Академический Документы
Профессиональный Документы
Культура Документы
(CESMM)
KAMALALDIN ABD. LATIF JKR. MALAYSIA
31st
MARCH 2010
EQUATORIAL BANGI
CONTENT
OVERVIEW CLASS E EARTHWORK CLASS P ENVIRONMENTAL PROTECTION CLASS G ROADWORKS
CONTRACTOR
DURATION
OVERVIEW CESMM_________________________________________________________________________________________________
O4 BILL of QUANTITIES
Item Description - Describes briefly the work to be executed by the Contractor (the details of work will be described in the Tender Drawing and coverage rule in the Preamble to BQ and the MoM) e.g: Excavate unsuitable material below embankment or below Formation in cuttings as shown in the drawing or as per specification to disposal areas within the R.O.W as approved by the S.O.
Quantities - BQ quantity as a basis for estimating the rate - Final quantity to be remeasured
OVERVIEW CESMM_________________________________________________________________________________________________
O5 PREAMBLE to BQ
- Describes briefly the work to be executed by the Contractor (the details of work will be described in the Tender Drawing and items coverage in the Pramble to BQ and the MoM) e.g: Excavate unsuitable material below embankment or below Formation in cuttings as shown in the drawing or as per specification to disposal areas within the R.O.W as approved by the S.O.
Quantities - BQ quantity as a basis for estimating the rate - Final quantity to be remeasured
OVERVIEW CESMM_________________________________________________________________________________________________
O6 ITEM DESCRIPTION
- Describes briefly the WORK component (not the TASK i.e. how the Work should be done) to be executed by the Contractor - (the details of work will be described in the Tender Drawing and coverage rule in the Preamble to BQ and the MoM) e.g: - Excavate unsuitable material below embankment or below Formation in cuttings as shown in the drawing or as per specification to disposal areas outside the R.O.W as approved by the S.O. - Mild steel bar of nominal diameter 20mm not as: Supply, deliver, cut, bent and fix mild steel bar of diameter 20mm
OVERVIEW CESMM_________________________________________________________________________________________________
O7 MEASUREMENT RULE
Sets out the CONDITION under which the Work will be measured and the METHOD by which the Quantities shall be computed in accordance with paragraph 5.17 Section 5: Preparation of the Bill of Quantities 5.17 : All measurement shall be taken nett otherwise stated in the measurement rules of the CESMM. No allowance shall be made for bulking, shrinkages or wastages. Quantities can be rounded where appropriate but common sense must be applied. The total quantity and the effect on its rounding off must be considered. Where unavoidable, fractional quantities should be given to one decimal place only.
OVERVIEW CESMM_________________________________________________________________________________________________
O8 SPECIFICATION
Gives the requirement of the work wrt material use & method statement
Unsuitable material shall be excavated to such depth and over such area as directed by the S.O
OVERVIEW CESMM_________________________________________________________________________________________________
O9 CONSTRUCTION DRAWING
indicates shapes & dimension - length - breadth - depth as a basis for the Tenderer to calculate the rates for construction the final dimension will be determined base on actual requirement on site
OVERVIEW CESMM_________________________________________________________________________________________________
CLASS E - EARTHWORK
CESMM (UK)
- excavation in stages eg. excavate from 0m to 1.5m depth from 1.5m to 3.0m depth a.s.o - let the Contractor choose the appropriate method of construction - difficulties encountered and loss of productivity associated with increasing depth of excavation to be reflect in the builtup rate - measured whole - item description or drawing should indicate the depth of excavation to facilitate computation of rate by the contractor
CESMM (M)
CLASS E - EARTHWORK
Rule M1 In accordance with Paragraph 5.17, the quantities of earthwork shall be computed nett using dimension from the Drawings with no allowance for bulking, shrinkages or wastages. Where boundaries between different materials are not shown in the Drawings, measurement shall be made on Site.
