Page 43

load the leads

about the location of the database

Misunderstanding by the DBA Loaded with wrong scrubbing information Customers complaining about DNC 6 Wrong scrubbing information provided by client services/developer

Update Script

Incorrect script deployed

Missing some information from script

Miscommunication between developer and client services 5 5

No process controls available Client services normally mentions the scrubbing criteria Developer just relies on the information provided

32 Double check with the client services before actually scrubbing the leads Communication regarding script must be documented and understanding must be developed by asking questions Script must be verified after development and before UAT There should be more focus to improve testing environment and employees should be encouraged to do more and more testing in test Arsalan Ahmed (Database Administrator)

72

Bilal Sheikh (Software Engineer)

100

Developer missed the script

No process controls available Basic testing is performed before going live

120

Bilal Sheikh (Software Engineer) Afaq Ali (Deputy Head of Production)

Missing some call disposition term codes

Functionality not working in production environment Term codes were not added

168

216

SIX SIGMA (BLACK BELT)PROJECT

Page 44

Dialer Application Update

Applications crashing

Agents get kicked out of system 8

Unhandled Exception 4

Some level of exception handling is done by the developer Once issues are reported the parameters are double checked to find out if anything was missed Information only flows through formal emails

128

Applications not starting

Production affected

Parameters not adjusted properly

63

Application not working properly

Some functionalities stop working like TPV

Controller and CTI Engine are not synchronized

120

environment before going live More importance needs to be given to the exception handling in programming Updated parameters should be verified by the supervisor or checked by other team member in order make sure changes are correct Both dialer development and CTI Engine development team should have a closer interaction and communication before making any changes in any component. There should be more informal communication

Abul Asim (Senior Software Engineer)

Ahmed Usman (Supervisor Systems and Production)

Abul Asim (Senior Software Engineer) Ahmed Raza (Software Engineer)

SIX SIGMA (BLACK BELT)PROJECT

Page 45

Windows Server Update

Dialer Applications crashing

Dialer applications not starting and agents can't login

Wrong version upgrade

Normally version upgrade is done over the phone as some times clients need not to be aware of the change

96

Unnecessary upgrade to some application and frameworks

Normally upgrades are not allowed

96

Change dialing parameters

Dialing stopped

agents not getting calls

Applied wrong parameter

No process controls available Normally when the issue arises, parameters are checked to make sure if these were updated correctly or not

Everything regarding new and old version must be documented including what is current version, what is new version and are the back out steps in case a change is failed Automatic upgrade must be turned off as it affect custom build application Parameters should be double checked Change management system must be properly implemented and every change must be properly documented and approved before actual change is implemented. Change must be verified by supervisor or another person

Afaq Ali (Deputy Head of Production)

Rizwan Ali (System Administrator)

Dialing with wrong parameters

Too fast dialing

Dialing in wrong time zones Dialing in wrong mode

TAR updated with high value TAR updated with low value Wrong time zones opened Incorrect dialing mode applied

4 4 5

6
6

72
72

150

Zeeshan Jamil (Supervisor Systems and Production) Asim Zafar (Director IT Operations) Shoib Sakoor (Head of Production)

30

SIX SIGMA (BLACK BELT)PROJECT

Page 46

Process Failure Mode and Effect Analysis: DIALER SOFTWARE FAILURE


Process Function / Requirements Software Crash Potential Failure Mode Application closed itself Potential Effect of Failure Agents logged out and are in downtime Potential Cause / Mechanism of Failure Unhandled exception Current Process Controls Some known exceptions are handled through programming RPN Recommended Action(s) There should be a more focus on exception handling and development team should be more concerned about this Application threads should be properly controlled and memory should be managed in a better way Capacity should be continuously monitored and whenever there are new agents added to the system, the capacity must be rechecked to analyze if current resources are enough to handle this or not Before deployment of application, an extensive QA/testing should be performed and specially stress testing should also be performed

Responsibility Abul Asim (Senior Software Engineer/Program Architect)

S 8

96

Too many processes running

No process control available

96

Abul Asim (Senior Software Engineer/Program Architect)

Capacity issues

No process control available

Afriaz Cheema (Manager Systems and Production)

64

QA/Testing not performed extensively 4

No process control available 6 192

Abdullah (Head of QA)

SIX SIGMA (BLACK BELT)PROJECT

Page 47

Compatibility issues with other components Parameter Configuration Application not starting or crashing again and again Agents logged out and are in downtime Wrong parameters applied 8

