Architectural Millwork Plan view indicates cabinets check for elevation at each location. Lobby security desk layout and space sufficient for all controls and panels? Scope of built-in items vs. furniture and loose items determined? Wall cabinets shown in dashed lines match elevations? Food service equipment, drop-ins, buffets, equipment cutouts coordinated? Space above wall cabinets closed-off with a drywall soffit? Elevations and plan views indicate same cabinet and casework layout. Millwork wall panels include details for attachment, interface with adjoining walls? Column wrap details coordinated with walls (ceiling interface, support, call-outs) MEP rough-in provisions considered in millwork design? Types of laminates indicated locations appropriate? Manufactured casework includes dimensions (match standard sizes?) Wood finish to match trim, casing, doors, furniture? Custom millwork units (extent of details design required?) Open shelving, cabinet doors, and counter heights, shown on drawings. Sub tops required below stone counters. Supports and backing shown in walls (who provides?) Grading and quality standards given (WIC Premium)? Temperature and climate control at time of installation. Ventilation requirements for finish application. Temporary humidity control equipment required Cabinet hardware, accessories, ornamental metals, glass, stone, (scope included) Toe space details, do they allow for floor tolerances?

1 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Doors/Frames/Hardware Door schedule provided. Door openings on drawings all have a Door Number. Door ratings shown at rated wall conditions (part of schedule) Door undercut shown (compare to floor finishes and threshold in room) Doorframe throat sizes are determined from wall schedule? Electronic door hardware required (check with security drawing) Magnetic hold opens shown at exit locations (check fire alarm drawing) Electric hardware, access control, monitors, handicap openers who installs scope? Aluminum door frames not shown in rated walls? Rated doors and frames; can they be made without special testing? Custom door and frame profiles required? Blockouts for floor-mounted closures shown slab thickness allow? Hardware schedule complete (correct for door function?) Special doors in sound walls hardware shown? (STC ratings called out?) Door thickness sufficient for hardware specified? Mounting blocks required for attaching door closers? Hollow metal specifications call for reinforcements for closures, hinges, etc.? Hardware ADA requirements shown (part of drawings?) Hardware carries appropriate U.L. listing for its application? Fire doors shown where required check door schedule. Details for pocket doors, slider doors, BI-fold boors, blind doors, etc? Windows have a type and number on the drawings (frame call out) Gates have a door number (part of separate section?) What is hardware? Overhead doors find all locations on drawings and compare to list in specs. Doors listed in schedule found on the plan views with corresponding number

2 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Interior Walls Wall types shown on plan views. Specs include mildew resistant drywall products (check exposed areas) Wall type schedule provided. Fire ratings coordinated with wall types and locations Dimensions for walls shown from grid lines (check dimension strings) Fire rated shafts indicated on drawings. Demising walls required verify occupancy and building types. Plumbing chase walls have mildew resistant drywall spec Clear note all dimensions are from face of stud or face of finish. Elevations show wall mounted items or backing locations with dimensions Door and window frame details in walls shown. Expansion joints shown installation details indicated in walls. Walls to structure shown and coordinated with HVAC and plumbing. Cement board or better called for at tile or stone finishes. Returns shown at window heads, jambs, and sills. Rated shaft walls shown at all elevators, duct chases, and other shafts Shaft walls extending to roof, exhaust, or return air (special drywall spec) Horizontal duct enclosures shown on Architectural check against Mechanical Sealants called for where required (who provides sound caulking) Insulation shown in wall types (thermal or sound) Sound ratings specified located on drawings with correct wall type. Wall backing located where needed (check elevations)? Chase walls shown with proper width for plumbing. Walls built around unusual structural elements detailed (not just a wall type?)

3 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Ceilings Soffits shown at ceiling transitions and height changes Acoustic ceiling types called out. Ceiling heights shown on reflected ceiling drawings Ceiling types on reflected ceilings match room finish schedule Special ceiling finish required in kitchen and food prep areas. Suspended ceilings require added support, bridging, or framing. Vaulted or raised ceilings can be installed (review MEP routing in ceiling space) Items mounted to ceilings details shown? Sprinkler heads, diffusers, lights in ceilings shown coordinate with MEP drawings. Areas without ceilings require special treatment of exposed items? Hard lids shown in all toilet room areas? Wires required for light fixtures who provides? Insulation required above ceilings shown (revise to underside of slab/roof) Ceilings types specified with 3 manufacturers Face drops required at wall openings or room divisions? Are there blind pockets at exterior wall how do ceilings tie-in? Starting points for installation noted on drawing Review MEP device locations shown on Architectural with MEP drawings

4 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Flooring Recesses shown in slabs for all thickset finishes. Flooring finishes indicated on finish plan match schedule? Room Finish Schedule includes flooring type in each room Flooring finishes noted on drawings included in specifications. Colors and styles been selected and/or products specified? Details shown at dissimilar floor finishes. Proper surface preparation specified. Flooring expansion joints shown. Waterproofing shown and detailed under finishes where required. Stone or tile joints detailed where critical. Wood flooring slab depressed, sub floor, vapor barrier, sleepers, insulation shown? Expansion joints located, are divider strips properly located to minimize cracking Thresholds shown and ramps, meet ADA requirements? Moisture barrier specified below resilient and sheet flooring? Interior Finishes Room finish schedule complete. Painting schedule issued shown in finish schedule. All scheduled finishes specified. Hard finishes account for construction tolerances Wall finishes proper for the application (wall washes and gloss paint don't mix)? Details developed showing typical locations and heights for wall mounted items.

