Академический Документы
Профессиональный Документы
Культура Документы
Kent Fong
Pre-Risk Studies
Abu Dhabi
Engineers
Mariners
Singapore
The Marine Environment Shortage of Vessels/Equipment Shortage of Marine Qualified Personnel Increasingly Shorter Project Schedules Increasingly Tighter Project Budgets Pushing the boundaries Water Depths, Novel Installation Methodologies etc
Design Failure - Extreme environment (incorrect criteria or non adherence to environmental limits. Design Failure - Poor design (Lack of time to prepare or inappropriate experience). Poor Procedures - Lack of time to prepare or inappropriate experience. Operator Error - Overwork or lack of training. Vessel or Equipment Failure - Over work & lack of routine maintenance. Equipment Materials failure Insufficient QA/QC. Failure to capture lessons learnt Lack of Time or Loss of Expertise.
With due consideration to the above, the insurer will allocate a risk level to each key marine operation based on the ALARP principle and the Marine Warranty scope will be a function of this risk.
Probability of Hazard
Likely Reasonably probable Unlikely Remote Extremely remote Theoretically possible
Minor
Severe
Fatal
W2 W1 W0
W3 W1 W2 W1 W0 W3 W2 W1 W0
W2
W0
W1
W3
W1
W2
Scope Increase For e.g. High Asset value / Schedule Impact or claims history
Inspection/audit of marine transportation, tow and construction vessels, jack-up rigs and Mobile Offshore Drilling Units. Attendance on-site to witness and approve W1,W2 or W3 Marine Operations As required.
W3
Marine Operations Load out*, Float out, Float on/off. Towed and Self Propelled Transports. Launching, Upending, Positioning. Setting, Piling, Grouting. Lifting, Lift-off or Mating Operations. Transit and Positioning of Jack-ups. and semi-subs. Pipelaying & Flexible/Cable Lay Subsea structures Installation Operations. Pipe/Cable Crossing & Trenching
Substructure Loadout Transportation & Installation
Jacket Transport & Tow Vessel Surveys Jacket Initial Skidding to Loadout Area Jacket Loadout onto transportation Barge Jacket Seafastening and Sailaway Jacket Launch, Up-end, & Wet Tow Jacket Set-down/Installation Jacket Pile Handling & Piling (1st Pile only)
X X X X X X
X X X X X X
X X X X X X X
X X X X X
Line pipe Transport & Tow Vessel Surveys Line pipe joint Loadouts Export Pipeline and Flowlines transportation & Installation Line pipe joint seafastening and Sailaways Line pipe joint Discharges Line pipe transhipments to Pipelay Vessel Lay vessel Suitability Survey Line pipe/ flowline Installation
WARRANTY PROCEDURES
Attendance (On-site)
Condition and Suitability Surveys of Vessels
Prior to approving a marine operation involving vessels it is required that the vessel be surveyed by the MWS to confirm its suitability. Several key requirements are checked: Vessel condition is suitable for the task Vessel has required statutory certification Vessel is adequately manned and managed Vessel specifications/capacities have been accurately presented. The attending surveyors role is to ensure conceptual reviews are reflected in the physical form for the envisaged operation. Often the attending surveyor is incorporated into the JHA and or Hazid process. Key preparations elements of the operation are checked and verified prior to issue of the Certificate of Approval. The operation is then monitored to ensure compliance with the approved procedures.
Certificate of approval
Certificate of approval
Loadout Float-out Sailaway Load-in Back-load Launch Upend Lifted installation Float-over MoU positioning Mooring Hook-up Pipelay & Crossings
ANY QUESTIONS?
are not constrained by financial or contractual motives when performing operations assessments
If MWS approval is not provided prior to the commencement of a scope defined operation then the Assured can be called in breach of their Insurance requirements by the insurer.