INTRODUCTION

This measurement schedule has been developed to be used as a tool to facilitate QS staff in taking off quantities of excavation, concrete, reinforcement and formwork in foundation and RC structure

BENEFITS Easy to use Speed in taking off User friendly guides to assist Only by inserting dimensions (nos, length, width & height) quantites such as excavation, concrete work, blinding and formwork are automatically calculated Schedules given assist the user in taking off in a systematic manner

FOUNDATIONS / FOOTINGS / PILE CAPS/ COLUMN BASES SCHEDULE


User guides (to be read together with the schedule below) A. Dimensions to be keyed in - white columns
1. Foundation/base type
- Key in type of foundations - eg. P1, P2 (refer to foundation layout plan) - Pit foundations, if their length exceed four times their width, it shall be considered as trench, separate from pit foundations

B. Dimensions automatically calculated - blue columns


1. Total Depth
- Total depth for excavation - Formula : Height/thickness of foundation (H) + Thickness of blinding + Height of column stump

2. Nos. Off
- Key in numbers of each type of foundation (calculated from foundation layout plan)

2. Maximum Depth of Excavation (to be mentioned in description) SMM2-D.10


- Depth Of Excavation shall be classified as follows:

3. Dimension
- L for length in Meter (Refer to detail drawing for each type of foundation - always take horizontal dimension as length) - W for width in Meter ( Ditto - always take vertical dimension as width) - H for height or thickness of the foundation in Meter (Refer to detail drawing for each type of foundations)

Maximum depth not exceeding 0.25m Maximum depth not exceeding 1.00m Maximum depth not exceeding 2.00m Maximum depth not exceeding 4.00m thereafter in 2.00m stages

} } automatic selection } } } to be keyed-in

4. Blinding - Key in thickness of concrete blinding in Meter 5. Column Stump Height


- Measured from top of foundation to top of ground slab in Meter

3. Excavating pits having both plan dimensions (length & width) less than 1.25m (SMM2-D.12.6)
If any of this pits excvn falls under this category, its will be calculated automatically and separated from the others Formula for quantity: Length (L) x Width (W) x Total Depth - unit M3

4. Excavating pits
Formula for quantity: Length (L) x Width (W) x Total Depth - unit M3 Nos - need to be stated in description

6. Water Table - If there is, key in, in Meter. Check with the designer especially for areas where water table is high. - If none , key in ' 0 ' or leave it blank

5. Excavating trench
The foundation will consider as strip footing/foundation Formula refer to item 4

6. E.O excavating below ground water level


If Water Table Height (item A/6) keyed in, this item will be calculated Formula for quantity: Length (L) x Width (W) x (Total Depth - water table) - unit M3 Pit and trench foundations will be combined under one item

7. Concrete in pit & trench


Formula: Length (L) x Width (W) x Height/Thick (H) - unit M3

8. Concrete blinding
Formula: Length (L) x Width (W) x Blinding Thickness - unit M3

9. Formwork to sides of pit/trench foundations


If Height/Thick (H) exceeding 1M measure in Square meters (M2) Formula: Girth {Length(L)x2 + width(W)x2} x Height(H) If Height/Thick (H) not exceeding 1M measure in meters (M) stating the height in categories: Not Exceeding 250mm high 250mm - 500mm high 500mm - 1.00m high

Please refer to sheet ' WBLFF- TO list' for detail taking off list and order to taking off

FOUNDATIONS / FOOTINGS / PILE CAPS/ COLUMN BASES SCHEDULE


FOUNDATION/ BASE TYPE PIT TRENCH NO. OFF L DIMENSION W H BLINDING THICK COL. STUMP HEIGHT TOTAL DEPTH MAX DEPTH EXCVN. WATER TABLE HEIGHT EXC PITS BOTH PLAN DIMENSION <1.25M NOS. QTY EXCAVATING PITS NOS QTY EXCVTG TRENCH STRIP FDN E.O. EXCVTG BELOW GWL PIT/TRENCH CONCRETE IN PIT TRENCH CONC BLINDING PIT TRENCH <250 FWK TO SIDES OF PIT FDN 250 - 500 500-1000 >1000 (M2) FWK TO SIDES OF FDN TRENCH <250 250 - 500 500-1000 >1000(M2)