CLASS E - EARTHWORK
IMPORTED FILL Importing fill materials occur, when CUT (effective) FILL = -ve
DIPOSAL OF EXCAVATED EARTH Disposing of excavated materials occur, when CUT (effective) FILL = +ve
RULE 1
4.0
4.0
Fill Cut
RULE 1
6.0
Fill Cut
RULE 1
1.2
1.5
Balance Cut & Fill Situation 6.0 4.8 To Fill 6 units require 7.5 units Cut - 6.0 units (4.8 units) Imported - 1.5 units (1.2 units)
RULE 1
1.2
1.5
Computation of Filling Rate 6.0 4.8 6.0 m3 @ RM5.00 RM30.00 1.5 m3 @ RM10.00 RM15.00 Fill = RM45.00/6 m3 = RM7.50/m3
CLASS E - EARTHWORK
BACK ISSUES: Defination for ROCK JKR/SPJ/1988 Specification for Roadworks published by Jabatan Kerja Raya, Malaysia Rock shall mean material found in ledges or masses in its original position which would normally have to be loosened either by blasting or pneumatic tools or, if excavated by hand, by wedges and sledge hammers. It shall NOT include material which can be loosened with a track-type tractor with mounted and drawn ripper of the following description:
Class E Earthwork (CESMM)__________________________________________________________________________
ROCK CLASSIFICATION
Totally weathered
THE PROBLEM
THE PROBLEM
On Site: In between the two extreme material on site (earth and rock) we have HARD MATERIAL
which is not been clearly defined not included in the scope of specification which the Contractor has to excavate but not priced accordingly the current practice, it is usually been paid under normal excavation i.e. excavation in earth
Resulting in: Claim by the Contractor due to low productivity for excavation in natural hard material (get paid for earth excavation instead of excavation in rock)
Class E Earthwork (CESMM)____________________________________________________________________________
THE SOLUTION
REDEFINE ROCK ROCK or ARTIFICIAL HARD MATERIAL shall be material that requires the use of either hydraulic rock breaker, pneumatic tools or explosives. ..(CESMM) DEFINE NATURAL HARD MATERIAL NATURAL HARD MATERIAL shall be material other than ROCK and ARTIFICIAL HARD MATERIAL that requires ripping and other specialised equipment. . (CESMM)
HARD MATERIAL/ROCK EXCAVATION shall required one or a combination of the following methods:
Excavation using track excavator exceeding a mass of 44 tones and 321 BHP rating Ripping using a tractor unit of minimum weight of 37 tones and 305 BHP rating and a ripper attached Excavation using pneumatic tools Open blasting Controlled blasting
COMPROMISE
ADDITIONAL DESCRIPTION RULE
Item description for EXCAVATION IN NATURAL HARD MATERIAL and ROCK shall state the method of excavation where appropriate A4
This clause will cater for Designers requirement to dictate the method of construction where specific need prevails
EIA REPORT
(MITIGATION MEASURES)
DESIGNER
DRAWING & SPECS & BILL of QUANTITIES
CONTRACTOR
Class P Environmental Protection & Enhancement (CESMM)______________________________________________________________
OLD PRACTICE
itemised under Preliminaries description of Bill too general, up to the Contractors imagination in determining the coverage required for the Environmental Protection & Enhancement no indication as to what the work items included under this Class allocated sum is Lump Sum (no detailed breakdown of work given)
e.g.
To carry out environmental protection works according to the existing laws and regulations
CURRENT PRACTICE
separate Bill for Environmental Protection & Enhancement work items to be indicated item description has to be clear and concise allocated as Provisional Sum or can be subjected to re-measurement of quantities at the end of contract
ITEMS COVERAGE
7 items coverage:
Appointment of Environmental Officer Preparation of Environmental Management Plan (EMP) Pollution Control Measures Preservation of Flora Preservation of Fauna Environmental Monitoring Programme Environmental Audit
SAMPLE BQ
Code
Unit
Qty.
Rate
Amt.
P1 0 0
APPOINTMENT OF ENVIRONMENTAL OFFICER Appoint an Environmental Officer for the duration of the contract period. PREPERATION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) To prepare the Environmental Management Plan (EMP) according to the guideline produced by the Department of Environment (DOE). POLLUTION CONTROL MEASURES Water Quality Control, Silt Fence Supply and install 1.0m height silt fence including non-woven geo-textile and wooden post with dimension as shown in the drawing or as directed by the S.O. Gabion Wall To construct gabion earth retaining wall of dimension as shown in the drawing using block stones of size 150mm Sediment Basin To construct sediment basin of the dimension: 7m x 4m x 2m 15m x 4m x 2m Silt Trap To construct Silt Trap of the following dimensions: 2m x 3m 4m x 6m
manmonth
P200
sum
P300 P311
m2
P312
m3
P313
nr nr
P314
nr nr
Code P321
DESCRIPTION Air Quality Control,Tyre Washing Facilities Supply portable water jet including operators, water tank and other necessary equipment needed to carry out the cleaning tyres of vehicles at the exits of the worksite Water Browser Truck Supply Browser Truck to carryout water spraying 3 times a day along existing road and near settlement as directed by S.O Lorry Wash Trough To construct Lorry Wash Trough of dimension: 2m x 5m x 250mm deep nr
Unit
Qty.
Rate
Amt.
nr
P322
nr
P323
P331
Noise Control, Noise Barrier Supply and install 1.0m height concrete reflective type noise barrier with dimension as shown in the drawing or as directed by the S.O Vibration Control To carryout vibration control at the following locations: a. Hospital Besar Kuala Terengganu m2
P340
sum
Code P411
DESCRIPTION CONSERVATION / PRESERVATION Preservation of Flora,Floral Survey Report Conduct Flora Survey and prepare 30 copies of Floral Survey Report according to the format as set in Appendix Floral Conservation Plan Prepare Floral Conservation Plan according to the format as set in the Appendix Relocation of Trees a) To relocate the following flora species to the approved location within the construction site: 1. Tongkat Awang 2. Tualang Salak b) To relocate the following flora species to the Arboretum at Pusat Penyelidekan Tumbuhan Hutan di Kuala Berang, Terengganu 1. Kemuning Minyak 2. Kemuning Kuning
Unit
Qty.
Rate
Amt.
sum
P412
sum
P413
nr nr
nr nr
DESCRIPTION Preservation of Fauna Fauna Survey Report Conduct Fauna Survey and prepare 30 copies of Fauna Survey Report according the format as set in Appendix Relocation of Fauna To relocate the following fauna species to Taman Negara Belum, Ulu Perak, Darul Redzuan: 1. Gajah 2. Harimau Conservation of Archeological / Heritage
Unit
Qty.
Rate
Amt.
sum
P422
nr nr
P423