Proof of Concept

Proof of Concept Execution Guide

Product Cost Planning & Actual Costing

Proof of Concept

Table of Contents
1. Product Cost Planning Execution Guide - Proof Of Concept....................4 1.1. Production of Raw Brine Essentials for Planning Cost...............................4

2. POC - Organisation Structure ..................................................................5 3. Creation of Master Records for Production.............................................6

3.1. Creation of Raw Material Masters...............................................................6 3.2. Creation of Finished Good Material Master................................................12 3.3. Creation of Bill of Material ......................................................................15 3.4. Creation of Work Centers........................................................................17 3.5. Creation of Routing.................................................................................18 4. Product Cost Planning-Determining Planned cost per unit .....................21 4.1. Planning Cost Element wise data in Cost Centers. .....................................21 4.2. Viewing Cost Centre Report ....................................................................23 4.3. Planning of activities at Production cost centers.........................................25 4.4. Planning Output of Service Department Activities......................................27 4.5. Calculation of Planned Activity Prices of Production & service Cost Centers & Validation of calculated results............................................................30 4.6. Planning consumption of Service Cost Centers Activity output by Production Cost Centers ....................................................................................37 4.7. Execution of Plan Reconciliation ..............................................................40 4.8. Execution of Plan Distribution Cycle..........................................................48 4.9. Entering Statistical Key Figures for Plan Assessment Cycle........................50

4.10. Execution of Plan Assessment Cycle.......................................................52 4.11. Updating Planned RM/PM purchase prices in Material Master ....................54 4.12. Running & saving of Cost Estimate.........................................................57 4.13. Marking & Releasing of Standard Cost Estimate.......................................61 5. Product Costing- Determining Actual cost per unit .................................66 5.1 Purchase of Raw Material..........................................................................66 5.2 Goods Receipt ........................................................................................68 5.3 Creation of Production Order.....................................................................70 5.4 Releasing, Scheduling & Costing the Production Order................................73 5.5 Goods Issue to Production Order...............................................................78 5.6 Confirmation of Quantity & Activity for Operations ......................................80

Product Costing

Page 2 of 94

Proof of Concept

5.7 Goods Receipt of Finished Goods against Production Order..........................84 5.8 Creation of Sales Order............................................................................87 5.9 Delivery of Finished Goods .......................................................................89 5.10 Picking of goods & Posting of Goods Issue................................................91 5.11 Billing .................................................................................................93

6. Glossary.................................................................................................94

Product Costing

Page 3 of 94

Proof of Concept

1. Product Cost Planning Execution Guide Proof Of Concept


1.1. Production of Raw Brine Essentials for Planning Cost.

Raw Materials Required 1. Raw Salt 2. Sea Water

Operations

Departments Performing Operations (Production Cost Centers)

1. Dissolving 2. Refining

------ ------

Dissolver Refinery

Support Departments (Service Cost Centers) 1. Accounts, 2. Canteen, 3. Facilities, 4. Security.

Expected Output in POC for Planned Cost of Raw Brine in Rs./ KG Name Raw Materials Dissolver Production OHS Refinery Production OHS Service CC Cost Total Cost of Production Total Cost 140.00 26.80 52.71 15.86 235.37 Fixed 0.00 26.80 52.71 15.86 95.37 Variable 140.00 0.00 0.00 0.00 140.00

Product Costing

Page 4 of 94

Proof of Concept

2.

POC - Organisation Structure

The following picture depicts the organization structure used for POC.

Client

218

Company

Controlling Area

Tata Chemicals

TCL

Company Code

Tata Chemicals Ltd (TCL)

Sales Organization

Purchase Organization

Plant

Sales Org TCL

Purchase Org TCLP

Plant SA

Distribution Channels

Distribution Channel TC

Divisions

Division TC

Sales Office

Sales Office 0001 Storage Location WIT

Storage Location

Product Costing

Page 5 of 94

Proof of Concept

3.

