Вы находитесь на странице: 1из 6

SEHAT DIRGANTARA

Komp. BPK II No D-7 Jl. Musyawarah, Kebon Jeruk Jakarta Barat 11530 Indonesia Mobile: 0897 082 8021 Email: dirgantara.sehat@gmail.com Personal Details
Date of Birth Health Nationality Language Known : : : : May 14, 1982 Good, have no physical defects Indonesian English

Profile summary
Highly self-motivated engineer in telecom project with strong technical skills, non technical skills, proven record of accomplished projects, problem-solving and detail oriented. Has more than 5 years experiences telecom related with BTS/Node B installation, test & commissioning. Take a role in the field to perform node B for 3G/UMTS network service as site engineering surveyor, node B 3G/UMTS site implementation engineer and Field Maintenance Engineer. Technical Literate Having good knowledge in GSM 2G/3G network system Have experience installation, commissioning and troubleshooting BTS Siemens, BTS NSN, BSC3i NSN. Have experience commissioning and troubleshooting HiT 7035, 7050, 7070, 7300 and SRALXD). Familiar Map Info 7.0, Visio, MS Office, Internet, Global Positioning System (GPS), Compass, Site Master (Anritsu). Work Experience Oct 20, 2011 Present Position: Front Office Engineer FO Transmission Engineer Regional: Jakarta Responsibility: Responsible for the surveillance of the E&M alarms in GSM & RAN network by OSS. Monitor escalation and manage problem reported in all 2G/3G Radio network fault alarm with OSS Huawei M2000. Monitor escalation and manage problem reported in all 2G Radio network fault alarm with OSS Radio Commander (RC) Siemens. Monitor and escalation transmission fault alarm to related team (Field Maintenance Team or Back Office Team) with Huawei U2000, NSN Net Viewer and TNMS Core/CDM Client NSN. Monitor and support Plan work (PW) and Change Request (CR) activity until finish PT. Huawei Tech. Investment (Under DGE Outsource)

Monitor and support swap activity from NSN site to Huawei site by Rollout Project Team. Create, update/manage and close trouble ticket for any detected problem. Open permit for Rollout Team/Sub Contractors for enter to the site. Escalated customer related issues to the Customer. Call-out the Field Technician/Sub Contractors with a work order for all the faults and activities. Assist the FO shift leader in producing activity report for KPI calculation, shift handover, customer complain and data communication. Support Network Performance Team for check active alarm, log alarm, do performance test and create/manage performance trouble ticket for network performance improvement. Responsible for customer complain related network performance problem. Assist the operation team in process improvement and ongoing development of tools and system. Mar 01, 2011 Oct 19, 2011 Investment Position: TOC Engineer Field Maintenance Engineer Regional Technical Support Regional: Bali Lombok Responsibility: Assistance Regional manager to set up technical support in region. In charge of regional facility maintenance, spare part management, network documentations and quality management To have efficient and documented routines, procedures with all concerned inter working units like different system support units, inter working operators, subcontractors, rollout units, planning and engineering units Responsible for the delivery of Managed Service Projects. Implement effective O & M processes, procedures and establish work standards to manage effective regional operation of facility and spare parts. Ensure service levels are achieved as per agreed SLA to fulfill the Companys mission and customer requirements. To initiate network improvement projects to reduce network outages. Coordination of activities and work schedules of the field personnel in accordance to ongoing projects and activities. To give regular reporting of field maintenance performance and ensure operation and maintenance performance goals are met. Responsible site inspection and PM quality audit in regional. Performs corrective and preventive maintenance of the following telecommunication equipment. Ensure Trouble Ticket (TT) and Preventive Maintenance (PM) progress to match the KPI/SLA target. Responsible second level technical support for subcontractor engineer in region. Perform real-time surveillance for all Transmission equipment. Analyze, correlate, categorize and prioritize faults. Guiding and Coordinating with FLM Engineer to solve the problem. Make sure the stability of Customer Network. To assist and cooperate with related department to achieve the SLA Ability to deal with high demands, workload and emergencies Willingness to be on call and to work at nights PT. Huawei Tech. (Under DGE Outsource)