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

COLUMN STUMPS SCHEDULE ( NOS & QTY)


User guides (to be read together with the schedule below) Dimensions to be keyed in - white columns
A. Column stumps schedule (nos)
1. Type Key in type of columns ,eg. C1, C2 (refer to column schedule plan/column layout plan) 2. Location Key in location, normally referred to grid line eg. 1/A-H 3. Key in numbers of each type of column along the grid line rows

Dimensions automatically calculated - blue columns


A. Column stumps schedule (nos)
1. Total numbers and type of colums will be transfer to the next schedule

B. Column stumps schedule (Qty)


1. Shape Choose shape of column by clicking arrow down key ( there are 4 choices) Column will be considered as wall when their length exceed four times their width 2. Dimensions L for length in Meter ( if your column is round, dont fill in the dimension) W for width/thick in Meter ( if your column is round, dont fill in the dimension) R for radius in Meter ( for round column only, if your column is square/rectangular/wall dont fill in the dimension) H for height in Meter (measure from top of footing/foundation to top of ground slab)

B. Column stumps schedule (Qty)


1. Type of column and total numbers will be carried from the above schedule 2. Concrete col - M3 Formula: L x W x H x total Nos. (square & rectangular Col) Formula: 3.14 x R2 x H x total nos. (round col) 3. Concrete wall - M3 Formula: L x W x H x total Nos. Stating the thickness in the following categories: not exceeding 100mm 100mm - 150mm 150mm - 300mm exceeding 300mm 4. Formwork Column - M2 Formula: (L + W)2 x H x total Nos.(square & rectangular Col) Formula: 2 x 3.14 x R x H x total nos. (round col) 5. Formwork Wall Formula (faces): (L x H)2 x total Nos. - M2 Formula (ends): H x2 x total Nos. - M Stating the width in the following categories: Not exceeding 250mm Wide 250mm - 500mm wide exceeding 500mm wide (state the width)

Please refer to sheet ' WBLFF- TO list' for detail taking off list and order to taking off

COLUMN STUMPS SCHEDULE (NOS.)


TYPE LOCATION

TOTAL

COLUMN STUMPS SCHEDULE (QTY)


TYPE COLUMN TOTAL NO SHAPE L DIMENSIONS W R
(Round col.)

CONCRETE H COL <100

CONCRETE WALLS 100-150 150-300 >300

FORMWORK COLUMNS
SQ/REC ROUND

FORMWORK WALLS FACES <250 ENDS 250-500 >500 -

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

GROUND BEAM SCHEDULE (Non suspended Ground Floor Slab) User guides (to be read together with the schedule below) A. Dimensions to be keyed in - white columns
1.Location/ Grid line Refer to layout floor plan - horizontal & vertical grid 2. Dimensions L = Total length per grid line in Meter W = width of beam in Meter H = heigth of beam in Meter 3. Deductions CL = last column on left (refer to grid line - if the grid line starts from the center take half) CI = Intermediate columns along grid line CR = last column on rigth (refer to grid line - if the grid line starts from the center take half) Pits = length/width of pits/footings along grid line Slab = Thickness of slab along grid line 4. Blinding Thickness Thickness of blinding for the beam