Creation of Master Records for Production

3.1.Creation of Raw Material Masters Use The Parameters for Creating Raw Materials Master are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

MM01 Logistics /Material Management/Material Master/Material/Create(General)/Immediately Or Logistics /Production/Master data /Master/Material/Create(General)/Immediately

Field Name Industry Sector Material Type Plant Storage Location

Values Chemical Industry Raw material SA(number) MIT(number)

Product Costing

Page 6 of 94

Proof of Concept

Product Costing

Page 7 of 94

Proof of Concept

Enter

Press Enter Field Name Views Values Basic Data 1, Basic Data2, Purchasing, MRP1, MRP2, MRP3, Accounting 1, Accounting 2, Cost estimate1, Costing 2,

Product Costing

Page 8 of 94

Proof of Concept

Product Costing

Page 9 of 94

Proof of Concept

Field Name Name Basic Unit Measure Material Group Tab Sales: general/plant Availability Check Trans Grp Loading Grp Tab MRP1 MRP Type MRP Controller Lot Size

Values Raw Salt KG SPI1

Values Sea Water L SP11

KP 0006 0003

KP 0006 0003

PD 001 EX(Lot For Lot Order Quantity)

PD 001 EX(Lot For Lot Order Quantity)

TAB MRP 2 Sched Margin Key TAB MRP 3 Availability Check Tab Forecasting Forecast Model
Product Costing

000

000

KP (no Check)

KP (no Check)

N
Page 10 of 94

Proof of Concept

Product Costing

Page 11 of 94

Proof of Concept

Field Name

Values

Values

Tab Accounting 1 Valuation class Price Unit Price Control Tab Cost Estimate 1 With Qty Structure Material origin Check Check Check Check 3000 1 V(moving Average Price) 3000 1 V(moving Average Price)

3.2.Creation of Finished Good Material Master. Use The Parameters for Creating Finished Goods are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code IMG Menu

MM01 Logistics /Material Management/Material Master/Material/Create(General)/Immediately Or Logistics /Production/Master data /Master/Material/Create(General)/Immediately

Product Costing

Page 12 of 94

Proof of Concept

Field Name Industry Sector Material Type Plant Storage Location

Values Chemical Industry Finished goods SA(number) MIT(number)

Product Costing

Page 13 of 94

Proof of Concept

Field Name Material Name Basic Unit Measure Material Group Tab Accounting 1 Valuation class

Values 123 Raw Brine Kg SPI1

7920 (Finished Goods)

Price Unit Price Control

1 S(Standard Price)

Note: For all other views, enter the details as given in 3.1.1 above.

Product Costing

Page 14 of 94

Proof of Concept

3.3.Creation of Bill of Material Use The Parameters for Creation of BOM are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

CS01 Logistics/production/Master data/Bill of Material/Material BOM /Create

Field Name Material No Plant BOM usage

Values 123(Purified Brine) SA(Soda Ash) 1( Production)

Press Enter.

Product Costing

Page 15 of 94

Proof of Concept

Field Name Item Category Component QTY

Values L(Stock Item) 116(Raw salt) 1

Values L(Stock Item) 120(Sea Water) 2

Go to Menu-Header and enter the base quantity (Quantity to which all component quantities in a BOM relate.) Field Name Base Quantity Save the BOM created. Values 1 Kg

Product Costing

Page 16 of 94

Proof of Concept

3.4.Creation of Work Centers Use The Parameters for creation of Work Center are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

CR01 Logistics/production/Master data/Work Centers/Work Center/Create

Product Costing

Page 17 of 94

Proof of Concept

Field Name Work Center Work Center Category Person Responsible Usage Standard Value Key

Values DISSOLVER 001(Machine ) 001 001(Only routings) SAP1

Values Refinery 001(Machine ) 001 001(Only routings) SAP1

3.5.Creation of Routing Use The Parameters for Creation of routing for FG 123 (Purified Brine) are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

CA01 Logistics/Production/Master data/Routings/Routings/Standard Routings/Create

Field Name Material No Plant Press Enter.

Values 123 SA

Product Costing

Page 18 of 94

Proof of Concept

Assign the Operations in Routing as per the details given below:

Field Name Work Center Control Key Base Qty Unit Machine (ACT1) Labour (ACT2) Unit

Values DISSOLVER PP01 10 Kg 10 H

Values REFINERY PP01 10 Kg 40 H

Product Costing

Page 19 of 94

Proof of Concept

Product Costing

Page 20 of 94

Proof of Concept

4. Product Cost cost per unit

Planning-Determining

Planned

4.1. Use

Planning Cost Element wise data in Cost Centers.

