Вы находитесь на странице: 1из 87

Airborne Geophysical Survey South Kimberley, Western Australia Project 1149

Surveyed January - September 2008

Survey Operations and Logistics Report


Prepared for

Survey Flown by:

GPX Surveys Pty Ltd Job Number 2289

GENERAL SURVEY INFORMATION .......................................................................................................3 1.1 1.2 1.3 INTRODUCTION ....................................................................................................................................3 SURVEY SUMMARY ..............................................................................................................................3 SURVEY PERSONNEL ...........................................................................................................................5

SURVEY SPECIFICATIONS.....................................................................................................................6 2.1 2.2 SURVEY MAPS ....................................................................................................................................6 SURVEY SPECIFICATIONS...................................................................................................................10

EQUIPMENT SPECIFICATIONS ............................................................................................................12 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 SURVEY EQUIPMENT SUMMARY ..........................................................................................................12 DATA ACQUISITION EQUIPMENT..........................................................................................................13 MAGNETOMETER PROCESSOR ...........................................................................................................14 MAGNETOMETER SENSOR .................................................................................................................15 FLUXGATE MAGNETOMETER ..............................................................................................................15 SPECTROMETER ................................................................................................................................16 BAROMETRIC PRESSURE SENSOR ......................................................................................................16 RADAR ALTIMETER ............................................................................................................................16 DGPS RECEIVER ..............................................................................................................................17 BASE MAGNETOMETER ......................................................................................................................17

EQUIPMENT CALIBRATIONS AND DATA ACQUISITION CHECKS ..................................................21 4.1 4.2 4.3 4.4 4.5 4.6 DYNAMIC MAGNETOMETER COMPENSATION .......................................................................................21 HEADING ERROR CHECK ...................................................................................................................29 SYSTEM PARALLAX TESTS .................................................................................................................30 PRE-SURVEY RADIOMETRIC CALIBRATION TESTS................................................................................31 DAILY RADIOMETRIC SYSTEM TESTS ..................................................................................................32 TIME SYNCHRONISATION....................................................................................................................34

DATA VERIFICATION AND PRELIMINARY PROCESSING.................................................................35 5.1 5.2 DATA VERIFICATION AND CHECKS ......................................................................................................35 DATA ARCHIVES ................................................................................................................................36

FINAL PROCESSING .............................................................................................................................37 6.1 6.2 6.3 FINAL MAGNETIC DATA PROCESSING .................................................................................................37 FINAL RADIOMETRIC DATA PROCESSING ............................................................................................38 FINAL ELEVATION DATA PROCESSING.................................................................................................42

FINAL DELIVERABLES .........................................................................................................................45 7.1 FINAL GRIDS AND DATA PRODUCTS ....................................................................................................45

MAP IMAGES..........................................................................................................................................46 8.1 8.2 8.3 8.4 8.5 8.6 FLIGHT PATH.....................................................................................................................................46 DIGITAL TERRAIN MODEL ...................................................................................................................46 TOTAL MAGNETIC INTENSITY ..............................................................................................................47 TOTAL MAGNETIC INTENSITY 1VD ......................................................................................................47 RADIOMETRIC TERNARY CMY COLOURS ............................................................................................48 RADIOMETRIC TERNARY RGB COLOURS ............................................................................................48

CONTRACTOR INFORMATION.............................................................................................................49

APPENDIX A: LOCATED DATA FORMAT AND PROCESSING SPECIFICATIONS ...................................50 APPENDIX B: WEEKLY PRODUCTION SUMMARY .....................................................................................54

1 GENERAL SURVEY INFORMATION


1.1 INTRODUCTION In January 2008, GPX Airborne commenced a fixed wing airborne magnetic and radiometric survey for Geoscience Australia in the Kimberley region, Western Australia. The survey was flown using a Cessna 210 fixed wing aircraft with registration VH-KWW. This report summarises the procedures, details and equipment used by GPX Airborne in the acquisition, verification and processing of the airborne geophysical data. Client: GPX Project Number: Survey Area: Field Bases (WA, 2008): Kimberley Hotel, Halls Creek Fitzroy River Lodge, Fitzroy Crossing Kimberley Hotel, Halls Creek Fitzroy River Lodge, Fitzroy Crossing Derby Boab Inn, Derby Kimberley Hotel, Halls Creek VH-KWW Radiometric Calibrations: Pad calibrations Carnamah Range Test Flight Aircraft and cosmic background test flight Mobilisation: Production: Demobilisation: Line km surveyed: 1.2 SURVEY SUMMARY 23rd October 2007 4th January 2008 22nd January 2008 17th 23rd January 2008 24th January 3rd October 2008 4th October 2008 166,588.6 km 17th January 3rd April 3rd April 14th May 14th May 31st July 31st July 2nd August 2nd August 20th August 20th August 3rd October Geoscience Australia 2289 Kimberley SE and Kimberley SW, WA

Aircraft equipment installation on VH-KWW was carried out at Jandakot airport in October 2007 and the radiometric pad calibrations were conducted in Bankstown NSW in October 2007. Radiometric equipment calibration flights were carried out during January 2008 at Carnamah test range and aircraft background and cosmic test flights were flown at high altitude over the Indian Ocean near Perth. On 17th January 2008 the crew arrived in Halls Creek. The aircraft arrived on 23rd January. On 24th January a reconnaissance flight,

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 3 of 87

compensation box flight and the first production flight was flown. The final flight was on 3rd October 2008. Data acquisition was monitored in the aircraft and preliminary data checks were performed after each flight at the field bases. At the end of each days flying all data was sent back to the offices of GPX Surveys for further processing and review. Throughout the survey system stability and continuity had been monitored. During the survey there were 17.5 days lost due to weather. There was an additional 51.0 days down time during the survey due to scheduled and unscheduled aircraft and equipment maintenance. Thirty (30.0) of these days were for standard hundred and fifty hurly maintenance. Between 24th August and 23rd September 2008 flying was suspended due to mustering in the survey area. The aircraft was unable to fly over Ellendale mine due to regular blasting taking place. This affected lines 300940 300991, 301130 301132 and 301150 301161.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 4 of 87

1.3

SURVEY PERSONNEL

The following personnel were involved on this project: Airborne Operations Manager: Project Manager: Bob Blizzard Don Copley Liam Parry Shane Hulme Michael Pritchard Operators: Raphael Fisher Dean Reynolds Donna Donavan-Hicks Jeff Ibbotson Tom McLeod Phil Kitto Ian Brown Tim Cousin Russell Donavan-Hicks Final Data Processing: Technical Support: Cathy Car Bob Taylor Mike Barrett Joe Kita Survey Pilots: Chris Hurst Steve Helliwell Guy Nash Ash Mangos Mike Nelson Vincent Wong Chase Legasse

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 5 of 87

2 SURVEY SPECIFICATIONS
2.1 SURVEY MAPS

Overview Map The following map provides an overview of the planned survey area.

