Leader-Wai Kee (C&T) Joint Venture Remaining Engineering Infrastructure Works for Pak Shek Kok Development Package

2A Risk Assessment Ref. No. PSK/RA/034 Risk Assessment for Construction of Manholes S746, S746t, S756 & S756t at Landscape Node P1 1. Work Sequence: Item 1. Excavation 2. Work inside excavated trench 3. Erection of Formwork 4. Fix reinforcement steel bar 5. Concrete Pouring 6. Dump soil with truck 7. Backfill with Excavator 8. Lifting operation
Prepared By : Checked By : Approved by : Date : Date : Date :

Affected person(s) Labourers, excavator operator Labourers, levelers Carpenters, levelers, labourers Bar fixer, labourers Labourers, mobile crane operator Dump truck operator, labourers Labourers, excavator operator Labourers, mobile crane operator

Activities 1a 2a 3a 4a 5a 6a 7a 8a

Remark

Page 1 of 4

Leader-Wai Kee (C&T) Joint Venture Remaining Engineering Infrastructure Works for Pak Shek Kok Development Package 2A Risk Assessment Ref. No. PSK/RA/034
Item No. Cause / Initial Event Consequence 1a Excavation Collapse of earth. - Persons falling into excavation trenches. - Workers being struck by excavators. - Collapse of heavy equipment / material. Collapse of earth. - Persons falling into excavation trenches. - Collapse of heavy equipment / material. Risk Ranking Existing Mitigating Controls Provide suitable PPE. Weekly inspection and fill Form 4 by competent person. - Fencing along edge of excavation trench. - Heavy equipment/ material should not be place along the edge of excavation. L 2 S 4 R/R S Required Provide toolbox talk to workers. Assign qualified and experienced supervisor for the job. - Provide safe access and egress - Post up emergency procedures and contact lists. - Provide water pump for dewatering in case of heavy rainstorm. Additional Mitigating Controls (A.L.A.R.P.) Risk Ranking L S R/R 1 4 S By Whom

Engineer Foreman

2a

Work inside excavated trench

Provide suitable PPE. Weekly inspection and fill Form 4 by competent person. - Fencing along edge of excavation trench. - Heavy equipment/ material should not be place along the edge of excavation.

Provide toolbox talk to workers. Provide safe access and egress. Provide water pump for dewatering in case of heavy rainstorm.

Engineer Foreman

3a

Erection of Formwork

Collapse of - Provide suitable PPE: formwork. safety helmet, safety gloves - Fall of person. - Follow the sequence of - Fall of objects. formwork erection. - Provide working platform when necessary. Trip over Back Injury Contused by re-bar Provide suitable PPE: safety helmet, safety gloves, etc. - Bar bending machine equipped with emergency switch.

Provide toolbox talk to workers. Qualified and experienced engineer shall carry out the design of temporary formwork. - Construction of manhole will split into three stage so as to eliminate the risk of work at height Provide tool box talk to workers Maintain good housekeeping. Ensure workers are familiar with the proper manual handling procedures

Engineer Foreman

4a.

Fix reinforcement steel bar

Engineer Foreman

Page 2 of 4

Leader-Wai Kee (C&T) Joint Venture Remaining Engineering Infrastructure Works for Pak Shek Kok Development Package 2A Risk Assessment Ref. No. PSK/RA/034
Item No. Cause / Initial Event Consequence 5a Concrete Pouring Collapse of formwork - Vibration Overturn of truck - Truck strike nearby personnel. Risk Ranking Existing Mitigating Controls Provide suitable PPE, safety helmet, safety gloves, etc. - Provide access and egress. Provide suitable PPE, Safety helmets and reflective vests. - Truck to be maintained in good condition. - Truck driver has valid license. - Ensure truck station on steady level and firm soil before dumping. Provide suitable PPE, safety helmet and reflective vests. - Weekly inspection and fill Form 4 by competent person. - Fencing along edge of excavation trench. - Heavy equipment/ material should not be place along the edge of excavation. L 2 S 4 (A.L.A.R.P.) Risk Ranking R/R Required L S R/R S - Provide toolbox talk to workers. 1 4 S - Qualified and experienced engineer shall carry out the design of temporary formwork. S Provide safety toolbox talk to workers. - Workers are not allowed to distract truck driver during soil dumping. - Assign look out man to control the dump truck. - Inspect dump truck before use. 1 4 S Additional Mitigating Controls By Whom Engineer Foreman

6a

Dump soil with truck -

Engineer Foreman Truck Driver

7a

Backfill with Excavator

Collapse of earth. - Persons falling into excavation trenches. - Workers being struck by excavators. - Collapse of heavy equipment / material.

Provide tool Box talk to workers. Assign qualified and experienced supervisor for the job - Provide safe access and egress.

M -

Engineer Foreman Safety supervisor

Page 3 of 4

Leader-Wai Kee (C&T) Joint Venture Remaining Engineering Infrastructure Works for Pak Shek Kok Development Package 2A Risk Assessment Ref. No. PSK/RA/034
Item No. Cause / Initial Event Consequence 8a Lifting operation Risk Ranking Existing Mitigating Controls L 2 S 4 R/R S Required Operators must attend associated training course. Lifting appliance and lifting gear should be thoroughly examined by RPE and hold valid certificate. Valid examination certifications should be displaced at a prominent location. Operators shall not use mobile phone while operating of equipment and never disturbed by other workers. Assigned operator should perform daily inspection in order that equipment should be in good condition. Additional Mitigating Controls (A.L.A.R.P.) Risk Ranking L S R/R 1 4 S By Whom Engineer Foreman Safety Officer

Heavy - Provision of suitable PPE, equipment safety helmet, safety belt, traveling hit and proper footwear and nearby personnel reflect vest, etc. and plant - Select suitable size and - Collapse of functions of plant and boom/jib due to equipment for the work with failure of proper sitting / placement connection of arranged. pins or wire - Carry out weekly slings. inspection and maintenance of the equipment. - Riggers have to thoroughly examine the lifting gear and condition of pins before work. -

Page 4 of 4