Вы находитесь на странице: 1из 6

2

nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria
Multiobjective Artificial Bee Colony Algorithm for
Economic/Emission Optimal Power Flow problem
S. Mouassa T. Bouktir
Department of Electric Engineering, University of Stif, (19000)-ALGERIA
souhil.mouassa@yahoo.fr tbouktir@yahoo.fr

Abstract This paper presents a new application of the
artificial bee colony algorithm (ABC) for solving the
Multiobjective optimal power flow. The MOABC is to
simultaneously minimize total fuel cost and emission cost of
generation with considering various constraints i.e. limits on
generator real and reactive power outputs, bus voltages,
transformer tap-setting, and power flow of transmission lines.
This approach is evaluated on the standard IEEE 30-bus system
with six generating units .The results obtained using the
proposed approach is compared with results of other
optimization method. Simulation results demonstrate that
Artificial Bee Algorithm (ABC) provides better results than
other heuristic techniques.

Key words - Artificial Bee Algorithms (ABC), Multiobjective
optimization (MO), Emission/Economic optimal power flow.

I. INTRODUCTION
n the last decade the basic objective of optimal power
flow has dealt to minimize only one objective such as
fuel cost [1]. In addition, the increasing public awareness
of the environmental protection and the passage of the Clean
Air Act Amendments of 1990 have forced the utilities to
modify their design or operational strategies to reduce
pollution and atmospheric emissions of the thermal power
plants [2], which are pollutant gases (Nox, SO2, CO2, CO) .
Several options are proposed to reduce unit emissions
like installing cleaning equipments, changing to fuel with
less pollutants or dispatching with emission considerations
[3].
Conventional optimal power flow cannot meet the
environmental protection requirements, since it only
considers minimising the total fuel cost. Traditional
optimization techniques, such as gradient-based method are
difficult to extend to the true Multiobjective case, because
they were not designed to deal with multiple optimal
solutions. In most case, Multiobjective problems have to be
scaled to a single objective problem before the optimization
[4]. Different techniques have been reported in the literature
pertaining to emission/economic optimal power flow
(EEOPF) problem. In [5] the authors present an enhanced
genetic algorithm (EGA) for the solution of the OPF problem
with both continuous and discrete control variables [6]. In
[7], the authors have proposed the use of an Bacteria
Foraging in human intestine invented by Passino to solve
environmental constrained economic Dispatch, is used to
optimize the generation schedule for any power system. Two
conflicting objectives (i) cost and (ii)emission are optimized
simultaneously. In [8], the authors have proposed the use of
an ant colony search algorithm to solve the economic power
dispatch with pollution control. To accelerate the processes
of ant colony optimization (ACO), the controllable variables
are decomposed to active constraints that directly affect the
cost function included in the ACO process and the passive
constraints which are updated using conventional power
flow.
This paper proposes a simple approach based on
Artificial bee colony algorithm implemented with Matlab
program to minimize the total fuel cost of generation and
emission gaz cost caused by fossil based thermal generating
units and also maintaining an acceptable system performance
in terms of limits and security constraints.
II. PROBLEM FORMULATION
Emission/economic optimal power flow involves the
simultaneous optimization of fuel cost and emission objectives
that are conflicting in nature satisfying the system and unit
equality and inequality constraints. The general problem
formulation is as follows.
The Multiobjective Economic and emission optimal
power flow problem is converted into single optimization
problem by introducing price penalty factor [9]:

= , + 1 , (1)

where the scaling factor was selected as 550.66 in this
study is a compromise factor varied in the range 0 1
The boundary values =1 and =0 give the conditions for the
pure minimization of the fuel cost function and the pure
minimization of the emission cost [10]:
Subject to :
g, = 0 (2)
avec , 0 (3)
Where
g, : is the equality constraints ;
, : is the system inequality constraints;
: is the vector of dependent variables (state variables)
including load bus voltage magnitudes .
: is the vector of control variables including real power
generation outputs except at the slack bus
1
, voltage
magnitudes

of all PV buses including the slack bus and


transformer tap settings.
expressed as

=
1
,

. .

,
1
. .

,
1
. .

(4)
where , and are the number of load buses, the
number of generators, and the number of transmission lines,
respectively.
Hence, u can be expressed as:

=
2
. .

,
1
. .

,
1
. .