The Parameters for Planning Cost Element wise data in Cost Centers are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KP06 Accounting/Controlling/Cost Center Accounting /Planning/Cost & Activity Inputs/Change

Field Name Layout Plan Version From & to Periods Year Cost Center (from to) Activity Type (from - to) Cost Element (from to) Entry 1-101 0 (Zero) 1 to 12 2005 * * *

Values

Free (not Form based)

Click on the Overview Screen Icon (Top Left of the screen)

Product Costing

Page 21 of 94

Proof of Concept

Entries are to be made as per layouts given below for each cost center.

To go to next Dept (i.e. Cost Center) use Black Down Arrow Icon (Third from Top Left).

Product Costing

Page 22 of 94

Proof of Concept

4.2.

Viewing Cost Centre Report

The data prepared on excel as shown below needs to be checked with SAP Report

Cost Center Group ===> Cost Center ===> CE 430000 453000 416300 416400 Cost Ele. Descrpn Salary Maintenance Water Gas TOTAL Own Cost

Production DISSO LVER REFINA RY ACTTS

Service CANT SEC UR FACILI TIES

Total

5000 300 200 1000

8000 900 1500 2000

3000 100

2000 100 200 500

500

100 25

18600 1300 2025 3500 0 25425

6500

12400

3100

2800

500

125

Transaction Code SAP EASY Access

S_ALR_87013611 Accounting/Controlling /Cost Center Accounting /Information System/ Reports for Cost Center Accounting/Plan Actual Comparison/Cost Centers Actual Plan Variance

Field Name Controlling Area Fiscal Year From & To Periods Plan Version Cost Center Group Cost Element Group Execute. TCL 2005 1 to 12 0

Values

Can be given if required Can be given if required

Product Costing

Page 23 of 94

Proof of Concept

Product Costing

Page 24 of 94

Proof of Concept

4.3. Use

Planning of activities at Production cost centers.

The Parameters for Planning of activities (measurable Output) of Production Cost Centers are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KP26 Accounting/Controlling/Cost Center Accounting /Planning/ Activity Output Prices /Change

Field Name Version From Period To Period Fiscal Year Cost Center Activity type Entry 0 1 12 2005 * * Free

Values

To go to next Dept (i.e. Cost Center) use Black Down Arrow Icon (Third from Top Left). Enter the following data:

Product Costing

Page 25 of 94

Proof of Concept

Cost Centre /Field Name Dissolver/ Plan Activity Refinery/ Plan Activity

Values Under Act1 Under Act2 300 250

Product Costing

Page 26 of 94

Proof of Concept

4.4. Use

Planning Output of Service Department Activities.

The parameters for entering Plan Output Values of Service Departments Activities are defined here. (Note: Before starting this activity, it is necessary to complete the Cost Element wise Planning for the relevant service cost centers thru transaction KP06 as explained in 3.1 above.) Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KP26 Accounting/Controlling/Cost Center Accounting /Planning/ Activity Output/Prices/ Change

Field Name Version From Period To Period Fiscal Year Cost Center or CC Group Activity type or Activity Type Group Entry 0 1 12 2005

Values

* Can be given as required * Can be given as required Free

Product Costing

Page 27 of 94

Proof of Concept

To go to next Dept (i.e. Cost Center) use Black Down Arrow Icon (Third from Top Left). Once you arrive at the required production cost Center update as below, Field Name Cost centre Activity Type Plan Activity Values Facilities Cups 125

Product Costing

Page 28 of 94

Proof of Concept

Product Costing

Page 29 of 94

Proof of Concept

4.5.

Calculation of Planned Activity Prices of Production & service Cost Centers & Validation of calculated results

Use The Parameters for Calculation of Planned Activity Prices of Production & Service Cost Centers are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KSPI Accounting/Controlling/Cost Center Accounting /Planning/ Allocations/ Price Calculation

Field Name All Cost Centers

Values Production & Service CC group (To be done separately for each)

Version Period Fiscal Year Test run

0 1 to 12 2005 First in Test Run and then post

Product Costing

Page 30 of 94

Proof of Concept

a) Production Cost Centers

Product Costing

Page 31 of 94

Proof of Concept

Go back. The system will ask whether to post these prices. If clicked on Yes, it will post the prices (even though the report is executed in Test Run).

