Академический Документы
Профессиональный Документы
Культура Документы
Agenda
Ballast Control
Sequences Controls
9/4/2012
2
BCS Overview - Methodology Air over water system Powered by external hydrostatics and pressurized Tower air
WATER SUPPLY NO NC NO AIR SUPPLY NO NC NO AIR VENT TO ATMOSPHERE NO O
WATER SUPPLY
NO NC NO AIR SUPPLY
NO
NC
NO AIR SUPPLY
NO NC NO
NO
NC
NO VENT
NO NC
VENT TO ATMOSPHERE
NO
NC
DECK 4
COMPRESSED AIR
COMPRESSED AIR
COLUMN OF SEAWATER
DECK 3
SEA WATER
SEAWATER
BALLASTING OPERATIONS
SEA WATER
NORMAL OPERATIONS
BCS Overview - Methodology Settings Goals Maintain acceptable Tilt Drilling to maximize drilling time In the drilling setting, the Tower will automatically Allow for Tilt corrections ballast once a certain Tilt by Engineer for any is reached reason Non-Drilling Minimize load change on In the non-drilling setting, bottom the Tower will be ballasted only when desired by the Minimal involvement from Engineer* Engineers*
*EngineerreferstoanypersonqualifiedtooperatetheTowerBCS
4
Ballasting change is always equal and opposite for diagonal tubes The Ballast System Steps (back to zero or tilt induced)
Greater attitude (Heel or Trim) is corrected first Venting is performed first to correct half of the major attitude Pressurization is used to correct for other half of major attitude
Screens
BallastControl Parameters
Parameters - Inclinometers
Two redundant inclinometers will be mounted to the BCS rack in the MCC Should be aligned horizontally above the Tower center of gravity Sensor output is RS232 but will be converted to 24V 420mA before reaching BCS Tilt is the Resultant of Heel and Trim Deviation tolerance is set by Engineer Tilt can be determined by either instrument individually or an average of the inclinometers
Parameters - Inclinometers
Pressure alarms in the SCF are a function of the allowable load on the soil
10
12
Parameters screen shows both values and the discrepancy between the two The current PIT used for the level calculations shows in blue If a PIT is suspected to be faulty, the other can be used Tank levels are calculated using the draft mark input
13
14
Pressure deviation
Allowable difference between 2 redundant instruments
Go to Zero
Begins ballasting to take Tower back to a minimal Tilt
Shutdown
Stops current ballasting sequence and closes all valves
Position Reset
Sends platform back to the original default position; this position is set by the Engineer
16
Ballast Control - Sequences Shows the operation that the BCS is currently rectifying
Heel Negative Heel Positive Trim Negative Trim Positive
Leak detection is normally closed Open circuit means either leak or faulty sensor Leak can be confirmed manually using sounding tubes
18
Ballast Control Pressure/Level Indication The levels are calculated directly from the pressures with respect to draft Percentage full is percentage of available ballast Pressure values are blue if the tank is full and green if the tank is in working range
19
Ballast Control Valve Heel, Trim and resultant Tilt are shown on the Ballast Control Screen Positive heel and positive trim are towards the respective arrows
21
Drawings
22
Drawings
23
Drawings
24
Drawings
25
Drawings
26
Drawings
27
Drawings
28
Drawings
29
Drawings
30