Вы находитесь на странице: 1из 15

CRONOGRAMA VALORIZADO DE OBRA

Obra :
Sub Pres:

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN
PACCHAC - TAPO - TARMA - JUNIN

Plazo :

240

Dias calendarios

MES 1

MES 2

MES 3

June-2013
ITEM

DESCRIPCION

UND

METRADO

PU

PARCIAL

DIAS

INICIO

FIN

10

11

12

13

14

15

16

MES 4

July-2013
17

18

19

20

21

22

23

24

25

26

27

28

29

30

10

11

12

13

14

15

16

17

MES 5

August-2013
18

19

20

21

22

23

24

25

26

27

28

29

30

31

10

11

12

13

14

15

16

17

September-2013
18

19

20

21

22

23

24

25

26

27

28

29

30

31

10

11

12

13

14

15

16

17

October-2013
18

19

20

21

22

23

24

25

26

27

28

29

30

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE


01
01.01
01.01.01

MEJORAMIENTO DE CAPTACION EXISTENTE


TRABAJOS PRELIMINARES
150

Alquiler de Local para la Obra

mes

1.00

150.00

150.00

14 01/06/13

14/06/13

01.01.02

Limpieza de Terreno Manual

m2

4.62

2.96

13.68

1 01/06/13

01/06/13

01.01.03

Trazo y replanteo en Terreno Normal

m2

5.31

1.49

7.91

1 02/06/13

02/06/13

01.02

100%
14
###
7.9
###

DEMOLICIONES
52

01.02.01

Demolicin Estructura de Concreto

est

1.00

51.58

51.58

1 03/06/13

03/06/13

###

01.02.02

Picado para Salida de Tubera en Cmara de Carga

pto

2.00

11.82

23.64

1 03/06/13

03/06/13

###

01.02.03

Picado y Raspado de Tarrajeo Existente Interior

m2

7.59

41.26

313.16

1 03/06/13

03/06/13

###

01.02.04

Picado y Raspado de Tarrajeo Existente Exterior

m2

19.75

41.26

814.89

1 03/06/13

03/06/13

###

Eliminacin de Material Excedente

01.02.05

24
313
815
32

m3

1.50

21.50

32.25

1 04/06/13

04/06/13

01.03.01

Tapa de Concreto para Estructuras segun diseo

und

2.00

88.30

176.60

1 06/06/13

06/06/13

01.03.02

Tarrajeo Interior con Impermeabilizante cem: arena 1:2

m2

7.59

30.41

230.81

1 04/06/13

04/06/13

01.03.03

Tarrajeo en exteriores con Cemento-Arena

m2

19.75

36.56

722.06

1 04/06/13

04/06/13

01.03.04

Acabado Pulido de Piso con Mortero 1:2

m2

4.62

17.26

79.74

1 05/06/13

05/06/13

m2

19.75

9.50

187.63

1 07/06/13

07/06/13

und

1.00

51.47

51.47

1 06/06/13

06/06/13

01.03

01.04
01.04.01
01.05
01.05.01
01.05.02
01.05.03
01.05.04
02
02.01
02.01.01
02.01.02

###

REVOQUES ENLUCIDOS Y MOLDURAS


177
###
231
###
722
###
80
###

PINTURA
Pintura Ltex dos manos en exteriores

188
###

SUMINISTRO E INSTALACION DE TUBERIAS


Canastilla de 2 1/2"

51
###
95

Valvula Compuerta de Bronce de Union Roscada de 2 1/2"

und

1.00

95.00

95.00

1 06/06/13

06/06/13

Tubera Galvanizada 2 1/2"

0.98

110.43

108.22

1 04/06/13

04/06/13

Tubera Galvanizada 4"

1.77

150.18

265.82

1 04/06/13

04/06/13

Limpieza de Terreno Manual

m2

4.52

2.96

13.38

1 01/06/13

01/06/13

Trazo y replanteo en Terreno Normal

###
108
###
266
###

MEJORAMIENTO DE RESERVORIO EXISTENTE


TRABAJOS PRELIMINARES
13
###
15

m2

10.24

1.49

15.26

1 02/06/13

02/06/13

02.02.01

Demolicin Estructura de Concreto

est

1.00

51.58

51.58

1 03/06/13

03/06/13

###

02.02.02

Picado para Salida de Tubera

pto

3.00

11.82

35.46

1 03/06/13

03/06/13

###

02.02.03

Picado y Raspado de Tarrajeo Existente Interior

m2

25.35

41.26

1,045.94

2 03/06/13

04/06/13

02.02.04

Picado y Raspado de Tarrajeo Existente Exterior

m2

38.00

41.26

1,567.88

2 03/06/13

04/06/13

02.02.05

Eliminacin de Material Excedente

m3

3.17

21.50

68.16

1 05/06/13

05/06/13

176.60

1 08/06/13

08/06/13

02.02

02.03

52
35
1045.94

2.00

88.30

02.03.02

Tarrajeo Interior con Impermeabilizante cem: arena 1:2

m2

25.35

30.41

770.89

3 05/06/13

07/06/13

02.03.03

Tarrajeo en exteriores con Cemento-Arena

m2

39.00

36.56

1,425.84

2 05/06/13

06/06/13

02.03.04

Acabado Pulido de Piso con Mortero 1:2

m2

15.47

17.26

267.01

1 07/06/13

07/06/13

m2

38.00

9.50

361.00

2 08/06/13

09/06/13

und

1.00

51.47

51.47

1 08/06/13

08/06/13

02.05.01

###

PINTURA
Pintura Ltex dos manos en exteriores

361
100%

SUMINISTRO E INSTALACION DE TUBERIAS


Canastilla de 2 1/2"

51
###
190

Valvula Compuerta de Bronce de Union Roscada de 2 1/2"

und

2.00

95.00

190.00

2 06/06/13

07/06/13

Valvula Compuerta de Bronce de Union Roscada de 4"

und

1.00

168.00

168.00

1 06/06/13

06/06/13

02.05.04

Tubera Galvanizada 2 1/2"

4.36

110.43

481.47

2 04/06/13

05/06/13

02.05.05

Tubera Galvanizada 4"

3.16

150.18

474.57

2 04/06/13

05/06/13

Limpieza de Terreno Manual

m2

9.00

Trazo y replanteo en Terreno Normal

03.01.01

100%
100%
267

02.05.03

03.01

###
770.89
1425.84

02.05.02

03

###

177

und

02.05

100%
68

Tapa de Concreto para Estructuras segun diseo

02.04.01

100%
1567.88

REVOQUES ENLUCIDOS Y MOLDURAS

02.03.01

02.04

###

DEMOLICIONES

100%
168
###
481.47
100%
474.57
100%

CONSTRUCCION DE CAMARA ROMPEPRESION


TRABAJOS PRELIMINARES
1 01/06/13

01/06/13

9.00

1.49

13.41

1 02/06/13

02/06/13

Excavacin manual en Terreno Normal

m3

3.18

68.77

218.69

3 03/06/13

05/06/13

03.02.02

Eliminacin de Material Excedente

m3

3.18

21.50

68.37

1 06/06/13

06/06/13

###

m2

2.89

26.68

77.11

1 06/06/13

06/06/13

###

471.70

679.25

1 11/06/13

11/06/13

03.02

03.03
03.03.01
03.04

2.96

27

26.64

m2

03.02.01

03.01.02

13

218.69

Solado E=4" Mezcla 1:10 Cemento Hormign

77

CONCRETO ARMADO
679

m3

1.44

03.04.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

50.75

4.36

221.27

1 07/06/13

07/06/13

03.04.03

Encofrado y Desencofrado Normal

m2

21.33

46.37

989.07

3 08/06/13

10/06/13

m2

12.52

38.60

483.27

2 12/06/13

13/06/13

glb

1.00

385.19

385.19

1 14/06/13

14/06/13

kg

2,450.06

0.12

294.01

1 02/06/13

02/06/13

03.06
03.06.01
04
04.01

100%
68

Concreto Armado f'c= 210 kg/cm2

03.05.01

###

CONCRETO SIMPLE

03.04.01

03.05

###

MOVIMIENTO DE TIERRAS

###
221
###
989.07
100%

REVOQUES ENLUCIDOS Y MOLDURAS


Tarrajeo Frotachado

483.27
100%

SUMINISTRO DE ACCESORIOS
Suministro de Accesorios para Camara RompePresion

385
###

FLETE
Flete Transporte - Peso

294
###

SISTEMA DE ALCANTARILLADO Y LETRINAS


01

TRABAJOS PRELIMINARES

01.01

Alquiler de Local para la Obra

mes

8.00

150.00

1,200.00

240 01/06/13

26/01/14

01.02

Cartel de Identificacin de la Obra de 3.60 X 2.40 M

und

1.00

#####

1,159.84

1 01/06/13

01/06/13

01.03

Trazo, replanteo y Nivelacin en Redes de Alcantarillado (03 Veces: Inicial, durante la


