The Budget is introduced, at this time, in order to allow for the required 60
days of advertising before conducting a Public Hearing on the proposed water
and wastewater rate increases. We propose to hold a Public Hearing on June 4,
2009. At that meeting, the Board may consider the adoption of the Budget and
Rates either as introduced, or as amended. Conducting a Public Hearing on
June 4, 2009, also provides staff time to make requested modifications by the
ACSA Board of Directors prior to the regularly scheduled Board Meeting on June
18, 2009, if necessary.
Board Action
GWF/dbh/dmg
020204 Proposed FY 2010 Budget Board Memo 031309
MEMORANDUM
To: Board of Directors
From: Gary W. Fern, P.E., Executive Director
Date: March 13, 2009
Re: Proposed FY 2010 Budget
cc: James M. Bowling, IV
The ACSA Staff is pleased to present this Proposed FY 2010 Budget for
the Albemarle County Service Authority. I would like to recognize Ms. Lisa Bree-
den and the Staff of the Finance Department as well as the Directors, Managers,
and Supervisors who with considerable effort developed the Proposed Budget
and Rates. The Budget is introduced at this time in order to allow for the re-
quired 60 days for advertising before conducting the Public Hearing on the pro-
posed rate increases. We propose to hold the Public Hearing on June 4, 2009.
At that meeting, the Board may consider the adoption of the Budget, either as
introduced or as amended. In the interim period, the ACSA Staff can address
concerns raised by members of the Board.
Revenues:
Expenses:
Departmental Staffing:
Administration Department:
Engineering Department:
Maintenance Department:
The largest contributor of this estimated cost is the North Fork Regional
Pump Station Project. The project is estimated to cost $5,770,450 in both FY
2010 and FY 2011. In addition, the Meadowcreek Basin Sewer Rehabilitation
Project is estimated to cost $2,000,000 in FY 2010. This project will reduce infil-
tration/inflow in the Meadowcreek Drainage Basin and is expected to reduce the
number of sewer system overflows experienced in the Meadowcreek Interceptor.
The Maintenance Department will continue to perform in-house construction on
some of the projects within the CIP. Details of the FY 2010 CIP Projects are pro-
vided in a memorandum dated March 12, 2009.
The proposed rates for FY 2010 are shown on Page 10. The proposed
total water consumption (1,610,474,000 gallons) and wastewater generation
(1,288,123,000 gallons) represents decreases of 7.1% and 6.5% from the flows
proposed in FY 2009. These rates reflect the application of $2,000,000 from the
Repair, Replacement & Rehabilitation (3R) Fund. An increase of 9% is proposed
for the fixed monthly charge.
To promote greater conservation, an increase of 9% to the residential wa-
ter rates is proposed for Level 1, while increases of 14% and 17% are proposed
for Levels 2 and 3, respectively. An increase of 13% is proposed for the non-
single family residential water rate. The sewer rate is proposed to increase from
$7.00 per thousand gallons to $8.11 per thousand gallons (16%). This increase
is mainly attributed to the proposed wastewater projects to be undertaken in the
CIP.
In addition to the Volume Rate Changes, the ACSA staff is proposing to
increase the RWSA Capacity Fees, System Development Fees, and Water Local
Facilities Fees. No changes are proposed for the Sewer Local Facilities Fees.
These increases are a result of projects being undertaken by the RWSA and the
ACSA.
Anticipated Reserves:
We request that the Board of Directors authorize the advertisement for a Public
Hearing to address the FY 2010 Budget and Rates at 7:00 p.m. on Thursday, June 4,
2009.
GWF/anw
020204FY2010Budget031309
Proposed Revenues and Expenses
FY 2010
Revenues
Revenues
Total Volume Charges 21,409,619
Projected Debt for
Total Service Charges 1,122,244
Capital Expenses
System Connection Charges 1,585,371
Transfer for Capital
15.4% Expenses
Farmington Capital Recovery 29,000
Miscellaneous Revenue 773,900 7.7%
Projected Debt for Capital Expenses 5,000,000
Transfer for Capital Expenses 2,490,678
32,410,812
Expenses
Purchase of Water/Wastewater, Buck Mtn Surc
Miscellaneous Revenue 11,474,244
