Вы находитесь на странице: 1из 49

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

DESIGN OF INNER LONG. GIRDER (LG2)

Section Properties

Left Anchor. 0.000 L Sec 0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec

Section under consideration


Dist. of Section 'X' from Left Side Jacking End (Anchorage)

0.000 m

0.20

1.85

3.35

3.64

6.14

9.11

12.08

Dist. of Section 'X' from cL of Left Support

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

Col.- 1

Col.- 2

Col.- 3

Col.- 4

Col.- 5

Col.- 6

Col.- 7

Col.- 8

Item. No.

Description

Units

Properties of non-composite section: Precast Girder Only

1.
1a

Area of Precast Girder

m2

1.171

1.171

1.171

0.723

0.723

0.723

0.723

0.723

1b

c.g. of girder from Top of girder

Yt

0.769

0.769

0.769

0.781

0.781

0.781

0.781

0.781
0.819

1c

c.g. of girder from soffit of girder Yb

0.831

0.831

0.831

0.819

0.819

0.819

0.819

1d

Overall Depth of Girder

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1e

Moment of Inertia of Section

Iz

m4

0.2640

0.2640

0.2640

0.2218

0.2218

0.2218

0.2218

0.2218

1f

Section Modulus of Top

Zt

m3

0.3435

0.3435

0.3435

0.2838

0.2838

0.2838

0.2838

0.2838

1g

Section Modulus of Bottom

Zb

m3

0.3177

0.3177

0.3177

0.2709

0.2709

0.2709

0.2709

0.2709

m3

0.0903

0.0903

0.0903

0.0542

0.0542

0.0542

0.0542

0.0542

kN/m

29.28

29.28

29.28

18.08

18.08

18.08

18.08

18.08

mm

457

457

457

255

255

255

255

255

0.711

0.711

0.711

0.795

0.795

0.795

0.795

0.795

1h

First moment of area above and about


N.A of Composite Section

1i

Weight of Girder per metre

1j.

Notional size (mm) of the Cross Section

wg

1k.

Coeff. depending on notional size for Shrinkage kh

h0

2.

Properties of Composite Section: Precast Girder + Deck Slab

2a

Area of Composite Section

2b

c.g. of Section from Top of Deck Slab Yt

m2

1.831

1.831

1.831

1.383

1.383

1.383

1.383

1.383

0.672

0.672

0.672

0.576

0.576

0.576

0.576

0.576
1.244

2c

c.g. of Section from soffit

Yb

1.148

1.148

1.148

1.244

1.244

1.244

1.244

2d

Overall Depth of the Section

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

2e

Moment of Inertia of Section

Iz

m4

0.5927

0.5927

0.5927

0.4985

0.4985

0.4985

0.4985

0.4985

2f

Section Modulus at Top of Slab

Zts

m3

0.8819

0.8819

0.8819

0.8655

0.8655

0.8655

0.8655

0.8655

2g

Sec. Modulus at Bottom of Slab

Zbs

m3

1.3111

1.3111

1.3111

1.4004

1.4004

1.4004

1.4004

1.4004

2h

Sec.Modulus of Bottom of Section

Zb

m3

0.5163

0.5163

0.5163

0.4007

0.4007

0.4007

0.4007

0.4007

2i

First moment of area of Composite Sec.

m3

0.4612

0.4612

0.4612

0.3618

0.3618

0.3618

0.3618

0.3618

above & about N.A of Composite Section

h0

2j.

Notional size (mm) of the Cross Section

1k.

Coeff. depending on notional size for Shrinkage kh

mm

582

582

582

405

405

405

405

405

0.700

0.700

0.700

0.724

0.724

0.724

0.724

0.724

Bending Moments & Shear Forces at Various Sections of Long.-Girder due to Self Weight
Due to Dead Load in between End Blocks
Due to Dead Load at End Blocks
Extra Loading due to End Block
11.202 kN/m
2.000 m

0.723
1.171

x
x

25
25

=
=
=

18.078 kN/m
29.280 kN/m
11.202 kN/m

1.500 m

1.500 m

2.000 m

18.078 kN/m

0.350

23.750 m

0.350

Ra

Rb
Span Length

Due to symmetry of Loading Reaction on either Support


Ra
=
Rb
=
18.078
x 24.450
2

+ 11.202

23.750 m

x 2.00

11.202

x 1.500

Bending Moments at Various Sections of Precast Girder due to Self Weight


a)

