Академический Документы
Профессиональный Документы
Культура Документы
JSW Group
JSW is a part of US $ 10 Billion O.P Jindal Group Engaged in core sector business like Steel, Aluminum, Power, Port, and Mining across the globe JSW Energy Limited (JSWEL) is the power Generating Company of the Group, formed in the year 1994 JSWEL at present has an installed capacity of 1160 MW in Bellary (the first independent power producer of Karnataka State) and 270 MW in Barmer JSWEL signed an MOU with Govt. of Maharashtra, to set up a port-based TPPJune 2005 Estimated cost of the imported-coal based 4x300 MW TPP at Jaigad in Ratnagiri District: Rs 4500 Cr.
3 x 300 MW imported coal based TPP at Ratnagiri, Maharashtra 6 x 135 MW Lignite based TPP at Barmer, in Rajasthan
in
Date
Oct 06, 2006 Mar 03, 2007 Mar 28, 2007 May17, 2007 Nov15, 2007 Apr 23, 2008 Apr 16, 2010 & Jun 28, 2010 Aug 21, 2010
5
Fumigation Chamber
13
Fumigation Chamber
14
Fumigation Chamber
15
Fumigation Chamber
16
Fumigation Chamber
17
18
19
20
21
23
24
The above information has been drawn from the satellite imagery furnished by Environmental Information Centre, New Delhi. The above interpretation is supported with ground checks and ground truth verification.
25
26
Directed a re-examination of the EC by the EAC, preferably within 3 months, on the basis of Reports submitted by KKVD
27
Re examination of EC by MOEF
Nov 11, 2009: As directed by the Delhi High Court, the EAC/MOEF reassessed the Environmental Clearance granted to the Project. It had also taken the views of MPCB and KKVD representatives on the Project and decided to visit the Project site. Nov 13, 2009: A Sub-Committee of the EAC/MOEF visited the project site for an on-the-spot inspection. It had visited KKVD as well the next day to review the Fumigation Chamber study underway there and interacted with the scientists involved. Jan 12, 2010: The EAC/MOEF considered the Sub-Committee report and recommended upholding of the EC granted in May 2007, albeit with certain additional conditions. Apr 16, 2010: The MOEF imposed an additional condition regarding installation of FGD system as an additional environmental safeguard measure. Jun 28, 2010: The MOEF permitted commissioning of the Project, subject to simultaneous implementation of FGD System in a time-bound manner.
28
29
c) A copy of the annual report on baseline of mango, cashew and marine life for 2008-09 has been submitted by Krishi vidyapeeth, Dapoli. The same has been submitted to EAC-Thermal. d) Two year fumigation study has been completed by KKVD scientists. e) Project proponent has spent Rs. 142 lakhs so far against procurement of equipment and honorarium etc. in line agreement with KKVD.
30
contd.
Status of compliance
Space provision shall be made for installation of Adequate space provision (~20,000 sq. FGD of requisite efficiency of removal of SO2, if m) has been made for retrofitting of FGD, required at later stage. if required. Moreover, FGD plant would be installed as per the commitment given to MOEF. Cooling water blow down will be discharged from Blow down will be discharged from the the cold water side and not from the hot water cold end of the closed-loop cooling side. towers. Coal with ash content not exceeding 12 % and Being complied with. sulphur content not exceeding 0.6 % shall be used. Rain water harvesting should be adopted. Central Ground Water Authority/Board shall be consulted for finalization of appropriate rain water harvesting technology within a period of three months from the date of clearance. A rain water storage structure (capacity:-14,000 m3) has been constructed near the project site. Also CGWB, Nagpur has been approached for guidance. Other rainwater techniques like recharging pits are being implemented in the project area.
31
contd
Status of compliance
Two bi-flue stacks of 220 m height each with exit Stack no1 is in for operation for unit #1. velocity of at least 21m/s shall be provided with The continuous on-line monitoring is continuous online monitoring system. provided. Stack no2 is ready for operation. High efficiency Electrostatic precipitator (ESPs) having efficiency of 99.9% shall be installed so as to ensure that particulate emissions do not exceed 100mg/Nm3.
ESP 1- is in operation for unit#1 ESP 2 Mechanical & electrical work completed cable termination in progress ESP 3 Mechanical & electrical work completed cable termination in progress ESP 4 outer body erection work is completed. The same ready by Nov 2010.
32
contd
Status of compliance
A MOU has been signed with M/s Lafarge & its associates for 100% fly ash utilization. The team is monitoring the quality parameters at site. The evacuation by agency & other local brick makers has started. The HCSD system is also being implemented for emergency disposal. Order is placed on M/s BSBK. About 25 ha area has been developed including 4500 Alphanso mango, 500 nos. of cashew plantations in 5 km radius of project site. About 2500 samplings have been planted around emergency ash dyke area. Additional land is being developed for increasing green belt area. ASI has been approached for guidance on additional protection measures. As per the directions of ASI, a specific EIA report (prepared by NEERI) has been submitted on 22/6/2010.