Figure 1: Map of the planned survey area.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 6 of 87

Detail Maps Detailed maps of the planned survey areas are shown below.

Figure 2: Map of the south west survey.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 7 of 87

Figure 3: Map of the south east survey.

1:250,000 sheet series covered The following 1:250,000 Australian mapping series maps were in part covered by this survey:

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 8 of 87

1:250,000 Sheet Name Lennard River Lansdowne NoonKanbah Mount Ramsay Crossland Mount Bannerman Charnley Mount Elizabeth Yampi Derby Dixon Range Gordon Downs Billiluna

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 9 of 87

2.2

SURVEY SPECIFICATIONS

Job Specifications The following are the flying specifications, equipment sample rates and line specifications for the survey: Flying Specifications Minimum line length: Nominal ground clearance: 5000 metres 60 m

Sample Rates Magnetometer: Altimeter: Base magnetometer: Spectrometer: 10 Hz 1 Hz 1 Hz 1 Hz

Line Specifications Both Survey Areas Traverse line spacing: Traverse line direction: Traverse line numbers: 400m 000 and 180 300010 304050 (SW Area) 100010 104040 (SE Area) & 200020 204070

Tie line spacing: Tie line direction: Tie line numbers:

4000 metres 090 and 270 317010 317430 (SW Area) 117010 117280 (SE Area) & 217010 217440

Note: The last digit in the traverse and line numbers indicates the attempt number where 0 is the first attempt and 1 is the second attempt, etc

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 10 of 87

Boundary Coordinates The following coordinates are in GDA94 MGA52 and define the survey areas:

South West Kimberley


Point 1 2 3 4 5 6 7 8 9 10 11 12 Easting 20594 160297 136114 136488 164354 164210 180904 183203 130354 129293 76269 21922 Northing 8114933 8117678 8105173 8082615 8082789 8094661 8094927 7951862 7950909 8006312 8005238 8058049

South East Kimberley


Point 1 2 3 4 5 6 7 8 9 10 11 Easting 180904 186805 187055 221573 221787 268435 267810 340320 342589 185093 184136 Northing 8094927 8095017 8078617 8078815 8063217 8063805 8119153 8119834 7843159 7841093 7896479

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 11 of 87

3 EQUIPMENT SPECIFICATIONS
3.1 SURVEY EQUIPMENT SUMMARY Aircraft installation was done in October 2007. System tests and calibrations were conducted in October 2007 and January 2008. The following equipment was used in the survey. Survey Platform: Data Acquisition and Survey System: Magnetometer Processor: Magnetometer Sensor: Fluxgate Magnetometer: Magnetic Base Stations: Spectrometer: Temperature and Humidity Sensor: Barometric Pressure Sensor: GPS and DGPS Receiver: Radar Altimeter: In-field Computer: In-field Software: Cessna 210 (VH-KWW) Pico Envirotec AGIS PC104 Pico Envirotec MMS-4 Geometrics G-822A Cesium Vapour Billingsley Ultra Miniature TFM 100G2 GEM GSM-19W Overhauser Exploranium GR820 (32 litre crystal) Vaisala HMP233 Vaisala PTB220 CSI DGPS Max Collins ALT-50A Toshiba Notebook ChrisDBF, GPX custom software

Figure 4: Cessna 210 with registration VH-KWW.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 12 of 87

3.2

DATA ACQUISITION EQUIPMENT

The data acquisition console is a Pico Envirotec AGIS PC104. This is a versatile multifunction system that is capable of operation in many different configurations, depending on platform type, navigation and system requirements. For this survey the AGIS PC104 was used for navigation and flight control, data recording, real-time monitoring of magnetic data and data retrieval. Navigation and Flight Control The AGIS PC104 is used to guide the aircraft on a pre-defined flight plan that can be generated in UTM or Latitude/Longitude coordinates. The pre-defined flight plan can be designed to file prior to the start of the project, entered or altered in the AGIS system or delineated on-the-fly e.g. while in the air flying the boundary and entering corner coordinates. Co-ordinates can only be entered in the WGS84 datum system, this has been implemented to avoid confusion and eliminate possible conversion errors. Normal survey altitude and ground speed, with pre-set tolerances are also entered. The pilot display consisted of a 2-line strip display or more comprehensive Pilot Guidance Unit (PGU). The strip display is driven directly from the AGIS PC104 console; whereas the PGU is a self-contained computer system that is capable of more demanding navigation functions such as drape flying using a pre-programmed altitude grid. The desired flight line is selected from the operator interface, which will either be a keyboard or touch-screen. Data Recording The AGIS PC104 relates all acquired data to the instant position from the GPS receiver and records the collected data to three separate data files. The data is recorded in compressed binary format, to a commercial solid-state hard disk. The flight path file is recorded from AGIS program start-up to shutdown and cannot be turned off by the operator. It contains position, timing, altitude and basic data. The data file is recorded whenever the acquisition system is On-line. It contains all navigation data plus enabled data. The raw data file, when enabled and supported by the GPS receiver in use, contains raw GPS data necessary for post-flight position correction. It is recorded from AGIS program start-up to shutdown. Real-time Data Display and Status Monitoring The AGIS displays flight path and geophysical data as it is acquired aiding the data quality control and real time navigation guidance. The user is presented with graphical representations of the survey area, flight lines, navigation status, and sensor data.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 13 of 87

Several other status indications are also provided which will either change state indicating a major system malfunction, such as a magnetometer failure, or will change state during normal operation, indicating data being written to a file etc.

Figure 5: AGIS real-time data and status display.