(5)
I
2
nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria
where NT is the number of the tap changing transformers.
III. OBJECTIVE FUNCTIONS
A. Fuel Cost Objective
The classical economic dispatch problem of finding the
optimal combination of power generation, which minimizes
the total fuel cost while satisfying the total required demand
can be mathematically stated as follows [11]:
, =
( ) h c P b P a
NG
i
i Gi i Gi i
/ $
1
2

=
+ +
(6)
where
: total fuel cost ($/hr),

($/h MW2),

($/h MW),

($/h),:
are fuel cost coefficients of

unit,

is the real power


generation of

unit

B. Emission Objective
The most important emissions considered in the power
generation industry due to their effects on the environment
are sulfur dioxide (SO2) and nitrogen oxides (NOx). These
emissions can be modeled through a combination of
polynomial and exponential terms [12]:

, = ( ) ( ) ( )

+ +
NG
i
Gi i i i Gi i Gi i
P e d c P b P a
1
2 2
2
2
2
exp + 10
(7)
where
2
,
2 ,

2
,

and

are coefficients of the

generator emission characteristics.


- Equality Constraints
Power balance is equality constraint. The total power
generation must cover the total demand (P
D
) and real power
loss in transmission lines (Ploss). Itcan be expressed as
follows. [1]

( )

=
= +
NG
i
loss Di Gi
P P P
1
0
(8)
The total transmission network losses the power system is
obtained by

=
( ) | |
j i j i j i
NL
k
k
V V V V g o o +

=
cos 2
2 2
1
(9)

- Inequality Constraints
For stable operation, generator voltage, real power output
and reactive power output are restricted by the lower and
upper limit as follows.

(10)

(11)

(12)
= 1, . ,
also Transformer tap settings are restricted by the minimum
and maximum limits as follows.
- Security Constraints
Theses These incorporate the constraints of voltage
magnitudes of load buses as well as transmission line load-
ings as follows [13].
Theses incorporate the constraints of voltage magnitudes
of load buses as well as transmission line loadings as
follows :


(13)

, (14)
- Voltage Deviation
One of the important indices of power system security is
the bus voltage magnitude. The voltage magnitude deviation
from the reference value at each load bus must be as small as
possible [10] .The deviation of voltage is given as follows:


V = V
i
V
i
rf

NB
i=1
(15)

where,

is the reference value of the voltage magnitude


at load bus i.
IV. OVERVIEW OF ARTIFICIAL COLONY
BEE ALGORITHM (ABC)

Among the algorithms based on the foraging behavior of
honey bees, the ABC was designed to deal with numerical
optimization problems. ABC is based in two natural
processes: The recruitment of bees into a food source and the
abandonment of a source.
Three types of bees are considered in the ABC: employed,
onlooker and scout bees. The number of employed bees is
equal to the number of food sources and an employed bee is
assigned to one of the sources. [14]
A bee waiting on the dance area for making decision to
choose a food source is called an onlooker and a bee going to
the food source visited by it previously is named an
employed bee. A bee carrying out random search is called a
scout. In the ABC algorithm, first half of the colony consists
of employed artificial bees and the second half constitutes
the onlooker. For every food source, there is only one
employed bee.
The employed bee whose food source is exhausted by the
employed and onlooker bees becomes a scout. In the ABC
algorithm, each cycle of the search consists of three steps:
sending the employed bees onto the food sources and then
measuring their nectar amounts; selecting of the food sources
by the onlookers after sharing the information of employed
bees and determining the nectar amount of the foods;
determining the scout bees and then sending them onto
possible food sources. At the initialization stage, a set of
food source positions are randomly selected by the bees and
their nectar amounts are determined. Then, these bees come
into the hive and share the nectar information of the sources
with the bees waiting on the dance area within the hive. At
the second stage, after sharing the information, every
employed bee goes to the food source area visited by her at
the previous cycle since that food source exists in her
memory, and then chooses a new food source by means of
visual information in the neighborhood of the present one. At
the third stage, an onlooker prefers a food source area
depending on the nectar information distributed by the
employed bees on the dance area. [15] As the nectar amount
2
nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria
of a food source increases, the probability with which that
food source is chosen by an onlooker increases, too. Hence,
the dance of employed bees carrying higher nectar recruits
the onlookers for the food source areas with higher nectar
amount. After arriving at the selected area, she chooses a
new food source in the neighborhood of the one in the
memory depending on visual information. Visual
information is based on the comparison of food source
positions. When the nectar of a food source is abandoned by
the bees, a new food source is randomly determined by a
scout bee and replaced with the abandoned one. In our
model, at each cycle at most one scout goes outside for
searching a new food source and the number of employed
and onlooker bees were equal [15].The probability

of
selecting a food source i is determined using the following
expression:

=
0.9

+ 0.1 (16)

Where

the fitness of the solution is represented by the


food sources i .
The food source in the neighborhood of a particular food
source is determined by altering the value of one randomly
chosen solution parameter and keeping other parameters
unchanged. This is done by adding to the current value of the
chosen parameter the product of a uniform value between -1
and 1 and the difference in values of this parameter for this
food source and some other randomly chosen food source
[15]. Formally, suppose each solution

= 1,2, ,

consists of d parameters and let the solution be:

=
1
,
2
, ,

(17)
With parameter values
1
,
2
, .


In order to determine a solution i,

in the neighborhood of

, a solution parameter j and another solution

=
1
,
2
, ,

are selected randomly. Except


for the value of the selected parameter j, all other parameter
values of

are same as

, i.e.

=
1
,
2
, .
1

.
+1

of the selected parameter j in

is determined using the


following formula

(18)

Where 1,2, . . , and 1,2, . . , are randomly
chosen indexes. (D is the number of parameters to be
optimized and each parameter is real coded), although k is
determined randomly, it has to be different from i

is a
random number between [-1, 1].If the resulting value falls
outside the acceptable range for parameter j, it is set to the
corresponding extreme value in that range.
V. APPLICATION OF ABC ALGORITHM ON (ED)
PROBLEM:
In ABC algorithm, the position of a food source
represents a possible solution to the optimization problem
and the nectar amount of a food source corresponds to the
quality (fitness) of the associated solution. The number of the
employed bees is equal to the number of food sources, each
of which also represents a site, being exploited at the
moment or to the number of solutions in the population. In
ABC Optimization, the steps given below are repeated until a
stopping criterion is satisfied. [16]
The following steps describe how ABC algorithm is applied to
the problem under consideration:

1. BEGIN
2. Initialize the set of food sources

0
, = 1, . . ,
sources
3. Evaluate each

0
, = 1, . . ,
4. g =1
5. REPEAT
6. FOR = 1 to
7. Generate V
i
g
with X
i
g1
by Using equation 18
8. Evaluate V
i
g

9. IF V
i
g
is Better than X
i
g1

10. V
i
g
= X
i
g

11. ELSE
12. X
i
g
= X
i
g1

13. END IF
14. END FOR
15. FOR = 1 to
16. Select, based on fitness proportional selection food source
X
i
g

17. Generate V
i
g
,with X
i
g

18. Evaluate V
i
g

19. IF
g
i
V is Better than
g
i
x
20. V
i
g
= X
i
g

21. END IF
22. END FOR
23. Generate new food solutions at random for those
whose limit to be improved has been reached.
24. Keep the best solution so far.
25. g=g+1.
26. UNTIL g=MCN
27. END
VI. THE SAMPLE PROBLEM SOLUTION WITH ABC

The function given in Equation 6 is taken as a sample
problem. The number of variables is assigned to 6, while the
iteration number of the algorithm is assigned to 50. The
focus should be on ensuring that the size of the colony is
twice the number of the variables, because half of the colony
will be assigned as employed bees. At the first step of the
algorithm, the colony is created randomly. This colony is
given in Table 1. As seen in Table 1, half of the colony
represents the employed bees and the other half of the colony
represents the onlooker. After creating the initial colony,
employed bees nectars are replaced keeping their minds on
the amount of the nectar in each nectar resources. Employed
bees transfer the amount of nectars and the position
information to the onlooker bees in each cycle.
2
nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria
When the employed bee finds a new nectar resource having
more amount of nectar, it replaces the new resource amount
in mind. The information change in the employed bee mind
is presented for the13th and 14th cycles in Table 2. change of
the nectar resources belong to the 1st and 5th bee mind, in
Table 2, It is seen that the position information change of the
nectar resources belong to the 1st and 5th bee mind, in Table
2. Since those two bees meet the criteria for nectar resources,
having more nectar in the 10th cycle, they changed the
position informations in their minds [17].