At

=
b)

At
-

=
c)

At
-

0.000 L Section

0.000 m from cL of Support

251.811
x
11.202
x
-1.793 kN-m

0.000
0.350

0.069 L-Section
251.811
x
11.202
x
356.927 kN-m
0.133 L-Section
251.811
x
11.202
x
11.202
x
618.063 kN-m

18.078
0.175

0.350

1.650 m from cL of Left Support


1.650
( 18.078
2.000
x
(
2.000

x
-

2.000
1.000

3.150 m from cL of Left Support


3.150
( 18.078
2.000
x
(
3.500
0.750
x
(
3.500

x
-

3.500
1.000
2.000

(1)

0.175

1.000

1.750

0.500

251.811 kN

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


d)

At
-

=
e)

At
-

=
f)

At
-

=
g)

At
-

=
h)

At
-

=
i)

At
-

=
j)

At
-

=
k)

At
-

=
l)

At
-

=
m)

At
-

0.145 L-Section
251.811
x
11.202
x
11.202
x
663.617 kN-m

3.444 m from cL of Left Support


3.444
( 18.078
2.000
x
(
3.794
0.750
x
(
3.794

x
-

3.794
1.000
2.000

0.250 L-Section
251.811
x
11.202
x
11.202
x
987.505 kN-m

5.938 m from cL of Left Support


5.938
( 18.078
2.000
x
(
6.288
0.750
x
(
6.288

x
-

6.288
1.000
2.000

0.375 L-Section
251.811
x
11.202
x
11.202
x
1226.502 kN-m

8.906 m from cL of Left Support


8.906
( 18.078
2.000
x
(
9.256
0.750
x
(
9.256

x
-

9.256
1.000
2.000

0.500 L-Section
251.811
x
11.202
x
11.202
x
1306.168 kN-m

11.875 m from cL of Right Support


11.875
( 18.078
2.000
x
( 12.225
0.750
x
( 12.225

x
-

12.225
1.000
2.000

0.625 L-Section
251.811
x
11.202
x
11.202
x
1226.502 kN-m

8.906 m from cL of Right Support


8.906
( 18.078
2.000
x
(
9.256
0.750
x
(
9.256

x
-

9.256
1.000
2.000

0.750 L-Section
251.811
x
11.202
x
11.202
x
987.505 kN-m

5.938 m from cL of Right Support


5.938
( 18.078
2.000
x
(
6.288
0.750
x
(
6.288

x
-

6.288
1.000
2.000

0.855 L-Section
251.811
x
11.202
x
11.202
x
663.617 kN-m

3.444 m from cL of Right Support


3.444
( 18.078
2.000
x
(
3.794
x
0.750
(
3.794

x
-

3.794
1.000
2.000

0.867 L-Section
251.811
x
11.202
x
11.202
x
618.063 kN-m

3.150 m from cL of Right Support


3.150
( 18.078
2.000
x
(
3.500
0.750
x
(
3.500

x
-

3.500
1.000
2.000

0.931 L-Section
251.811
x
11.202
x
356.927 kN-m

1.650 m from cL of Right Support


1.650
( 18.078
2.000
x
(
2.000

x
-

2.000
1.000

1.000 L-Section
251.811
x
11.202
x
-1.793 kN-m

0.000 m from cL of Right Support


0.000
( 18.078
0.350
x
0.175

1.897

0.500

3.144

0.500

4.628

0.500

6.113

0.500

4.628

0.500

3.144

0.500

1.897

0.500

1.750

0.500

1.000

0.350

0.175

0.350

11.202

0.350

2.000

11.202

2.000

3.500

11.202

2.000

3.794

11.202

2.000

6.288

11.202

2.000

Shear Force at Various Sections of Precast Girder due to Self Weight


a)

At

0.000 L-Section
=

0.00 m from cL of Support


251.811
18.078

=
b)

At

241.563 kN

0.069 L-Section
=

1.650 m from Support


251.811
18.078

=
e)

At

193.250 kN

0.133 L-Section
=
=

d)

At

0.145 L-Section
=
=

c)

At

0.250 L-Section
=

3.150 m from Support


251.811
18.078
11.202
x
0.750
157.732 kN
3.444 m from Left Support
251.811
18.078
11.202
x
0.750
152.421 kN
5.94 m from Left Support
251.811
18.078

