Академический Документы
Профессиональный Документы
Культура Документы
*Project Selection (based upon commercial or non-commercial considerations) *Project Charter (authorization) *Project Scope Statement
Project Implementation
Hire people, build teams and establish offices and systems Procure Materials, Equipment etc. Teams work with material and equipment Verify performance
Modify, as required.
The acceptable levels of variance should be determined at the outset of the project EVA
Difference between;
Monitoring
Control
Evaluation
Close/Termination
Exit Strategy (Donors are Extremely Interested)
Warranty/Guarantee
Area B 02.00
Group Level
Electromechanical A 01.02 Electrical and control 01.02.01 Piping 01.02.02 Equipment 01.02.03 Preparation Tests 01.02.04
Electromechanical B 02.02
WorkPackage Level
Electrical and Control 02.02.01 Piping 02.02.02 Equipment 02.02.03 Preparation Tests 02.02.04
BUILDING A HOUSE
CONSTRUCTION OF HOUSE
OUT BUILDINGS
CIVIL
CARTENTER/ PLUMBER
FENCE
GROUND
FOUNDATIONS
WALLS
ROOF
DOORS/ WINDOW
BIC PLUMBING
WIRING PAINTING
FINISHING
100% Rule. If not included in WBS, it is not in scope. Planned outcomes and deliverables, not planned activities
Schedule Flights
Contact Outfitter
Obtain emerg. #s
Bring Cards
Rent Van
Rent canoes
Get deposits
Arrange contact
Arrange Motel
Rent Tents
Prepare 7 breakfasts
Retain Receipts
Bring scotch
Prepare 7 lunches
Prepare 6 dinners
Close-out trip
Schedule Flights
Contact Outfitter
Obtain emerg. #s
Bring Cards
Rent Van
Rent canoes
Get deposits
Arrange contact
Arrange Motel
Rent Tents
Prepare 7 breakfasts
Retain Receipts
Bring scotch
Prepare 7 lunches
Prepare 6 dinners
Close-out trip
Schedule Flights
Contact BW Outfitter
Obtain emerg. #s
Bring Cards
Rent Van
Rent canoes
Get deposits
Arrange contact at BW
Arrange Motel
Rent Tents
Prepare 7 breakfasts
Retain Receipts
Bring scotch
Prepare 7 lunches
Prepare 6 dinners
Close-out trip
Schedule Flights
Contact BW Outfitter
Obtain emerg. #s
Bring Cards
Rent Van
Rent canoes
Get deposits
Arrange contact at BW
Arrange Motel
Rent Tents
Prepare 7 breakfasts
Retain Receipts
Bring scotch
Prepare 7 lunches
Prepare 6 dinners
Close-out trip
Needs Assessment
Research Vendors
Schedule Installation
Needs Analysis
Research Sites
Schedule Training
Prepare Site
Write RFP
Train
Review Proposals
Configure System
Rank Proposals
Install System
Recommendation
Assess Needs
Research Vendors
Schedule Installation
Analyze Needs
Research Sites
Schedule Training
Prepare Site
Write RFP
Train Sysadmins
Review Proposals
Configure System
Rank Proposals
Install System
Make Recommendations
Scope of work includes; construction of main house, its outbuildings, and landscaping/garden. The construction of main house can be sub divided into civil works, carpentry/plumbing work, and electrical/paint work. The outbuildings consist of a garage, drive way, and a greenhouse. Landscaping/garden includes garden, and fencing of grounds. The civil works can be further subdivided into foundations, walls, and roofing. The carpentry/plumbing work includes doors/windows, cabinets, and plumbing work. The electrical/paint work includes wiring, painting, and internal finishing work.
Estimating
Resources Time
Costs
Dummy activities
Activity on Node
Activities drawn on Nodes Arrows are used to represent Flow
An activity cannot begin until all preceding connected activities have been completed
Each activity should have a unique identification number An activity identification number must be larger than that of any activities that precede it Looping is not allowed Conditional statements are not allowed
Work Breakdown Structure, Most Likely Durations & Precedence Relationships for a Project
Activity A. Select computer software B. Install software C. Install office network D. Test software E. Develop database F. Train employees G. Implement system
Immediate Predecessor(s)
A A B B C,D E,F
Draw Network Diagram Budget approval from the CEO is required before purchasing a new machine for a factory. The use of new machine necessitates employing a new operator from outside the organization. The operator must be specially trained, using a training manual and some special equipment, which is delivered with the machine. The training itself does not depend upon the new machine being installed and working. Once the machine is installed and the operator is trained, production can be started.
What is the expected project completion date? What are the scheduled start/end dates for each activity?
Which activities are critical? How long can a non-critical activity be delayed?
If these activities are delayed, the whole project is delayed To reduce the overall duration of the project look at the critical activities
a+ 4m +b t e= 6
Activity
A B C
s =
a 6
a
2 8 2
m
8 10 3
b
10 12 15
s2
1.78 .44 4.69
7.33 10 4.83
Solved Example
Act. Description A B C D E F G H I J R &D P lan Mkt Res Routing P rototype Mkt Broch. C ost E st. P rod. Test Mkt S urvey P ricing/F cast F inal Report Pre. A A A C D B, E H F, G, I Opt. (a) 4.0 1.0 2.0 3.0 2.0 1.5 1.5 2.5 1.5 1.0 ML (m) Pes. (b) 5.0 1.5 3.0 4.0 3.0 2.0 3.0 .5 2.0 2.0 12.0 5.0 4.0 11.0 4.0 2.5 4.5 5 2.5 3.0 Exp. (t) 6 2 3 5 3 2 3 4 2 2 Var 1.78 0.44 0.11 1.78 0.11 0.03 0.25 0.69 0.03 0.11
Let T be total time of project. Expected value of T is calculated as: The variance in project completion time is:
E(T) = t A + t E + t H + t I + t J = 17
= + + + +
2 2 A 2 E 2 H 2 I 2 2 2 J
20 17 z= = 3/1 . 65 = 1 .82
By looking this z factor of 1.82 in the z table, we get the value of 0.9656, which means the chances of completing this project in 20 weeks are 96.56%.