Вы находитесь на странице: 1из 6

Daily Construction Report(DCR)

DCR # : 230 DCR Date : Thursday, February 02, 2012 Recording Date : 3-Feb-12

To Supervision Consultant :
Temp

From Contractor : Weather


Bright Sun

15
Wind
Rain Dust

Humidity
High
Dry Moder Humid

Clear

Overca st

Still

Moder

MACHINERY USED
Augering Machine Size No. On Site Hrs Hydraulic Placing Boom Bar bending Machine Bar cutting Machine Elect. Wood Saw Bull Dozer Compressor Concrete Pump Mobile Crane Tower Crane Dewatering pump

Dump Truck Size No. On Site Hrs

6-Wheel

Dumpers

Excavator

Bob cat

Generator

Grader

Half Lorry

Hoist

Jack hammer Size No. On Site Hrs Wheel Loader Size No. On Site Hrs

Plate Compactor

Roller Compactor

Total Station

Tractor

Trailer

Transit Concrete Mixer

Vibrator

Water Pump with Water Tank

Welding Machine

1
8

4
8

JCB

INDIRECT MAN POWER (Indicate P for part time)


Project Manager No. On Site 1 Elect. Eng. No. On Site 2 Plumb/FF Eng. 1 HVAC Eng. 1 Project Engineer Senior Engineer Project Coordinator 1 QA/QC Eng. 1 Admin Staff 2 Secretery 1 Architect 1 Quantity Surveyor 1 Scheduler 1 Draftsman 2 Site Eng. 4 Safety officer Safety Helper 1 2 Srtuctural Eng. Total 10 Total 12

Grand Total Indirect Manpower

22

DISTRIBUTION

KEO(A/E)

Projacs(CM)

Owner

NASA Construction Gen. Trad. and Cont. Co. W.L.L

1 of 6

Daily Construction Report(DCR)


DIRECT MAN POWER (P for part time)
Civil Foreman No. On Site 4 Carpenter Skld. No on site 30 Mason Skld. No on site 4 Fire System Skld. No on site 4 Ceramic Skld. No on site Pre-cast Skld. No on site Tiler Skld. No on site Concrete casting Skld. No on site 2 Help. 2 Skld. Help. Skld. Help. Skld. Help. Help. Skld. 8 Labour Help. 12 Site office Maint. Skld. Help. Skld. Help. False Ceiling Skld. Help. Skld. Glazing Help. Skld. 11 IT Labors Help. Help. Skld. Help. 2 Skld. 7 Stones Help. Help. 2 HVAC Help. 3 Skld. 8 Aluminium Skld. Help. Skld. 20 Plasterer Help. 14 Skld. Help. 10 Skld. 20 Joiner Help. Skld. 3 Pipe Fitter Help. 4 Painter Help. 8 Skld. Elect. Foreman 2 Plumb/FF Foreman 2 Steel Fixer Help. 10 Skld. 2 Electrician Help. 3 Skld. 7 Marble Help. HVAC Foreman 2 Land surveyor Store Keeper 1 Welder Help. 1 Guards 2 Machine Operator 1 Driver 4 Total 19

Water Proofer Skld. 2 Plumber Help. 4 Help.

Total 74

Total 23

Total 28

Total 28

Total 25

Total 20

Total 4

Grand Total - Direct Man Power MATERIAL DELIVERED TO THE SITE Quantity Unit

221 Origin/Manufacturer

Sr. No:

Description

SITE SAFETY
We have inspected the works, working area, procedures and practices and have found the following items are satisfactory with regard to safety precautions
Electrical(Temp Light, Temp. Power, Generators, etc.) Access (Ladder tied-off, walk ways clear, etc.) Temporary works (scaffolding, shoring, hoists, rubbish chutes, etc.)

Equipment (excavator, tower & mobile cranes, loaders lifts, etc.) PPE (All personnel provided with personal protective equipment compliant to safety standards and codes. and informed of emergency management procedures) Warnings at hazard areas (pits, holes, tripping hazards, stair Provisions for first aid stocked landing, floor and roof edges, etc.)

NASA Construction Gen. Trad. and Cont. Co. W.L.L

2 of 6

Daily Construction Report(DCR)


DCR # 230 DAILY ACTIVITIES Location Zone 04 Zone 03 Zone 02 Zone 01
Task activity CCS ID

DCR Date:

Thursday, February 02, 2012 % of completio n

Start Date

Finish Date

Remarks

Basement-02(-7.00)

Basement-01(-3.50)

Finishes

Zone 04 Zone 03 Zone 02 Zone 01

Finishes

B2F-F170 22-Dec-11 B2F-210 26-Nov-11

29-Jan-12 14-Jan-12

75% 34%

NASA Construction Gen. Trad. and Cont. Co. W.L.L

3 of 6

Daily Construction Report(DCR)


DCR # 230 DAILY ACTIVITIES Location Zone 04 Zone 03 Zone 02 Zone 01
Task activity CCS ID

DCR Date: Start Date Finish Date

Thursday, February 02, 2012 % of completio n

Remarks

Ground floor (0.00)

Finishes

Zone 04 Zone 03 Zone 02 Zone 01

First floor (+3.50)

Finishes

NASA Construction Gen. Trad. and Cont. Co. W.L.L

4 of 6

Daily Construction Report(DCR)


DCR # 230 DAILY ACTIVITIES Location Zone 04 Zone 03 Zone 02 Zone 01
Task activity CCS ID

DCR Date: Start Date Finish Date

Thursday, February 02, 2012 % of completio n

Remarks

Second floor (+7.00)

Third floor (+10.50)

Finishes

Zone 04 Zone 03 Zone 02 Zone 01

Finishes

NASA Construction Gen. Trad. and Cont. Co. W.L.L

5 of 6

Daily Construction Report(DCR)


DCR # 230 DAILY ACTIVITIES Location Zone 04 Zone 03 Zone 02 Zone 01
Task activity CCS ID

DCR Date: Start Date Finish Date

Thursday, February 02, 2012 % of completio n

Remarks

Fourth floor (+14.00)

Zone 01 Zone 02 Roof floor (+17.50) Zone 03 Zone 04

Remarks

KEO(A/E) Site Engineer's Signature :

Finishes

Finishes

NASA Construction Gen. Trad. and Cont. Co. W.L.L

6 of 6

Вам также может понравиться