(2)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

=
b)

At

0.375 L-Section
=
=

a)

At

0.500 L-Section
=
=

h)

At

0.625 L-Section
=
=

h)

At

0.750 L-Section
=
=

h)

At

0.855 L-Section
=
=

h)

At

b)

At

0.931 L-Section
=
=

a)

At

1.000 L-Section
=
=

DESIGN OF INNER LONG. GIRDER (LG2)


0.750

8.906 m from Left Support


251.811
18.078
11.202
x
0.750
53.669 kN
11.875 m from cL of Right Support
251.811
18.078
11.202
x
0.750
0.000 kN
8.906 m from cL of Right Support
251.811
18.078
11.202
x
0.750
53.669 kN
5.938 m from cL of Right Support
251.811
18.078
11.202
x
0.750
107.339 kN
3.444 m from cL of Right Support
251.811
18.078
11.202
x
0.750

9.256

11.202

2.000

12.225

11.202

2.000

9.256

11.202

2.000

6.288

11.202

2.000

3.794

11.202

2.000

3.500

11.202

2.000

2.000

11.202

2.000

0.350

11.202

0.350

152.421 kN

0.867 L-Section
=

11.202
107.339 kN

S. Rastogi

3.150 m from cL of Right Support


251.811
18.078
11.202
x
0.750
157.732 kN
1.650 m from cL of Right Support
251.811
18.078
193.250 kN
0.000 m from cL of Right Support
251.811
18.078
241.563 kN

B.M. & S.F. at Various Sections of Long.-Girder due to Weight of Diaphragm cast with Girder
Span Length
Conc. Load on the Span
Dist. of W 1 from Supp. RL
Conc. Load on the Span
Dist. of W 2 from Supp. RL
Conc. Load on the Span
Dist. of W 3 from Supp. RL

L
W1
a1
W2
a2
W3
a3

=
=
=
=
=
=
=

23.750
3.538
0.000
4.664
11.875
3.538
23.750

m
kN
m
kN
m
kN
m

W2

W1

3.54 kN
11.875 m

L
(W1 x a1)
L

0.000

L
(W2 x a2)
L

2.332

L
(W3 x a3)

3.54 kN
11.875 m

23.75 m

RL

Reaction at Ends
All reactions are in kN
Due to Conc. Load W 1
Due to Conc. Load W 2
Due to Conc. Load W 3
Reaction
kN
Formula used
Value
Formula used
Value
Formula used
Value
RL
3.538
W2 x ( L - a2)
2.332
W3 x ( L - a3)
0.000
W1 x ( L - a1)
RR

W3

4.66 kN

3.538

Resultant
Reaction
5.870
5.870

Span Moment at any Section distant X from Left end


At 0.000 L-Sec.

Span Moment ( at X

0.000 m) from Left Supp. =

0.000 kN-m

Mx =

RL * X

At 0.069 L-Sec.

Span Moment ( at X

1.650 m) from Left Supp. =

3.848 kN-m

Mx =

RL * X

At 0.133 L-Sec.

Span Moment ( at X

3.150 m) from Left Supp. =

7.346 kN-m

Mx =

RL * X

At 0.145 L-Sec.

Span Moment ( at X

3.444 m) from Left Supp. =

8.031 kN-m

Mx =

RL * X

At 0.250 L-Sec.

Span Moment ( at X

5.938 m) from Left Supp. =

13.846 kN-m

Mx =

RL * X

At 0.375 L-Sec.

Span Moment ( at X

8.906 m) from Left Supp. =

20.770 kN-m

Mx =

RL * X

At 0.500 L-Sec.

Span Moment ( at X

11.875 m) from Right Supp. =

27.693 kN-m

Mx =

RL * X

At 0.625 L-Sec.

Span Moment ( at X

8.906 m) from Right Supp. =

20.770 kN-m

Mx =

RR * (L - X)

At 0.750 L-Sec.

Span Moment ( at X

5.938 m) from Right Supp. =

13.846 kN-m

Mx =

RR * (L - X)

At 0.855 L-Sec.

Span Moment ( at X

3.444 m) from Right Supp. =

8.031 kN-m

Mx =

RR * (L - X)

At 0.867 L-Sec.

Span Moment ( at X

3.150 m) from Right Supp. =

7.346 kN-m

Mx =

RR * (L - X)

At 0.931 L-Sec.

