Академический Документы
Профессиональный Документы
Культура Документы
2 Tools & Techniques 1 Data Gathering and Representation Techniques 2 Quantitative Risk analysis and Modeling Techniques 3 Expert Judgment
ect
-XXX
96
The project cost management plan sets the format and establishes criteria for planning, structuring, estimating, budgeting, and controlling project costs (Section 7.0). Those controls may help determine the structure and/or application approach for quantitative analysis of the budget or cost plan. 11.4.1.4 Schedule Management Plan The project schedule management plan sets the format and establishes criteria for developing and controlling the project schedule (Section 6.0). Those controls and the nature of the schedule itself may help determine the structure and/or application approach for quantitative analysis of the schedule. 11.4.1.5 Organizational Process Assets The organizational process assets useful to Perform Quantitative Risk Analysis process are Information on prior, similar completed projects, Studies of similar projects or technology or process by risk specialists, and Risk databases from industry or proprietary sources.
-XXX
97
11.4.2.1 Data Gathering and Representation Techniques a. Interviewing. Interviewing techniques draw on experience and historical data to quantify the probability and impact of risks on project objectives. The information needed depends upon the type of probability distributions that will be used. For instance, information would be gathered on the optimistic (low), pessimistic (high), and most likely scenarios for some commonly used distributions. Examples of three-point estimates for cost are shown in Figure 11-13. Additional information on three point estimates is in Estimate Activity Durations (Section 6.4.2.4) and Estimate Costs (Section 7.1.2.5). Documenting the rationale of the risk ranges and the assumptions behind them are important components of the risk interview because they can provide insight on the reliability and credibility of the analysis.
Range of Project Cost Estimates WBS Element Design Build Test Total Project Low Rs. 5 M Rs. 15 M Rs. 10 M Rs. 30 M Most Likely Rs. 6 M Rs. 20 M Rs. 12 M Rs. 38 M High Rs. 8 M Rs. 25 M Rs. 20 M Rs. 53 M
Interviewing relevant stakeholders helps determine the three-point estimates for each WBS element for triangular, beta or other distributions. In this example, the likelihood of completing the project at or below the most likely estimate of $41 million is relatively small as shown in the simulation results in Figure 11-16 (Cost Risk Simulation Results). Low Most Likely High Figure 11-13. Range of Project Cost Estimates Collected During the Risk Interview b. Probability distributions. A smooth continuous curve of probability distributions, used extensively in modeling and simulation (Section 11.4.2.2) shows the uncertainty in values i.e. inaccurate values such as durations of schedule activities and costs of project components. In such cases we can take nearest suitable but definite values to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree. A sample of widely used continuous distributions are shown in Figure 11-14. These distributions depict shapes that are compatible with the data typically developed during the quantitative risk analysis. Uniform distributions can be used only if there is no obvious
98
value that is more likely than any other between specified high and low bounds, such as in the early concept stage of design.
11.4.2.2 Quantitative Risk Analysis and Modeling Techniques Commonly used techniques include both event-oriented and project-oriented analysis approaches including: a. Sensitivity analysis. Sensitivity analysis helps to determine which risks have the most potential impact on the project. It examines the extent of uncertainty of each project element affecting the objective under examination when all other uncertain elements are held at their baseline values. One typical display of sensitivity analysis is the tornado diagram, which is useful for comparing relative importance and impact of variables that have a high degree of uncertainty to those that are more stable. b. Expected monetary value analysis. Expected monetary value (EMV) analysis is a statistical concept that calculates the average outcome for uncertain scenarios (i.e., analysis under uncertainty). The EMV of opportunities will generally be expressed as positive values, while those of risks will be negative. EMV requires a risk-neutral assumption, neither risk averse, nor risk seeking. EMV for a project is a numerical product of the value and probability of occurrence and adding the products together. A common use of this type of analysis is in decision tree analysis (Figure 11-15).
c. Modeling and simulation. A project simulation uses a model that translates the specified detailed uncertainties of the project into their potential impact on project objectives. Iterative simulations are typically performed using the Monte Carlo technique. In a simulation, the project model is computed many times (iterated), for different input values (e.g., cost estimates or activity durations) chosen at random. A probability distribution (e.g., total cost or completion date) is calculated from the iterations. For a cost risk analysis, a simulation uses cost estimates. For a schedule risk analysis, the schedule network diagram and duration estimates are used. The output from a cost risk simulation is shown in Figure
99
11-16. It illustrates the respective likelihood of achieving specific cost targets. Similar curves can be developed for schedule outcomes. 11.4.2.3 Expert Judgment Experts should have relevant, recent experience. Expert judgment is required to identify potential cost and schedule impacts, to evaluate probability, and to define inputs (such as probability distributions) into the tools. Expert judgment also comes into play in the interpretation of the data. Experts should be able to identify the weaknesses of the tools as well as their relative strengths. Experts may determine when a specific tool may or may not be more appropriate for or suitable to the organizations capabilities and culture.
-XXX
100
101