Product Costing

Page 32 of 94

Proof of Concept

Similarly, execute the planned price calculation for Service cost Centers. b) Service cost Centers

Product Costing

Page 33 of 94

Proof of Concept

Product Costing

Page 34 of 94

Proof of Concept

The Planned prices posted as above should be checked and validated through transaction KP26. The relevant screen Shots are given below:

Product Costing

Page 35 of 94

Proof of Concept

Product Costing

Page 36 of 94

Proof of Concept

4.6.

Planning consumption of Service Cost Centers Activity output by Production Cost Centers

Use The parameters for Planning Consumption of Service Cost Centers Activity Output in Production Cost Centers are explained here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KP06 Accounting/Controlling/Cost Center Accounting /Planning/Cost & Activity inputs/ Change

After you press Enter, system shows, by default, the first layout i.e. 1-101. Click on Next Layout Icon to select the layout 1-102. Field Name Layout Plan Version From & to Periods Year Cost Center (from to) Activity Type (from - to) Cost Element (from to) Entry 1-102 0 (Zero) 1 to 12 2005 * Prod CC Group can be selected * As required * Free (not Form based) Values

Click on Overview Screen Icon (on Top Left corner of the screen)

Product Costing

Page 37 of 94

Proof of Concept

Enter the following values Receiver Cost Centre Sender cost centre Planned Fixed consumption 100 50

Dissolver Refinery

Facilities Facilities

Product Costing

Page 38 of 94

Proof of Concept

Product Costing

Page 39 of 94

Proof of Concept

4.7. Use

Execution of Plan Reconciliation

Plan Reconciliation is executed to identify and reconcile mismatches, if any, between Sender CCs Output and Receiver CCs Input. The procedure for executing Plan reconciliation is explained here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KPSI Accounting/Controlling/Cost Center Accounting /Planning/Planning Aids / Plan Reconciliation

Field Name All Cost Centers Plan Version From & to Periods Year Test Run Details List Select 0 (Zero) 1 to 12 2005

Values

Do in Test Run First Select.

Product Costing

Page 40 of 94

Proof of Concept

Execute.

Product Costing

Page 41 of 94

Proof of Concept

If the Results are correct, then Save it. (System posts the data even if it is executed in Test Run)

Once these results are posted, system will automatically post the Plan Cost of Service Cost Centers to Production Cost Center based on the Activity Consumption planned by them. See the Cost Center Report Screen Shots given below.

Product Costing

Page 42 of 94

Proof of Concept

1. For all Cost Centers

Product Costing

Page 43 of 94

Proof of Concept

2. For Service Cost Center (i.e. Sender)

Product Costing

Page 44 of 94

Proof of Concept

3. For Production Cost Centers (Receivers)

Product Costing

Page 45 of 94

Proof of Concept

NOTE: If there are any differences in Plan Data between the Output of Service Cost Centers & consumption of Production Cost Centers, it will be reflected in the Plan Reconciliation Report. If the data is posted after execution of KPSI, system will automatically adjust the values of output of Service Cost so as to match with consumption by production cost centers. Screen Shots relevant for automatic matching of Sender & Receiver Activity Quantities are given below

Product Costing

Page 46 of 94

Proof of Concept

Product Costing

Page 47 of 94

Proof of Concept

4.8.

Execution of Plan Distribution Cycle Use The procedure for execution of plan Distribution Cycle is explained here. After execution of distribution cycle, the sender cost centers cost will be allocated to receivers cost centers, based on the criteria defined in the cycle. Ideally, the entire cost of sender cost centre should be distributed to the receivers. In distribution, sender cost centers cost is allocated to the receivers in the respective cost elements. Hence, Secondary cost element is not required for distribution. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KSVB Accounting/Controlling/Cost Center Accounting /Planning/ Allocations/Distribution.

First execute in Test Run, analyze the results & then execute to post

Product Costing

Page 48 of 94

Proof of Concept

First execute in Test Run, analyze the results & then execute to post .Click on the number in sender/receiver column to see the details of distribution. For checking whether entire cost of Service CC has been distributed to other cost centers, go to the cost centre report (S_ALR_87013611).