Span Moment ( at X

1.650 m) from Right Supp. =

3.848 kN-m

Mx =

RR * (L - X)

At 1.000 L-Sec.

Span Moment ( at X

0.000 m) from Right Supp. =

0.000 kN-m

Mx =

RR * (L - X)

(3)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

Shear Force at any Section distant X from Left end


At 0.000 L-Sec.

Shear Force ( at X

0.000 m) from Left Supp. =

2.332 kN

Sx =

RL

At 0.069 L-Sec.

Shear Force ( at X

1.650 m) from Left Supp. =

2.332 kN

Sx =

RL

At 0.133 L-Sec.

Shear Force ( at X

3.150 m) from Left Supp. =

2.332 kN

Sx =

RL

At 0.145 L-Sec.

Shear Force ( at X

3.444 m) from Left Supp. =

2.332 kN

Sx =

RL

At 0.250 L-Sec.

Shear Force ( at X

At
At
At
At
At
At
At
At

Shear Force
Shear Force
Shear Force
Shear Force
Shear Force
Shear Force
Shear Force
Shear Force

=
=
=
=
=
=
=
=

0.375
0.500
0.625
0.750
0.855
0.867
0.931
1.000

L-Sec.
L-Sec.
L-Sec.
L-Sec.
L-Sec.
L-Sec.
L-Sec.
L-Sec.

( at
( at
( at
( at
( at
( at
( at
( at

X
X
X
X
X
X
X
X

5.938 m) from Left Supp. =


8.906 m)
11.875 m)
8.906 m)
5.938 m)
3.444 m)
3.150 m)
1.650 m)
0.000 m)

from Left Supp. =


from Right Supp. =
from Right Supp. =
from Right Supp. =
from Right Supp. =
from Right Supp. =
from Right Supp. =
from Right Supp. =

2.332 kN

Sx =

RL

2.332
2.332
2.332
2.332
2.332
2.332
2.332
2.332

Sx
Sx
Sx
Sx
Sx
Sx
Sx
Sx

RL
RL
RR
RR
RR
RR
RR
RR

kN
kN
kN
kN
kN
kN
kN
kN

=
=
=
=
=
=
=
=

Additional Moment in Precast Girder due to Lifting and Transportation


Cable Inclination to Horizontal
Assuming tension in the Cable is "T"
Vertical Componant of T
Hence Tension in Cable
Compression exerted by cable into gir.

=
Tsin =

90.00 degree
257.681 kN (Refer Reac. due to self weight of Girder & Diaphragm)

T=

257.681 kN

Tcos =

0.000 kN
cg. of Sec.

Summary of B.M. & S.F. for Precast Girder due to Self Wt. & Lifting of Girder

23.750 m

Dist. of Sec. Due to Self Wt. of Precast Girder & Diaphragm


Section

0.000 L Section

Additional B.M. due to Lifting of Girder

from Left Face

B.M.

S.F.

Stress at

Stress at

Force

cg. of Girder

Sagg. Mom.

of I-Girder

kN-m

kN

Top of Gir

Bottom of Gir.

kN

from Top

due to Lifting

Stress at

Stress at

(MPa)

(MPa)

(kN-m)

(MPa)

(MPa)

0.200 m

-1.793

243.895

-0.005

0.006

0.000

0.769 m

0.000

0.000

0.000

Top of Gir Bottom of Gir.

