Академический Документы
Профессиональный Документы
Культура Документы
Rem Dur
Early Start
Early Finish
1998 S O
1999 J J
2000 F M
06JAN99 17MAR99 09MAR99 13MAY99 19APR99 30APR99 24JUL99 26AUG99 07JUL99 22JUL99 17SEP99 29OCT99
+ Maintenance Projects
148 23JUN98A 17MAR99
HRS x 100
40 36 32 28
Resource/Cost Graph Legend Resource: ETS2RED Peak early usage per Month (Current Estimate) Above maximum usage Above normal usage Normal usage Maximum limit Normal limit Current estimate curve Detail scale (left): HRS
28 24 20 16 12 8 4
24 20 16 12 8 4
J
Early Bar Target Bar Progress Bar Critical Activity
SWDV
S O 1998
J J 1999
F M 2000
Sheet 1 of 1
Activity ID
Early Start
JUL
AUG
1998 SEP
OCT
NOV
DEC
JAN
1999 FEB
MAR
DE Design Phase
ATDESF0805 ATDEWL0820 ATDESF0810 8 10 7 8 10 7 0 17SEP98 0 22DEC98 0 11JAN99 25SEP98 01JAN99 18JAN99 6,144.00 2,616.00 5,320.00
Revise Physical Data Design Develop/Review Procedures Develop Test Scripts
CO Coding Phase
ATCOWL0615 ATCOWL0605 ATCOWL0620 ATCOSF0760 ATCOWL0610 ATCOWL0625 ATCOSF0765 ATCOSF0770 ATCOSF0755 ATCOSF0775 ATCOWL0635 ATCOWL0630 ATCOWL0640 6 41 40 16 64 46 34 10 14 23 8 36 6 0 41 40 16 64 46 34 10 14 23 8 36 6 100 13JUL98A 03AUG98A 0 04SEP98 0 18SEP98 0 29SEP98 0 29SEP98 0 02OCT98 0 13OCT98 0 18NOV98 0 04DEC98 0 23DEC98 0 25DEC98 0 31DEC98 0 16JAN99 30OCT98 12NOV98 16OCT98 25DEC98 04DEC98 20NOV98 28NOV98 19DEC98 18JAN99 02JAN99 18FEB99 22JAN99 2,160.00 5,036.85 14,400.00 3,499.20 23,040.00 16,560.00 12,240.00 8,000.00 480.00 8,280.00 1,600.00 12,960.00 3,840.00
Update Data Dictionary Create Unit & System Test Cases Modify System Logic Review/Create Process Model Review/Create Data Model Revise/Create Dialog Design Modify Process Model Modify Data Model Revise/Create Batch Designs Revise/Create Program Documentation Revise/Create User Views Code and Compile Programs/Modules Update Change Specifications
+ TE Testing Phase
208 165 32 15JUL98A 01MAY99 25,200.00
+ IM Implementation Phase
129 129 0 22SEP98 19MAR99 25,200.00
SWDV
Sheet 1 of 1
Activity ID
ATCOWL0615 ATCOWL0605 ATCOWL0620 ATCOWL0610 ATCOWL0625 MNCOWL0865 ATCOWL0630
Rem Dur
0 41 40 64 46 21 36
Early Start
Early Finish
03AUG98A 30OCT98 12NOV98 25DEC98 04DEC98 27NOV98 18FEB99
MNGR SUBP
1998 O
1999 A
x 100
Resource/Cost Graph Legend Resource: EPG2MEW Total early usage per Week (Current Estimate) Current estimate curve
Project Start Project Finish Data Date Run Date 10JUL98 26JUL02 14SEP98 13NOV96 Early Bar Progress Bar Critical Activity
SWDV
16 14 12 10 8 6 4 2
X 10HRS
18 16 14 12 10 8 6 4 2
O 1998
F
Sheet 1 of 1
A 1999
Top priority
0 0
RPANLD0250 Determine 12 Iterations 0 JUL-20-98A AUG-06-98A MNDESF0750 -1 Update 14 Maintenance 14 Specifications JAN-05-99 DEC-17-98
RPTEHK0311 Select Iteration 12 Activities 0 JUL-28-98A AUG-12-98A MNTESF0790 -1 Define Test 16 Control 16 Procedures JAN-27-99 JAN-06-99 MNIMWL0922 -1 Finalize Test 4 Strategy 4 JAN-28-99 FEB-02-99 MNTESF0795 Execute Tests FEB-03-99 -1 16 16 FEB-24-99 MNTESF0770 -1 Ensure 11 Data/Transaction 11 Consistency MAR-11-99 FEB-25-99
CSCOCH0525 -44 Convert Static 4 and Acquire New 4 Data DEC-16-99 DEC-21-99
0 0
-20 0 0 MAR-03-00
ATTESF0460
SEP-14-98
0 1 1 SEP-14-98