m Obra y Final)
3,013.81

0.57

1,717.87

9 02/06/13

10/06/13

01.04

glb

1.00

#####

9,280.64

1 02/06/13

02/06/13

365.26

14.76

5,391.24

5 24/07/13

28/07/13

02.01.02

Excavacion de Zanja para Tuberias en Terreno Normal C/Maquinaria Hmax=3.00m


m3

450.59

16.88

7,605.96

7 24/07/13

30/07/13

02.01.03

Excavacin de Zanja para Tuberas Aprom=0.80 Hmx<= 2.00m en Roca Fija

m3

1,386.09

60.71

84,149.52

28 31/07/13

27/08/13

02.01.04

Excavacin de Zanja para Tuberas Aprom=0.80 Hmx<= 3.00m en Roca Fija

m3

811.87

69.47

56,400.61

21 28/08/13

17/09/13

02.01.05

Excavacin para Buzones en Terreno Normal Hprom=2.5m

m3

42.24

34.39

1,452.63

02.01.06

Movilizacin de Maquinarias y Herramientas para la Obra

Excavacion para Buzones en Roca Fija

m3

101.08

59.16

5,979.89

7605.96

6 26/06/13

815.85

8.25

6,730.76

33 31/07/13

01/09/13

2,197.96

58.26

128,053.15

11 18/09/13

28/09/13

m3

879.12

29.19

25,661.51

13 02/07/13

14/07/13

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

1,428.57

34.34

49,057.09

8 15/07/13

22/07/13

Cama de Apoyo c/Arena, E=0.10m

3,052.50

8.11

24,755.78

10 02/09/13

11/09/13

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

3,052.50

3.17

9,676.43

12 11/10/13

22/10/13

Relleno con Material Propio E=6" inc. Compactacin con Plancha

m3

3,052.50

15.92

48,595.80

17 23/12/13

08/01/14

Suministro e Instalacin de tubera de PVC- U UF ISO 4435 DN 160mm Incluye anillo


m

1,203.94

20.98

25,258.66

14 12/09/13

25/09/13

Suministro e Instalacin de tubera de PVC- U UF ISO 4435 DN 200mm Incluye anillo


m

1,848.56

29.78

55,050.12

21 12/09/13

02/10/13

Entablado de Proteccin Temporal en Excavaciones con madera corriente H prom=1.0


m

1,622.12

34.13

55,362.96

11 31/07/13

10/08/13

03.03
04
04.01

670.50

2 23/10/13

24/10/13

29.48

13,266.00

26 25/10/13

19/11/13

450.00

2.58

1,161.00

12 20/11/13

01/12/13

04.01.04

Cama de Apoyo c/Arena, E=0.10m

450.00

8.11

3,649.50

6 02/12/13

07/12/13

04.01.05

Relleno con Material Propio

450.00

13.46

6,057.00

3 23/12/13

25/12/13

Eliminacion de Material Excedente

m3

und

9.94

20.63

205.06

1 26/12/13

26/12/13

Conexin y empalme a red de desague PVC hasta 6" incluye accesorios

90.00

228.70

20,583.00

15 08/12/13

22/12/13

04.02.02

Suministro e Instalacin de caja de concreto para desage 12"x24" incluye tapa c/marco
und FF 90.00

210.76

18,968.40

12 23/12/13

03/01/14

Red de Agua PVC SAP 1/2"

pto

75.00

8.60

645.00

2 20/11/13

21/11/13

Red de Agua PVC SAP 2 1/2"

pto

10.00

32.67

326.70

1 28/08/13

28/08/13

Media Caa Buzon Estandar

und

75.00

49.34

3,700.50

8 24/07/13

m2

8.48

26.68

226.25

1 26/06/13

26/06/13

und

44.00

#####

62,553.92

11 27/06/13

07/07/13

und

4.00

#####

8,161.12

7 27/06/13

03/07/13

und

18.00

#####

42,586.20

8 08/07/13

15/07/13

06.01.06

Buzn de Concreto D=1.20m, H=3.00m, e=0.20m

und

9.00

#####

23,734.44

8 16/07/13

23/07/13

und

173.00

51.92

8,982.16

5 26/09/13

30/09/13

26.92%

###

100%
###
22746.88

Dado de Concreto para empalme de Buzn (0.55x0.55x0.55) f'c=175 kg/cm2

100%
23734.44
100%

8982.16
100%

1617.83

3,052.50

0.53

1,617.83

8 03/10/13

10/10/13

07.02

Prueba Hidrulica+Desinfeccin Tub160-200mm a Zanja Tapada

3,052.50

1.42

4,334.55

7 09/01/14

15/01/14

07.03

Prueba Compactacin de Suelos (Proctor Modificado Densidad de Campo)

und

15.00

25.00

375.00

11 16/01/14

26/01/14

100%

LETRINAS DE ARRASTRE HIDRAULICO


TRABAJOS PRELIMINARES
Trazo y replanteo en Terreno Normal

276

m2

185.09

1.49

275.78

1 02/06/13

02/06/13

08.02.01

Excavacin de zanjas en Pozo de Filtracin

m3

190.05

26.29

4,996.41

12 03/06/13

14/06/13

08.02.02

Cama de Apoyo c/Arena, E=0.10m

110.00

8.11

892.10

2 15/06/13

16/06/13

08.02.03

Acarreo de Material Excedente

m3

237.56

29.19

6,934.38

9 15/06/13

23/06/13

08.02.04

Eliminacin de Material Excedente

m3

237.56

21.50

5,107.54

10 24/06/13

03/07/13

m3

21.18

449.00

9,509.82

3 09/07/13

11/07/13

###

MOVIMIENTO DE TIERRAS
4996.41
100%
892.1
100%
6934.38
100%

Concreto Armado f'c= 175 kg/cm2

m2

97.35

46.37

4,514.12

11 26/06/13

06/07/13

Acero de Refuerzo Fy = 4200 kg/cm2

kg

214.50

4.36

935.22

2 07/07/13

08/07/13

Muro de Ladrillo KK 18H (9x13x24) Soga en Pozo

m2

100%

330.00

93.67

30,911.10

11 15/06/13

25/06/13

100%

CONSTRUCCION DE CASETA
13715.03

Colocacion de Calamina N30

m2

688.16

19.93

13,715.03

7 06/06/13

12/06/13

Correas de Madera 2"X2"

1,296.90

6.67

8,650.32

5 01/06/13

05/06/13

Correas de Madera 1"X2"

671.55

4.65

3,122.71

3 01/06/13

03/06/13

100%

08.04.04

Correas de Madera 1"X3"

302.50

5.60

1,694.00

3 01/06/13

03/06/13

100%

Bisagra Aluminizada Capuchina de 3" x 3"

pza

110.00

36.53

4,018.30

3 13/06/13

15/06/13

Cerrojo para Puerta de 1/2" X 0.15 M

und

55.00

29.71

1,634.05

2 16/06/13

17/06/13

100%

1694

CERRAJERIA
4018.3
100%
1634.05
100%

PINTURA
Pintura anticorrosiva y esmalte en Calaminas

m2

688.16

15.12

10,404.98

10404.98

3 13/06/13

15/06/13

100%

APARATOS Y ACCESORIOS SANITARIOS


3559.05

Inodoro Ecologico

und

55.00

64.71

3,559.05

5 13/06/13

17/06/13

08.07.02

Tubera PVC SAL 4"

165.00

23.13

3,816.45

9 17/06/13

25/06/13

08.07.03

Codo PVC SAL 4"x45

pza

110.00

26.18

2,879.80

10 26/06/13

05/07/13

08.07.04

Tubera de PVC SAL 2"