B. Dimensions automatically calculated - blue columns


1. Nett Length for Concrete - M Formula = L - CL - CI - CR 2. Nett Length for Excavation - M Formula = L - Pits 3. Nett Depth for excavation - M Formula = H + blinding thickness 4. Quantity for Excavation trench - M3 Formula = Nett Length excavation x W x Nett Depth 5. Quantity For Concrete - M3 Formula = Nett length concrete x W x H 6. Quantity For Blinding - M3 Formula = Nett length concrete x W x Thickness 7. Formwork - M/M2 If Height/Thick (H) exceeding 1M measure in Square meters (M2) Formula: Nett Length concrete x Height (H) If Height/Thick (H) not exc. 1M measure in meters (M) stating the height in categories: Not Exceeding 250mm high 250mm - 500mm high 500mm - 1.00m high

Note: Beam for non suspended slab measured full size. Concrete bed measured in between beams

GROUND BEAM SCHEDULE (Non Suspended Ground Floor Slab)


LOCATION/ GRID LINE L DIMENSIONS W H CL CI DEDUCTIONS CR PITS SLAB NETT LENGTH CONC NETT LENGTH EXCVN NETT DEPTH EXCVN EXCVN. TRENCH CONC. BLINDING THK QTY FORMWORK NOT EXC. 1.0M HIGH (M)
<250MM 250-500MM 500MM-1.0M EXC. 1.0M

(M2) -

TOTAL

GROUND BEAM SCHEDULE (Suspended Ground Floor Slab)


User guides (to be read together with the schedule below)
A. Dimensions to be keyed in - white columns
1.Location/ Grid line Refer to layout floor plan - horizontal & vertical grid 2. Dimensions L = Total length per grid line in Meter W = width of beam in Meter H = heigth of beam in Meter 3. Deductions CL = last column on left (refer to grid line - if the grid line starts from the center take half) CI = Intermediate columns along grid line CR = last column on rigth (refer to grid line - if the grid line starts from the center take half) Pits = length/width of pits/footings along grid line Slab = Thickness of slab along grid line 4. Blinding Thickness Thickness of blinding for the beam

B. Dimensions automatically calculated - blue columns


1. Nett Length for Concrete - M Formula = L - CL - CI - CR 2. Nett Length for Excavation - M Formula = L - Pits 3. Nett Depth for excavation - M Formula = H - Slab thickness + blinding thickness 4. Quantity for Excavation trench - M3 Formula = Nett Length excavation x W x Nett Depth 5. Quantity For Concrete - M3 Formula = Nett length concrete x W x (H - slab thickness) 6. Quantity For Blinding - M3 Formula = Nett length concrete x W x Thickness 7. Formwork - M/M2 If Height/Thick (H) - slab thickness exceeding 1M measure in Square meters (M2) Formula: Nett Length concrete x (Height (H) - slab thickness) If Height/Thick (H) - slab thickness not exc. 1M measure in meters (M) stating the height in categories: Not Exceeding 250mm high 250mm - 500mm high 500mm - 1.00m high

Note: Beams for suspended slab measured up to soffits of slab Concrete bed measured across beams

GROUND BEAM SCHEDULE (Suspended Ground Floor Slab)


LOCATION/ GRID LINE L DIMENSIONS W H CL CI DEDUCTIONS CR PITS SLAB NETT LENGTH CONC NETT LENGTH EXCVN NETT DEPTH EXCVN EXCVN. TRENCH CONC. BLINDING THK QTY FORMWORK NOT EXC. 1.0M HIGH (M)
<250MM 250-500MM 500MM-1.0M

TOTAL -

ORK
EXC. 1.0M

(M2) -

BAR REINFORCEMENT SCHEDULE


User guides (to be read together with the schedule below)