Administration Department
2.4% 1,366,025
Finance Department 1,364,600
Farmington Capital
Engineering Department 1,273,300
Recovery
Maintenance Department 2,246,800
Total Volume
0.1%
Operating Reserve 565,047
Charges
800 Code Equipment Expenses 249,300
66.1%
Capital Improvement Expenses 12,621,550
Repair, Renewal, & Rehabilitation Reserves 666,609
System Connection
Project New Debt Service 210,637
Charges
Existing Debt Service and Amortization 372,700
4.9% Total Service Charges
32,410,812
3.5%
Expenses
Project New Debt
Service
Repair, Renewal, & Existing Debt Service
0.6%
Rehabilitation Reserves and Amortization
2.1% 1.1%
Capital Improvement
Expenses
38.9% Purchase of
Water/Wastewater,
Buck Mtn Surcharge
35.4%
800 Code Equipment Administration
Expenses Department
0.8% 4.2%
Finance Department
4.2%
Operating Reserve
1.7% Engineering
Department
Maintenance 3.9%
Department
6.9%
FY 2010 FY 2010 as
FY 2009 Proposed % of FY 2009
R W SA EX P EN SES
Buck Mountain Surcharge $ 104,600 72,400 69.2%
Purchase of Bulk Water 6,123,902 6,260,146 102.2%
Sewer Treatment Expense 5,480,564 5,141,698 93.8%
WASTEWATER
Urban $2.722/TG $3.073/TG $ 4,827,236 4,524,166 93.7%
Scottsville $25,968/mo $25,420/mo 321,111 305,043 95.0%
StoneRobinson School Actual Actual 32,441 21,467 66.2%
Glenmore $24,606/mo $24,252/mo 299,776 291,022 97.1%
OP ERATI N G SUP P LI ES
503510300 Office Supplies $ 14,683 9,033 13,600 14,482 17,000 117.4%
503510305 Copier Supplies 1,112 994 1,900 1,900 2,000 105.3%
503510310 Janitorial Supplies 2,254 2,679 3,500 2,800 2,800 100.0%
503510370 Heating Fuel 2,778 2,237 3,800 4,000 4,300 107.5%
503510380 Small Tools & Equipment 0 17,925 36,400 36,400 32,500 0.0%
Subtotal: $ 20,827 32,868 59,200 59,582 58,600 98.4%
CAP I TAL OUTLAYS
503510800 Office Equipment $ 33,935 4,726 4,726 4,722 0 0.0%
503510810 Furniture and Fixtures 11,860 0 0 0 0 0.0%
503510830 Machinery and Equipment 0 0 0 0 0 0.0%
Subtotal: $ 45,795 4,726 4,726 4,722 0 0.0%
CAPI TAL OUTLAYS
503520800 Office Equipment $ 1,800 0 0 0 161,000 0.0%
503520810 Furniture and Fixtures 500 2,400 2,400 2,400 0 0.0%
503520830 Machinery and Equipment 775 0 0 0 0 0.0%
OP ER ATI NG SUP P LI ES
503540330 Personal Protective Equipment 221 172 350 1,125 800 71.1%
503540360 Fuel, Oil & Grease 17,249 9,380 16,000 27,280 21,800 79.9%
503540380 Small Tools & Equipment 5,662 20,019 32,950 32,950 18,300 55.5%
R EP AI R & M AI NTENANCE SUP P LI ES
503540400 Vehicle Supplies $ 3,826 670 2,500 4,200 2,000 47.6%
R EP AI R S AND M AI NTENANCE
503540600 Equipment Repair and Maintenance $ 331 325 1,350 2,200 2,600 118.2%
503540650 Vehicle Repair and Maintenance 2,741 605 1,500 3,200 2,200 68.8%
CAP I TAL OUTLAYS
503540800 Office Equipment $ 0 0 0 0 0
503540810 Furniture and Equipment 605 0 0 0 0
503540830 Machinery and Equipment 50,861 50,373 48,100 56,985 0 0.0%
OP ERATI N G SUP P LI ES
503550320 Shop Supplies 3,621 1,493 8,500 8,700 7,800 89.7%
503550330 Personal Protective Equipment 11,988 7,976 14,000 18,735 15,300 81.7%
503550360 Fuel, Oil & Grease 61,598 33,125 60,000 77,530 81,800 105.5%
503550380 Small Tools & Equipment 20,390 26,110 58,000 58,500 77,000 131.6%
CAP I TAL OUTLAYS
503550800 Office Equipment $ 11,564 0 0 0 0
503550810 Furniture and Fixtures 0 0 0 0 0
503550830 Machinery and Equipment 317,313 135,141 352,000 429,200 88,300 20.6%
Subtotal: $ 328,877 135,141 352,000 429,200 88,300 20.6%
* Ongoing Projects
Residential Water Rates per 1,000 Gallons
Level 1: 0 3,000 gallons per Month $ 3.86 $ 4.22 9% $ 4.91 $ 5.16 $ 5.00 $ 5.02
Level 2: 3,001 6,000 gallons per Month $ 6.10 $ 6.95 14% $ 7.08 $ 7.44 $ 7.21 $ 7.23
Level 3: Over 6,000 gallons per Month $ 10.90 $ 12.71 17% $ 16.94 $ 17.80 $ 17.26 $ 17.31
Projected Capacity & Connection Fees
Projected
2009 2010 2011 2012 2013 2014
FY 2009 Beginning Operating & Maintenance Reserve $ 2,523,311
Projected
2009 2010 2011 2012 2013 2014
Beginning 3R Reserve $ 6,993,884
Projected Debt Service
Base Assumptions
Average Cost Increases: 12.0%
Interest Rate on Borrowings: 5.0%
Growth Rate Customer: 0.5%
Consumption Growth Rate: 0.0%
Interest Earned on Investments: 3.5%
O&M Reserve: 2.0%
Repair, Renewal & Replacement "3R" Reserve: 0.4%