Medium priority
-4 8 8 JAN-01-99
RPANHK0919 -4 Review Project 29 Plan & Create 29 Stage Report FEB-26-99 JAN-19-99
MNANWL0670 Review/Revise 12 Physical Design 0 Requirements AUG-21-98A SEP-03-98A MNANSF0635 Maintenance Project Initiation JUN-23-98A MNDESF0740 Design Physical 12 On-line 0 Architecture AUG-05-98A JUL-16-98A MNCOSF0680 Design Physical 12 Batch 0 Architecture AUG-27-98A JUL-28-98A CSANCH1775 Review Results 9 of Business 0 Process AUG-03-98A AUG-18-98A
0 0
0 0
16 1 1
JAN-28-99
Available time
MNANWL0665 6 Review Prototype 12 and Specify Logic 12 NOV-11-98 NOV-26-98 MNANSF0640 Establish Task 18 Scenarios 0 JUL-24-98A AUG-18-98A
MNIMSF0745 6 Determine 12 System 12 Acceptance DEC-14-98 NOV-27-98 MNANWL0660 Review Required 13 System 0 Specification AUG-19-98A SEP-04-98A
MNTESF0780 7 Specify Audit and 11 Control 11 RequirementsDEC-29-98 DEC-15-98 MNDEWL0749 6 Update 12 Functional 12 Specification DEC-30-98 DEC-15-98
ACT DES
TF OD RD ES EF
Driving relationship Nondriving relationship Critical color
SWDV
Sheet 1A of 2H
Early Start
Early Finish
Late StartAUG S
1996 O N
1997 J J
D JAN
0 100 11SEP96A 10 16 31 33 48 30 32 26 43 28 31 40 31 30 22 0 28 15 15 0 5 10 0 10 0 15 2 5 0 3 15 2 0 50 12SEP96A 15OCT96 0 25SEP96 0 27SEP96 0 30SEP96 0 29OCT96 0 30OCT96 0 01NOV96 0 11NOV96 0 27NOV96 0 04DEC96 0 11DEC96 0 27DEC96 0 16JAN97 0 17JAN97 0 06FEB97 0 0 28FEB97 0 28FEB97 0 03MAR97 0 07MAR97 0 07MAR97 0 14MAR97 0 25MAR97 0 09APR97 0 0 23APR97 0 23APR97 0 25APR97 0 0 14MAY97 0 20MAY97 0 20MAY97 0 23MAY97
Early Bar Progress Bar Critical Activity
APEX
16OCT96
12DEC96 06DEC96 18DEC96 11NOV96 18DEC96 06JAN97 29JAN97 13JAN97 23JAN97 21FEB97 28FEB97 28FEB97 25NOV96 20MAR97 24JAN97 14FEB97 14FEB97 04DEC96
20MAR97 29APR97 21MAR97 16APR97 28FEB97 13MAR97 02APR97 27MAR97 09APR97 20MAR97 22APR97 21APR97 13MAY97 23APR97 24APR97 05MAY97 09APR97
Acme Motors Plant Expansion and Modernization Bars by Department, Early Start
Acme Motors REPORT DATE 19OCT96 RUN NO. 49 12:20 Current/Target Start Dates by Dept/Project
Plant Expansion and Modernization START DATE 15JUL96 FIN DATE 04FEB98 DATA DATE 23SEP96 PAGE NO. 1
Early Start-Current/Target By Proj Automated System 16JUL96A 15JUL96 03SEP96A 03SEP96 10SEP96A 10SEP96 09SEP96A 30AUG96 16JUL96A 15JUL96 15JUL96A 15JUL96 20JAN97 20JAN97 Building Addition 15JUL96A 15JUL96 16SEP96A 30AUG96 Conveyor System 20JAN97 20JAN97 12MAY97 12MAY97 23JUL97 22JUL97
Department ENG
TOTAL 15JUL96A 15JUL96 03SEP96A 30AUG96 10SEP96A 10SEP96 09SEP96A 30AUG96 15JUL96A 15JUL96
PCH
Purchasing Department
ISD
CON
Construction Department
Acme Motors REPORT DATE 19OCT96 RUN NO. 35 11:31 Procurement: Early Finish by Step
Plant Expansion and Modernization START DATE 15JUL96 FIN DATE 04FEB98 DATA DATE 23SEP96 PAGE NO. 1
Procurement Project Item Drawings/ Samples Review and Approve Prepare & Solicit Bids Review/Apprv Bids Award Contract Fabricate/ Deliver
DESCRIPTION
Robotics Automation System TEMPC Temperature Control Equip SYSTC System Controller
Office Building Addition BRICK Brick PUMP Heat Pump FLOOR Flooring
02MAY97 02MAY97
09MAY97 09MAY97
23MAY97 23MAY97
28MAY97 28MAY97
29MAY97 29MAY97
08AUG97 08AUG97
02MAY97
09MAY97
23MAY97
28MAY97
