CONTENTS

1.

GENERAL 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 SECTION INCLUDES DESCRIPTION OF WORK REFERENCES & STANDARDS SUBMITTALS QUALITY ASSURANCE EXTENDED WARRANTY DELIVERY, STORAGE HANDLING DOCUMENT PRECEDENCE MOCK-UP AND

2.

PRODUCTS 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 BOWLING CENTRE SPECTATORS SEATS (RETRACTABLE) SQUASH COURT GYMNASIUM AND SPORTS HALL FLOORING SAUNA ROOM STEAM ROOM AQUARIUM CERAMIC

GENERAL

1.1

Section Includes
Particular specifications, material selection and General Provisions of the Contract, including General Conditions, Conditions of Particular Application and Specification Sections, apply to different Architectural elements work and execution.

1.2

Description of Work
This section covers the special components of the following items: 1.2.1 Gym and sports hall 1.2.2 Sauna and steam 1.2.3 Ceramic tiles.

1.3

Reference and Standards


Work in this section shall be performed in strict accordance with the stipulations of the British Standard Specifications (BS) latest edition, the specifications of the American Society for Testing and Materials (ASTM) or other equivalent International Standards and sound practice. All subject to full compatibility between systems.

1.4

Submittals
Submit the following in accordance with Shop Drawings, Product Data & Samples Submittals: 1.4.1 1.4.2 Product data for each type of details, materials, dimensions, profiles, finishes and general recommendations. Shop drawings showing plans, elevation, sections large-scale details indicating profiles of each element, all in accordance with related material specifications. Provide samples of materials and finishes for approval by COMPANY.

1.4.4

1.5

Quality Assurance
1.5.1 Manufacturer's Instructions: In addition to the requirements of Specifications comply with manufacturer's instructions and recommendations for all phases of work, including preparation of substrate, applying materials and protection of installed units. Installers Experience: Work of this Section will be carried out by an installer having a minimum of five (5) years experience in performing such works. Panel tolerances for squash court panels shall comply with tolerances as published by the World Squash Federation (WSF).

1.5.2

1.5.3

1.6

Extended Warranty
Without depraving COMPANY of their rights under the provisions of the Contract, the Contractor warrant and agree to repair or replace the expansion joint that does not meet requirements or does not remain watertight during a period of ten (10) years after the date of subtended completion. Installation workmanship and wood floor system is warranted for a period of one year from date of installation.

1.8

Delivery, Storage and Handling


1.8.1 1.8.2 All materials shall be kept under cover and free from dampness and extreme temperature. Deliver and store all components in such a way to prevent damage to them.

1.8.3 1.8.4 1.8.5

1.8.6 1.8.7 1.8.8

1.8.9

No materials shall be delivered to the jobsite until building is completely enclosed and weather tight. Unloading and stocking materials into the court area to be the responsibility of the main CONTRACTOR unless otherwise arranged. It is CONTRACTORs responsibility that proper humidity and temperature be maintained in the court area. Therefore, the permanent HVAC shall be in operation and maintaining court area temperature between 26 degrees and 40%-60% humidity prior to and continuously after installation. All finishes should never be subjected to direct sunlight, rain, or wide variations of ambient conditions. Proper store for materials should be maintained by stacking in a clean, dry, storage area. Material shall be stacked flat and delivered on skids. After delivery, materials shall have banding and wrap removed to allow panels to acclimate to room conditions. Material not properly protected and stored and which is defaced or damaged shall be rejected.

1.9

Document Precedence
It shall be the CONTRACTORS responsibility to be, or to become, knowledgeable of the requirements of the referenced Codes and Standards. The CONTRACTOR shall notify the COMPANY of any apparent conflict between this specification, the related data sheets, the Codes and Standards and any other Specifications noted herein. Resolution and/or interpretation precedence shall be obtained from the COMPANY in writing before proceeding with the shop drawings/manufacture. In case of conflict, most stringent criteria shall apply. Requirements as specified in MANUFACTURERS instructions shall be followed where applicable.

1.10 Mock-up
1.10.1 1.10.2 Provide a mock-up where designated by COMPANY. Retain mock-up until completion of the work. Approved mock-ups shall serve as a standard for similar work throughout the buildings.

PRODUCTS

2.1

Gymnasium Flooring
Finishes of floor shall be full Polyurethane System (7mm thick), a resilient polyurethane flooring system, which consist of 5mm thick base sealed with polyurethane layer. The top-coat is installed consisting of 2mm thick self-levelling polyurethane with matt coat finish. Game line is finally applied onto the polyurethane flooring when cured. This system is supplied in a variety of colours as shown on the drawings.

2.2

Ceramic
2.7.1 General CONTRACTOR shall provide data sheets & samples for all Ceramic tiles, as shown on Architectural Design Package. All tiles sizing & materials shall be compatible with Design Drawings & Specifications. For tiles faces CONTRACTOR shall follow the table below:

END OF SECTION