Product Costing

Page 49 of 94

Proof of Concept

4.9.

Entering Statistical Key Figures for Plan Assessment Cycle Use The procedure for entering SKF for executing Plan Assessment Cycle is explained here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

KP46 Accounting/Controlling/Cost Center Accounting /Planning/ Statistical Key Figures/ Change

Give Parameters as per screen shots given below.

Product Costing

Page 50 of 94

Proof of Concept

Product Costing

Page 51 of 94

Proof of Concept

4.10. Use

Execution of Plan Assessment Cycle

The procedure for execution of plan Assessment Cycle is explained here. After execution of assessment cycle, the sender cost centers cost will be allocated to receivers cost centers based on the criteria defined in the cycle. Ideally, the entire cost of sender cost centre should be distributed to the receivers. In assessment, it is allocated through a single line item (secondary Cost element) in the receiver cost centre. Procedure Access the activity using one of the following navigation options: Transaction Code SAP EASY Access KSUB Accounting/Controlling/Cost Center Accounting /Planning/ Allocations/Assessment

Enter the parameters as per the screen shot given below

First execute in Test Run, analyze the results & then execute in production run to post .Click on the number in sender/receiver column to see the details of assessment.

Product Costing

Page 52 of 94

Proof of Concept

The result of the assessment cycle is as shown in the screen shot below. For verification of the resultant output, go to the cost centre report (S_ALR_87013611).

Product Costing

Page 53 of 94

Proof of Concept

4.11.

Updating Planned RM/PM purchase prices in Material Master Use The Parameters for updating the planned RM/PM purchase prices in Material Master are defined here. Prerequisites 1. For all the RM/PM codes, planned purchase prices should be available from Purchase Department. These planned prices should be with reference to price unit in Accounting 1 view of the Material master of the respective material. 2. Before updating the planned price field, it is necessary to know beforehand the costing variant which will be used for annual planning and the planned price field (in RM/PM Material Master) to which it is linked through valuation variant. In our example, we have used Costing Variant ZPC5 in which pricing strategy for materials as per valuation variant (TCL _New Valuation Variant) is Planned Price3 or Moving average Price. The relevant screen shots are given below:

Click on Valuation variant and view the pricing strategy for materials.

Product Costing

Page 54 of 94

Proof of Concept

Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

MM02 Logistics/Materials management/Material Master /Material/Change

Go to Costing 2 View of the material master and put the price in the planned price 3 field. Date should be first date of the year for which plan is to be prepared.

Product Costing

Page 55 of 94

Proof of Concept

Save it & do the same for other raw materials. When the number of RM/PM is large, in that case we can use LSMW for mass upload. However, LSMW needs to be created.

Product Costing

Page 56 of 94

Proof of Concept

4.12. Use

Running & saving of Cost Estimate

The Parameters for running & saving the Cost estimate for the material are defined here. The cost estimate determines what costs go into the standard price for the material. Only those cost components, that are flagged as relevant for stock valuation, are included in the standard price. A material cost estimate is used to calculate the standard price which will be updated in the material master record. Procedure Access the activity using one of the following navigation options: Transaction Code SAP EASY Access CK11n Logistics/Production-Process/Product Cost planning/ Material Costing/Cost Estimate with Qty Structure/Create

Field Name FG Material No. Plant Costing Variant Costing Version

Values 123 SA ZPC5(as mentioned before) 1

Product Costing

Page 57 of 94

Proof of Concept

Product Costing

Page 58 of 94

Proof of Concept

Give the Costing dates, Qty Structure date & Valuation Date & press enter

Product Costing

Page 59 of 94

Proof of Concept

Check the Standard Cost estimate results and verify it with the desired result. Then Save it by clicking on the save icon. The cost estimate must be executed with a costing variant (made for the specific purpose like Annual Planning, Inventory Valuation, and Current Costing etc.) and saved. Once it is released thru transaction CK24, it will be updated in the Master record of the FG/ SFG. Transaction CK24 is explained below.

Product Costing

Page 60 of 94

Proof of Concept

4.13.