A. Dimensions to be keyed in - white columns


1. Reference Refer to grid line/ types/items 2. Reinforcement Bar Ref Size Reference of bar (top/bot/by coding/links/stirrups/ etc.) Size/Diameter and type of bar Choose by clicking arrow down key T = High tensile bar R = Mild steel bar (for this schedule, only T & R bar provided. If there is Y bar (high yield) take it as T bar. No Each Number of bars in each item Nos. Off Number of items Length Total length of bar together with bends/hooks/etc. For minimum bend and hook allowances refer to BS4466:1989 (as table below) MILD STEEL BARS Bar size Hook Bend Allowance Allowance 6 8 10 12 16 20 25 32 40 100 100 100 110 150 180 230 290 360 100 100 100 100 100 100 130 160 200 HIGH TENSILE/HIGH YIELD BAR Bar size Hook Bend Allowance Allowance 6 8 10 12 16 20 25 32 40 100 100 110 140 180 220 350 450 560 100 100 100 100 100 110 180 230 280

B. Dimensions automatically calculated - blue columns


1. Main bar Formula: Length x No. Each x Nos. off

2. Binders/links/stirrups Formula: Length x No. Each x Nos. off Formula for No. Each = length / centers + 1

Or For Mild Steel Bar - Hook 9D, Bend 5D For High Tensile - Hook 11D, Bend 5.5D 3. Remarks

BAR REINFORCEMENT SCHEDULE


REFERENCE REF REINFORCEMENT BAR SIZE NO EA NO OFF MAIN BARS T16 T20 1.579 2.467 BINDER R9 0.499 REMARKS R10 0.617 R12 0.888 -

LENGTH

T6 0.222 -

T10 0.616 -

T12 -

T22 2.985 -

T25 3.855 -

T32 6.313 -

R6 0.222 -

R8 0.395 -

LENGHT : MULTIPLY BY : TOTAL :

0.888 -

COLUMNS SCHEDULE ( NOS & QTY)


User guides (to be read together with the schedule below) Dimensions to be keyed in - white columns
A. Columns schedule (nos)
1. Type Key in type of columns ,eg. C1, C2 (refer to column schedule plan/column layout plan) 2. Location Key in location, normally referred to grid line eg. 1/A-H 3. Key in numbers of each type of column along the grid line rows

Dimensions automatically calculated - blue columns


A. Columns schedule (nos)
1. Total numbers and type of colums will be transfer to the next schedule

B. Columns schedule (Qty)


1. Shape Choose shape of column by clicking arrow down key ( there are 4 choices) Column will be considered as wall when their length exceed four times their width 2. Dimensions L for length in Meter ( if your column is round, dont fill in the dimension) W for width/thick in Meter ( if your column is round, dont fill in the dimension) R for radius in Meter ( for round column only, if your column is square/rectangular/wall dont fill in the dimension) H for height in Meter (measure from top of footing/foundation to top of ground slab)

B. Columns schedule (Qty)


1. Type of column and total numbers will be carried from the above schedule 2. Concrete col - M3 Formula: L x W x H x total Nos. (square & rectangular Col) Formula: 3.14 x R2 x H x total nos. (round col) 3. Concrete wall - M3 Formula: L x W x H x total Nos. Stating the thickness in the following categories: not exceeding 100mm 100mm - 150mm 150mm - 300mm exceeding 300mm 4. Formwork Column - M2 Formula: (L + W)2 x H x total Nos.(square & rectangular Col) Formula: 2 x 3.14 x R x H x total nos. (round col) 5. Formwork Wall Formula (faces): (L x H)2 x total Nos. - M2 Formula (ends): H x2 x total Nos. - M Stating the width in the following categories: Not exceeding 250mm Wide 250mm - 500mm wide exceeding 500mm wide (state the width)

Please refer to sheet ' FRAME- TO list' for detail taking off list and order to taking off

COLUMN SCHEDULE (NOS.)


TYPE LOCATION

TOTAL

COLUMNS SCHEDULE (QTY)


TYPE COLUMN TOTAL NO SHAPE L DIMENSION W R
(Round col.)