TABLEAU 1. THE INITIAL COLONY CREATED RANDOMLY
Employed bees Onlooker bees

113,060 63,091 17,584 14,805 19,889 28,637
171,697 44,791 18,813 13,521 11,355 25,33
106,940 25,918 49,35 14,271 27,953 22,31
209,326 64,073 32,388 21,645 15,771 30,35
197,907 58,238 15,784 17,789 15,381 38,27

109,148 63,091 17,584 14,804 19,889 28,637
171,696 44,791 18,813 13,521 16,810 25,324
200,00 64,073 32,388 21,645 15,771 25,215
197,907 61,968 15,784 17,789 15,380 38,269
171,697 44,791 18,813 13,521 16,81 25,324

TABLEAU 2. THE CHANGE OF INFORMATION IN MIND ACCORDING TO
CYCLES
48th Cycle 49th Cycle

113,060 50,130 21,891 14,611 12,982 12
147,994 50,133 21,888 14,622 12,891 12
106,948 50,097 21,891 14,612 12,818 12
200,00 50,089 21,890 14,622 13,013 12
197,907 50,110 21,886 14,624 12,926 12

113,060 50,074 21,891 14,614 12,796 12
171,697 50,133 21,888 14,622 12,929 12
106,940 50,097 21,891 14,614 12,844 12
200,000 50,089 21,890 14,622 13,013 12
197,907 50,110 21,886 14,606 12,926 12


The ABC-OPF has been developed by the use of
MATLAB version 7.9 and the system configuration is micro
portable processor with 2 GHz speed and 3 GB RAM. It is
tested using the IEEE 30-bus system [18].The system
consists of 41 lines, 6 generators, 4 Tap-changing
transformers, and shunt capacitor banks located at 2 buses
(Figure 2).The parameter settings to execute ABC.OPF are
number of the bees in the colony=20, limit=160,
maxcycle=100, the power mismatch tolerance is 0.001,
S
b
=100, the power demand equal 283.4MW and other
parameters are presented in (Table 3).


Figure 1. IEEE 30-bus Electrical system topology
TABLEAU 3. PARAMETERS OF THE STANDARD IEEE 30-BUS SIX-
GENERATOR TEST SYSTEM

U
n
it
Cost Coefficients Emission Coefficients
c b a c
2
b
2
a
2
d e
1 0 2.0 0.0037 4.09 -5.554 6.49 2.0E4 2.86
2 0 1.7 0.0175 2.54 -6.047 5.64 5.0E4 3.33
3 0 1.0 0.0625 4.26 -5.094 4.59 1.0E6 8.00
4 0 3.25 0.0083 5.33 -3.550 3.38 2.0E-3 2.00
5 0 3.00 0.0250 4.26 -5.094 4.59 1.0E-6 8.00
6 0 3.00 0.0250 6.13 -5.555 5.15 1.0E-5 6.67

To demonstrate effectiveness of the proposed approach,
three different cases have been considered as follows:
Case 1 : Best minimum Fuel Cost
Case 2 : Best minimum Emission Cost
Case 3 : Best Compromise (Fuel +Emission)
The results including the generation cost, the emission
level and power losses are shown in Table 4. This table gives
the optimum generations for minimum total cost in three
cases: first is the minimum generation cost without using
into account the emission level as the objective function
(=1), an equal influence of generation cost and emission
cost in this function and at last a total minimum emission is
taken as the objective of main concern (=0).

TABLEAU 4. THE OPTIMAL RESULTS FOR THE THREE CASES

Variables min max Case 1 Case2 Case 3
PG1 (MW)

50 200 178,1896 68,0584 129,9592
PG2 (MW)

20 80 21,395 71,204 56,5821
PG5 (MW)

15 50 21,395 50,00 25,7065
PG8 (MW)

10 35 21,5015 35,00 35,00
PG11 (MW)

10 30 11,8695 30,00 22,4951
PG13 ( MW)

12 40 12,00 68,0584 20,1588
VG1 (Pu)

0,95 1,1 1,100 1,0516 1,0552
VG2 (Pu)

0,95 1,1 1,0903 1,047 1,0387
VG5 (Pu)

0,95 1,1 1,0591 1,028 1,0088
VG8 (Pu)

0,95 1,1 1,0551 1,0337 1,0204
VG11 (Pu)

