LARSEN & TOUBRO LIMITED MSQ(EPCC 1) UP GRADATION


DPT PROCEDURE DATE:-01.11.2007 REV.NO.- 0 PROCEDURE NO.LT/MSQ/P/DPT//007

CONTENTS

1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

SCOPE REFERENCE DOCUMENT GENERAL QUALIFICATION OF PERSONNEL MATERALS PROCEDURE INTERPRETATION POST CLEANING DOCUMNTATION SAFETY

APPROVED BY L & T

REVIEWED / APPROVED BY JACOBS

PAGE NO.- 2 OF 4

LARSEN & TOUBRO LIMITED MSQ(EPCC 1) UP GRADATION


DPT PROCEDURE DATE:-01.11.2007 REV.NO.- 0 PROCEDURE NO.LT/MSQ/P/DPT//007

1.0

SCOPE: This procedure describes the method for Penetrant Testing of materials and welds, for structure erection and fabrication work of MSQ (EPCC-1) up gradation Project, IOCL Panipat.

2.0 3.1
3.2

REFERENCE DOCUMENTS:

ASME Section V: Nondestructive Examination ASME B31.3 Chemical plant and petroleum refinery piping. ASNT Recommended practice : SNT-TC-1A 3.0 3.1 GENERAL Penetrant Testing shall be applied to detect discontinuities that are open to the surface of nonferrous and other materials. Typical defects which are detectable by this method are surface cracks, porosity, laminations, seams, laps etc. 3.2 4.0 4.1 Prior to examination, surface to be checked visually and adjacent area shall be cleaned, to allow the pentrant to enter the discontinuities. QUALIFICATION OF PERSONNEL Individuals performing penetrant examination shall be qualified ASNT level-II in accordance with SNT-TC-1A or equivalent.

3.3

4.2 Trained Person may perform the testing under Level II qualified persons instruction and supervision.
5.0 5.1 Materials All DP materials such as Penetrant, Developer and Cleaner shall be from the following reputed manufacturers. Magnaflux, P Met, Flaw check & Pradeep metal brands are acceptable. Batch certificates shall be submitted for review prior to use.

5.2

APPROVED BY L & T

REVIEWED / APPROVED BY JACOBS

PAGE NO.- 3 OF 4

LARSEN & TOUBRO LIMITED MSQ(EPCC 1) UP GRADATION


DPT PROCEDURE DATE:-01.11.2007 REV.NO.- 0 PROCEDURE NO.LT/MSQ/P/DPT//007

6.0 6.1

PROCEDURE Surface preparation The surface to be examined and all adjacent areas within at least 1 shall be clean & dry, free from dirt, oil, grease, loose rust, paint ,welding flux, spatter and other extraneous matter that obscure surface openings or otherwise interfere with the examination.

6.2
6.3

Temperature Surface temperature shall be between 50 degree F (10 deg. C) to 125 Deg. F (52 Deg .C) Penetrant application Solvent removable type visible liquid penetrant (red in colour) shall be applied uniformly by pressurized container attached with spray nozzle over the required surface area / brush

6.4 6.5

Dwell time (penetration time) shall be 10 minutes (min) or as specified by manufacturer but care shall be taken so that penetrant does not get dried up. Removal of excess Penetrant After the specified dwell time penetrant shall be removed by repeated wiping with lint free material or absorbent paper, till the traces of penetrant has been removed. Care shall be taken to minimize removal of penetrant from discontinuities. Remaining traces can be removed by lightly wiping the surface with damped cloth or absorbent paper moistened with cleaner. (Surface flushing with solvent is prohibited.)

6.6

Developing Only wet developer in pressurized container with spray nozzle should be used. It shall be applied immediately after removal of excess penetrant from the surface. Avoid excess coating or insufficient coating conditions, which might impair the effectiveness of the test. Before use, stir the chemical thoroughly.

APPROVED BY L & T

REVIEWED / APPROVED BY JACOBS

PAGE NO.- 4 OF 4

LARSEN & TOUBRO LIMITED MSQ(EPCC 1) UP GRADATION


DPT PROCEDURE DATE:-01.11.2007 REV.NO.- 0 PROCEDURE NO.LT/MSQ/P/DPT//007

7.0 7.1 7.2

INTERPRETATION Interpretation shall be done between 5 to 30 minutes after the developer coating becomes dry. Acceptance standard shall be as per ASME B 31.3 / Contract specification. Any defect found shall be repaired either by grinding, chipping or re-welding if required or re test to be done with the above procedure in defective area.

8.0

POST CLEANING After the completion of interpretation, the area shall be cleaned thoroughly by cotton waste so that no trace of DPT material left is left out.

9.0 10.

DOCUMENTATION The test results shall be recorded in Format No. LT/MSQ/DPT/016 SAFETY All safety precautions shall be taken as per HSE requirements of the project.

APPROVED BY L & T

REVIEWED / APPROVED BY JACOBS