CONCRETE H COL <100

CONCRETE WALLS 100-150 150-300 >300

FORMWORK COLUMNS
SQ/REC ROUND

FORMWORK WALLS FACES <250 ENDS 250-500 >500 -

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

FLOOR & ROOF BEAMS SCHEDULE


User guides (to be read together with the schedule below)
A. Dimensions to be keyed in - white columns
1.Location/ Grid line Refer to layout floor plan - horizontal & vertical grid 2. Shape Choose shape of column by clicking arrow down key (there are 3 choices) Attached for beams attached with slabs on both sides Isolated for beams which not attached with any slab End for beams at the end of slab 3. Dimensions L = Total length per grid line in Meter W = Width of beam in Meter H = Heigth of beam in Meter 4. Floor Height Measure from top of floor slab to top of upper floor slab (next floor level) 5. Deductions CL = Last column on left (refer to grid line - if the grid line starts from the center take half) CI = Intermediate columns along grid line CR = Last column on rigth (refer to grid line - if the grid line starts from the center take half) Slab = Thickness of slab along grid line

B. Dimensions automatically calculated - blue columns


1. Nett Length for Beams- M Formula = L - CL - CI - CR 2. Quantity For Concrete - M3 Formula = Nett length beam x W x (H - slab thickness) Isolated beams and attached beams are measured separately 3. Formwork - M2 GIRTH Girth for isolated beam = W + 2H Girth for attached beam = W + 2(H-slab thickness) Girth for end beam = W + (H-slab thickness)+ H QTY Formula : Girth x Nett length Formwork for soffits of beams over 3.5m measured separately and stating the height in further stages of 1.50m

Note: Beams for suspended slab measured up to soffits of slab Concrete slab measured across beams

FLOOR/ROOF BEAMS
LOCATION / GRID LINE SHAPE L DIMENSIONS W H FLOOR HEIGHT CL DEDUCTIONS CI CR SLAB NETT LENGTH BEAM CONCRETE BEAMS ISOLATED BEAMS ISOLATED GIRTH ATTACHED END FORMWORK
QTY/SOFFIT HEIGHT

<3.50 -

>3.50 -

TOTAL

ELEMENT : WORK BELOW LOWEST FLOOR FINISH


TAKING OFF LIST NO A ITEM Column Bases/Pad footings/ Strip footing/Pile caps 1 2 3 4 5 6 7 1 2 3 1 2 3 4 5 6 1 2 3 4 5 6 7 8 DETAIL MEASUREMENT Excavations Disposal excavated material Filling to excavation Blinding Concrete Formwork Reinforcement Concrete Formwork Reinforcement Excavations Disposal excavated material Blinding Concrete Formwork Reinforcement Excavations (bed) / Filling (slab) Disposal excavated material (bed) Hardcore DPM Blinding Concrete Formwork Reinforcement UNIT M3 M3 M3 M3 M3 M/M2 KG M3 M2 KG M3 M3 M3 M3 M/M2 KG M3 M3 M2/M3 M2 M3 M3 M/M2 KG/M2 REMARKS

Same quantities as per excavation Qty. excavation - qty. concrete

Column Stumps

Ground Beam

Bed/Slab

ITEM NO.
A

ORDER TO TAKING OFF


EXCAVATION

UNIT

DESCRIPTIONS

SMM REF.
Section D General Rules; D.10

REMARKS

Depth classification; Max depth n.ex. 0.25m " 1.00m " 2.00m " 4.00m thereafter in 2.00m stages Starting Level; Ground level, Reduced Level, Formation level or such level which excavation will commence (normally start from Formation level, a level which formed after earthwork has been done) Quantity for excavation is measured from the actual dimension/size as shown on the drawings/plans. Std. Spec C/3.7 & 8

D.11

A.1

Reduced level

M3

Excavating to reduce level, Maximum depth not exceeding ..