115.50

19.74

2,279.97

6 06/06/13

11/06/13

08.07.05

Codo PVC SAL 2"x90

pza

55.00

17.96

987.80

4 12/06/13

15/06/13

08.07.06

Sombrero para Ventilacin de PVC 2"

und

55.00

2.12

116.60

10 16/06/13

25/06/13

10.01

100%
8650.32
3122.71

08.07.01

10

54.55%
100%

08.04.03

09.02

2462.25

45.45%

935.22

08.04.02

09.01

30.00%

2051.87

30911.1

08.04.01

09

1532.26

70.00%

9509.82

Encofrado y Desencofrado Normal

08.03.03

08.07

3575.28

CONCRETO SIMPLE

08.03.02

08.06.01

42.86%

PRUEBAS HIDRAULICA EN TUBERIA DE ALCANTARILLADO


m

08.06

63.64%
3497.62

57.14%

42586.2

Prueba Zanja Abierta o Zanja Tapada P/Tub.Desague 8"

08.05.02

39807.04

36.36%
4663.50

CONCRETO SIMPLE

07.01

08.05.01

9.52%

226

Buzn de Concreto D=1.20m, H=2.5m, e=0.20m

08.05

5242.87

90.48%

100%

31/07/13

Buzn de Concreto D=1.20m, H=2.0m, e=0.20m

08.04

49807.25

327

Buzn de Concreto D=1.20m, H=1.50m, e=0.15m

08.03.04

90.91%

3700.5

Solado E=4" Mezcla 1:10 Cemento Hormign

08.03.01

50329.96

###

BUZONES DE ALCANTARILLADO DINT=1.20M HASTA 3.00M

06.01.05

08.03

###

BUZONES DE CONCRETO

06.01.04

08.02

100%

100%

REPARACION DE TUBERIAS ROTAS

06.01.03

08.01.01

100%

SUMINISTRO E INSTALACION DE TUBERIAS

06.01.02

08.01

100%

3571.62

04.02.01

08

###

670.5

1.49

450.00

07

93.94%

100%

TRABAJOS PRELIMINARES
450.00

06.02.01

###

100%

INSTALACIONES DOMICILIARIAS

06.02

###

9676.43

06.01.01

80.95%

6322.84

25258.66

06.01

45657.64

###

24755.78

Refine y Nivelacin en Terreno Normal

06

###

SUMINISTRO E INSTALACION DE TUBERIAS

Excavacin de Zanja para Tuberas Aprom=0.60 (Conexiones Domici)

05.02

83.33%

CAMA Y RELLENO

Trazo y replanteo en Terreno Normal

05.01

96.43%

128053.15

04.01.03

05

###

49057.09

04.01.02

04.02

4983.24

25661.51

04.01.01

04.01.06

81144.18

100%

01/07/13

Acarreo de Material Excedente

03.02

###
###

19.05%

25/06/13

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

03.01

100%

10742.97

15 11/06/13

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Normal

03

100%

1452.63

02.01.10

02.02.03

###

5391.24

02.01.09

02.02.02

155.00
12.92%

EXCAVACIONES

02.01.08

02.02.01

150.00
12.50%

100%

MOVIMIENTO DE TIERRAS

02.01.07

02.02

155.00
12.92%

1717.87

Excavacion de Zanja para Tuberias en Terreno Normal C/Maquinaria Hmax=2.00m


m3

02.01

155.00
12.92%

###

###

02.01.01

02

150.00
12.50%
###

100%
3816.45
100%
1439.90

1439.90

50.00%

50.00%

2279.97
100%
987.8
100%
116.6
100%

FLETE
24908.89

Flete Transporte - Peso

kg

207,574.09

0.12

24,908.89

22 02/06/13

23/06/13

Flete Transporte - Volumen

vje

9.00

#####

9,900.00

9 24/06/13

02/07/13

8.00

250.00

2,000.00

4 11/06/13

14/06/13

51.88

100%
7700.00

2200.00

77.78%

22.22%

IMPACTO AMBIENTAL
Capacitacin en Medidas de Mitigacin Ambiental

2000
100%

PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES


01

TRABAJOS PRELIMINARES
2075.2

01.01

Caseta de Almacn y Guardiana c/triplay y parantes de madera tornillo (aprox. 12m2)


m2+ calamina 40.00

2,075.20

2 03/10/13

04/10/13

01.02

Trazo y replanteo en Terreno Normal con Equipo

m2

846.48

1.11

939.59

2 05/10/13

06/10/13

01.03

Movilizacin de Maquinarias y Herramientas para la Obra

glb

1.00

#####

9,280.64

1 05/10/13

05/10/13

72,412.03

02
02.01

939.59

72412.03

Excavacion en Terreno Rocoso

m3

591.36

122.45

12 07/10/13

18/10/13

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

94.12

58.26

5,483.43

4 19/10/13

22/10/13

02.01.03

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

847.44

3.17

2,686.38

4 23/10/13

26/10/13

02.01.04

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

435.85

34.34

14,967.09

3 27/10/13

29/10/13

m2

4.71

26.68

125.66

1 27/10/13

27/10/13

02.03

###

MOVIMIENTO DE TIERRAS

02.01.02

02.02.01

100%
###

02.01.01

02.02

100%

TANQUE IMHOFF

100%
5483.43
100%
2686.38
100%
14967.09
100%

CONCRETO SIMPLE
Solado E=2" Mezcla 1:10 Cemento Hormign
CONCRETO ARMADO

126
###

02.03.01
02.03.02
02.03.03
02.04

Concreto Armado f'c= 210 kg/cm2

m3

90.28

42,585.08

5 11/11/13

15/11/13

Acero de Refuerzo Fy = 4200 kg/cm2

kg

1,914.34

4.36

8,346.52

5 28/10/13

01/11/13

Encofrado y Desencofrado Muros Reforzados

m2

443.83

471.70

32.23

14,304.64

9 02/11/13

10/11/13

ACABADOS FINALES

02.04.01

Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm

m2

375.31

30.41

11,413.18

5 18/11/13

22/11/13

02.04.02

Water Stop de Meopreno de 6" Provicion y Colocado

172.80

7.30

1,261.44

1 27/10/13

27/10/13

02.04.03

Escalera tipo gato tub. 20 mm

und

4.00

115.00

460.00

1 23/11/13

23/11/13

02.04.04

Baranda de Tubo F.G. Pasamano 1 1/2" - Parante 1" X 1m

24.00

74.31

1,783.44

3 23/11/13

25/11/13

122.31

5,870.88

02.05

###

02.05.01

Suministro e Instalacin de tubera SCH 40- 8"

48.00

1 16/11/13

16/11/13

02.05.02

Suministro e Instalacin Codo PVC 200 mm S-20

und

14.00

763.14

1 17/11/13

17/11/13

02.05.03

Suministro e Instalacin Tee PVC 200 mm S-20

und

4.00

66.69

266.76

1 17/11/13

17/11/13

02.05.04

Suministro e Instalacin Vlvula de Compuerta FF Mazza 200 mm

und

4.00

#####

4,722.88

1 23/11/13

23/11/13

02.05.05

Batle de Madera Tratada 1.70X1.20X0.50 m

und

4.00

156.82

627.28

1 23/11/13

23/11/13

03
03.01

54.51

LECHO DE SECADO
MOVIMIENTO DE TIERRAS
52689.01

03.01.01

Excavacion en Terreno Rocoso

m3

430.29

122.45

52,689.01

18 05/10/13

22/10/13

03.01.02

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

137.57

58.26

8,014.83

7 23/10/13

29/10/13

03.01.03

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

73.68

3.17

233.57

2 30/10/13

31/10/13

03.01.04

Acarreo de Material Excedente

m3

516.35

29.19

15,072.26

10 30/10/13

08/11/13

03.01.05

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

516.35

34.34

17,731.46

3 09/11/13

11/11/13

03.02
03.02.01

32.40

26.68

864.43

1 01/11/13

01/11/13

Concreto Armado f'c= 210 kg/cm2

m3

48.80

471.70

23,018.96

5 11/11/13

15/11/13

Acero de Refuerzo Fy = 4200 kg/cm2

kg

764.40

4.36

3,332.78

4 02/11/13

05/11/13

Encofrado y Desencofrado Muros Reforzados

m2

273.84

32.23

8,825.86

5 06/11/13

10/11/13

m2

330.29

30.41

10,044.12

7 18/11/13

24/11/13

42.00

122.31

5,137.02

1 16/11/13

16/11/13

03.04
03.04.01
03.05

Solado E=2" Mezcla 1:10 Cemento Hormign

m2

CONCRETO ARMADO

ACABADOS FINALES
Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm
INSTALACIONES HIDRAULICAS