0,95 1,1 1,0016 1,0960 1,0847
VG13 (Pu) 0,95 1,1 1,100 1,0994 1,0781
T6-9 0,9 1,1 0,97 1,03 1,07
T6-10 0,9 1,1 1,1 1,05 0, 96
T4-12 0,9 1,1 1,00 1,01 1,00
T27-28 0,9 1,1 1,05 0,98 1,05
Fuel Cost
($/h)

285,8 1404,67 800,9275
934,126

819,997
Emission
Cost ($/ton)

0,230 0,44117 0,3712
0,2174

0,2701

Transmissio
n losses
(MW)
_ _ 9,1783 3,5208 6,5017

Algorithm converges to the 800. 9275 ($/h) which is the
lowest cost in Table 4, and those results are compared with
GA, Bees algorithm, in Table 5, clearly demonstrates the
ability of the proposed approach to find the least generation
cost than the classical and non-classical optimization
approaches It is necessary to note that all control variables
are remained within their permissible limits.







2
nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria
TABLEAU 5. COMPARISON OF DIFFERENT OPF METHODS OF
IEEE 30 BUS SYSTEM.
variable GA [6] BA-OPF [8] ABC-OPF
PG1 (MW)

177,28 176,467 178,1896
PG2 (MW)

48,817 48,736 21,395
PG5 (MW)

21,529 21,730 21,395
PG8 (MW)

21,81 21,272 21,5015
PG11 (MW)

11,325 12,128 11,8695
PG13 (MW)

12,087 12,532 12,00
Fuel Cost
($/h)
802,0012 802,305 800,9275
Losses
(MW)
9,4563 9,467 9,1783
Population 50 40 20
Iteration 100 50 100

In effect we have compared the emission cost calculated
in the case 1 with that of case 3, in see a reduction of
27.23% the gas emission in the atmosphere. The
convergence of fuel cost and emission objective functions for
(=0, =1) are shown in figure 2. Figure. 3 shows the typical
convergence characteristics of best compromise solutions
through the algorithm proceeding, (=0.5)