Marking & Releasing of Standard Cost Estimate Use The Parameters for Marking & release of the standard Cost estimate for the material are explained here. Once the standard cost estimate is released, the standard price will appear in the Accounting 1 & Costing 2 view of Material Master. To view the cost component structure, double click on the current period field. Procedure Access the activity using one of the following navigation options: Transaction Code SAP EASY Access CK24 Logistics/Production-Process/Product Cost planning/ Material Costing/Price Update

First click on marking allowance to allow release of standard cost for the current period. This is to be done only once at the beginning of the period.

Product Costing

Page 61 of 94

Proof of Concept

Give the costing variant & version

Product Costing

Page 62 of 94

Proof of Concept

Save and go back to the main screen.

Give the material number and execute in test run first. Check it & mark. It will show the future price calculated.

Now go back and click on release. Following screen shot shows the released standard cost estimate.

Product Costing

Page 63 of 94

Proof of Concept

Check and save it. Cross check the updated price in the material master as shown in the screen shot below.

Product Costing

Page 64 of 94

Proof of Concept

(Note: Please consider the values shown in the screen shot as only the reference values. Do not cross check the same with the desired output. The purpose is to show the flow of activities.)

Product Costing

Page 65 of 94

Proof of Concept

5. Product Costing- Determining Actual cost per unit

5.1 Purchase of Raw Material Use The Parameters for Purchase of Raw Materials are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

ME21N Logistics/ Materials Management / Purchasing / Purchase Order / Create / Vendor /Supplying Plant Known.

Field Name Vendor Purchasing Org Purc. Group Company Code Material PO Quantity Net Price Material PO Quantity Plant Net Price Delivery Date

Values 200000 TCLP SPI (SPI Purchase Group) TCL 116 10 KG 18 120 5L SA 2 30.08.2005

Product Costing

Page 66 of 94

Proof of Concept

Press Enter. Under Material Data Tab: Uncheck nfo Update field.

Now Confirm the Net Price entered is same as displayed, else re-enter. Press Enter Save

Product Costing

Page 67 of 94

Proof of Concept

5.2 Use

Goods Receipt

The Parameters for Goods Receipt of Raw Materials are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP EASY Access

MIGO_GR (MIGO) Logistics/ Materials Management / Purchasing / Inventory Management / Goods Movement/ Goods Receipt / Purchase Order / GR for Purchase Order.

Field Name Purchase Order Posting & Document Date

Values 4500000040 25.11.2005

Press enter

Field Name Stor Loc

Values MIT

Check Item OK check box Press Enter Save

Product Costing

Page 68 of 94

Proof of Concept

Product Costing

Page 69 of 94

Proof of Concept

5.3 Use

Creation of Production Order

The Parameters for Creation of Production Order are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

CO01 Logistics/Production/Production Control/order/create/with material

Product Costing

Page 70 of 94

Proof of Concept

Product Costing

Page 71 of 94

Proof of Concept

Field Name Material Production Plant Order Type

Values 123(Raw Brine) SA PP01 (Standard Production Order)

Field Name Total qty Finish Date

Values 10 07.10.2005

Product Costing

Page 72 of 94

Proof of Concept

5.4

Releasing, Scheduling & Costing the Production Order

Release the Order

Product Costing

Page 73 of 94

Proof of Concept

Scheduling

Carry out Costing

Product Costing

Page 74 of 94

Proof of Concept

Product Costing

Page 75 of 94

Proof of Concept

Check the planned cost calculated as follows

Product Costing

Page 76 of 94

Proof of Concept

Check all the tabs on the main screen of the production order & save.

Product Costing

Page 77 of 94

Proof of Concept

5.5
Use

Goods Issue to Production Order

The Parameters for Goods Issue to Production Order are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

MB1A Logistics/Production/Production Control/ Goods Movement/ MB1A Goods Issue

Field Name Document Date Posting Date Movement Type Plant

Values xx.xx.2005 xx.xx.2005 261 SA(number)

Enter the details as given below:

Product Costing

Page 78 of 94

Proof of Concept

Click on the overview to check the issues made

Product Costing

Page 79 of 94

Proof of Concept

Save the document.

