Академический Документы
Профессиональный Документы
Культура Документы
Goldhofer SPMT
Goldhofer SPMT
Goldhofer SPMT
Goldhofer SPMT
Goldhofer SPMT
1) Capacity (nominal 35 ton max per axle line) 420,000lbs per 6 line SPMT 2) Length/width per 6 line (30ft length x 10 ft wide) + 14ft power pack 3) Steering modes as shown
10
Goldhofer SPMT
11
12
13
14
2)
2)
15
1)
2)
Secure bridge spans to Barnhart 5ft girders Secure Barnhart shoring system to Goldhofer SPMT
16
17
18
19
20
21
22
23
24
25
Removal Concept
26
Removal Concept
27
Removal Concept
28
Removal Concept
29
Removal Concept
30
Removal Concept
31
32
33
Scope of Work
1. Transportation of 24 good spans from the east bound lane to the west bound lane 2. Realigning of 80 bridges span
34
Relocation of Spans
35
36
37
38
39
40
We had 24 days to complete We finished in 17 days Over 3,000 Man Hours No incidents
41
42