Data Retrieval The AGIS PC104 provides the facility to transfer the recorded data from the internal solidstate disk to compact flash media immediately following the completion of the survey flight. The data is then transferred from the compact flash media to the field laptop. Recorded data is not deleted from the main disk until this retrieved data has been verified error free. 3.3 MAGNETOMETER PROCESSOR

The magnetometer processor is a Pico Envirotec MMS-4 Magnetometer Processor. This is an advanced frequency-measuring device that can support four continuous signal magnetometers (Cs, He, K). It is a hardware-software designed system, exhibiting simplicity, easy interfacing and substantial versatility. Magnetometer readings are synchronized with the PPS (Pulse Per Second) signal derived from the GPS for accurate timing. The MMS-4 contains 8 channels of analog differential inputs. The first 4 analog channels are sampled synchronously with MMS-4 at up to 50 samples per second. The remaining 4 analog channels are sampled at 10 samples per second. Analog data is integrated into the magnetometer data stream. The magnetic values and GPS time is recorded by a TM-6 magnetometer.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 14 of 87

Specifications Input: Coaxial - Larmour signal over DC Power Supply Resolution: Sampling rates: Dynamic range: Synchronization: 0.0002 nT (Gamma) = 0.2 picoTesla 5, 10, 20, 25, 50, 100 Hz 15,000 to 100,000nT GPS PPS (Pulse Per Second)

3.4

MAGNETOMETER SENSOR

The magnetometer sensor is a Geometrics G-822A, which employs an optically pumped cesium-vapour atomic magnetic resonance system that functions as the frequency control element in an oscillator circuit. Specifications Operating Range: Sensitivity: 20,000 100,000 nT Typically 0.002 nT P-P at a 20Hz sample rate Heading Error: Output: 3.5 FLUXGATE MAGNETOMETER < 0.15 nT over entire 360 Larmour frequency, 3.498572 Hz/nT

The fluxgate magnetometer is a Billingsley Ultra Miniature TFM 100G2. This unit is a low noise, high sensitivity unit, packaged into a compact housing. An analog DC output voltage is produced for each of the measured X, Y and Z orthogonal components of the current magnetic field. Specifications Axial Alignment: Sensitivity: Noise: Output: Orthogonality better than 1 100V / nT 20pT RMS / Hz @ 1Hz 100T = 10V

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 15 of 87

3.6

SPECTROMETER

The spectrometer is an Exploranium GR820 system. The unit comprises of 2 detector crystal packs which give a total volume for detection of 32 litres. The spectrometer employs automatic gain stabilisation control to eliminate the need to heat the detectors. Signal processing automatically perform digital gain control to the individual crystal spectra, ensuring the summed spectrum is stable. Specifications Sensitivity: Maximum count rate: Detector volume: Detector weight: 3.7 BAROMETRIC PRESSURE SENSOR 0 3.0 MeV 100,000 counts/sec 16.7 Litres (each) 83.9 kgs (each)

The barometric pressure sensor is a Vaisala PTB220. The unit provides both a digital RS232 output and Analogue voltage or current output directly proportional to the measured Barometric Pressure. The unit is a Class A commercial grade device housed in a rugged aluminium enclosure. Specifications Range: Resolution: Accuracy at +20C: 3.8 RADAR ALTIMETER 500 1100 hPa 0.01 hPa 0.1 hPa

The radar altimeter is a Rockwell Collins ALT-50A two-antenna unit operating at a centre frequency of 4300MHz. The voltage output to the data system is directly proportional to the aircraft flying height with an output characteristic of 20mV/ft up to 500ft, then 10.4V + 3mV/ft above 500ft. Specifications Accuracy: 3ft - 0 to 150ft range 2% of indicated altitude 150-500 ft 3.5% of indicated altitude 500-2000 ft Measurement Rate: 10Hz minimum

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 16 of 87

3.9

DGPS RECEIVER

The DGPS receiver is a CSI DGPS MAX, which is a 12-channel combined GPS/DGPS unit. The DGPS MAX is able to use differential corrections received through an internal WAAS demodulator, VLF beacon receiver, or the OmniSTAR DGPS Service. The DGPS position data was used for aircraft navigation and for processing the aeromagnetic data. Specifications GPS Position update rate: GPS Input frequency: DGPS Update rate: DGPS Solution Used: Antenna: 3.10 BASE MAGNETOMETER Diurnal activity was monitored using portable GEM GSM-19W Overhauser magnetometers and sampled at 1 Hz. The unit has a built-in GPS receiver. Specifications Type: Resolution: Sensitivity: Absolute Accuracy: Dynamic Range: Sampling Rate: Data Storage: Data Retrieval: Overhauser Magnetometer 0.01 nT 0.02 nT 0.1nT 10,000 to 120,000 nT 1 hour to 5 Hz Internal memory Up to 115,200bps serial transfer 5Hz L1 Typically every 6 seconds OmniSTAR VBS Fugro L1/Differential Wideband

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 17 of 87

Base Station Location Halls Creek The primary base station at Halls Creek was located near the air strip. Location Coordinates: Datum: 018.2333584S 127.6669168E WGS84

Figure 6: Base magnetometer location (image courtesy of Google Earth).

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 18 of 87

Fitzroy Crossing The primary base station at Fitzroy Crossing was located near the air strip. Location Coordinates: Datum: 018.1781782S 125.5627280E WGS84

Figure 7: Base magnetometer location (image courtesy of Google Earth).

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 19 of 87

Derby The primary base station at Derby was located near the air strip. Location Coordinates: Datum: 017.3656406S 123.6697823E WGS84

Figure 8: Base magnetometer location (image courtesy of Google Earth).

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 20 of 87

4 EQUIPMENT CALIBRATIONS AND DATA ACQUISITION CHECKS


4.1 DYNAMIC MAGNETOMETER COMPENSATION Aircraft compensation tests were flown at high altitude on the 4 survey line headings and also at +/-15 to the line headings (to accommodate for cross wind flying conditions). The data for each heading consists of a series of aircraft manoeuvres with large angular excursions: specifically pitches, rolls and yaws. This is done to artificially create the worst possible attitudes and rates of attitudinal change likely to be encountered while on line and compensate for any magnetic noise created by the aircraft's motion within the earth's magnetic field. This data is processed to obtain the REAL TIME COMPENSATION terms of which the aircraft used the standard 17 term model. These terms include permanent, induced and eddy values. These coefficients may be applied in real time or during post processing. Note that this form of compensation will only remove those noise effects modelled in the manoeuvres test flight. External noise sources and random motions of the stinger with respect to the aircraft airframe generally establish the noise floor for this type of installation. The surveyor's goal is to achieve a 4th difference noise level on the order of 0.01 nT RMS during normal surveying conditions. In general, this noise level was routinely achieved or bettered as a matter of course. The following is a list of dates in which a compensation test had been flown and the flights they were used on.
Compensation Flight Data th 24 January 2008 30th January 2008 Flight range compensation applied to 1-4 5-240

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 21 of 87

Magnetic compensation flight path The images below are of the compensation flight paths.