03.05.01

Suministro e Instalacin de tubera Schedule (200mm)

03.05.02

Suministro y Colocacin de Accesorios en Lecho de Secados

glb

1.00

#####

1,899.06

1 17/11/13

17/11/13

03.05.03

Suministro e Instalacin Grava 3/4 - 2"

m3

11.09

62.87

697.23

2 25/11/13

26/11/13

03.05.04

Suministro e Instalacin Grava 1/4 - 7/8"

m3

11.09

62.87

697.23

2 27/11/13

28/11/13

03.05.05

Suministro e Instalacin Arena Gruesa

m3

9.24

76.37

705.66

2 29/11/13

30/11/13

03.06

TECHOS Y COBERTURAS

03.06.01

Tijerales de Madera Tipo I

und

5.00

196.03

980.15

1 16/11/13

16/11/13

03.06.02

Tijerales de Madera Tipo II

und

5.00

215.13

1,075.65

1 16/11/13

16/11/13

Cobertura de Techo con calamina galvanizada de 0.80x1.80m

m2

163.00

19.93

3,248.59

2 17/11/13

18/11/13

Limpieza manual de Terreno Normal

m2

21.24

2.95

62.66

1 30/11/13

30/11/13

Trazo y replanteo en Terreno Normal

m2

21.24

1.49

31.65

1 01/12/13

01/12/13

03.06.03
04
04.01
04.01.01
04.01.02
04.02

POZO PERCOLADOR
TRABAJOS PRELIMINARES

MOVIMIENTO DE TIERRAS

04.02.01

Excavacin de zanjas en Pozo de Filtracin

m3

73.28

26.29

1,926.53

5 02/12/13

06/12/13

04.02.02

Eliminacin de Material Excedente

m3

351.74

21.50

7,562.41

4 07/12/13

10/12/13

04.03

CONCRETO SIMPLE

04.03.01

Concreto 1:10 +30% PG para Cimientos

m3

1.15

192.49

221.36

1 15/12/13

15/12/13

04.03.02

Encofrado y Desencofrado de Cimientos

m2

25.64

40.85

1,047.39

2 13/12/13

14/12/13

04.04

CONCRETO ARMADO

04.04.01

Concreto Armado f'c= 175 kg/cm2

m3

1.79

449.00

803.71

2 20/12/13

21/12/13

04.04.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

82.52

4.36

359.79

2 18/12/13

19/12/13

Encofrado de Losa y Tapa

m2

7.83

102.45

802.18

2 16/12/13

17/12/13

m2

67.86

113.22

7,683.11

5 07/12/13

11/12/13

glb

4.00

110.88

443.52

1 22/12/13

22/12/13

04.04.03
04.05
04.05.01
04.06
04.06.01
04.07

MURO DE ALBAILERIA
Muro de Ladrillo KK 18H (9x13x24) Cabeza en Pozo
SUMINISTRO DE ACCESORIOS
Suministro y Colocacin de Accesorios en Pozo
VARIOS

04.07.01

Suministro e Instalacin Piedra Chancada de 1/2"

m3

25.95

15.87

411.83

2 13/12/13

14/12/13

04.07.02

Suministro e Instalacin Grava 2"

m3

3.69

15.87

58.56

1 12/12/13

12/12/13

Limpieza manual de Terreno Normal

m2

1.44

2.95

4.25

1 17/11/13

17/11/13

Trazo y replanteo en Terreno Normal

05
05.01
05.01.01
05.01.02

CAJAS DE INSPECCION Y DISTRIBUCION


TRABAJOS PRELIMINARES

m2

1.44

1.49

2.15

1 18/11/13

18/11/13

05.02.01

Excavacin de zanjas para Caja de Inspeccin

m3

1.16

26.29

30.50

1 24/11/13

24/11/13

05.02.02

Eliminacin de Material Excedente

m3

1.16

21.50

24.94

1 25/11/13

25/11/13

Concreto Armado f'c= 175 kg/cm2

m3

0.78

449.00

350.22

1 28/11/13

28/11/13

Acero de Refuerzo Fy = 4200 kg/cm2

kg

29.46

4.36

128.45

1 25/11/13

25/11/13

Encofrado y Desencofrado de Caja de Inspeccin

m2

13.51

102.45

1,384.10

2 26/11/13

27/11/13

m2

6.08

30.41

184.89

1 29/11/13

29/11/13

05.02

05.03
05.03.01
05.03.02
05.03.03
05.04
05.04.01
05.05

MOVIMIENTO DE TIERRAS

CONCRETO ARMADO

REVOQUES ENLUCIDOS Y MOLDURAS


Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm
EXCAVACION Y TENDIDO DE TUBERIAS

05.05.01

Excavacin de Zanja para Tuberas Aprom=0.60 Hmx<= 1.00m en Terreno Normal


m3 Manual

8.96

26.29

235.56

3 19/11/13

21/11/13

05.05.02

Tuberia PVC SAL 4"

28.00

23.13

647.64

2 22/11/13

23/11/13

Relleno con Material Propio E=6" inc. Compactacin con Plancha

m3

8.96

15.92

142.64

1 24/11/13

24/11/13

Limpieza manual de Terreno Normal

m2

2,527.89

2.95

7,457.28

2 16/12/13

17/12/13

Trazo y replanteo en Terreno Normal

m2

2,527.89

1.49

3,766.56

2 18/12/13

19/12/13

05.05.03
06
06.01
06.01.01
06.01.02
06.02

CERCO PERIMETRICO
TRABAJOS PRELIMINARES

MOVIMIENTO DE TIERRAS

06.02.01

Excavacin manual en Terreno Normal

m3

2.25

68.77

154.73

2 20/12/13

21/12/13

06.02.02

Acarreo de Material Excedente

m3

2.81

29.19

82.02

1 22/12/13

22/12/13

Eliminacin de Material Excedente

m3

2.81

21.50

60.42

1 23/12/13

23/12/13

m3

2.25

449.00

1,010.25

1 31/12/13

31/12/13

06.02.03
06.03
06.03.01
06.04

CONCRETO SIMPLE
Concreto Armado f'c= 175 kg/cm2
VARIOS

06.04.01

Colocacin de Parantes de Eucalipto de 1.85 x 3"

