Вы находитесь на странице: 1из 6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code

Descriptions (blank) Design Works Gen Requirements/Temp Facilities Mobilization & Demobilization Site Works GRP Trenching Ductile Trenching Excavation Earth Works Backfill Shaft works Shaft-Finishes Drainage Backdrops Micro Tunneling Piling Works Pile Installation Pile Load Test Asphalt Works Septic tank Demolition Pavements & Walkways Boundary Wall Gravel Surfacing Road Work Fencing Works (blank) Play Ground Water Works Road Traffic Marking Planting Landscaping / Hardscaping Civil Works Cast-in-place Concrete Manhole Concrete Finishes & Coating Pre-cast Concrete Minor Works/Structures Pipe Connection Masonry Works Glass Block Works Ext Wall Cladding Structural Steel & Metal Works Design & Inspection Structural Steel Fabrication & Paint Machining Erection/Installation Metal Works Wood & Plastic Works Architectural Wood Works Wood Works Fabrication & Finishing Decorative Panels Thermal & Moisture Protection
C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

1-6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code


Descriptions Damproofing & Waterproofing Thermal Protection & Insulation Roofing & Waterproofing Doors & Windows Steel Doors & Frames Wood Doors Aluminium Doors & Frames Entrances & Storefronts Windows Skylight Hardware Glass Doors & Partitions Curtain Wall System Finishing Works Plaster & Gypsum Plaster Tile Works Ceillings Works Flooring Walls & Columns Paints & Coatings Miscellaneous Works (Special Items) Louvers & Vents Service Building System Sign Lockers Column & Wall Protection Metal Storage Shelving Toilet Partitions & Accessories Toilet & Bath Accessories General Services & Maintenance Valves & Gauges Hood & Ventilation Eqpt Building Equipments & Devices Labortory Equipment School Equipment Furnishing Furniture Special Purpose Room Building Offices Elevators Mechanical Works Mechanical Maintenace & Repair Install Pipes Mechanical Pumps Maintenace Finishing & Parts Cost of Spare Parts - Pumpex/ Pumps Cost of Pumps - Pumpex/ Pumps Pump Potable Water Network Sewerage Network Drainage Network Reflected Pool Test Pipes Service Relocation
C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

2-6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code


Descriptions Materials Fire Protection System Plumbing Fixture & Equipment Water Storage Tank RC Tank Fiber Tank HVAC HVAC/Airconditioning Works HVAC-Equipment Electrical Works Electrical Maintenance & Repairs Electrical Rough-in Electrical Lighting StreetLighting Works Division Management-OH General Manager PROJECT DIRECTOR Construction Manager DEPUTY PROJECT MANAGER SR. CONSTRUCTION MANAGER Project Manager Execution Manager Technical Engineer ENGINEERING MANAGER Workshop Manager Workshop Supervisor Architect Structural Engineer Electromechanical Manager Electromechanical Engineer Cost Engineer Contracts Manager CONTRACTS ENGINEER Safety Manager HSE MANAGER PROJECT CONTROL MANAGER PROCUREMENT MANAGER PROJECT COORDINATOR PROCUREMENT ADMINISTRATOR Area Manager (blank) Site Manager Site Engineer Site Engineer - Civil SITE ENGINEER - ELECTRICAL SITE ENGINEER - MECHANICAL Site Engineer - MEP Field Engineer QA/QC Engineer QA/QC Helper QC Inspector - Civil QC INSPECTOR - ELECTRICAL QC INSPECTOR - MECHANICAL QC INSPECTOR - WELDING/NDT
C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

3-6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code


Descriptions QC INSPECTOR -COMMUNICATIONS QC Inspector - MEP Surveyor MATERIAL RECEIVING INSPECTOR Surveyor Helper ASST. SURVEYOR Site Supervisor/Foreman FOREMAN - CIVIL FOREMAN - ELECTRICAL FOREMAN - MECHANICAL Site Supervisor - Civil Site Supervisor - MEP Electrical Engineer Mechanical Engineer Pile/Shaft Manager Pile/Shaft Site Engineer Pile/Shaft Mech Engineer Planning Engineer QC MANAGER QA MANAGER Project Engineer Civil Engineer MATERIAL ENGINEER PROCUREMENT QC SUPERVISOR - CIVIL PROCUREMENT QC SUPERVISOR - ELECTRICAL PROCUREMENT QC SUPERVISOR - MECHANICAL PROCUREMENT QC SUPERVISOR - WELDING / NDT QA/QC Supervisor QC SUPERVISORS - CIVIL QC SUPERVISORS - ELECTRICAL QC SUPERVISORS - MECHANICAL QC SUPERVISORS - WELDING/NDT Superintendent SUPERINTENDANT - CIVIL SUPERINTENDANT - ELECTRICAL SUPERINTENDANT - MECHANICAL Tunneling Manager Tunneling Engineer Trenching Engineer (blank) (blank) (blank) (blank) (blank) (blank) (blank) Quantity Surveyor SR. QUANTITY SURVEYOR Scheduler ASST. PLANNERS Draftsman Maximo planner IT Support I.T ENGINEER
C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

4-6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code


Descriptions Janitor (blank) MATERIAL RECEIVING INSPECTOR EXPEDITOR PROCUREMENT COORDINATOR ACCOUNTANT Purchaser Equipment Coordinator LOGISTIC SUPERVISOR/ EQPT. CONTROL Driver LIGHT VEHICLE DRIVERS Timekeeper Storekeeper Store Helper ASST. STORE KEEPER Public Relation GOVT. & P.R. OFFICER Liason Officer Administrator SITE ADMIN. ASST. ADMIN. Camp Officer Safety Officer SAFETY SUPERVISOR Safety helper SAFETY WORK PERMIT RECEIVER Safety Inspector Scaffold Supervisor Scaffold Inspector Work Permit receiver Laboratory Technician Skilled Labor Unskilled Labor LOGISTICS LABOR NURSE Secretary Tea Boy OFFICE BOY - SAPMT OFFICE BOY - PID OFFICE BOY - PROPONENT OFFICE BOY - AMC Guard General Mechanic Fabricator DOCUMENT CONTROLLER ASST. DOCUMENT CONTROLLER Trainee Equipment Operator MAXIMO REQUESTER Staff Expenses Medical fees/Medicine Site Vehicles Equipment Rental Depreciation Charges
C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

5-6

2011_MCG Cost Code List_REV-27-12-2011 (Masterlist) overall code


Descriptions Fuel Cost/Consumables Transportation Equipment Repair & Maintenance Job Site Office Ofiice Supplies/Equipment/Printing IT Express mail Electricity/Utilities Telephone/Fax/Bravo Travel Expenses General expenses Meals Cost & Allowances Water charges Safety & General Protection Uniforms & Allowances Dumpsters/General Site Cleaning Toilet cleaning charges Permits Amana Dumping Fees Penalties/Tickets Speciality Expenses Bonus & Incentives Certification-Eqpt Shop & Rental Saudization Allowance Project Insurance Performance/Advance Payment Bond Misc. Financial Charges LC Issuance & Acceptances Project Damages & Claims Tender Bids Contingency O.T. & OPERATIONAL COST Division HO & Staff Office & Staff Unused Equipment Charges Other Expenses Used Equipment Tunneling Used Equipment Piling Rented Equipment-General HO Other Expenses Corporate fee

C:\Users\Safraz\Desktop\work files\Jezan\Cost code\2011_MCG Cost Code List_REV-27-12-2011 - overall code 14-04-13

6-6

Вам также может понравиться