D.12.4

area concrete bed (if suspended grd flr slab this item not measured)

A.2

Pits Pile caps Pad footings

M3

Excavating pits to receive .. starting from . level, maximum depth not exceeding (In. no) Excavating pits to receive .. starting from . level, maximum depth not exceeding , both plan dimensions less than 1.25m (In. no)

D.12.6

D.12.6

All pits excavation can grouped together. Starting level normally from formation level. For both plan dimensions (length & width) less than 1.25m measured separately. Stating the number (total number of pits irrespective the size)

ITEM NO.
A A.3

ORDER TO TAKING OFF


EXCAVATION (cont'd) Trench Strip footing Ground beam

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M3

Excavating trench to receive .. starting from . level, maximum depth not exceeding

D.12.7

All trench excavation can grouped together as foundation, but for purpose of valuation and v.o, it's easier to measure separately.

A4

Extra Over Items Excavating in rock

M3

Extra Over excavation in rock

D.12.2

Also can be measured as an item by itself. ( not as E.O ). Extra Over for each of the various types of excavation (each type of excavation has their own E.O). Quantity can be measure by allow % of the excavation or actual quantity of the rock (depend on engineer's proposal). Std. Spec C/.6.2

Excavating below ground water level

M3

Extra Over Excavating below ground water level

D.12.14

For area which water level is high. E.O to all types of excavation irrespective of depth. of excavation (each type of excavation has their own E.O). Quantity can be measure by allow % of the excavation or actual quantity of the rock (depend on engineer's proposal).

A5

Disposal of water Water in the ground

ITEM

Disposal of water in the ground for keeping the excavations free of ground water

D.16

If there is an item for excavating below ground water level. Std. Spec C/3.9

ITEM NO.
A A6

ORDER TO TAKING OFF


EXCAVATION (cont'd) Disposal of excavated material Disposal on site

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M3

Disposal of excavated material within site in permenent spoil heaps, ..meter from the excavation. Remove excavated material within site in m distance from the excavation. Spread within site excavated material Disposal of excavated material off site at contractor own source

D.18

All types of excavation can be grouped together To be save allow both types of disposal

M3

D.18

M3 Disposal off site M3

D.18 D.19

A7

Filling Filling to excavations

M3

Filling to excavations, material arising from the excavation Filling to excavations, material to be obtained off site at contractor own source Filling to excavations, material .. deposited and compacted in layers, *mm maximum thickness. Filling to make up levels over 250mm thk, material arising from the excavation Filling to make up levels n.ex 250mm thk, material to be obtained off site, hardcore as specified, average thickness mm.

M3

D.23 & 25 Filling materials: a. Material arising from the excavation b. Ditto to be selected and treated D.23 & 25 c. Material to be obtained off site Filling to all types of excavation can be D.23 & 25 grouped together D.27 Std. Spec C/4.12 D.23 & D.26

M3

Filling to make up levels

M3

M2

D.23 & D.26

A8

Surface treatment

M2

Applying anti-termite treatment as specified

D.30.2

Std. Spec - apply to area ground slab (C/4.13)

ITEM NO.
B B.1

ORDER TO TAKING OFF


CONCRETE WORKS IN-SITU CONCRETE

UNIT

DESCRIPTIONS

SMM REF.
F.1 Generally

REMARKS

Plain in-situ concrete / Reinforced in-situ concrete Grade concrete F.2.1 Thickness categories: Not exceeding 100mm 100mm - 150mm 150mm - 300mm exceeding 300mm

F.3

Concrete Categories: 1. Foundations in trenches 2. Isolated foundation bases 3. Ground Beam 4. Pile caps 5. Beds 6. Suspended slabs 7. Isolated columns

Plain concrete (blinding)

M3

Plain in-situ concrete grade . blinding bed; laid on earth or hardcore; not exceeding..thick.

All blinding works can grouped together under one item.

Reinforced concrete

M3

Reinforced in-situ concrete grade . in.

In Follow concrete categories. Column stump is under isolated column.