und

06.04.02

Colocacin de Alambre de Pas

Puerta c/marco de madera y malla de acero

und

06.04.03
07

100%

CONCRETO SIMPLE

03.03.02
03.03.03

100%
8014.83

03.03.01

03.03

###

INSTALACIONES HIDRAULICAS

50.00

37.73

1,886.50

9 22/12/13

30/12/13

1,750.50

29.24

51,184.62

4 01/01/14

04/01/14

1.00

393.90

393.90

1 05/01/14

05/01/14

FLETE
12903.23

07.01

Flete Transporte - Peso

kg

107,526.89

0.12

12,903.23

12 03/10/13

14/10/13

07.03

Transporte con Acemilas Dprom=300m hacia PTAR

kg

107,526.89

0.57

61,290.33

17 04/10/13

20/10/13

COSTO DIRECTO
GASTOS GENERALES
UTILIDAD

PRESUPUESTO TOTAL

1,515,437.27

AVANCE MENSUAL
AVANCE ACUMULADO
PORCENTAJE MENSUAL
PORCENTAJE ACUMULADO

61290.33
100%

S/. 200,011.07
24,001.33
20,001.11

S/. 228,515.00
27,421.80
22,851.50

S/. 149,021.65
17,882.60
14,902.17

S/. 282,868.60

12.00%
10.00%

181,852.47
151,543.73
1,848,833.47

244,013.51

278,788.30

181,806.42

345,099.69

1.00000
18.00%

1,848,833.47
332,790.02

244,013.51
43,922.43

278,788.30
50,181.89

181,806.42
32,725.16

345,099.69
62,117.94

2,181,623.49

287,935.94

328,970.19

214,531.58

407,217.63

287,935.94
287,935.94

328,970.19
616,906.13

214,531.58
831,437.71

407,217.63
1,238,655.34

13.20%
13.20%

15.08%
28.28%

9.83%
38.11%

18.67%
56.78%

SUBTOTAL
FACTOR DE RELACION
IGV

100%

33,944.23
28,286.86

MES 6

MES 7

MES 8

Nov ember-2013
28

29

30

31

10

3571.62

9694.38

26.92%

73.08%

11

12

13

14

15

16

17

December-2013
18

19

20

21

22

23

24

25

26

27

28

29

30

10

11

12

13

14

15

16

17

January-2014
18

19

20

21

22

23

24

25

26

27

28

29

30

31

10

11

12

13

14

150.00

155.00

130.00

12.50%

12.92%

10.83%

1064.25

###

91.67%

###

25727.19

22868.61

52.94%

47.06%

15

16

17

18

19

20

21

3649.5
100%
6057
100%
205
###

20583
100%
14226.30

4742.10

75.00%

25.00%

645
100%

4334.55
100%
375
100%

14967.09
100%

42585.08

22

23

24

25

26

100%
6677.22

###

80.00%

###
14304.64
100%

11413.18
100%

460
###
1783.44
100%

###
###
763
###
267
###
###
###
627
###

8014.83
100%
233.57
100%
3014.45

12057.81

20.00%

80.00%
17731.46
100%

864
###

23018.96
100%
3332.78
100%
8825.86
100%

10044.12
100%

###
###
###
###
697.23
100%
697.23
100%
705.66
100%

980
###
###
###
3248.59
100%

63
###
32
###

1926.53
100%
7562.41
100%

221
###
1047.39
100%

803.71
100%
359.79
100%
802.18
100%

7683.11
100%

444
###

411.83
100%
59
###

4.3
###
2.2
###

31
###
25
###

350
###
128
###
1384.1
100%

185
###

235.56
100%
647.64
100%
143
###

7457.28
100%
3766.56
100%

154.73
100%
82
###
60
###

###
###

1886.5
100%
51184.62
100%
394
###

S/. 274,988.34
32,998.60
27,498.83

S/. 189,534.23
22,744.11
18,953.42

S/. 106,469.60
12,776.35
10,646.96

S/. 84,028.78
10,083.45
8,402.88

335,485.77

231,231.76

129,892.91

102,515.11

335,485.77
60,387.44

231,231.76
41,621.72

129,892.91
23,380.72

102,515.11
18,452.72

395,873.21

272,853.48

153,273.63

120,967.83

395,873.21
1,634,528.55

272,853.48
1,907,382.03

153,273.63
2,060,655.66

120,967.83
2,181,623.49

18.15%
74.92%

12.51%
87.43%

7.03%
94.46%

5.54%
100.00%

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM

240

DESCRIPCION

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE


01
01.01

MEJORAMIENTO DE CAPTACION EXISTENTE


TRABAJOS PRELIMINARES

01.01.01

Alquiler de Local para la Obra

mes

1.00

150.00

150.00

01.01.02

Limpieza de Terreno Manual

m2

4.62

2.96

13.68

01.01.03

Trazo y replanteo en Terreno Normal

m2

5.31

1.49

7.91

01.02

DEMOLICIONES

01.02.01

Demolicin Estructura de Concreto

est

1.00

51.58

51.58

01.02.02

Picado para Salida de Tubera en Cmara de Carga

pto

2.00

11.82

23.64

01.02.03

Picado y Raspado de Tarrajeo Existente Interior

m2

7.59

41.26

313.16

01.02.04

Picado y Raspado de Tarrajeo Existente Exterior

m2

19.75

41.26

814.89

01.02.05

Eliminacin de Material Excedente

m3

1.50

21.50

32.25

01.03

100.00%
150.00
100.00%
13.68
100.00%
7.91

100.00%
51.58
100.00%
23.64
100.00%
313.16
100.00%
814.89
100.00%
32.25

REVOQUES ENLUCIDOS Y MOLDURAS

01.03.01

Tapa de Concreto para Estructuras segun diseo

und

2.00

88.30

176.60

01.03.02

Tarrajeo Interior con Impermeabilizante cem: arena 1:2

m2

7.59

30.41

230.81

01.03.03

Tarrajeo en exteriores con Cemento-Arena

m2

19.75

36.56

722.06

01.03.04

Acabado Pulido de Piso con Mortero 1:2

m2

4.62

17.26

79.74

100.00%
176.60
100.00%
230.81
100.00%
722.06
100.00%
79.74

m2

19.75

9.50

187.63

100.00%
187.63

01.04
01.04.01
01.05

PINTURA
Pintura Ltex dos manos en exteriores
SUMINISTRO E INSTALACION DE TUBERIAS

01.05.01

Canastilla de 2 1/2"

und

1.00

51.47

51.47

01.05.02

Valvula Compuerta de Bronce de Union Roscada de 2 1/2"

und

1.00

95.00

95.00

01.05.03

Tubera Galvanizada 2 1/2"

0.98

110.43

108.22

01.05.04

Tubera Galvanizada 4"

1.77

150.18

265.82

02

MEJORAMIENTO DE RESERVORIO EXISTENTE

100.00%
51.47
100.00%
95.00
100.00%
108.22
100.00%
265.82

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM
02.01

240

DESCRIPCION

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

TRABAJOS PRELIMINARES

02.01.01

Limpieza de Terreno Manual

m2

4.52

2.96

13.38

02.01.02

Trazo y replanteo en Terreno Normal

m2

10.24

1.49

15.26

02.02

100.00%
13.38
100.00%
15.26

DEMOLICIONES

02.02.01

Demolicin Estructura de Concreto

est

1.00

51.58

51.58

02.02.02

Picado para Salida de Tubera

pto

3.00

11.82

35.46

02.02.03

Picado y Raspado de Tarrajeo Existente Interior

m2

25.35

41.26

1,045.94

02.02.04

Picado y Raspado de Tarrajeo Existente Exterior

m2

38.00

41.26

1,567.88

02.02.05

Eliminacin de Material Excedente

m3

3.17

21.50

68.16

02.03

100.00%
51.58
100.00%
35.46
100.00%
1,045.94
100.00%
1,567.88
100.00%
68.16

REVOQUES ENLUCIDOS Y MOLDURAS

02.03.01

Tapa de Concreto para Estructuras segun diseo

und

2.00

88.30

176.60

02.03.02

Tarrajeo Interior con Impermeabilizante cem: arena 1:2

m2

25.35

30.41

770.89

02.03.03

Tarrajeo en exteriores con Cemento-Arena

m2

39.00

36.56

1,425.84

02.03.04

Acabado Pulido de Piso con Mortero 1:2

m2

15.47

17.26

267.01

100.00%
176.60
100.00%
770.89
100.00%
1,425.84
100.00%
267.01

m2

38.00

9.50

361.00

100.00%
361.00

02.04
02.04.01
02.05

PINTURA
Pintura Ltex dos manos en exteriores
SUMINISTRO E INSTALACION DE TUBERIAS

02.05.01

Canastilla de 2 1/2"

und

1.00

51.47

51.47

02.05.02

Valvula Compuerta de Bronce de Union Roscada de 2 1/2"

und

2.00

95.00

190.00

02.05.03

Valvula Compuerta de Bronce de Union Roscada de 4"

und

1.00

168.00

168.00

02.05.04

Tubera Galvanizada 2 1/2"

4.36

110.43

481.47

02.05.05

Tubera Galvanizada 4"