No process control available

96

Implemented himself checks the parameters

144

Agents are not able to perform their jobs properly 5

Syntax mistake 2

Implemented himself checks the parameters Implemented himself checks the parameters

30

Some values missed 3

90

Too much load

Software crashes or starts malfunctioning

Leads are unnecessarily burned

No further agents are able to login

Stuck channels are not released so rest of the leads are marked as ND Resources utilization is too high and no further resources are available to perform further actins

No process control available 5 5 125

All relevant stakeholders should be involved during development process Parameters should be double checked and if possible there should be tools available instead of updating anything from backend Training should be given to the technical teams on the current tools being used Parameters should be double check with another team member immediately after any updating This needs to be taken care at programming level

Afriaz Cheema (Manager Systems and Production)

Ahmed Usman (Supervisor Systems and Production)

Rabia (Manager Training and Development)

Ali Gohar (Analyst Systems and Production)

Abul Asim (Senior Software Engineer/Program Architect)

No process control available 3 4 60

OPS team should always inform technical teams if there is any change in current resources allocation

Matthew Debelak (Operations Manager)

SIX SIGMA (BLACK BELT)PROJECT

Page 48

Lead disposition is not properly updated

Application is responding slow to database

No process control available

120

There should a more focus performance optimization

Abul Asim (Senior Software Engineer/Program Architect)

SIX SIGMA (BLACK BELT)PROJECT

Page 49

Process Failure Mode and Effect Analysis: FACILITIES FAILURE


Process Function / Requirements System Crash Potential Failure Mode System shutdown Potential Effect of Failure All relevant resources are in downtime Potential Causes / Mechanisms of Failure Too much workload Current Process Controls Network utilization is normally monitored by GNOC RPN Recommended Actions Systems should be monitored continuously to check their capacity. Stress testing should also be performed after every couple of months Compatibility issues must be taken into consideration before updating any software and all stake holders should be informed about the update Nothing can be done Hardwares must be continuously updated Generators should be ready with extra fuel available

Responsibility Afriaz Cheema (Manager Systems and Production)

S 8

64

Incompatibility while updating with new software/hardware

Head of production normally checks with the development team about incompatibility issues

120

Afriaz Cheema (Manager Systems and Production) Afaq Ali (Deputy Head of Production)

Unexpected error

Facility Evacuation

System never comes backup All systems are shutdown

All resources are in downtime All relevant resources are logged out

Hardware failure 8 Storm 8 Heavy Rains

No process control available Nothing can be done

96

144

2 2

UPS are available in case of electricity failure

3 3

48 48

Ehtesham Opel (Manager System Administrator) John Skubis (Field Support Officer)

SIX SIGMA (BLACK BELT)PROJECT

Page 50

Earthquake

Maintenance

System not available for production

Production cannot be started

Maintenance started on wrong time due to misunderstanding

No process control available Normally emails mention the time

96

Nothing can be done Time should be properly mentioned either its Pakistan time, US time or UK time Hardwares must be continuously updated An extra resource should be hired who could be contacted during off contact hours of primary person Antivirus must be regularly updated and security policies must be tightened without exception to anyone. WSUS server must be installed so that all users are automatically updated on regular basis Munam Khalid (Helpdesk Analyst)

120

Hardware failure during maintenance No one available to restart system after maintenance as the person is moved to another site for some other maintenance Antivirus was not updated

No process control available On contact person is normally available

96

120

Afriaz Cheema (Manager Systems and Production) Shoib Sakoor (Head of Production)

Virus Attack

System shutdown

All user disconnected 8

Some malicious software was installed Windows domain server was attacked due to lack of security Some malicious software/patch was installed that affected the software

System not recognizing the users Some applications not functioning properly

Some users cannot login

Antivirus is manually updated All users are not allowed to install the software Antivirus and security policies are in place

48

64

96

Ehtesham Opel (Manager System Administrator) Shakeel Husain (Manager Networks)

Users are not able to perform their jobs properly

60

SIX SIGMA (BLACK BELT)PROJECT

Page 51

Process Failure Mode and Effect Analysis: PROCEDURE ERROR


Process Function / Requirements Login Agents Potential Failure Mode Agents Stuck on agent application Potential Effect of Failure Can't login Potential Causes / Mechanisms of Failure Dialer is down and was not restarted Current Process Controls No process control available RPN Recommended Actions Before production starts check all the dialers that these are restarted Before production login a test agent to make sure that dialer applications are up and running