Figure 9: Flight path of the compensation flight on 24th January 2008

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 22 of 87

Figure 10: Flight path of the compensation flight on 30th January 2008.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 23 of 87

Diurnal activity during compensation flight The diurnal collected during the compensation flight was relatively quiet as shown in the following figure.

Figure 11: Diurnal activity during compensation flight (24 January 2008).

th

Compensation lines flown in this period

Figure 12: Diurnal activity during compensation flight (30 January 2008).

th

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 24 of 87

Compensation results (24th January 2008)

Figure 13: East bound compensation line (24 January 2008).

th

Figure 14: West bound compensation line (24 January 2008).

th

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 25 of 87

Figure 15: North bound compensation line (24 January 2008).

th

Figure 16: South bound compensation line (24 January 2008).

th

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 26 of 87

Compensation results (30th January 2008)

Figure 17: East bound compensation line (30 January 2008).

th

Figure 18: West bound compensation line (30 January 2008).

th

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 27 of 87

Figure 19: North bound compensation line (30 January 2008).

th

Figure 20: South bound compensation line (30 January 2008).

th

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 28 of 87

4.2

HEADING ERROR CHECK

Historically, heading error checks have been an essential part of the aeromagnetic data acquisition procedure but their importance now has diminished. GPX Surveys now corrects for these effects using the dynamic aircraft magnetic compensation system and specially developed software. In the past, repeatable heading errors of less than one nanotesla (1.0 nT) were considered good. Dynamic compensation typically yields heading errors in the order of 0.1 to 0.3 nT, which are effectively eliminated by modern data levelling techniques. Below are the results of the heading error check of VH-KWW at commencement of survey.
Line L95101005:0 L95201005:0 L95301005:0 L95401005:0 ALL Heading East North West South Minimum 50653.46 50654.34 50654.08 50655.18 50653.46 Maximum 50656.08 50656.24 50656.60 50657.14 50657.14 Mean 50654.81 50655.29 50655.37 50656.14 50655.36 Heading 0.55 0.07 -0.01 -0.78 Std Dev 0.79 0.59 0.76 0.59 0.83 # readings 33 30 33 26

Figure 21: Heading test flight for VH-KWW.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 29 of 87

Figure 22: Location of the heading test flight.

4.3

SYSTEM PARALLAX TESTS

One of the processing parameters required to process digital data was the parallax or offset time, between the time the digital reading was taken by the instrument and the time the position fix for the fiducial of the reading was obtained. Each instrument magnetometer, altimeter, spectrometer, barometer and thermometer - may have a different parallax, so the parallax must be computed for each instrument. The parallax correction derived is the correction to be applied to each survey line. A positive parallax indicates the instrument reading is ahead of the position of the fiducial. Each integer fiducial represents one second so the parallax can be expressed in either fiducial or seconds. The correct fiducial is computed by:
Pc = Fr - Pi where Pc = Parallax corrected fiducial Fr = Fiducial for recorded reading

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 30 of 87

Pi = Instrument parallax

Results of parallax test A summary of the parallax corrections to the different data types is shown below:

Data GPS Position Magnetic Data Radiometric data Radar Altimeter Barometric Altimeter GPS derived DEM Barometric derived DEM Temperature Pressure Humidity GPS Altimeter Fluxgates 4.4

Parallax applied (seconds) 2.5 1.6 0.0 1.5 1.5 1.0 1.0 1.5 1.5 1.5 1.0 0.0

PRE-SURVEY RADIOMETRIC CALIBRATION TESTS

Several pre-survey calibration tests were conducted to calculate height attenuation coefficients, sensitivity coefficients, stripping ratios, and to estimate aircraft and cosmic background radiation. The calibration methods are as generally described by Grasty and Minty (1995) and the International Atomic Energy Agency (2003). The calibration test result values are listed in below: VH-KWW Aircraft Background Date 22 Jan 2008 Window TC K U Th TC K U Th Alpha Beta Gamma a b c TC K Value 124.61 23.96 3.33 1.26 0.790752 0.046416 0.036223 0.043527 0.2448 0.4241 0.7580 0.0589 -0.0042 -0.0075 0.007056 0.009348

Cosmic Background

22 Jan 2008

Stripping

23 Oct 2007

Height Attenuation

4 Jan 2008

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 31 of 87

Air/Ground @50m

4 Jan 2008

Air/Ground @60m

4 Jan 2008

U Th Dose K U Th Dose K U Th

0.008227 0.006851 29.9564 95.99 9.69 6.15 27.87 88.14 8.82 5.82

4.5

DAILY RADIOMETRIC SYSTEM TESTS

Daily tests were performed on the radiometric system to monitor system sensitivity and stability. These tests are as generally described by Grasty and Minty (1995) and the International Atomic Energy Agency (2003). A system stability test was performed at the start and end of each day. This was done using a thorium source placed a least 40cm from the centre of each detector. The average deadtime and background corrected thorium window was calculated and checked to be within 3 percent from the average of all other calibrations. Additionally a low-level test line was flown of at least 100 seconds in duration, This was used to establish that the soil moisture had not changed significantly and that the spectrometer system is functioning correctly. There were five low level test lines that were flown during the survey. The coordinates are listed below and their location is plotted next page.
Start Easting 341900 326920 763700 134820 592100 End Easting 341900 344590 763700 148200 605100 Start Northing 7961130 7959240 7990800 7951250 8079240 End Northing 7978070 7959240 8007360 7951250 8079240 Length of Line (km) 16.94 17.67 16.56 13.38 13.00

Location Halls Ck Halls Ck Fitzroy Crossing Fitzroy Crossing Derby

Test Line 5000 17040 2640 17280 10330

Projection GDA94 MGA 52 GDA94 MGA 52 GDA94 MGA 51 GDA94 MGA 52 GDA94 MGA 51

Table 1: Low level test line information.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 32 of 87

Low Level Test Line Location

Figure 23: Low level test lines flown from Fitzroy and Derby air bases.

