NEDO-MEA Meeting

11 December 2012

MEA Background
Bangkok, Nonthaburi and Samutprakan Service area : 3,192 km2 Maximum Demand : 8,383 MW Substation no.: 149 no.: Number of customer : 3,115,695 115,
Load April , 2012

Time

Distribution facilities
Transformers
Terminal station 230/69-115 kV ( 17 stations) 18,205.88 MVA Substation 69-115/12-24 kV ( 149 stations ) 18,405.00 MVA Distribution 12-24 kV/230-380 V 14,148.68 MVA

TRANSMISSION LINES
230 kV ( 6 LINES ) 49.54 cct-km 115 kV ( 38 LINES ) 722.75 cct-km 69 kV ( 77 LINES ) 897.88 cct-km

DISTRIBUTION LINES
24 kV ( 1,156 LINES ) 12,829.52 cct-km 12 kV ( 464 LINES ) 4,279.18 cct-km Low voltage 27,211.83 cct-km

OPTICAL FIBER
ADSS Structure Cable 10,000.00 cct-km

Operation and maintenance


No subsidiary company 24 kV line maintenance by district office 69 and 115 kV maintenance by Maintenance department Substation equipment maintenance by Maintenance department

Quality of supply

Adder

Energy Regulatory Commission


policy framework as to ensure the equality and fairness nested between consumers, producers, and other relevant interest groups. The primary functions and duties
to oversee the regulations that deal with electricity systems of generation, transmission, distribution, and their system operator. monitoring energy market conditions by tariff review, licensing, approval of power purchase, dispute settlement and fulfilling its mandate, in order to counterbalance each other, to ensure maximum interests of the people and the country

Challenge
1. Power System Power Quality, Reliability, Security Loss Reduction, Economic 2. Service Energy usage efficiency New Service 3. Renewable Energy Manage and Support New Technology (EV, Energy Storage) 4. IT Interoperability and Standard
11

Smart Grid Roadmap


Stage 1 2012 2016 Laying the Foundations Stage 2 2017 2021 Large Scale Implementation Automation substation in all service area (170 stations) Manage and Control LBS in distribution network cover all of service area

40 automation substations

Manage and Control LBS in distribution network cover 30% of service area. Power system

Outage area monitoring and management Outage monitoring and management system for HV and MV network system all network Automatic service restoration (Selfhealing) in some area. Asset management
12

Automatic service restoration (Selfhealing) in all area

Smart Grid Roadmap


Stage 1 2012 2016 Laying the Foundations Stage 2 2017 2021 Large Scale Implementation

Automatic meter reading (AMR) for commercial and industrial customer Service Daily load profile and power consumption monitoring for customer via internet and mobile phone Street light control

13

Smart Grid Roadmap


Stage 1 2012 2016 Laying the Foundations Stage 2 2017 2021 Large Scale Implementation

Support integration of SPP/VSPP and renewable energy Energy conservation & Alternative energy Pilot project of 20 EV and 10 charging stations to study the effect to power system Pilot project of energy storage Building Energy Management System (BEMS)

Monitoring and control SPP/VSPP and renewable energy in widely area Support widely used of EV and charging station and electric vehicle to grid (V2G) Energy Storage for power security Integration of BEMS and home energy management system

14

MEAs Smart Grid Projects


objective
Substation Automation According to IEC 61850 Remote control of distribution switch with Distribution Management System Outage monitor in high voltage and medium voltage system self-healing in some area AMR for Commercial and industrial customer Ready for SPP/VSPP and Renewable Energy connection Pilot use of EV and charging station Pilot use of Energy Storage Building Energy Management System p

EMS

DMS

Project SA BEMS
p

EV

ESS

AMR

p p

p p

p p

p p p p p p p

MEAs Smart Grid Implementation Plan and Budget


Budget (MBaht) Project EMS DMS SA BEMS EV ESS AMR Total 2555 360.3 150.0 20.5 328.172 858.97 2556 40.0 561.8 165.0 34.0 20.5 0.5 822 2557 311.1 475.84 180.0 36.0 15.25 360.85 1379 2558 121.80 200.0 17.0 15.25 20 374.1 2559 121.80 220.0 20.0 362 Total 351.1 1,641.54 915.0 107.0 71.5 20.5 689.022 3,795.66

VSPP
VSPP or Very Small Power Producer is a power generator of a private sector , state agency , state owned enterprise or individual who generate and sell electrical power less than 10 MW to MEA or PEA. Fuels which are used in a power generation process are solar energy , biogas and biomass energy , hydropower , natural gas and etc. The objectives for purchasing electrical power from VSPP are to support an efficient use of resources and reduce pollution effect to the environment

Number of VSPP

Condition or regulations to be authorized as VSPP


Power Generation Using Renewable Energy ( attached 1 ) Power Generation Using Cogeneration Energy ( attached 2 )

The procedure to be authorized as VSPP


1. Procedures and criteria for consideration of power purchase from VSPPs. 2. Conditions for purchasing electrical power from VSPPs. 3. Power purchasing point and connection point. 4. Costs incurred for VSPPs.