Responsibility Jawad Hassan (Analyst Systems and Production)

S 8

64

Agents kicked out of agent application immediately after they login

Can't start production

Controller is down and was not restarted CTI Engine is not properly working Dialogic is not working properly X-ten /dial pad is not configured properly

No process control available

288

Jawad Hassan (Analyst Systems and Production)

216

3 No process control available 4

216 Agents should be properly given training regarding how to configure the phone before they login Agents should always sit on their designated stations New agents must always be assigned to the campaign by requesting the required Jason Oliver(Operations Manager)

192

8 Audio codec is not configured

3 Specific agents are assigned to the campaign when it created

168

Joane (Operations Supervisor) Joane (Operations Supervisor)

No campaigns loaded

Can't start production 8

Not assigned to the specific campaign

168

SIX SIGMA (BLACK BELT)PROJECT

Page 52

Logging in to wrong dialer

Supervisors inform the agents about their current dialer 3 7 168

No dialing

Long wait time 7

Campaign not setup to dial during the specific time agents try to login

Reboot Dialer

Dialer never comes backup

Loss of production 8

Was shutdown instead of reboot Hardware failure Dialogic was not started with optimum settings CTI Engine threads were not stable when next application was started

Production time is normally communicated to Technical teams before production starts No process control available No process control available No process control available

168

technical teams before they try to login OPS team should be informed if dialer is changed and it should be documented and OPS should acknowledge the receipt of email as well OPS team must ensure that they always inform technical teams if there is any change in production time Shutdown option should be disabled for the user Nothing can be done Technical support teams should be given proper training and their knowledge should be continuously updated regarding the

Afriaz Cheema (Manager Systems and Production)

Jason Oliver(Operations Manager)

168

Nadeem (System Administrator)

112

Applications Failing to start

Dialer is not ready for production 8

64

256

Afriaz Cheema (Manager Systems and Production) Shoib Sakoor (Head of Production)

SIX SIGMA (BLACK BELT)PROJECT

Page 53

Applications were started in wrong sequence One of the applications were not started

112

168

Script Deployment

Script Missing

Agents can't see the script and can't properly communicate with customers Performance impacting as agents can't properly communicate with customers

Wrong Script shown

Script was not deployed on one of the terminal servers Some files were not copied Version number was not updated

Script and files are manually checked on all terminal servers

60

current processes. Checklists should be maintained and followed if a process always follows the same steps. A test agent should also be logged in before production to ensure applications are properly working An automated application should be developed that deploys the script itself

Afaq Ali (Deputy Head of Production)

4 Script version is checked by the person who updates the script

120 An automated application should be developed that updates the script version automatically Afaq Ali (Deputy Head of Production)

96

SIX SIGMA (BLACK BELT)PROJECT

Page 54

Critical identified processes which should be monitored on regular basis according to corresponding recommended actions.
Process Function / Requirements Potential Effects of Failure Potential Causes / Mechanisms of Failure Current Process Controls Root Cause Category RPN

Potential Failure Mode

Recommended Action(s) Before production login a test agent to make sure that dialer applications are up and running Technical support teams should be given proper training and their knowledge should be continuously updated regarding the current processes. Checklists should be maintained and followed if a process always follows the same steps. A test agent should also be logged in before production to ensure applications are properly

Responsibility

Login agents

Agents Stuck on agent application

Can't login

Controller is down and was not restarted

No process control available

288

Jawad Hassan (Analyst Systems and Production)

Procedure Error

Reboot dialer

Applications Failing to start

Dialer is not ready for production

CTI Engine threads were not stable when next application was started

No process control available

256

Afriaz Cheema (Manager Systems and Production) Shoib Sakoor (Head of Production)

Procedure Error

SIX SIGMA (BLACK BELT)PROJECT

Page 55

Update Script

Incorrect script deployed

Missing some call disposition term codes

Term codes were not added

Basic testing is performed before going live

216

Login agents

Agents Stuck on agent application

Can't login

CTI Engine is not properly working

No process control available

216

Apply filter

wrong leads get buffered

Agents talking to wrong customers

Import date of leads not updated

no process controls available

196

Software Crash

Application closed itself

Agents logged out and are in downtime

QA/Testing not performed extensively

No process control available

192

working There should be more focus to improve testing environment and employees should be encouraged to do more and more testing in test environment before going live Before production login a test agent to make sure that dialer applications are up and running Double check the filter with developer and with Ops manager to discuss the result of implementation and avoid requesting filter change himself Before deployment of application, an extensive QA/testing should be performed and

