Академический Документы
Профессиональный Документы
Культура Документы
CETHAR VESSELS LIMITED Leading manufacture of AFBC , CFBC , WHRB for sponge iron kiln Gas, cement kiln gas ,DG exhaust gas & supply of power plant on EPC basis for more than two decades . Tied up with Riley Power Inc, USA for PC fired boilers of sub critical & super critical pressure. Collaboration with Riley / Siemens Benson Technology for super critical PC boilers.
Executing O & M contracts of captive power plants of any Capacity through Cethar energy ltd.
Major projects under execution: 2x 135 MWe IPP with CFBC Boiler 2 x 350 MWe PF Fired Boiler 2 x 300 MWe PF Fired Boiler 2 x 150 MWe IPP with CFBC Boiler - M/s.Aryan Coal Beneficiation - M/s.Ind Barath energy Ltd. - M/s.Meenakshi energy Ltd. - M/s.Shree cement
Credentials
CVL had designed, manufactured, erected and commissioned more than 1000 FBC boilers. Based on our versatile experience during operation and maintenance, we have listed few problems faced and the causes, solution given for the information to this elite league
Case study I :
Reported issue:
Tube failure of grid panel in CFBC boiler
BACKGROUND :
Plant capacity
Boiler capacity
:
:
2 X 25MW CPP
114 TPH
Type of firing
Steam pressure
:
:
CFBC
88 Kg/cm
Steam temperature :
Grid tube size location
: :
520 5 C
51.0 X 4.0 mm 1,2,17,18,19,20,21,24,25,26th row from combustor left side
BACKGROUND :
Boiler commissioned on
Tube failed on
: 20.08.2009
: (a) Tube No : 1, 2 (b) Tube No : 19, 20, 21 (c) Tube No: 24, 25, 26 (d) Tube No: 16, 17 : 4 Months
Observations
(A)Sample No. 17& 24 :
Observations
Sample No. 20, 16, 1 & 2 :
Observations
Sample No. 19, 21 : Erosion is found at 25 mm from one end.
10
Observations
Sample No 26: This tube length 320 mm have no crack indication.
11
Failure Analysis
Dimensional Measurements :
Diameter and thickness of grid panel tube sample measured at various location and given below
12
Failure Analysis
Chemical Analysis :
Spectroscopically chemical analysis of failed tube sample carried out. Values are given below
13
Failure Analysis
14
Failure Analysis
Hardness measurement :
Hardness measurement using Rockwell B scale was done on failed tubes. The values given below
15
Failure Analysis
16
Overheating of tube around Ac1 for prolonged period. Fluctuating load. Thermal Cyclic variation.
17
18
Solution
19
Conclusion
There is no grid panel tube failure till date after refractory laying.
20
Case study 2:
Reported issue:
Excess coal consumption
21
Boiler capacity
Type of firing
: 40 TPH
: AFBC
Steam pressure
: 68 ata
22
23
Plant visit was made, boiler operating data, fuel input were collected and analyzed
24
Boiler data:
Boiler operating capacity Steam pressure Steam temperature Feed water temperature : 37.5 TPH : 68.007 ata : 495 C : 122C
25
Lower GCV of fuel comparing to design Loss in efficiency due to the above was 3.501%
26
Conclusion:
Corrected efficiency is 85.2% Fuel moisture to be controlled for achieving the guaranteed thermal Efficiency of the boiler
27
THANKS CVL
28