3.16

150.18

474.57

100.00%
51.47
100.00%
190.00
100.00%
168.00
100.00%
481.47
100.00%
474.57

m2

9.00

2.96

26.64

100.00%
26.64

03
03.01
03.01.01

CONSTRUCCION DE CAMARA ROMPEPRESION


TRABAJOS PRELIMINARES
Limpieza de Terreno Manual

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM
03.01.02
03.02

240

DESCRIPCION
Trazo y replanteo en Terreno Normal

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

m2

9.00

1.49

13.41

1
100.00%
13.41

Excavacin manual en Terreno Normal

m3

3.18

68.77

218.69

03.02.02

Eliminacin de Material Excedente

m3

3.18

21.50

68.37

100.00%
218.69
100.00%
68.37

m2

2.89

26.68

77.11

100.00%
77.11

03.03.01
03.04

Solado E=4" Mezcla 1:10 Cemento Hormign

m3

1.44

471.70

679.25

03.04.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

50.75

4.36

221.27

03.04.03

Encofrado y Desencofrado Normal

m2

21.33

46.37

989.07

100.00%
679.25
100.00%
221.27
100.00%
989.07

m2

12.52

38.60

483.27

100.00%
483.27

glb

1.00

385.19

385.19

100.00%
385.19

kg

2,450.06

0.12

294.01

100.00%
294.01

03.06
03.06.01
04
04.01

CONCRETO ARMADO
Concreto Armado f'c= 210 kg/cm2

03.05.01

CONCRETO SIMPLE

03.04.01

03.05

MOVIMIENTO DE TIERRAS

03.02.01

03.03

REVOQUES ENLUCIDOS Y MOLDURAS


Tarrajeo Frotachado
SUMINISTRO DE ACCESORIOS
Suministro de Accesorios para Camara RompePresion
FLETE
Flete Transporte - Peso
SISTEMA DE ALCANTARILLADO Y LETRINAS

01

TRABAJOS PRELIMINARES

01.01

Alquiler de Local para la Obra

mes

8.00

150.00

1,200.00

01.02

Cartel de Identificacin de la Obra de 3.60 X 2.40 M

und

1.00

1,159.84

1,159.84

01.03

Trazo, replanteo y Nivelacin en Redes de Alcantarillado (03 Veces: Inicial, durante la Obra
m y Final) 3,013.81

0.57

1,717.87

01.04

Movilizacin de Maquinarias y Herramientas para la Obra

02
02.01
02.01.01

glb

1.00

9,280.64

9,280.64

Excavacion de Zanja para Tuberias en Terreno Normal C/Maquinaria Hmax=2.00m m3

365.26

14.76

5,391.24

12.50%
150.00
100.00%
1,159.84
100.00%
1,717.87
100.00%
9,280.64

12.92%
155.00

MOVIMIENTO DE TIERRAS
EXCAVACIONES
100.00%
5,391.24

12.92%
155.00

12.50%
150.00

12.92%
155.00

12.50%
150.00

12.92%
155.00

10.83%
130.00

CRONOGRAMA VALORIZADO DE OBRA


PROYECTO
LUGAR
PLAZO

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PACCHAC - TAPO - TARMA - JUNIN

ITEM

240

DESCRIPCION

DIAS CALENDARIOS
UND

02.01.02

Excavacion de Zanja para Tuberias en Terreno Normal C/Maquinaria Hmax=3.00m m3

02.01.03

Excavacin de Zanja para Tuberas Aprom=0.80 Hmx<= 2.00m en Roca Fija

02.01.04

METRADO

PU

PARCIAL

450.59

16.88

7,605.96

m3

1,386.09

60.71

84,149.52

Excavacin de Zanja para Tuberas Aprom=0.80 Hmx<= 3.00m en Roca Fija

m3

811.87

69.47

56,400.61

02.01.05

Excavacin para Buzones en Terreno Normal Hprom=2.5m

m3

42.24

34.39

1,452.63

02.01.06

Excavacion para Buzones en Roca Fija

m3

101.08

59.16

5,979.89

02.01.07

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Normal

815.85

8.25

6,730.76

02.01.08

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

2,197.96

58.26

128,053.15

02.01.09

Acarreo de Material Excedente

m3

879.12

29.19

25,661.51

02.01.10

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

1,428.57

34.34

49,057.09

02.02

Cama de Apoyo c/Arena, E=0.10m

3,052.50

8.11

24,755.78

02.02.02

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

3,052.50

3.17

9,676.43

02.02.03

Relleno con Material Propio E=6" inc. Compactacin con Plancha

m3

3,052.50

15.92

48,595.80

Suministro e Instalacin de tubera de PVC- U UF ISO 4435 DN 160mm Incluye anillo m

1,203.94

20.98

25,258.66

03.02

Suministro e Instalacin de tubera de PVC- U UF ISO 4435 DN 200mm Incluye anillo m

1,848.56

29.78

55,050.12

03.03

Entablado de Proteccin Temporal en Excavaciones con madera corriente H prom=1.0m

1,622.12

34.13

55,362.96

04.01

16.67%
996.65
3.03%
203.96

96.43%
81,144.18
19.05%
10,742.97

93.94%
6,322.84

80.95%
45,657.64

3.03%
203.96
100.00%
128,053.15

100.00%
25,661.51
100.00%
49,057.09

100.00%
24,755.78
100.00%
9,676.43
52.94%
25,727.19

SUMINISTRO E INSTALACION DE TUBERIAS

03.01

04

100.00%
1,452.63
83.33%
4,983.24

2
100.00%
7,605.96
3.57%
3,005.34

CAMA Y RELLENO

02.02.01

03

100.00%
25,258.66
90.48%
49,807.25
9.09%
5,033.00

9.52%
5,242.87

90.91%
50,329.96

INSTALACIONES DOMICILIARIAS
TRABAJOS PRELIMINARES

04.01.01

Trazo y replanteo en Terreno Normal

450.00

1.49

670.50

04.01.02

Excavacin de Zanja para Tuberas Aprom=0.60 (Conexiones Domici)

450.00

29.48

13,266.00

04.01.03

Refine y Nivelacin en Terreno Normal

450.00

2.58

1,161.00

04.01.04

Cama de Apoyo c/Arena, E=0.10m

450.00

8.11

3,649.50

04.01.05

Relleno con Material Propio

450.00

13.46

6,057.00

04.01.06

Eliminacion de Material Excedente

m3

9.94

20.63

205.06

100.00%
670.50
26.92%
3,571.62

73.08%
9,694.38
91.67%
1,064.25

8.33%
96.75
100.00%
3,649.50
100.00%
6,057.00
100.00%
205.06

47.06%
22,868.61

CRONOGRAMA VALORIZADO DE OBRA


PROYECTO
LUGAR
PLAZO

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PACCHAC - TAPO - TARMA - JUNIN

ITEM
04.02

240

DESCRIPCION

DIAS CALENDARIOS
UND

PU

PARCIAL

Conexin y empalme a red de desague PVC hasta 6" incluye accesorios

04.02.02

Suministro e Instalacin de caja de concreto para desage 12"x24" incluye tapa c/marco
und FF

und

90.00

228.70

20,583.00

90.00

210.76

18,968.40

Red de Agua PVC SAP 1/2"

pto

75.00

8.60

645.00

05.02

Red de Agua PVC SAP 2 1/2"

pto

10.00

32.67

326.70

06.01

und

75.00

49.34

3,700.50

06.01.02

Solado E=4" Mezcla 1:10 Cemento Hormign

m2

8.48

26.68

226.25

06.01.03

Buzn de Concreto D=1.20m, H=1.50m, e=0.15m

und

44.00

1,421.68

62,553.92

06.01.04

Buzn de Concreto D=1.20m, H=2.0m, e=0.20m

und

4.00

2,040.28

8,161.12

06.01.05

Buzn de Concreto D=1.20m, H=2.5m, e=0.20m

und

18.00

2,365.90

42,586.20

06.01.06

Buzn de Concreto D=1.20m, H=3.00m, e=0.20m

und

9.00

2,637.16

23,734.44

und

173.00

51.92

8,982.16

07

100.00%
226.25
36.36%
22,746.88
57.14%
4,663.50

25.00%
4,742.10

63.64%
39,807.04
42.86%
3,497.62
100.00%
42,586.20
100.00%
23,734.44

CONCRETO SIMPLE
Dado de Concreto para empalme de Buzn (0.55x0.55x0.55) f'c=175 kg/cm2

100.00%
8,982.16

PRUEBAS HIDRAULICA EN TUBERIA DE ALCANTARILLADO


100.00%
1,617.83

0.53

1,617.83

07.02

Prueba Hidrulica+Desinfeccin Tub160-200mm a Zanja Tapada

3,052.50

1.42

4,334.55

07.03

Prueba Compactacin de Suelos (Proctor Modificado Densidad de Campo)

und

15.00

25.00

375.00

m2

185.09

1.49

275.78

100.00%
275.78

m3

190.05

26.29

4,996.41

100.00%
4,996.41

08.02.01

100.00%
3,700.50

3,052.50

08.02

100.00%
326.70

08.01.01

100.00%
645.00

Prueba Zanja Abierta o Zanja Tapada P/Tub.Desague 8"

