ACEE 434 Environmental Systems Design

Week 13 November 25, 25 2009


ACEE 434 Fall 2009 HDP

Putting All Together

ACEE 434 Fall 2009 HDP

Summary
Collect Information Determine Process Schematic

Design Unit Operations and Processes

Check Mass Balance


Iteration

P&ID, Lay-Out, Hydraulics

Detail Design (Civil, Mechanical, and Electronical)

ACEE 434 Fall 2009 HDP

Collection of Information
1. Geographical, sociological, meteorological characteristics of the region where the treatment plant will be built. 2. Wastewater characterization 3. Wastewater flow expectation 4. Effluent regulation 5. Effluent ff reuse consideration 6. Financial state

ACEE 434 Fall 2009 HDP

Process Schematic
Screens Influent Effluent

Inert Solids

Thickener

http://www.thewatertreatmentplant.com/gifs/image.jpg

ACEE 434 Fall 2009 HDP

Maas/Flow Balance

ACEE 434 Fall 2009 HDP

Term Project
The following information is given for an activated sludge wastewater treatment plant General information:
Constituent Current Population (capita) Annual population growth rate (%) Wastewater flowrate (L/capita/d) Peak wastewater flowrate (L/capita/d) Average wastewater temperature during summer (oC) Average wastewater temperature during winter (oC) Target effluent BOD Target effluent TSS Concentration, mg/L 50,000 3 200 300 22 9 10 10

ACEE 434 Fall 2009 HDP

Term Project
The following information is given for an activated sludge wastewater treatment plant Wastewater characteristics:
Constituent BOD sBOD COD sCOD rbCOD TSS VSS TKN NH4+-N TP Alkalinity bCOD/BOD ratio fd Concentration, mg/L 196 98 400 180 110 210 180 35 25 6 200 (as CaCO3) 1.6 0.15

ACEE 434 Fall 2009 HDP

Term Project
Kinetic Parameters:
Parameter m Ks Y kd Unit g VSS/g VSS/d mg bCOD/L g VSS/g bCOD g VSS/ g VSS/d Value 3.0 60.0 0.40 0.08

Parameters for Aeration:


Parameter alpha F (diffuser fouling factor) Beta Elevation Effective DO saturation depth Aeration tank liquid depth Clean H2O oxygen transfer rate Unit Unitless Unitless Unitless m m m % Value 0 45 0.45 0.90 1.0 300 2.5 30 30

ACEE 434 Fall 2009 HDP

Term Project
1. Your job is to design a wastewater treatment plant based on the information 1 provided. The design packet should include a process schematic, tables of mass balances at average and peak flows, layout of the plant, calculations for the design of every unit operations and processes, and justifications (or assumptions) for the calculations. 2. You can choose or combine any y unit operations p and/or p processes if the scheme meets the effluent requirement. 3. The treatment plant should meet the population growth of the town for 10 years from now on.

ACEE 434 Fall 2009 HDP

10