BIO Mas Boiler wood hut expansion

Description Unit Rate Qty Amount

supply cutting welding painting and erection of 12'-6'' high 1 6'x3isection iron columns with base concrete and base plate NOS 2 6'x3' Roof truss on the side Ft supply cutting welding painting 4'x2', 2mm lipped channel purlene supply and laying of 0.4mmZn Al colour bonded roofing sheets supply and laying of Zn Al rain water gutteres with brackets supply and laying of Zn Al down pipes with brackets 4'' floor concrete with reinforcement both ways 4'' thick wall up to 3' with plaster back side 7' high above the wall and length 15ft fence Supply and fixing of 8"X4" H iron beam for front side to remove 10 existing column Total Project Amount
3 4 5 6 7 8 9

24200 2200 285 165 425 425 235 210 24500 47500

2 25.5 148 546 40 30 300 45 1 1

48,400.00 56,100.00 42,180.00 90,090.00 17,000.00 12,750.00 70,500.00 9,450.00 24,500.00 47,500.00 418,470.00 209,235.00

Ft Sq.ft Ft Ft Sq.ft Sq.ft item

Advance required (Cost Of material)

50%

Saw dust storage along the boudary

Erma Consultantants and Engineers Pvt Ltd.

Page 1 of 3

Supply cutting welding painting and erection of 12'-6'' high 6'x3isection iron columns with base concrete and base plate 1 along the boundarary NOS Supply cutting welding painting and erection of 19' high 6'x3 I section iron columns with base concrete and base plate along the 2 existing wall behind the boiler with Brasing NOS
3 Supplyu and fabrication of 20" roof truss by 1" ft

24200

121,000.00

35800 8200 285 165 425 425 210 3900 210

5 5 270 1249 60 28 399 7 1019

179,000.00 41,000.00 76,950.00 206,085.00 25,500.00 11,900.00 83,790.00 27,300.00 213,990.00

supply cutting welding painting 4'x2', 2mm lipped channel purlene Supply and laying of 0.4mmZn Al colour bonded roofing sheets supply and laying of Zn Al rain water gutteres with brackets supply and laying of Zn Al down pipes with brackets Masonary wall 4'' wall up to 7' high along the boundrary with 8 plastering and painting. Total length 57' Masonary wall 4'' wall up to 7' high along the boundrary with 9 plastering and painting. Total length 57'ft
4 5 6 7 10 4'' thick floor concrete with 2''x2'' mesh

Sq.ft
ft ft ft

Sq.ft NOS Sq.ft

Supply and laying of 0.4mmZn Al colour bonded wall cladding for from cement block level up to roof level to the existing roof level of the boiler house with 1 1/2" x1 1/2 box bar frame withpainting 11 the stucture9(ETP side) Sq.ft

285

1000

285,000.00

Erma Consultantants and Engineers Pvt Ltd.

Page 2 of 3

Supply and laying of 0.4mmZn Al colour bonded wall cladding for from side roof of loading area upto the roof level of the boiler house with 1 1/2" x1 1/2 box bar frame withpainting the 12 stucture9(wood hut side) Sq.ft Supply and laying of 0.4mmZn Al colour bonded wall cladding for new saw dust hut from the roof level to the existing roof level of the boiler house with 1 1/2" x1 1/2 box bar frame withpainting the 13 stucture Sq.ft Total Project Amount Advance required (Cost Of material) 50%

285

371

105,735.00

285

533

151,905.00

1,529,155.00 764,577.50

Erma Consultantants and Engineers Pvt Ltd.