08.01

100.00%
20,583.00
75.00%
14,226.30

07.01

08

BUZONES DE ALCANTARILLADO DINT=1.20M HASTA 3.00M


Media Caa Buzon Estandar

06.02.01

BUZONES DE CONCRETO

06.01.01

06.02

REPARACION DE TUBERIAS ROTAS

05.01

06

SUMINISTRO E INSTALACION DE TUBERIAS

04.02.01

05

METRADO

100.00%
4,334.55
100.00%
375.00

LETRINAS DE ARRASTRE HIDRAULICO


TRABAJOS PRELIMINARES
Trazo y replanteo en Terreno Normal
MOVIMIENTO DE TIERRAS
Excavacin de zanjas en Pozo de Filtracin

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM

240

DESCRIPCION

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

08.02.02

Cama de Apoyo c/Arena, E=0.10m

110.00

8.11

892.10

08.02.03

Acarreo de Material Excedente

m3

237.56

29.19

6,934.38

08.02.04

Eliminacin de Material Excedente

m3

237.56

21.50

5,107.54

08.03

Concreto Armado f'c= 175 kg/cm2

m3

21.18

449.00

9,509.82

08.03.02

Encofrado y Desencofrado Normal

m2

97.35

46.37

4,514.12

08.03.03

Acero de Refuerzo Fy = 4200 kg/cm2

kg

214.50

4.36

935.22

08.03.04

Muro de Ladrillo KK 18H (9x13x24) Soga en Pozo

m2

330.00

93.67

30,911.10

688.16

19.93

13,715.03

Colocacion de Calamina N30

m2

08.04.02

Correas de Madera 2"X2"

1,296.90

6.67

8,650.32

08.04.03

Correas de Madera 1"X2"

671.55

4.65

3,122.71

08.04.04

Correas de Madera 1"X3"

302.50

5.60

1,694.00

45.45%
2,051.87

100.00%
13,715.03
100.00%
8,650.32
100.00%
3,122.71
100.00%
1,694.00

CERRAJERIA
Bisagra Aluminizada Capuchina de 3" x 3"

pza

110.00

36.53

4,018.30

08.05.02

Cerrojo para Puerta de 1/2" X 0.15 M

und

55.00

29.71

1,634.05

100.00%
4,018.30
100.00%
1,634.05

m2

688.16

15.12

10,404.98

100.00%
10,404.98

55.00

64.71

3,559.05

08.06.01
08.07

100.00%
9,509.82
54.55%
2,462.25
100.00%
935.22

100.00%
30,911.10

08.05.01

08.06

30.00%
1,532.26

CONSTRUCCION DE CASETA

08.04.01

08.05

CONCRETO SIMPLE

08.03.01

08.04

1
100.00%
892.10
100.00%
6,934.38
70.00%
3,575.28

PINTURA
Pintura anticorrosiva y esmalte en Calaminas
APARATOS Y ACCESORIOS SANITARIOS

08.07.01

Inodoro Ecologico

und

08.07.02

Tubera PVC SAL 4"

165.00

23.13

3,816.45

08.07.03

Codo PVC SAL 4"x45

pza

110.00

26.18

2,879.80

08.07.04

Tubera de PVC SAL 2"

115.50

19.74

2,279.97

08.07.05

Codo PVC SAL 2"x90

pza

55.00

17.96

987.80

08.07.06

Sombrero para Ventilacin de PVC 2"

und

55.00

2.12

116.60

100.00%
3,559.05
100.00%
3,816.45
50.00%
1,439.90
100.00%
2,279.97
100.00%
987.80
100.00%
116.60

50.00%
1,439.90

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM
09

240

DIAS CALENDARIOS

DESCRIPCION

UND

METRADO

PU

PARCIAL

Flete Transporte - Peso

kg

207,574.09

0.12

24,908.89

09.02

Flete Transporte - Volumen

vje

9.00

1,100.00

9,900.00

100.00%
24,908.89
77.78%
7,700.00

8.00

250.00

2,000.00

100.00%
2,000.00

40.00

51.88

2,075.20

10.01

FLETE

09.01

10

22.22%
2,200.00

IMPACTO AMBIENTAL
Capacitacin en Medidas de Mitigacin Ambiental
PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES

01

TRABAJOS PRELIMINARES

01.01

Caseta de Almacn y Guardiana c/triplay y parantes de madera tornillo (aprox. 12m2) +m2calamina

01.02

Trazo y replanteo en Terreno Normal con Equipo

m2

846.48

1.11

939.59

01.03

Movilizacin de Maquinarias y Herramientas para la Obra

glb

1.00

9,280.64

9,280.64

02
02.01

100.00%
2,075.20
100.00%
939.59
100.00%
9,280.64

TANQUE IMHOFF
MOVIMIENTO DE TIERRAS

02.01.01

Excavacion en Terreno Rocoso

m3

591.36

122.45

72,412.03

02.01.02

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

94.12

58.26

5,483.43

02.01.03

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

847.44

3.17

2,686.38

02.01.04

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

435.85

34.34

14,967.09

100.00%
72,412.03
100.00%
5,483.43
100.00%
2,686.38
100.00%
14,967.09

m2

4.71

26.68

125.66

100.00%
125.66

02.02
02.02.01
02.03

CONCRETO SIMPLE
Solado E=2" Mezcla 1:10 Cemento Hormign
CONCRETO ARMADO

02.03.01

Concreto Armado f'c= 210 kg/cm2

m3

90.28

471.70

42,585.08

02.03.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

1,914.34

4.36

8,346.52

02.03.03

Encofrado y Desencofrado Muros Reforzados

m2

443.83

32.23

14,304.64

100.00%
42,585.08
20.00%
1,669.30
100.00%
14,304.64

100.00%
11,413.18

02.04

80.00%
6,677.22

ACABADOS FINALES

02.04.01

Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm

m2

375.31

30.41

11,413.18

02.04.02

Water Stop de Meopreno de 6" Provicion y Colocado

172.80

7.30

1,261.44

100.00%
1,261.44

CRONOGRAMA VALORIZADO DE OBRA


PROYECTO
LUGAR
PLAZO

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PACCHAC - TAPO - TARMA - JUNIN

ITEM

240

DESCRIPCION

DIAS CALENDARIOS
UND

02.04.03

Escalera tipo gato tub. 20 mm

und

02.04.04

Baranda de Tubo F.G. Pasamano 1 1/2" - Parante 1" X 1m

02.05

METRADO

PU

PARCIAL

4.00

115.00

460.00

24.00

74.31

1,783.44

Suministro e Instalacin de tubera SCH 40- 8"

48.00

122.31

5,870.88

02.05.02

Suministro e Instalacin Codo PVC 200 mm S-20

und

14.00

54.51

763.14

02.05.03

Suministro e Instalacin Tee PVC 200 mm S-20

und

4.00

66.69

266.76

02.05.04

Suministro e Instalacin Vlvula de Compuerta FF Mazza 200 mm

und

4.00

1,180.72

4,722.88

02.05.05

Batle de Madera Tratada 1.70X1.20X0.50 m

und

4.00

156.82

627.28

03.01

6
100.00%
460.00
100.00%
1,783.44

INSTALACIONES HIDRAULICAS

02.05.01

03

100.00%
5,870.88
100.00%
763.14
100.00%
266.76
100.00%
4,722.88
100.00%
627.28

LECHO DE SECADO
MOVIMIENTO DE TIERRAS
100.00%
52,689.01
100.00%
8,014.83
100.00%
233.57
20.00%
3,014.45

03.01.01

Excavacion en Terreno Rocoso

m3

430.29

122.45

52,689.01

03.01.02

Refine y Nivelacin de Fondo y Paredes de Zanja en Terreno Rocoso

137.57

58.26

8,014.83

03.01.03

Relleno con Material Seleeccionado E=6" inc. Compactacin Manual

m3

73.68

3.17

233.57

03.01.04

Acarreo de Material Excedente

m3

516.35

29.19

15,072.26

03.01.05

Eliminacin de Mat.Excedente con Equipo d<= 5Km

m3

516.35

34.34

17,731.46

80.00%
12,057.81
100.00%
17,731.46

m2

32.40

26.68

864.43

100.00%
864.43

03.02
03.02.01
03.03

CONCRETO SIMPLE
Solado E=2" Mezcla 1:10 Cemento Hormign
CONCRETO ARMADO

03.03.01

Concreto Armado f'c= 210 kg/cm2

m3

48.80

471.70

23,018.96

03.03.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

764.40

4.36

3,332.78

03.03.03

Encofrado y Desencofrado Muros Reforzados

m2

273.84

32.23

8,825.86

100.00%
23,018.96
100.00%
3,332.78
100.00%
8,825.86

m2

330.29

30.41

10,044.12

100.00%
10,044.12

42.00

122.31

5,137.02

100.00%
5,137.02

03.04
03.04.01
03.05
03.05.01

ACABADOS FINALES
Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm
INSTALACIONES HIDRAULICAS
Suministro e Instalacin de tubera Schedule (200mm)