Figure 24: Low level test lines flown from Halls Ck air base.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 33 of 87

4.6

TIME SYNCHRONISATION

All data is recorded in GPS time so all data is automatically synchronised.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 34 of 87

5 DATA VERIFICATION AND PRELIMINARY PROCESSING


All data verification and preliminary processing and map production was conducted at the field office using a Toshiba notebook computer. ChrisDBF was the primary field quality control software. At the conclusion of each survey flight all magnetic data, altimeter data, GPS position, and diurnal data was transferred via compact flash memory onto the field computer for preliminary data verification. The raw data was transferred from the field onto the GPX Surveys ftp site for further verification and processing. 5.1 DATA VERIFICATION AND CHECKS

General Checks and Verification The magnetic data, diurnal data, radar altimeter, GPS height data and flight path was checked for noise, spikes, inconsistencies and deviations. Any inconsistencies were queried and flagged and discussed with the technicians and senior data processors. If necessary the equipment was checked over and any damages were repaired or replaced. Prior to survey resumption any repairs were thoroughly tested. Magnetic Data Checks The raw un-edited magnetic data was checked to identify noise and spikes. Single reading spikes were manually edited and if the noise exceeded the contract specifications, the line was re-flown. Diurnal Data Checks At the completion of each days flying the diurnal data was downloaded from the base magnetometer onto the field laptop via a RS-232 serial cable link. The data was plotted and analysed for noise, spikes and erroneous activity. Multiple readings were flagged as invalid and if invalid diurnal data occurred during survey the affected section was re-flown. The diurnal data was checked to see that the change in diurnal readings during the course of the survey did not exceed the specified tolerances. When this occurred the affected survey lines were re-flown. Radar Altimeter Checks The altimeter data was checked to ensure a reasonably constant height above the terrain was maintained. Any significant deviations were queried with the pilot and flagged. The section was then checked against contract specifications and if it was out of specification the section was checked against SRTM data and compared to terrain information in Google Earth. If none of these revealed a valid reason for being out of specification the section was re-flown.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 35 of 87

GPS Height Data Checks The aircrafts height above mean sea level was determined by data from the postprocessed GPS data. The GPS height of the aircraft is checked for data masking and equipment reliability. The aircraft GPS recorded the data in the WGS84 datum. Flight Path Checks The flight path was plotted against the flight plan and checked for deviations. Any significant deviations were queried with the pilot and flagged. The section was then checked against contract specifications and if it was out of specification the section was checked against SRTM data and compared to terrain information in Google Earth. If none of these revealed a valid reason for being out of specification the section was re-flown. The aircraft GPS recorded the data in the WGS84 datum. Digital Terrain Data After radar and GPS height data verification the radar altimeter height was subtracted from the GPS height to give the elevation of the terrain above mean sea level. The digital terrain data and was gridded to check for inconsistencies and errors. Radiometric Data The 256-channel radiometric data was viewed to confirm that the spectra peaks are correctly calibrated. The following peak locations were checked daily: Potassium 1460 keV Uranium 1760 keV Thorium 2614 keV

Gridding and Inspection The magnetic, digital terrain and radiometric data was gridded and displayed on screen. With the aid of sun-angles the gridded data was checked for inconsistencies and errors. Any inconsistencies were flagged and if necessary corrected. 5.2 DATA ARCHIVES

All raw and field processed aircraft data plus the raw diurnal base data were backed up onto an external hard drive at the end of each days survey. A further copy of the raw and edited data remained on the field laptop for the duration of the project. The raw data was also uploaded onto the company ftp site and the data backed up at the offices of GPX.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 36 of 87

6 FINAL PROCESSING
All final checks, verification and data processing were performed in the offices of GPX Surveys. The raw field data was transferred to the GPX Surveys ftp site at the end of each flight. The final processing of the data follows the same quality control checks that are made in the field however the final data has additional processes performed. No fieldprocessed data was used in the making of the final data. All data used in the final processing was within contract specifications. The following software was used in the final verification and data processing: 6.1 GPX proprietary software ChrisDBF Geosoft Oasis Montaj

FINAL MAGNETIC DATA PROCESSING

Initial checks on the field data were performed as described in section 5.1. The following processes were then performed on the magnetic data: Single reading spikes were manually edited. The magnetic data was diurnally corrected. System parallax was calculated and removed. The magnetic data was IGRF corrected. The magnetic data was tie line levelled. The magnetic data was micro levelled.

Diurnal Correction to the Magnetic Data The raw magnetic and diurnal data was checked for spikes and single reading spikes were manually edited. The synchronised digital diurnal data collected by the base station was first subtracted from the corresponding airborne magnetic readings to calculate a difference. The resultant difference was then subtracted from the base value to produce diurnally corrected magnetic data. Parallax Correction to the Magnetic Data A system parallax as described in section 4.3 was applied to the magnetic data.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 37 of 87

IGRF Correction to the Magnetic Data The diurnally corrected magnetic data has been corrected for the regional gradient by subtracting the calculated IGRF (2005 model) computed continuously over the whole area. The calculation of these corrections used the GPS flying height. An IGRF base value of 50620 nT was added to the data. Tie Line Levelling A crossover program was used to compute the magnetic difference between each tie line and the traverse line intersection. These differences were then applied to level the traverse lines to the tie lines. Micro Levelling Finally the data was micro-levelled using a proprietary program that more subtly levels the data. Micro levelling was used to remove residual differences with a long wavelength along line and short wavelength across line. Application of the micro-levelling process removed the streaks that were sometimes visible when using various grid enhancements. The process used a window width of 12 grid cells and a tolerance of 3 nanoTesla. Gridding and Inspection The magnetic data was gridded and grid image enhancements were computed and displayed on screen. These were also viewed with the aid of crossline sun angles and inspected for inconsistencies and errors and appropriate corrections were made if required. 6.2 FINAL RADIOMETRIC DATA PROCESSING

The data is processed in accordance with the International Atomic Energy Agency Guidelines for radioelement mapping using gamma ray spectrometry data (July 2003). Prior to final processing the data was validated using the methods described in Section 5.1. The following is a summary of processes that were performed on the radiometric data: Single reading spikes were edited. Noise removal from data using Noise Adjusted Singular Value Decomposition (NASVD). Apply the dead-time correction. The radiometric data was energy calibrated. Aircraft, cosmic and radon background radiation was removed. The stripping corrections were applied. System parallax was calculated and removed.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 38 of 87

The height data was corrected to standard temperature and pressure and then corrected to a nominal survey height using height attenuation coefficients. If necessary the data was levelled using tie line levelling and/or micro levelling techniques. The data was converted to elemental concentrations.