0.069 L Section

1.850 m

360.775

195.582

1.050

-1.136

0.000

0.769 m

0.000

0.000

0.000

0.133 L Section

3.350 m

625.409

160.064

2.203

-2.309

0.000

0.781 m

0.000

0.000

0.000

0.145 L Section

3.644 m

671.648

154.753

2.366

-2.480

0.000

0.781 m

0.000

0.000

0.000

0.250 L Section

6.138 m

1001.352

109.671

3.528

-3.697

0.000

0.781 m

0.000

0.000

0.000

0.375 L Section

9.106 m

1247.272

56.001

4.394

-4.605

0.000

0.781 m

0.000

0.000

0.000

0.500 L Section

12.075 m

1333.861

2.332

4.699

-4.925

0.000

0.781 m

0.000

0.000

0.000

0.625 L Section

15.044 m

1247.272

56.001

4.394

-4.605

0.000

0.781 m

0.000

0.000

0.000

0.750 L Section

18.013 m

1001.352

109.671

3.528

-3.697

0.000

0.781 m

0.000

0.000

0.000

0.855 L Section

20.506 m

671.648

154.753

2.366

-2.480

0.000

0.781 m

0.000

0.000

0.000

0.867 L Section

20.800 m

625.409

160.064

2.203

-2.309

0.000

0.781 m

0.000

0.000

0.000

0.931 L Section

22.300 m

360.775

195.582

1.050

-1.136

0.000

0.769 m

0.000

0.000

0.000

1.000 L Section

23.950 m

-1.793

243.895

-0.005

0.006

0.000

0.769 m

0.000

0.000

0.000

BM / SF at Various Sections of Precast Long.-Girder due to Weight of Shuttering (on Cantilever Side
Weight of Precast Panel Shuttering =

0.450 kN/m

0.450 kN/m
c/L of Symmetry

0.350

11.8750 m
Ra

Span Length

Due to symmetry of Loading Reaction on either Support


Ra
=
Rb
=
0.45
x
2

24.450

23.750 m

5.501 kN

BM at Various Sections of Precast Girder due to Weight of Permanent Shuttering


a)

b)

c)

d)

e)

At

At

At

At

At

0.000 L-Section

0.069 L-Section

0.133 L-Section

0.145 L-Section

0.250 L-Section

0.00 m from Left Support


=
5.501 x
0.000

0.450 x

0.350 x

0.350
2.000

-0.03 kN-m

1.65 m from Left Support


=
5.501 x
1.650

0.450 x

2.000 x

2.000
2.000

8.18 kN-m

3.15 m from Supp.


=
5.501 x

3.150

0.450 x

3.500 x

3.500
2.000

14.57 kN-m

3.44 m from Left Support


=
5.501 x
3.444

0.450 x

3.794 x

3.794
2.000

15.71 kN-m

5.938 m from Left Support


=
5.501 x
5.938

0.450 x

6.288 x

6.288

23.77 kN-m

(4)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


2.000
f)

g)

h)

i)

j)

k)

l)

m)

At

At

At

At

At

At

At

At

0.375 L-Section

0.500 L-Section

0.625 L-Section

0.750 L-Section

0.855 L-Section

0.867 L-Section

0.931 L-Section

1.000 L-Section

8.906 m from Left Support


=
5.501 x
8.906

0.450 x

9.256 x

9.256
2.000

29.72 kN-m

11.875 m from Right Supp.


=
5.501 x
11.875

0.450 x

12.225 x

12.225
2.000

31.70 kN-m

8.906 m from Right Supp.


=
5.501 x
8.906

0.450 x

9.256 x

9.256
2.000

29.72 kN-m

5.938 m from Right Supp.


=
5.501 x
5.938

0.450 x

6.288 x

6.288
2.000

23.77 kN-m

3.444 m from Right Supp.


=
5.501 x
3.444

0.450 x

3.794 x

3.794
2.000

15.71 kN-m

3.150 m from Right Supp.


=
5.501 x
3.150

0.450 x

3.500 x

3.500
2.000

14.57 kN-m

1.650 m from Right Supp.


=
5.501 x
1.650

0.450 x

2.000 x

2.000
2.000

8.18 kN-m

0.000 m from Right Supp.


=
5.501 x
0.000

0.450 x

0.350 x

0.350
2.000

-0.03 kN-m

Shear Force at Various Sections of Precast Girder due to Weight of Shuttering


a)

At 0.00 L Sec

0.00 m from Left Support =

5.501

0.45

0.350

5.34 kN

b)

At 0.07 L Sec

1.65 m from Left Support =

5.501

0.450

2.000

4.60 kN

c)

At 0.13 L Sec

3.15 m from Left Support =

5.501

0.45

3.500

3.93 kN

d)

At 0.15 L Sec

3.44 m from Left Support =

5.501

0.45

3.794

3.79 kN

e)

At 0.25 L Sec

5.94 m from Left Support =

5.501

0.45

6.288

2.67 kN

f)

At 0.38 L Sec

8.91 m from Left Support =

5.501

0.45

9.256

1.34 kN

g)

At 0.50 L Sec

11.88 m from Right Supp. =

5.501

0.45

12.225

0.00 kN

h)

At 0.63 L Sec

8.91 m from Right Supp. =

5.501

0.450

9.256

1.34 kN

i)