CRONOGRAMA VALORIZADO DE OBRA


PROYECTO
LUGAR
PLAZO

MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PACCHAC - TAPO - TARMA - JUNIN

ITEM

240

DESCRIPCION

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

03.05.02

Suministro y Colocacin de Accesorios en Lecho de Secados

glb

1.00

1,899.06

1,899.06

03.05.03

Suministro e Instalacin Grava 3/4 - 2"

m3

11.09

62.87

697.23

03.05.04

Suministro e Instalacin Grava 1/4 - 7/8"

m3

11.09

62.87

697.23

03.05.05

Suministro e Instalacin Arena Gruesa

m3

9.24

76.37

705.66

03.06

6
100.00%
1,899.06
100.00%
697.23
100.00%
697.23
100.00%
705.66

TECHOS Y COBERTURAS

03.06.01

Tijerales de Madera Tipo I

und

5.00

196.03

980.15

03.06.02

Tijerales de Madera Tipo II

und

5.00

215.13

1,075.65

03.06.03

Cobertura de Techo con calamina galvanizada de 0.80x1.80m

m2

163.00

19.93

3,248.59

100.00%
980.15
100.00%
1,075.65
100.00%
3,248.59

100.00%
62.66

04
04.01

POZO PERCOLADOR
TRABAJOS PRELIMINARES

04.01.01

Limpieza manual de Terreno Normal

m2

21.24

2.95

62.66

04.01.02

Trazo y replanteo en Terreno Normal

m2

21.24

1.49

31.65

04.02

Excavacin de zanjas en Pozo de Filtracin

m3

73.28

26.29

1,926.53

04.02.02

Eliminacin de Material Excedente

m3

351.74

21.50

7,562.41

100.00%
1,926.53
100.00%
7,562.41

CONCRETO SIMPLE

04.03.01

Concreto 1:10 +30% PG para Cimientos

m3

1.15

192.49

221.36

04.03.02

Encofrado y Desencofrado de Cimientos

m2

25.64

40.85

1,047.39

04.04

100.00%
31.65

MOVIMIENTO DE TIERRAS

04.02.01

04.03

100.00%
221.36
100.00%
1,047.39

CONCRETO ARMADO

04.04.01

Concreto Armado f'c= 175 kg/cm2

m3

1.79

449.00

803.71

04.04.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

82.52

4.36

359.79

04.04.03

Encofrado de Losa y Tapa

m2

7.83

102.45

802.18

100.00%
803.71
100.00%
359.79
100.00%
802.18

m2

67.86

113.22

7,683.11

100.00%
7,683.11

04.05
04.05.01
04.06

MURO DE ALBAILERIA
Muro de Ladrillo KK 18H (9x13x24) Cabeza en Pozo
SUMINISTRO DE ACCESORIOS

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

240

ITEM

DESCRIPCION

04.06.01

Suministro y Colocacin de Accesorios en Pozo

04.07

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

glb

4.00

110.88

443.52

Suministro e Instalacin Piedra Chancada de 1/2"

m3

25.95

15.87

411.83

04.07.02

Suministro e Instalacin Grava 2"

m3

3.69

15.87

58.56

05.01

m2

1.44

2.95

4.25

05.01.02

Trazo y replanteo en Terreno Normal

m2

1.44

1.49

2.15

100.00%
411.83
100.00%
58.56

100.00%
4.25
100.00%
2.15

MOVIMIENTO DE TIERRAS

05.02.01

Excavacin de zanjas para Caja de Inspeccin

m3

1.16

26.29

30.50

05.02.02

Eliminacin de Material Excedente

m3

1.16

21.50

24.94

100.00%
30.50
100.00%
24.94

CONCRETO ARMADO

05.03.01

Concreto Armado f'c= 175 kg/cm2

m3

0.78

449.00

350.22

05.03.02

Acero de Refuerzo Fy = 4200 kg/cm2

kg

29.46

4.36

128.45

05.03.03

Encofrado y Desencofrado de Caja de Inspeccin

m2

13.51

102.45

1,384.10

100.00%
350.22
100.00%
128.45
100.00%
1,384.10

m2

6.08

30.41

184.89

100.00%
184.89

8.96

26.29

235.56

05.04
05.04.01
05.05

REVOQUES ENLUCIDOS Y MOLDURAS


Tarrajeo con Impermeabilizante cem: arena 1:2 E= 1.50 cm
EXCAVACION Y TENDIDO DE TUBERIAS

05.05.01

Excavacin de Zanja para Tuberas Aprom=0.60 Hmx<= 1.00m en Terreno Normal Manual
m3

05.05.02

Tuberia PVC SAL 4"

28.00

23.13

647.64

05.05.03

Relleno con Material Propio E=6" inc. Compactacin con Plancha

m3

8.96

15.92

142.64

06
06.01

7
100.00%
443.52

TRABAJOS PRELIMINARES
Limpieza manual de Terreno Normal

05.03

CAJAS DE INSPECCION Y DISTRIBUCION

05.01.01

05.02

VARIOS

04.07.01

05

100.00%
235.56
100.00%
647.64
100.00%
142.64

CERCO PERIMETRICO
TRABAJOS PRELIMINARES

06.01.01

Limpieza manual de Terreno Normal

m2

2,527.89

2.95

7,457.28

06.01.02

Trazo y replanteo en Terreno Normal

m2

2,527.89

1.49

3,766.56

100.00%
7,457.28
100.00%
3,766.56

CRONOGRAMA VALORIZADO DE OBRA


MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, CONSTRUCCION DEL ALCANTARILLADO Y LETRINAS EN LA COMUNIDAD CAMPESINA DE SAN CRISTOBAL DE PACCHAC DISTRITO DE TAPO, PROVINCIA DE TARMA - JUNIN

PROYECTO
LUGAR
PLAZO

PACCHAC - TAPO - TARMA - JUNIN

ITEM
06.02

240

DESCRIPCION

DIAS CALENDARIOS
UND

METRADO

PU

PARCIAL

MOVIMIENTO DE TIERRAS

06.02.01

Excavacin manual en Terreno Normal

m3

2.25

68.77

154.73

06.02.02

Acarreo de Material Excedente

m3

2.81

29.19

82.02

06.02.03

Eliminacin de Material Excedente

m3

2.81

21.50

60.42

100.00%
154.73
100.00%
82.02
100.00%
60.42

m3

2.25

449.00

1,010.25

100.00%
1,010.25

50.00

37.73

1,886.50

100.00%
1,886.50

1,750.50

29.24

51,184.62

1.00

393.90

393.90

06.03
06.03.01
06.04

CONCRETO SIMPLE
Concreto Armado f'c= 175 kg/cm2
VARIOS

06.04.01

Colocacin de Parantes de Eucalipto de 1.85 x 3"

und

06.04.02

Colocacin de Alambre de Pas

06.04.03

Puerta c/marco de madera y malla de acero

und

07

100.00%
51,184.62
100.00%
393.90

FLETE

07.01

Flete Transporte - Peso

kg

107,526.89

0.12

12,903.23

07.03

Transporte con Acemilas Dprom=300m hacia PTAR

kg

107,526.89

0.57

61,290.33

100.00%
12,903.23
100.00%
61,290.33

Вам также может понравиться