Noise Adjusted Singular Value Decomposition (NASVD) The two most common processing methods for 256 channel noise reduction are: 1. Noise Adjusted Singular Value Decomposition (NASVD). This was developed specifically for radiometric processing. 2. Maximum Noise Fraction (MNF). This was developed for removing noise from satellite images and subsequently used in radiometric processing. Both methods use Principal Component Analysis (PCA) with the only difference being in the estimation of noise in the raw spectra and subsequent scaling before PCA. We have implemented and extensively used both methods but prefer NASVD because it is simpler, requires one less pass of the data and less observations for a good join when adjacent data sets are merged. However the 2 methods give almost the same result and both work well. Careful analysis of the eigenvalues and eigenvectors of the PCA is required to ensure the process has worked correctly. We use the 7 most significant principal components to reduce the data with the remainder considered to be noise. If this is not the case, as seen from eigenvalue and eigenvector plots, then there is a problem with the data. So this is an excellent quality control tool as well as a noise reduction method. There are strong theoretical reasons for this approach and if less than 7 components are used some signal is likely to be removed. On large surveys we have found it is best to use 7 components globally rather than having to make difficult decisions for different segments of the survey as this provides a globally consistent result. As final proof the method has worked correctly, residual line profiles and images of potassium, uranium and thorium must confirm that no signal is present. Also the ternary potassium, uranium and thorium image must be sharp. If signal has been removed this image will be blurred. Deadtime correction The GR-820 spectrometer requires a finite time to process each pulse from the detectors. The deadtime of the GR-820 is less than 5 microseconds per detector and this correction was applied.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 39 of 87

Energy Recalibration Spectra analysis was performed on each line of data and the position of the thorium and potassium peak positions determined and compared to their theoretical positions. The original spectra data was then mapped to the correct peak positions and new windowed data created for each of the standard IAEA windows as follows. Window Total Count Potassium Uranium Thorium Cosmic Peak Energy (KeV) 1460 1760 2615 Energy Window 410 1370 1660 2410 3000 (KeV) 2810 1570 1860 2810

Aircraft Background Correction The aircraft background radiation was removed by subtracting the aircraft background values from the Total Count, Potassium, Uranium and Thorium windows. The values that are used are in Appendix A. Cosmic Correction The effect of cosmic radiation was removed from each window by multiplying the cosmic channel by the cosmic stripping factor for each window and subtracting the result from the window data. The values that are used are in Appendix A. Radon Background Correction Although in the past upward looking crystals have often been used as an acceptable method of correcting for the effects of atmospheric radon in airborne radiometric surveys, we now consider this method to be inadequate to provide the data quality required by modern processing techniques for the following reasons. The crystal volume of the upward looking detectors is usually small relative to that of the primary downward looking detectors (typically 1 or 2 upward detectors for 4 downward detectors). For this reason, noise dominates signal in the spectra obtained from the upward looking detectors. Consequently the ability of these detectors to accurately reflect coincident (i.e. non geological) responses in the primary detectors is severely compromised. The low signal to noise ratio has the added affect of compromising spectral calibration of the upward looking detectors, further eroding their ability as indicators of coincident events. More importantly, the very nature of airborne radon distribution renders this method inherently inaccurate, as atmospheric radon does not exist in uniform distributions but rather in radon clouds that have a distinctly non uniform density distribution. Sensors receiving signal from different directions will therefore detect different radon responses. Another problem with upward looking crystals is preventing contamination effects from ground signal. This is especially a problem for low level surveys or for areas with

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 40 of 87

significant terrain variation where aircraft attitude movements will allow ground signal to be recorded by the upward looking crystals. It is clearly evident that any effective radon correction method should use the downward looking crystals only. For this reason we prefer to use the spectral ratio method for radon removal. This method uses the 352 keV uranium peak as a substitute for upward crystals. The only time upward crystals may be needed is where cesium contamination affects the use of the 352 keV uranium peak. The use of the low energy uranium peak at 352 keV instead of the 609 keV uranium peak should make even this use of upward crystals redundant. The 352 keV uranium peak is an extremely good detector of radon gas because very little radiation from the ground will reach the aircraft at this low energy. Also the thorium peak close to the 352 keV peak has much less intensity than the thorium peak close to the 609 keV uranium peak. Stripping Corrections The radiometric spectra of potassium (K), uranium (U) and thorium (Th) series overlap. To evaluate of any one spectral window, which is designed to detect one radioelement, requires removal of the spectral overlap. This process of removal of the spectral overlap is known as stripping. The stripping procedure uses spectral stripping ratios determined experimentally using concrete calibration pads of known K, U and Th concentration. The values that are used are in Appendix A. Parallax Correction A system parallax as described in section 4.3 was applied to the radiometric data. Calculation of Effective Height Spikes from the temperature and pressure data were removed. The radiometric data was converted to effective altitude at standard temperature and pressure (STP) using the expression: P 273 Alt ( STP) BA ( ) 1013 (T 273)
Alt(STP) = Effective altitude at STP in metres BA = Barometric Altitude in metres P = Pressure in millibars T = Temperature in C

Height Correction The temperature and STP corrected data was converted to a nominal survey height using the height attenuation coefficients.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 41 of 87

Tie Line Levelling A crossover program was used to compute the radiometric difference between each tie line and the traverse line intersection. These differences were then applied to level the traverse lines to the tie lines. Micro Levelling Micro levelling was used to remove residual differences with a long wavelength along line and short wavelength across line. Application of the micro levelling process removed the streaks that were sometimes visible when using various grid enhancements. The microlevel window width of 12 grid cells was used with the following tolerances for each channel. Channel Total Potassium Uranium Thorium Tolerance 6.0 nGy/hr 1.0 percent 1.0 eppm 1.0 eppm

Gridding and Inspection The radiometric data was gridded and grid image enhancements were computed and displayed on screen. These were also viewed with the aid of crossline sun angles and inspected for inconsistencies and errors and appropriate corrections were made if required. 6.3 FINAL ELEVATION DATA PROCESSING