Afaq Ali (Deputy Head of Production)

Change Error

Jawad Hassan (Analyst Systems and Production)

Procedure Error

Zeeshan Jamil (Supervisor Systems and Production)

Change Error

Abdullah (Head of QA)

Dialer Software

SIX SIGMA (BLACK BELT)PROJECT

Page 56

specially stress testing should also be performed Agents kicked out of agent application immediately after they login Agents should be properly given training regarding how to configure the phone before they login Change management system must be properly implemented and every change must be properly documented and approved before actual change is implemented. Change must be verified by supervisor or another person Parameters should be double checked and if possible there should be tools available instead of updating anything from backend

Login agents

Can't start production

x-ten / dial pad is not configured properly

No process control available

192

Jason Oliver(Operations Manager)

Procedure Error

Change dialing parameters

Dialing with wrong parameters

Dialing in wrong time zones

Wrong time zones opened

Normally when the issue arises, parameters are checked to make sure if these were updated correctly or not

150

Asim Zafar (Director IT Operations) Shoib Sakoor (Head of Production)

Change Error

Parameter configuration

Application not starting or crashing again and again

Agents logged out and are in downtime

Wrong parameters applied

Implemented himself checks the parameters

144

Ahmed Usman (Supervisor Systems and Production)

Dialer Software

SIX SIGMA (BLACK BELT)PROJECT

Page 57

System Crash

System never comes backup Software crashes or starts malfunctioning

All resources are in downtime Leads are unnecessarily burned

Hardware failure Stuck channels are not released so rest of the leads are marked as ND

Nothing can be done

144

Hardwares must be continuously updated This needs to be taken care at programming level Compatibility issues must be taken into consideration before updating any software and all stake holders should be informed about the update Time should be properly mentioned either its Pakistan time, US time or UK time

Ehtesham Opel (Manager System Administrator) Abul Asim (Senior Software Engineer/Program Architect)

Facilities Failure

Too much load

No process control available

125

Dialer Software

System Crash

System shutdown

All relevant resources are in downtime

Incompatibility while updating with new software/hardware

Head of production normally checks with the development team about incompatibility issues

120

Afriaz Cheema (Manager Systems and Production) Afaq Ali (Deputy Head of Production)

Facilities Failure

Maintenance

System not available for production

Production cannot be started

Maintenance started on wrong time due to misunderstanding

Normally emails mention the time

120

Munam Khalid (Helpdesk Analyst)

Facilities Failure

SIX SIGMA (BLACK BELT)PROJECT

Page 58

Xbar-R Chart of Downtime Stability Report


Is the process mean stable? Investigate out-of-control subgroups. Look for patterns and trends.
60 UCL=57.42

40
Mean

_ _ X=30.16

20 LCL=2.89 1 3 5 7 9 11 Subgroup 13 15 17 19

Is the process variation stable? Investigate out-of-control subgroups. Look for patterns and trends.
150 100 50 LCL=19.7 0 1 3 5 7 9 11 Subgroup 13 15 17 19 UCL=157.2 _ R=88.5

SIX SIGMA (BLACK BELT)PROJECT

Range

Page 59

Xbar-R Chart of Downtime Summary Report


Is the process mean stable? Evaluate the % of out-of-control subgroups. 0% > 5% 60 Xbar Chart Investigate out-of-control subgroups. UCL=57.42

Yes
0.0%

No
40
Mean

_ _ X=30.16

20 LCL=2.89 1 3 5 7 9 11 13 15 Subgroup 17 19

Comments The process mean is stable. No subgroups are out of control on the Xbar chart. 0

R Chart Investigate out-of-control subgroups. 150 100 50 LCL=19.7 0 1 3 5 7 9 11 13 15 Subgroup 17 19 UCL=157.2

CONCLUSIONS: Process Failure Mode & Effect Analysis (PFMEA), X-bar & R Charts are suitable for monitoring and controlling the system.

SIX SIGMA (BLACK BELT)PROJECT

Range

_ R=88.5

Page 60

SIX SIGMA (BLACK BELT)PROJECT

Page 61