OBJECTIVE
LV CABLES VOLTAGE DROP (RUN/START) IS THE MAIN CRITERIA (R cosfi + X sinfi) 100 L I DV = ---------------------------------------- (%) V1
where: V1 V1 V R X Cosfi Sinfi L I = = = = = = = = = V / 3 for 3-ph system V / 2 for 1-ph system. line to line voltage of the system (V) cable electrical resistance at rated operating temperature (ohm/km) cable reactance (ohm/km) power factor of the line current corresponding sinus line length (km) line current (A)
TRANSFORMER SIZING
HV/LV distribution transformers power rating (in a radial system ) shall be equal or greater than:
FAULT LEVEL
Simple Formula To Calculate the Short Circuit Power at the secondary side of a Transformer (considering infinite source on Primary side) Pcc = Where Pcc An ucc An / ucc is the Short Circuit Power at the Trafo. Secondary side in MVA is the Rating of the Transformer in MVA. is the Per unit impedance of the Trafo.
THE CALCULATIONS ARE PERFORMED USING THE SOFTWARE ETAP-POWER ETAPSTATION - ELECTRICAL TRANSIENT ANALYSER PROGRAM, FROM OTI OPERATION TECHNOLOGY, INC. FOR LOAD FLOW STUDIES, NEWTON RAPHSON METHOD IS UTILIZED. SHORT CIRCUIT CALCULATIONS USED TO VERIFY EQUIPMENT RATINGS IEC909 STD. IS USED.
110kV
REAL POWER FLOW REACTIVE POWER FLOW etc ARE WITHIN LIMITS ??
SOURCE
20000A
L O A D
UPON TO INTERRUPT FAULT CURRENTS HIGHER THAN THEIR INTERRUPTING RATINGS, DISASTROUS CONSEQUENCES CAN FOLLOW.
SOURCE
3 PHASE FAULT
30000A 30000A
L O A D
THE CALCULATIONS ARE PERFORMED USING THE SOFTWARE ETAP-POWER STATION ETAPELECTRICAL TRANSIENT ANALYSER PROGRAM, FROM OTI OPERATION TECHNOLOGY, INC.
TRANSFORMER 110kV
DETERMINE WHETHER THE MOTOR WILL START SATISFACTORILY & COME UPTO RATED SPEED.
11kV
IF SYSTEM VOLTAGE DROPS DOWN TO <75%, LOSS OF ALL MOTORS AND OTHER SENSITIVE LOADS MAY LARGE MOTOR OCCUR.
THE STUDY IS PERFORMED USING THE SOFTWARE ETAP-POWER STATION ETAPELECTRICAL TRANSIENT ANALYSER PROGRAM, BY OTI OPERATION TECHNOLOGY, INC. (UNDER DEVELOPMENT)