ITEM NO.
B B.2

ORDER TO TAKING OFF


CONCRETE WORKS (CONT'D)

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

F.8.4 REINFORCEMENT KG ..mm Diameter mild steel bar as links, stirrups, binders and the like in foundation

Classification: In foundation (bases, grd beam & pile cap) In ground slabs (beds) In Isolated column (stump)

KG

..mm Diameter high tensile deformed bar as straight and bend bars in ground beam. F.8.5 Categories: Straight and bend bars Curved bars Links,stirrups, binders and the like Spacers and chairs Curved bar Bar required to be formed to radius not exceeding the critical radius. If not, it will consider as straight bar. Size () 6 8 10 12 16 20 25 Critical Radius (mm) 2500 2750 3500 5000 7500 14000 30000

KG

High tensile deformed bar in foundation; ..mm diameter, straight and bent.

Allowance for bend and hook shall follow BS 4466:1989

ITEM NO.
B B.2

ORDER TO TAKING OFF


CONCRETE WORKS (CONT'D) REINFORCEMENT (cont'd)

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M2

Fabric reinforcement ; In ground slab; reference

F.9.2

Classification follows as bar reinforcement Quantity measured as the area covered.

Fabric reinforcement ; strip ...mm width; in ground slab; reference

F.9.4

B.3

FORMWORK

F.10.1

Categories; Foundations and beds (footings, pile caps bases, ground beams) Isolated features (stumps)

F.11.1

Height categories; (for height n.ex. 1m) Not exceeding 250mm high 250mm-500mm high 500mm-1.00m high

M2

Formwork to edges and faces of foundations Formwork to ground beam; 250mm500mm high.

WATEPROOFING AND ASPHALT WORK

Classfication; A layer of polythene sheet as specified damp proof membrane; .mm thick; laid on blinding. Damp proofing and tanking

ELEMENT : FRAME
TAKING OFF LIST NO A Columns ITEM 1 2 3 DETAIL MEASUREMENT Concrete Formwork Reinforcement UNIT M3 M2 KG REMARKS

Beams Floor beams Roof beams

1 2 3

Concrete Formwork Reinforcement

M3 M2 KG

ex. 3.5m in stages 1.5m

ITEM NO.
B B.1

ORDER TO TAKING OFF


CONCRETE WORKS IN-SITU CONCRETE

UNIT

DESCRIPTIONS

SMM REF.
F.1 Generally

REMARKS

Reinforced in-situ concrete Grade concrete

F.3 F.3.14 F.3.14 F.3.15

Concrete Categories: 1. Beams (attached and end beams) 2. Isolated beams 3. Isolated columns

Reinforced concrete

M3

Reinforced in-situ concrete grade . in.

In (follow concrete categories)

F.8.4 B.2 REINFORCEMENT KG Mild steel bar in ..., ..mm diameter as links,stirrups, binders and the like. F.8.4.c F.8.4.j

Classification: In suspended slabs (attached beams) In Isolated column, beams, lintels

KG

High tensile deformed bar in .; ..mm diameter, straight and bent. F.8.5 Categories: Straight and bend bars Curved bars Links,stirrups, binders and the like Spacers and chairs

KG

..mm Diameter high tensile deformed bar as straight and bend bars in

ITEM NO.
B B.2

ORDER TO TAKING OFF


CONCRETE WORKS (CONT'D) REINFORCEMENT (cont'd)

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

Curved bar Bar required to be formed to radius not exceeding the critical radius. If not, it will consider as straight bar. Size () 6 8 10 12 16 20 25 Critical Radius (mm) 2500 2750 3500 5000 7500 14000 30000

Allowance for bend and hook shall follow BS 4466:1989

B.3

FORMWORK

M2

Formwork to sides and soffits of beams, horizontal

F.10.1 F.10.1.d F.10.9

Categories; Isolated features (beams, columns) Height categories; (for soffits of beam over 3.50m ) Stating the height in further stages of 1.50m

F.14.1

Classification for formwork to beams a. Horizontal b. Sloping n.ex 15 from horizontal c. Sloping over 15 from horizontal