Академический Документы
Профессиональный Документы
Культура Документы
Chapter 7
Project execution, monitoring and control: Understanding earned value management
Learning outcomes
At the end of this session, you should be able to:
Reflect on the importance of project performance management, control and monitoring. Understand the basics of project costing. Define earned value management as a method to measure project progress. Describe the various terms used in earned value management. Illustrate how earned value management works. Describe how to monitor time performance. Describe the relationship between monitoring and controlling project performance and project risk. Describe configuration management and change control. Explain ethical considerations in project monitoring, control and evaluation.
2012/05/02
Project execution
The project execution phase follows the planning phase in the project management life cycle. It is the longest, most resource intensive phase of the project. It is during this phase that the work that has been planned is actually carried out. Here the project manager is responsible for initiating, managing and controlling all tasks, and directing the efforts of the project team. Includes stakeholder management, risk management as well as configuration management and change control.
2012/05/02
Cost estimation
Cost estimation
Roll up technique.
Iterative approach involves using the top down approach to derive a rough estimate and the bottom up approach to refine the estimate. Bottom up and top down estimates form budgets. Important to include contingencies in budgets.
2012/05/02
Cost estimation
2012/05/02
EVM
First implemented by the USA Department of Defence in the 1960s as part of its cost/schedule control systems criteria (C/SCSC). Introduced into industry in 1990s. EVM is a technique used to compare actual costs with planned costs as well as cost of work performed to date with planned costs. Generally suited to larger projects.
2012/05/02
Variances in cost and schedule performance Cost and scheduling performance indices to determine cost and scheduling efficiency Forecasted final cost at completion Future time performance.
2012/05/02
EVM Step 1
Project Objective: To develop a low cost surveillance drone within 9 weeks at a cost not exceeding R750 000. Milestones. Technical Requirements.
2012/05/02
EVM Step 4
EVM Step 5
2012/05/02
EVM Step 6
EVM Step 7
2012/05/02
EVM Step 7
EVM Step 8
10
2012/05/02
EVM Step 8
EVM Step 8
11
2012/05/02
EVM Step 8
12
2012/05/02
Earned schedule
Earned schedule
SVt = ES-AT = 2 4 = -2 (2 weeks behind schedule). SPIt= ES/AT = 2/4 = 0.5 (< 1 therefore behind schedule). ETCt= (PD-ES)/SPIt= (9-2)/0.5 = 14 weeks to completion at this point. EACt = AT + ETCt= 4 + 14 = 18 weeks . TSPI = (PD ES)/(PD AT) = (9 2)/(9 4) = 1.4 is indicative of the fact that the current schedule isnt feasible. The work rate has to be higher than it currently is.
13
2012/05/02
During the execution phase, potential sources of risk in South Africa might include:
Economic issues Labour unrest Technological failure Conflict, infighting and politicking Perceptions of political uncertainty by the international community Infrastructural issues.
14
2012/05/02
Functional Baseline: all initial information Allocated Baseline: performance specifications Product Baseline: relates to actual deliverable
CM consists of 4 stages: Configuration identification: risk identification, degree of interrelatedness etc Change control: project specific documentation of project changes to the baseline Status accounting: updating of change requests etc Verification: assurances that processes have been undertaken
Ethical issues might include: Altering of status reports Compromising quality Exploitative labour practises Many organisations provide ethical codes
and professional project managers would subscribe to PMIs ethical code too.
15
2012/05/02
16