Figure 2. Convergence Fuel Cost & Emission Cost of ABC-OPF

Figure 3. Convergence Best Compromise Fuel Cost of ABC-OPF

VII. CONCLUSION

In this paper, Artificial Bee Colony Algorithm has been
employed to the multi-objective optimal power flow. This
approach treats economic and emission impact as competing
objectives, which requires some reasonable trade-off among
objectives to reach an optimal solution. The feasibility of the
proposed method for economic power dispatch of power
system with pollution control is demonstrated on IEEE 30
bus system. It can be concluded that the ABC can be applied
to a wide range of optimization problems. In the future,
efforts will be made to incorporate with many constrain
(transient and voltage stability), and practical large sized
problems will be attempted by the proposed methodology.
VIII. REFERENCES
[1] S. A. a. W. P. A Pornrapeepat Bhasaputra, "Multiobjective Bees
Algorithm for Optimal Power Flow Problem ," ecti transactions on
electrical eng. electronics, and communications , vol. 9, no. 1, pp. 56-
63, Feb. 2011.
[2] M. A. Abido, "Environmental/Economic Power Dispatch Using
Multiobjective Evolutionary Algorithms," IEEE TRANSACTIONS
ON POWER SYSTEMS, vol. 18, no. 4, pp. 1529-1537, Nov. VOL. 18,
2003.
[3] S. H. a. S. P, "Economic/Emission Load Dispatch Using Artificial Bee
Colony Algorithm," in Proc. of Int. Conf. on Control, Communication
and Power Engineering, 2010, pp. 338-343.
[4] R. M. Hongwen Yan, "Multiobjective Electricity Power Dispatch
Using Multiobjective Particle Swarm Optimization," in Proceedings of
the 5th WSEAS International Conference on Applied Computer
Science, Hangzhou, China, April 2006, pp. 336-340.
[5] P. N. B. C. E. Z. a. V. P. A. G. Bakistzis, "Optimal power flow by
enhanced genetic algorithm," IEEE Trans. Power Systems, vol. 17, no.
2, pp. 229-236, May 2002.
[6] M B. Mahdad, T. Bouktir and K. Srairi, "OPF with Environmental
Constraints with Multi Shunt Dynamic Controllers using Decomposed
Parallel GA: Application to the Algerian Network," Journal of
Electrical Engineering & Technology, vol. 4, no. 1, pp. 55-65, 2009.
[7] a. A. K. S. J. Hazra, "Environmental Constrained Economic Dispatch
using Bacteria Foraging Optimization," IEEE Transactions on Power
Systems TPWRS, pp. 978-984, Nov. 2009.
[8] T. B. K. S. B. Mahdad, "Methodology based in Conclusion practical
fuzzy rules coordinated with asymetric dynamic compensation applied
to the unbalanced distribution network," International Review of
Electrical Engineering (IREE), vol. 3, no. 2, pp. 145-153, 2007.
[9] A. Lakshmi Devi and O. Vamsi Krishna, "combined economic and
emission dispatch using evolutionary algorithms -a case study ," ARPN
Journal of Engineering and Applied Sciences, vol. 3, no. 6, pp. 28-35,
Dec. VOL. 3, NO. 6, 2008.
[10] Tarek Bouktir, Rafik Labdani and Linda Slimani, "Economic Power
Dispatch of Power System with Pollution Control using Multiobjective
Particle Swarm Optimization," Journal of Pure & Applied Sciences,
vol. 4, no. 2, pp. 57-77, Jun. 2007.
[11] Robert T. F. Ah King, Harry C. S. Rughooputh and Kalyanmoy Deb2,
"Evolutionary Multi-Objective Environmental/Economic Dispatch:
Stochastic vs. Deterministic Approaches," in Evolutionary
Computation, CEC . IEEE Congress, 2006, pp. 946-953.
[12] WU Ya-li , XU Li-qing ZHANG Jin, "Multiobjective particle swarm
optimization based on differential evolution for
environmental/economic dispatch problem," in Chinese Control and
Decision Conference (CCDC), Chine, 2011, pp. 1498-1503.
[13] Prakornchai Polratanasuk , Pisit Mesacharoenwong ,Sumeth
Anantasate and Nopporn Leeprechanon, "Solving Optimal Power Flow
Problem Using Parallel Bee Algorithm," in International Conference on
ELECTRIC. POWER SYSTEMS, 2010, pp. 60-64.
[14] Efren Mezura-Montes, auricio Damian-Araoz and Omar Cetina-
Domngez, "Smart flight and dynamic tolerances in the artificial bee
colony for constrained optimization ," in Evolutionary Computation
(CEC), 2010 IEEE Congress, 2010, pp. 1-8.
[15] S. V. L. N. M. R. R. Srinivasa Rao, "Optimization of distribution
network configuration for loss reduction using artificial bee colony
algorithm," in World Academy of Science, Engineering and
Technology, 2008, pp. 708-714.
[16] S.Hemamalini and Sishaj P Simon, "economic load dispatch with
valve-point effect using artificial bee colony algorithm ," in xxxii
national systems conference, 2008, pp. 525-530.
[17] Ali Ozturk, Serkan Cobanli, Pakize Erdogmus and Salih Tosun,
"Reactive power optimization with artificial bee colony algorithm,"
Scientific Research and Essays , vol. 5, no. 19, pp. 2848-2857, Oct.
2010.
[18] Park, Jong-Bae; Jeong, Yun-Won; Shin, Joog-Rin; Lee, K.Y.; Kim,
Jin-Ho, "A Hybrid Particle Swarm Optimization Employing Crossover
Operation for Economic Dispatch Problems with Valve-point Effects,"
in Intelligent Systems Applications to Power Systems, International
Conference (ISAP), 2008, pp. 978-986.
1 10 20 30 40 50 60 70 80 90 100
790
795
800
805
810
815
820
825
830
835
840
Iterations
F
u
e
l

c
o
s
t


(
$
/
h
)


1 10 20 30 40 50 60 70 80 90 100
0.21
0.215
0.22
0.225
0.23
0.235
0.24
0.245
0.25
E
m
i
s
s
i
o
n


C
o
s
t

(
$
/
t
o
n
)
Fuel Cost
Emission Cost
1 10 20 30 40 50 60 70 80 90 100
815
817
819
821
823
825
827
829
831
833
835
837
839
840
Iteration
B
e
s
t

C
o
m
p
r
o
m
i
s
e



(
F
u
e
l

+
C
o
s
t

)


Best Compromise
2
nd
International Conference on Information Processing and Electrical Engineering, ICIPEE12 -Algeria

Вам также может понравиться