Initial checks on the field altimeter and GPS height data were performed as described in section 5.1. GPS Height Data The aircrafts height above mean sea level each second was determined by data from the post-processed GPS. The GPS height of the aircraft is verified to check for data masking and for equipment reliability. The GPS height data is used in the production of digital terrain maps. Parallax Correction A parallax error correction as described in section 4.3 was applied to the coordinate data. Digital Terrain Calculation and N-value correction After verification, the radar altimeter height was subtracted from the GPS height and the Geoid Ellipsoid separation (N-value) correction applied to give the elevation of the terrain above mean sea level. The average value of the N-value in this area is 25.0 metres.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 42 of 87

Tie Line Levelling A crossover program was used to compute the height difference between each tie line and the traverse line intersection. These differences were then applied to level the traverse lines to the tie lines. Micro Levelling Micro levelling was used to remove residual differences with a long wavelength along line and short wavelength across line. Application of the micro levelling process removed the streaks that were sometimes visible when using various grid enhancements. The process used a window width of 16 grid cells and a tolerance of 2m. Comparison to 9 second DEM of Australia The GPX survey DEM was compared to the Australian National Gravity Database available from Geoscience Australia. At the intersections of the GPX DEM and the Australian National Gravity Database the gravity data is all pre-1993 and therefore prior to the advent of accurate GPS technology. The Gravity database in this survey area has a positional accuracy of 50m horizontally and 2m vertically, which was deemed unsuitable to be used to adjust the survey data. The survey DEM was then compared to the publicly available 9 second DEM downloaded from Geoscience Australia. The average difference between these data was approximately -7.3 metres and this was added to the survey DEM. The following graph shows the resulting distribution of differences after subtracting a mean difference of 7.3 metres to the data collected by the aircraft. The resultant mean difference after correction is less than 1.0 metre.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 43 of 87

Figure 25: Histogram analysis of difference between the final GPX DEM grid and the 9 second DEM of Australia from Geoscience Australia.

DISCLAIMER Every effort has been made to make this model a useful general reference. No guarantee can be made that this model is a true representation of height above sea level as it can contain laser altimeter responses from buildings, trees and scrub. Users of the product should be aware of the topographic limitations mapped herewithin. Do not use this DTM for navigation purposes.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 44 of 87

7 FINAL DELIVERABLES
7.1 FINAL GRIDS AND DATA PRODUCTS Grids and located data were delivered on 2 sets of DVDs (original and archive copy). Grids All grids are in ERMapper format (*.ERS) and are based on the GDA94 datum and are projected in MGA Zone 52. The following grids were delivered: Digital Terrain Model (DEM) Total Magnetic Intensity (TMI) Total Magnetic Intensity First Vertical Derivative (TMI1VD) Reduced to Pole (RTP) Potassium (POT) Uranium (URA) Thorium (THO) Total Count (TOT)

Located Data (ASCII format) The located data is based on GDA94 datum and is projected in MGA Zone 52. The final located data and raw radiometric located data is in a format as described in Appendix A.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 45 of 87

8 MAP IMAGES
8.1 FLIGHT PATH

Figure 26: Flight path image.

8.2

DIGITAL TERRAIN MODEL

Figure 27: Digital terrain model image.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 46 of 87

8.3

TOTAL MAGNETIC INTENSITY

Figure 28: Total magnetic intensity image.

8.4

TOTAL MAGNETIC INTENSITY 1VD

Figure 29: Total magnetic intensity first vertical derivative image.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 47 of 87

8.5

RADIOMETRIC TERNARY CMY COLOURS

Figure 30: Radiometric ternary CMY colours image.

8.6

RADIOMETRIC TERNARY RGB COLOURS

Figure 31: Radiometric ternary RGB colours image.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 48 of 87

9 CONTRACTOR INFORMATION
GPX Surveys Pty Ltd ABN 48 110 619 602 Address: 4 Hehir Street, Belmont WA 6104 Australia Postal: PO Box 808, Cloverdale WA 6985 T +61 8 9477 5111 F +61 8 9477 5211 info@gpxsurveys.com.au www.gpxsurveys.com.au

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 49 of 87

APPENDIX A: LOCATED DATA FORMAT AND PROCESSING SPECIFICATIONS


Magnetic and Radiometric Data Description File
Project Survey area Located data type Surveyed by Job number Processed by Creation date SURVEY SPECIFICATIONS Survey flown Traverse line spacing Traverse line direction Tie line spacing Tie line direction Survey height LOCATED DATA FORMAT Variable Project number Line number Easting (MGA52) Northing (MGA52) Fiducial Flight number Date (YYYYMMDD) Longitude (GDA94) Latitude (GDA94) Bearing Radar altimeter Tie-levelled magnetics Final magnetics Pressure Temperature DATA PROCESSING COORDINATE DATA All lines are scissored to the following rules: 1) A 'smooth' edge outside the area boundary. 2) Maximum line overlap of 0 fiducials within the area boundary. The local projection is a UTM projection based on the GDA94 spheroid with a central meridian of 129 East degrees. System parallax of 2.5 fiducial has been removed. MAGNETIC DATA The magnetic data has been corrected for regional gradient by subtraction of IGRF model 2005 computed continuously over the whole area based on Units Undefined 9999 9999999 9999999.99 9999999.99 99999999 999 99999999 999.999999 999.999999 999 9999.9 99999.999 99999.999 9999.9 99.9 From 1 6 14 25 36 45 50 59 70 81 85 92 102 112 119 To 5 13 24 35 44 49 58 69 80 84 91 101 111 118 123 Format I5 I8 F11.2 F11.2 F9.0 I5 I9 F11.6 F11.6 F4.0 F7.1 F10.3 F10.3 F7.1 F5.1 January - October 2008 400 metres 000-180 degrees 4000 metres 090-270 degrees 60 metres GEOSCIENCE AUSTRALIA MAG/SPEC SURVEY KIMBERLEYS 0.1 Second FINAL MAGNETIC Data GPX AIRBORNE PTY LTD. 2289 GPX AIRBORNE PTY LTD. October 2008

metres metres

degrees degrees degrees metres nT nT millibars degrees C

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 50 of 87

the GPS height. Diurnal magnetic variations have been removed. System parallax of 1.6 fiducial has been removed. Tie-line levelling has been applied. Microlevelling has been applied. A base value of 50730 nT has been added to the data.