Dec 10, 2009 Feb 28, 2011 Position: Area Project Coordinator Regional: Makassar

PT. Ohmcell Network Solution Provider

Responsibility: Support NSN Telkomsel Project for Swap TI 2G Modernization in Makassar area. Monitoring Swap TI 2G Modernization in Makassar area for all activities. Ensure Area TI organization follows process, job descriptions and guide lines include in project plan. Manage, coordinate and reporting all Swap TI 2G Modernization activities within assigned zone from TI start until TI BAST acceptance. Scheduling and reporting daily Swap TI 2G Modernization activities. Ensure availability of equipment and materials as per planned rollout in close cooperation with NSN logistic. Ensure QA processes are followed and project KPI target are achieved. Follow up change request for additional works if needed. Provide report to NSN and Management for all Swap TI 2G Modernization activities. Design and execute implementation schedule to achieved target. Budgeting and costing all Swap TI 2G Modernization activities. Integrating and troubleshooting BTS Flexi EDGE. June 1, 2007 May 31, 2009 Position: QC Engineer (Telco Engineer) Outsource) Quality Assurance Quality Site Inspection Quality Health, Safety & Environment (QHSE) PT. Nokia Siemens Networks (Under DYKA, DGE

Regional: Jabotabek, West Java, Central Java, East Java, Bali, Lombok, South Sumatra, Jambi, Padang, Pekanbaru, Riau, Bangka Belitung, Pontianak, Makassar, Biak, Nabire and Jayapura. Responsibility: Inspection the projects roll-out such as Telecom Implementation (TI) and Civil Mechanical Electrical (CME) activities base on NSN Quality Guideline. Assist in the inspection of vendor (audit) supplied and fabricated materials for visible defects and insure compliance with specifications. Investigate assigned specific problem, determine root cause, and ensure corrective action and effectiveness. Support the Project Management by doing Inspection Process Audit (IPA) and Inspection Result Audit (IRA) and reporting the project roll-out activities. Prepared and issue the Quality alert which is not complied with the NSN Quality Management Guideline. Give an awareness and socialization to the project roll-out and subcontractors about Quality and Safety. Work close with Corporate Safety and Safety Officer in implementing the Safety aspect toward all employees and also subcontractors. Make sure site implementation is done properly by subcontractor. Ensure site implementation quality. Give SE input to project preparations. Support start-up team.

June 1, 2006 May 31, 2007 Position: BTS Engineer Regional: Semarang, Central Java

PT. Siemens Indonesia (Under DGE Outsource)

Responsibility: Commissioning, VSWR Measurement, Test Call, Troubleshooting, ATP Siemens Equipment 2G. Cross connection for E1 end to end readiness (software & physical) from node Bs to RNC before integration site. Supporting BTS and TRS team for Installation, Commissioning, Pointing, Crossconnect, prepare site folder, etc. Tower Climbing and MW antenna installation and commissioning. Work close with Corporate Safety and Safety Officer in implementing the Safety aspect toward all employees and also subcontractors. Monitoring and controlling qualified subcontractor status, to ensure the subcontractor fulfill our target and requirement. Ability in drive test analysis and reporting, cluster acceptance testing, networks problem troubleshooting. February 21, 2005 May 31, 2006 Position: Document Controller Incoming Quality Control Document Regional: Jakarta Responsibility: Managing incoming quality control document activities, to ensure the works unit target are achieved. Controlling document status by analyzing and measuring process based on costumer request. Used to make weekly and monthly report altogether presenting Incoming Quality Control Document performance. PT. Siemens Indonesia (Under Hardy & Kee Outsource)

Education
Management Bachelor Degree from Gunadarma University Depok, Jakarta Electrical Engineering Institute Sains and Technology National (ISTN), Jakarta GPA: 2, 99

Training / Courses / Seminar


2008 July 2008 March Introduction to OSH Management System, Risk Management and Job Safety Analysis (SMK3) PT. Sucofindo, Jakarta. Teleconsult Training Standard Operating Procedure (SOP)

Health Safety and Environment (HSE) Work at Height (WAH) Basic Civil Mechanical Electrical (CME) InfratechTraining Centre, Jakarta. 2008 January 2006 August First Aid Training Course PT. Teleconsult Nusantara, Jakarta. Tower Climbing Safety for Working on Top Tower PT. PLN (Persero) Bogor Training Center, Bogor. 2006 December 2005 October 2005 February BSS Installation Procedure Siemens Training Center, Cikarang UMTS System Overview Training Siemens Training Center, Jakarta. GSM System Overview Training Siemens Training Center, Jakarta.

I hereby certify that all the information stated above is true and correct. Should untruths be discovered during my employment, I fully agree to being dismissed for just caused.
RE CW20 - Capacity expansion daily progress report per 18 May 2011.msg