5 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Operable Partitions Structural Drawings for adequate structural support for the operable walls. Point loading conditions identified Structural support system meets the maximum deflection required. Continuous support system with bolted connections to allow adjustment Support and dimensions in the pockets where the partition system "stacks" Floors designed to ensure that there is no more than 1/8" maximum deflection. Finish materials at the storage pockets designed for durability and impact resistance Field installation of any applied wall covering specified. Location of sprinkler heads do not interfere with the partition system Review above ceiling details MEP distribution does not interfere with supports. One-hour wall shown above the ceiling at each partition panel location Toilet Accessories & Partitions Toilet accessories located in typical elevations. Toilet partitions dimensions per ADA, ceiling supported, floor mounted? Supports in ceilings and walls for partitions Accessory schedule included in specifications Miscellaneous Specialties Entrance mats shown with depressions detailed Vertical chutes mail, trash, linen, - shown and specified? Trash compactors size, rolling tracks, MEP distribution, containment, railings. Dock levelers bumpers, ledge angles, pit sizes, wiring, Window washing equipment tie-downs, electrical, sleeves, davit supports. Fire shutters detailed and connections called for in electrical drawings? Kitchen equipment MEP connections, fire suppression, equipment lists, dimensions Blinds/curtains attachment, support, soffits, curtain tracks, concealed pockets. Hospital equipment services identified, installation, backing, deferred approvals. Raised flooring calculations, pedestals, grounding, ramps, rails, floor depressions. Lobby directories recessed, lighted, wiring, supports, Signage per code, supports, lighted, ADA, fire/life/safety, sizes, locations. Projection screens mounting, wiring requirements, ceiling height, controls Security equipment reinforcing, ventilation, safety deposit boxes, wiring, Flagpoles size, footing requirements.

6 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Elevators/Escalators Elevator subcontractor review for Elevator Code requirements. Machine rooms located and dimensioned Elevators casing holes for hydraulic elevators specified for subsoil conditions. Equipment voltages coordinated with electrical check Electrical drawings. Cab finishes specified (or carried as an allowance) Threshold details coordinated with concrete slab edge (sill support by elevator sub?) Elevator divider beams shown, hoist beam included Elevator platform and equipment steel framing (per elevator sub, who provides) Piping from equipment rooms to elevators shaft roughed in. MEP services not located in Machine Room that are not specific to room. Fire sprinkler pre-action required? Motor sizes and pump sizes coordinated with electrical. Emergency telephone in the elevator? Elevator Pit ladders, pit lights, outlet, sump, and waterproofing? Hoist way has no pipes or ducts run into the shafts. Location of main control panel shown and detailed. Special framing required at main lobby for entrances? Proper ventilation shown in machine rooms. Skirts and surrounds on escalators (who provides?) Cants required and detailed in hoist ways? Hydraulic pits and jack hole size designed (early installation) Overhead support and/or rigging beams shown for Traction elevators. Proper elevator pit dimensions (per manufacturer)? Heat detectors shown at top of hoist ways access panel from outside shown? Elevator divider screens shown on drawings 6H screens between elevators. Elevations from floor to floor do not exceed elevator manufacturer height limits. Elevator override at top of hoist way has proper dimension clearance. Elevator pits include sumps ands sump pumps with storage tank to collect water.

7 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Plumbing Plumbing equipment specified and located on drawings. Under floor plumbing coordinated with foundations and pits. Floor drain and clean-out types coordinated and finish floor materials. Overhead pipes routed around electrical rooms. Roof drains shown at low point of roofs check Architectural. Overflow drains shown with separated piping or are their scuppers? Plumbing trees pre-assembled at chase walls (coordinate with wall types) Plumbing pits, vaults, and sumps detailed (monitoring, sleeves, link seals) Floor sinks, drains, troughs, janitor sinks details and blockouts needed Cleanouts are accessible in non-architectural areas. Adequate room around fixtures to meet handicap codes. Condensate piping shown to equipment including secondary condensate. Natural gas system piping show to required devices meter shown? Seismic bracing and seismic joints show on drawings method of support. Piping shown to all plumbing devices Pipe sizes are labeled on floor plans Pipe risers and mains get increasingly larger as more devices are added to system Waste and vent diagrams shown Isolation valves shown for domestic water Domestic hot water heating system shown and detailed. Waste piping shown to all drain locations check Architectural for proposed drains. Horizontal waste piping has proper fall.