Radiometric Channel Data Description File


Project Survey area Located data type Surveyed by Job number Processed by Creation date SURVEY SPECIFICATIONS Survey flown Traverse line spacing Traverse line direction Tie line spacing Tie line direction Survey height LOCATED DATA FORMAT Variable Project number Line number Easting (MGA52) Northing (MGA52) Fiducial Flight number Date (YYYYMMDD) Longitude (GDA94) Latitude (GDA94) Bearing Radar altimeter Pressure Temperature Final dose rate smoothed Final potassium smoothed Final uranium smoothed Final thorium smoothed Final dose rate not smoothed Final potassium not smoothed Final uranium not smoothed Final thorium not smoothed DATA PROCESSING COORDINATE DATA All lines are scissored to the following rules: 1) A 'smooth' edge outside the area boundary. 2) Maximum line overlap of 0 fiducials within Units Undefined 9999 9999999 9999999.99 9999999.99 99999999 999 99999999 999.999999 999.999999 999 9999.9 9999.9 99.9 999.999 99.999 99.999 999.999 999.999 99.999 99.999 999.999 From 1 6 14 25 36 45 50 59 70 81 85 92 99 104 112 120 128 136 145 153 161 To 5 13 24 35 44 49 58 69 80 84 91 98 103 111 119 127 135 144 152 160 168 Format I5 I8 F11.2 F11.2 F9.0 I5 I9 F11.6 F11.6 F4.0 F7.1 F7.1 F5.1 F8.3 F8.3 F8.3 F8.3 F9.3 F8.3 F8.3 F8.3 January - October 2008 400 metres 000-180 degrees 4000 metres 090-270 degrees 60 metres GEOSCIENCE AUSTRALIA MAG/SPEC SURVEY KIMBERLEYS 1 Second FINAL RADIOEMTRIC Data GPX AIRBORNE PTY LTD. 2289 GPX AIRBORNE PTY LTD. October 2008

metres metres

degrees degrees degrees metres millibars degrees C nGy/hr % ppm ppm nGy/hr % ppm ppm

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 51 of 87

the area boundary. The local projection is a UTM projection based on the GDA94 spheroid with a central meridian of 129 East degrees. System parallax of 2.5 fiducial has been removed. RADIOMETRIC DATA Raw channel data provided has been energy calibrated NASVD has been applied to channel data prior to windowing System parallax of 0.0 fiducial has been removed. Height attenuated to 60m AGL Airborne radon has been removed AIRCRAFT BACKGROUND Total Count Potassium Uranium Thorium COSMIC STRIPPING RATIOS Total Count Potassium Uranium Thorium COMPTON STRIPPING RATIOS alpha beta gamma a HEIGHT ATTENUATION COEFFICIENT Total Count Potassium Uranium Thorium SENSITIVITY CONSTANTS Total Count - nGy/hr Potassium - 1% Uranium - 1ppm Thorium - 1ppm WINDOW ENERGY LEVELS Total Count Potassium Uranium Thorium UNITS cps cps cps cps

124.61 23.96 3.33 1.26 0.790752 0.046416 0.036223 0.043527 0.2448 0.4241 0.7580 0.0589 0.007056 0.009348 0.008227 0.006851 per per per per

metre metre metre metre

27.87 cps 88.14 cps 8.82 cps 5.82 cps Low Energy High Energy 410.0 2810.0 1370.0 1570.0 1660.0 1860.0 2410.0 2810.0

keV keV keV keV

Digital Terrain Model Channel Data Description File


Project Survey area Located data type Surveyed by Job number Processed by Creation date SURVEY SPECIFICATIONS Survey flown Traverse line spacing January - October 2008 400 metres GEOSCIENCE AUSTRALIA MAG/SPEC SURVEY KIMBERLEYS 0.1 Second FINAL DEM Data GPX AIRBORNE PTY LTD. 2289 GPX AIRBORNE PTY LTD. October 2008

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 52 of 87

Traverse line direction Tie line spacing Tie line direction Survey height LOCATED DATA FORMAT Variable Project number Line number Easting (MGA52) Northing (MGA52) Fiducial Flight number Date (YYYYMMDD) Longitude (GDA94) Latitude (GDA94) Bearing Radar altimeter Pressure Temperature Final DEM GDA94 Final DEM AHD DATA PROCESSING

000-180 degrees 4000 metres 090-270 degrees 60 metres

Units

Undefined 9999 9999999 9999999.99 9999999.99 99999999 999 99999999 999.999999 999.999999 999 9999.9 9999.9 99.9 99999.9 99999.9

From 1 6 14 25 36 45 50 59 70 81 85 92 99 104 112

To 5 13 24 35 44 49 58 69 80 84 91 98 103 111 119

Format I5 I8 F11.2 F11.2 F9.0 I5 I9 F11.6 F11.6 F4.0 F7.1 F7.1 F5.1 F8.1 F8.1

metres metres

degrees degrees degrees metres millibars degrees C metres metres

COORDINATE DATA All lines are scissored to the following rules: 1) A 'smooth' edge outside the area boundary. 2) Maximum line overlap of 0 fiducials within the area boundary. The local projection is a UTM projection based on the GDA94 spheroid with a central meridian of 129 East degrees. System parallax of 2.5 fiducial has been removed. DIGITAL ELEVATION MODEL DATA DIGITAL ELEVATION MODEL CALCULATION The radar altimeter data was subtracted from the GPS heights to provide a digital elevation model which is height above the WGS84 spheroid. Using interpolation on the 120 second DMA Geoid model, a correction was computed and subtracted from the WGS84 data to convert to height above the geoid. DATA RELIABILITY This Digital Elevation Model (DEM) has been computed from data generated during the course of an airborne geophysical survey flown at a nominal spacing of 400m and data has been interpolated between such lines. Every effort has been made to make this model a useful general reference. No guarantee can be made that this model is a true representation of height above sea level as it can contain radar altimeter responses from buildings and in some instances dense timber. Users of the product should be aware of the topographic limitations mapped herewithin. Do not use this DEM for navigation purposes.

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 53 of 87

APPENDIX B: WEEKLY PRODUCTION SUMMARY

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 54 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 55 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 56 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 57 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 58 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 59 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 60 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 61 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 62 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 63 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 64 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 65 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 66 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 67 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 68 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 69 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 70 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 71 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 72 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 73 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 74 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 75 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 76 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 77 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 78 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 79 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 80 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 81 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 82 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 83 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 84 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 85 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 86 of 87

Project 2289, Geoscience Australia, Airborne Magnetic and Radiometric Survey, South Kimberley, WA Page 87 of 87

Вам также может понравиться