5.6
Use

Confirmation of Quantity & Activity for Operations

The Parameters for Confirmation of Quantity & Activity for operations to Production Order are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

CO11N Logistics/Production/Production Control/ Confirmation / Enter/ For Operation / Time Ticket

Product Costing

Page 80 of 94

Proof of Concept

Transaction Code

CO11N

Field Name Order Ope/Acty Confirm type Quantity Confirmation Activity Confirmation Machine Labor

Values 1000045 0030(Dissolver) Final confirmation 10(Order qty)

Values 1000045 0040(Refinery) Final confirmation 10(Order qty)

H 1H

Product Costing

Page 81 of 94

Proof of Concept

Product Costing

Page 82 of 94

Proof of Concept

Check the actual cost debited to the production order in the Cost Report.

Product Costing

Page 83 of 94

Proof of Concept

5.7 Use

Goods Receipt of Finished Goods against Production Order

The Parameters for Creation of Production Order Procedure

is

defined here.

Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

MB31 Logistics/Materials Mgt/Inventory mgt/Goods Receipt/For order

Enter the details as given below

Product Costing

Page 84 of 94

Proof of Concept

Save the document.

Product Costing

Page 85 of 94

Proof of Concept

Go to the Production order cost report and see the cost analysis

Product Costing

Page 86 of 94

Proof of Concept

5.8 Creation of Sales Order Use The Parameters for Creation of Sales Order are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

VA01 Logistics/Sales & Distribution/Sales/Order/Create

Enter the details as given below

Field Name Sold to party PO number & Date Payment terms Item 48 xxx / xx.xx.2005 As required 0010

Values

Product Costing

Page 87 of 94

Proof of Concept

Material Order Qty /UOM Item Category Plant /Storage Location

123 (Material Code) As required TAN As required

Press Enter. Select the Line item & go to Item conditions for Pricing

Enter the Pricing conditions as per example shown below

Product Costing

Page 88 of 94

Proof of Concept

Save the sales order & note the order number.

5.9 Use

Delivery of Finished Goods

Product Costing

Page 89 of 94

Proof of Concept

The Parameters for Creation of Sales Order are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

VL01N Logistics/Sales & Distribution/Shipping & transportation/Outbound delivery/Create/Single document/VL01n

Enter the details as shown in the example below

Product Costing

Page 90 of 94

Proof of Concept

Save & note the delivery number.

5.10 Use

Picking of goods & Posting of Goods Issue

The Parameters for Picking of goods & Post Good issue are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

VL02N Logistics/Sales & Distribution/Shipping & transportation/Outbound delivery/Change/VL02N

Put the delivery number and press enter Go to the Tab for Picking & enter the quantity to be picked

Product Costing

Page 91 of 94

Proof of Concept

Click on Post goods issue. The message will be displayed for Outbound Delivery Saved.

Product Costing

Page 92 of 94

Proof of Concept

5.11 Billing
Use The Parameters for Creation of Billing Document (i.e. Invoice) are defined here. Procedure Access the activity using one of the following navigation options:

Transaction Code SAP Easy Access

VF01 Logistics/Logistics Execution /Outbound Process /Goods Issue for Outbound delivery/Billing/ Billing Document / Create

Enter the Details as per screen shot below.

Save the document & check the messages. If any errors are there, correct the same & then Save. It will generate the Billing Document & also post the same in FI (i.e. release of invoice to accounts). Check the Accounting Document Posted.

Product Costing

Page 93 of 94

Proof of Concept

6.
Sr.No 1

Glossary
Terminology Material Master Meaning / Concept A data record containing all the basic information required to manage a material. This data is sorted according to various criteria including data of a descriptive nature (such as size, dimension and weight) and data with a control function (such as material type and industry sector). In addition to this data, which can be directly maintained by the user, it also contains data that is automatically updated by the system (such as stock levels).

BOM

It is a complete & formally structured list of components of a product. An organizational unit within a controlling area that represents a defined location of cost incurrence. A unit in a controlling area that classifies the activities performed in a cost center Replica of GL Codes in Co. It is a Bridge between FI & CO. It exists only in CO & is used for transferring costs from one CO Object to other. A process used for transferring cost from one CC to another in the same cost element. A process used for transferring cost from once CC to another by using a Secondary Cost Element. It defines one or more sequences of operations for the production of a material

Cost Centre (CC)

Activity Type

Primary cost Element

Secondary Cost Element

Distribution

Assessment

Routing

Product Costing

Page 94 of 94