8 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Fire Protection Sprinkler risers shown and drawn to scale at service entries. Sprinkler head placement coordinated with Architectural. Water curtain / deluge system at exterior walls / glass line. Fire pump and controller sized and located Fire pump room dimensioned for proper clearances Device schedule, indicator panel, sequence of operation on drawings. Sprinkler head centering or other spacing requirements described. Pressure reducing valves shown required? Fire Department Connection shown (and location accessible). Sprinkler drains shown on Plumbing drawings or near FCA riser. Fire hose cabinets located on drawings per code? Special requirements noted above NFPA part of documents? Rolf-Jensen report incorporated into Documents (outside consultant). Custom color head covers or recessed sprinkler heads required Fire pumps coordinated with electrical and emergency generator.

9 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


HVAC Overlay ductwork drawings with electrical, structural and architectural. Equipment rooms detailed and proper clearances shown. Ductwork sizes indicated on drawings Systems to each room are complete supply, return, exhaust Piping installation floor mounted, suspended from above (support available?). Separate piping drawings for hydronic water systems included. Device schedule provided for air distribution and other items Shaft locations and sizes match Architectural drawings. Louvers required and match Architectural elevations. Chilled water and heating water shown to all equipment. FCU units have condensate drain pans and drainage piping Condensate piping shown from all equipment to a drain location (secondary). Equipment supports and pedestals detailed? Equipment rooms dimensioned. Ceiling space enough for routing of mains Voltages of equipment coordinated with electrical. Use of ceiling space for return air? Other impacts to Architectural and electrical. Building controls sequence of operation provided. Piping sizes are shown and valves identified as needed for control (risers) Exhaust shown to all toilet rooms. Equipment pads shown on Structural Large ducts fit in available ceiling space (below beams) Flex connectors and vibration isolation shown and specified Specifications and mechanical details have same requirements. Reflected ceiling drawings and Mechanical drawings show same air devices Seismic bracing and seismic joints shown on drawings Structural supports shown for rooftop equipment. Equipment curbs designed for slopes in roof structure. Access panels shown in walls and hard ceilings (approved by Architect) Coordination drawings required in specifications (sign-off procedure) Project schedule allows for equipment lead times and fabrication Fire dampers shown in all the required locations (check rated wall locations)? Energy Management System shown and coordinated with controls. Shut down of all equipment handles by controls equipment (fire alarm interface) Low voltage control wiring outlined (who provides this scope?) Smoke control system designed and operation sequence listed? Stair pressurization design complete (coordinated with fire alarm)
10 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Electrical All items on drawings include a specification section. Power plans complete including panel schedules filled out Short Circuit study completed Title 24 calculations completed by Engineer Power routed to devices, motors, and equipment compare to other M and P drawings. Site lighting and power shown on site utilities matches electrical plan Maintenance outlets located at exterior and roof Light fixture layouts shown with circuit designations. Light fixture types and locations (coordinate with reflected ceilings) Panel schedules included with circuit information Work shown and specified from main electric service to build transformer. Main service electric duct bank (coordinate underground work and foundations). Light switch and outlet locations coordinated with Architectural floor plans Electrical equipment rooms sized properly for electric gear. Fuel storage and exhaust systems shown for emergency generator. Light fixture locations miss ductwork and structural members Light fixture locations coordinate with HVAC supply/return devices and sprinklers. Cable trays shown for distribution compare routing to Mechanical 120V power shown to controls Exit signs shown match required locations per Architectural. Conduit runs in structural decks sized and located to maintain proper conduit cover. Project schedule allows for lead-time for Electrical Switchgear and Equipment. Motor Control Center coordinated with Mechanical motor starter responsibility? Disconnect responsibility provided. Elevator motor sizes and voltages coordinated. Wall mounted transformers coordinated for adequate structural support. Electrical equipment rooms ventilated. Lighting controls and dimming system required (shown). Emergency lighting circuits and locations on plans shown. Shafts allow room for conduit risers for all systems (rooms are stacked) Specialty fixtures and chandeliers shown. Cross check other specification sections for electrical connection requirements. Coordinate voltages with other trades Conduit distribution shown for Owner provided special systems work? Electrical requirements with door hardware schedule complete?

11 of 10

FF&E CONSTRUCTABILITY REVIEW CHECK LIST


Special Systems Fire alarm system drawings and specifications provided (Design/Build?) Fire alarm devices shown, located, and match other documents Fire alarm system coordinated with Building Controls system Fire dampers shown on Mechanical drawings (fire alarm devices noted) Security system requirements, camera locations, door monitoring, access control Phone/Data device drawings included on special system or signal drawings Process controls and instrumentation integrated with other drawings? POS system and locations shown match Architectural Sound system shown, speaker locations, AV controls, wiring (match Architectural) Fire alarm wiring diagram included and per sequence of operations Fire alarm coordinated with elevator management and recall Fire alarm furnish and install duct detectors in duct (verify locations) Line voltage (120V) shown to each device location (who provides?) Wiring and installation of electrified door hardware and security (who provides?) Power required to controllers and devices (battery back-up?) CCTV equipment located on drawing (security console?) Telephone closets adequate size for equipment, boards, and future? Fire control room dimensioned and layout of panels and annunciation shown Security camera room dimensioned and panels and monitors shown Raceways provided for all special system trades (who installs) Fire suppression at equipment hoods coordinated with fire alarm HVAC equipment shutdown sequence part of which controls scope?