33
Adequate protection measures shall be taken to protect the Jaigad fort, a notified Archeological site, from the adverse impact of the power plant, if any, in consultation with Archeological Survey of India (ASI).
contd
Status of compliance
The company shall strictly follow the schedule for Complied with. It is under design commissioning of FGD i.e 23 months for the first unit engineering stage by M/s Alstom (india) form the date of the letter of intent dated 21st June, and EPC by EDAC. 2010 followed by interval of three months for the units 2,3 & 4; till 32 months The company shall deposit 10 % of the FGD cost which is The bank guarantee of Rs 52.7 Cr is Rs 527 Crores as mentioned vide your letter dated 21st submitted to Regional Officer, Kolhapur, June, 2010 as bank guarantee in MPCB on 1st July 2010. Continuous monitoring of ambient air quality & marine/esturine environment, plant health parameters & fisheries shall be carried out regularly for the entire life of the power plant & data submitted to the Regional Office of the Ministry & the concerned department in the state government. The data shall be evaluated periodically by a third party viz. College of fisheries, Konkan Krishi Vidyapeeth Ratangiri Being complied with. One Continuous ambient air quality monitoring station has been installed. Order for additional 2 stations has been placed & expected to be in place within the next three months.
34
contd
It shall be ensured that no spillage of sea water on the Being complied with land from the pipelines of intake & outfall takes place. RCC lined channels along the pipelines shall be provided to avoid any possible contamination of land with sea water. Dense plantation of density not less than 2500 Being complied with trees/shrubs per ha (and survival rate less than 70 %) including plantations of Alphanso mango & cashew interspersed with native plant species, shall be raised within & outside the study area to act as buffer. Also plantation of coconut & casurina all along the coast line shall be provided to serve as shelter belt. Sufficient funds earmarked for the same & schedule of implementation shall be submitted within six months to the Ministry .
35
36
Summe r Daily
29.9 19.6 53.1 45.0 9 38.9 30.82 23.26 15.74 5.49 14.20 0 2 37.46 4 18.7 3 14.81 11.12 7.50 29.7 25.8 18.5 13.6 2.63 11.00 4 1 22.12 0 4
27.2 39.3 33.2 27.5 17.5 3500 2000 4.03 WSW 1 21.18 15.54 15.44 5.42 12.10 1 8 27.64 4 2 13.3 12.6 11.6 10.7 0.55 10.20 6 7 12.01 0 6 44.4 37.3 23.8 16.4 12.80 0 8 30.47 4 0
Postmonsoo Season n al 5000 2500 5.59 WSW 3.16 2.47 Winter Winter Daily 3000 3000 4.24 SE
1.80
1.39
FGD-UNIT 2
FGD-UNIT 3 FGD-UNIT 4
TO SEA
38
Contd
3. Contingency Plan High Concentrated Slurry Disposal System (HCSD) Contract award Awarded to M/s BSBK Disposal Pond with lining 23 acre area earmarked Civil work is in progress
40
41
42
Mango Plantation
43
44
45
46
47
Contd.
48
49
Education to Society
JSW sent 50 local students to Dr Babasaheb Ambedkar Technical University for 3 year Diploma in Engineering course. After completion candidates are absorbed in JSW Group
JSW has imparted industrial training to about 20 local unemployed youth in masonry and allied works
50
JSW provided HDPE pipeline to facilitate water supply to Jaigad, Nandivade & Kunbiwadi villages.
51
Tailoring Centers: 3 tailoring units have been established for the village women, in the vicinity of the project. As of now, 47 women have been trained & currently 28 more are attending classes regularly.
Paddy Seeds Distribution - To increase the productivity of paddy cultivation, hybrid seeds distributed to farmers.
53
URJA; Primary Health Centre JSW started PHC in Jaigad. This PHC is having well qualified medical and Paramedical staff with all necessary medical instruments.
Student Health Check-up Camps - A Health check-up camp for all students had been organized in 12 primary schools of Jaigad Panchakroshi
54
Other CSR activities Bus Shelters: Constructed Bus Shelters for the benefit of the villagers. Village Road: Completed construction of 3 km of village road Street Light: Installation of street lights for village road under progress Employment to villagers: 500 villagers have been engaged at site from Dec, 2006 for various infrastructural works Self employment: Developed 24 groups of villagers/land losers as sub-contractors Facilities for schools: Computers, tables, benches, books, notebooks etc. have been donated to the schools in the vicinity
55
Dr. Viswanadha Sastri Associate Vice-President (Env.) JSW Energy Ltd. viswanadha.sastri@jsw.in
56