29MAY97
08AUG97
Acme Motors REPORT DATE 19OCT96 RUN NO. 47 12:13 Budgeted Effort and Cost Detail
Plant Expansion and Modernization START DATE 15JUL96 FIN DATE 04FEB98 DATA DATE 23SEP96 PAGE NO. 1
Budget Quantity/Cost for Engineers Quantity Cost Design Engineer Senior Field Engineer Field Engineer Automation Engineer Systems Engineer
DESCRIPTION
TOTAL
160 4800
640 15576 48 1056 1136 28400 336 6720 6 120 524 11528 112 2464 1324 30624
160 4800 Office Building Addition DESGN Design and Engineering Phase
1136 28400
342 6840
414 12420 16 480 336 20160 16 960 430 12900 352 21120
160 4800
260 5720 20 440 992 24800 960 19200 960 19200 1302 26040 24 528 304 6688 1628 37312 352 21120
Acme Motors REPORT DATE 19OCT96 RUN NO. 48 12:16 Earned Value Report - Cost
Plant Expansion and Modernization START DATE 15JUL96 FIN DATE 04FEB98 DATA DATE 23SEP96 PAGE NO. 1
COST ACCOUNT
RESOURCE
ACTIVITY
PCT CMP
ACTUAL ACW
EARNED BCW
BC
CO VAR
SCHE VAR
BUDGET
COMPL COST
ANALYST - Analyst-Systems Automation 11101 11101 11101 11211 11231 ANALYST ANALYST ANALYST ANALYST ANALYST AS100 AS101 AS102 AS205 AS217 100 100 100 100 0 400 1200 5160 1200 600 0 8160 1200 5160 1200 600 0 8160 1200 5160 1200 600 1200 9360 0 0 0 0 0 0 0 0 0 0 -1200 -1200 1200 5160 1200 600 1200 9360 1200 5160 1200 600 1200 9360
ATM ENG - Automation Systems Engineer 11101 11101 11223 11223 11223 11223 11314 11314 11415 11213 11211 11211 11233 11231 11231 11223 11223 12101 12223 12312 12311 ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG ATM ENG AS100 AS101 AS109 AS110 AS111 AS112 AS113 AS117 AS118 AS200 AS204 AS205 AS213 AS216 AS217 AS260 AS270 CS300 CS305 CS400 CS440 100 100 0 0 0 0 0 0 0 100 100 100 0 70 0 0 0 0 0 0 0 570 1760 7040 0 0 0 0 0 0 0 528 2640 880 0 1848 0 0 0 0 0 0 0 14696 1760 7040 0 0 0 0 0 0 0 528 2640 880 0 1663 0 0 0 0 0 0 0 14511 1760 7040 0 0 0 0 0 0 0 528 2640 880 528 2376 880 0 0 0 0 0 0 16632 0 0 0 0 0 0 0 0 0 0 0 0 0 -185 0 0 0 0 0 0 0 -185 0 0 0 0 0 0 0 0 0 0 0 0 -528 -713 -880 0 0 0 0 0 0 -2121 1760 7040 4224 4224 88 88 352 528 1584 528 2640 880 528 2376 880 1320 1584 5280 528 440 440 37312 1760 7040 4224 4224 88 88 352 528 1584 528 2640 880 528 1848 880 1320 1584 5280 528 440 440 36784
DES ENG - Design Engineer 11101 13106 13106 13106 13106 13106 13106 12311 DES ENG DES ENG DES ENG DES ENG DES ENG DES ENG DES ENG DES ENG AS101 BA400 BA469 BA470 BA501 BA530 BA560 CS430 100 100 0 0 100 0 0 0 300 1270 4800 9600 0 0 1680 0 0 0 16080 38936 4800 9600 0 0 1680 0 0 0 16080 38751 4800 9600 540 600 1680 0 0 0 17220 43212 0 0 0 0 0 0 0 0 0 -185 0 0 -540 -600 0 0 0 0 -1140 -4461 4800 9600 540 600 1680 240 240 4800 22500 69172 4800 9600 540 600 1680 240 240 4800 22500 68644
Acme Motors REPORT DATE 19OCT96 RUN NO. 50 12:22 Target / Current Start Dates by Dept/Manager
Plant Expansion and Modernization START DATE 15JUL96 FIN DATE 04FEB98 DATA DATE 23SEP96 PAGE NO. 1
Current Start vs. Target Start Department Supervisor Automation System Building Addition Conveyor System
DESCRIPTION
TOTAL
15JUL96A 15JUL96
20JAN97 20JAN97
16SEP96A 30AUG96
12MAY97 12MAY97
VENDR Vendor
16SEP96A 30AUG96
12MAY97 12MAY97
03SEP96A 30AUG96
23JUL97 22JUL97
09SEP96A 30AUG96
09SEP96A 30AUG96