At 0.75 L Sec

5.94 m from Right Supp. =

5.501

0.450

6.288

2.67 kN

j)

At 0.86 L Sec

3.44 m from Right Supp. =

5.501

0.450

3.794

3.79 kN

k)

At 0.87 L Sec

3.15 m from Right Supp. =

5.501

0.450

3.500

3.93 kN

l)

At 0.93 L Sec

1.65 m from Right Supp. =

5.501

0.450

2.000

4.60 kN

m)

At 1.00 L Sec

0.00 m from Right Supp. =

5.501

0.450

0.350

5.34 kN

Summary of B.M. & S.F. for Long.-Girder


Section

Distance of Due to weight of Shuttering ( Non Composite)

Due to Removal of Shuttering ( Composite)

w.r.t. to left

Section from

Bending

Shear

Stress at

Stress at

Bending

Shear

Stress at

Stress at

Stress at

temporary

Left Face of

Moment

Force

Top of Gir

Bottom of Gir.

Moment

Force

Top of Slab

Top of Gir

Bottom of Gir.

Support

I-Girder

kN-m

kN

(MPa)

(MPa)

kN-m

kN

(MPa)

(MPa)

(MPa)

0.000 L Sec

0.200 m

-0.028

5.344

0.000

0.000

0.028

-5.344

0.000

0.000

0.000

0.069 L Sec

1.850 m

8.177

4.601

0.024

-0.026

-8.177

-4.601

-0.009

-0.006

0.016

0.133 L Sec

3.350 m

14.573

3.926

0.051

-0.054

-14.573

-3.926

-0.017

-0.010

0.036

0.145 L Sec

3.644 m

15.707

3.794

0.055

-0.058

-15.707

-3.794

-0.018

-0.011

0.039

0.250 L Sec

6.138 m

23.769

2.672

0.084

-0.088

-23.769

-2.672

-0.027

-0.017

0.059

0.375 L Sec

9.106 m

29.718

1.336

0.105

-0.110

-29.718

-1.336

-0.034

-0.021

0.074

0.500 L Sec

12.075 m

31.701

0.000

0.112

-0.117

-31.701

0.000

-0.037

-0.023

0.079

0.625 L Sec

15.044 m

29.718

1.336

0.105

-0.110

-29.718

-1.336

-0.034

-0.021

0.074

0.750 L Sec

18.013 m

23.769

2.672

0.084

-0.088

-23.769

-2.672

-0.027

-0.017

0.059

0.855 L Sec

20.506 m

15.707

3.794

0.055

-0.058

-15.707

-3.794

-0.018

-0.011

0.039

0.867 L Sec

20.800 m

14.573

3.926

0.051

-0.054

-14.573

-3.926

-0.017

-0.010

0.036

0.931 L Sec

22.300 m

8.177

4.601

0.024

-0.026

-8.177

-4.601

-0.009

-0.006

0.016

1.000 L Sec

23.950 m

-0.028

5.344

0.000

0.000

0.028

-5.344

0.000

0.000

0.000

(5)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

BM / SF at Various Sections of Precast Long.-Girder due to Green Weight of Slab Conc.


Green Weight of Slab Concrete ( @
Temporary Live Load on the Deck (@

26 kN/m^3)
3.0 kN/m^2)
TOTAL

=
=
=

(Including Temporary Live Load)

17.160 kN/m
9.000 kN/m
26.160 kN/m

W1 : From End Diaphragm


26.160 kN/m

W2 : From Intermediate Diaphragm

W1

W2

0.350

11.875 m
Ra

Span Length

W1 =
Conc. Load on the Span
13.500 kN
a1 =
0.000 m
Dist. of W 1 from Supp. RL
W
2
=
Conc. Load on the Span
0.000 kN
a2 =
23.750 m
Dist. of W 2 from Supp. RL
Due to symmetry of Loading Reaction on either Support
Ra
=
Rb
=
26.16
x
2

23.750 m
c/L of Symmetry

24.45

13.500

0.000

333.306 kN

BM at Various Sections of Precast Girder due to Green Weight of Slab Concrete


a)

b)

c)

d)

e)

f)

g)

h)

i)

j)

k)

l)

m)

At

At

At

At

At

At

At

At

At

At

At

At

At

0.000 L-Section
=

0.00 m from Supp.


333.306 x 0.000 -

26.160 x

0.350 x

0.35
2.0

13.500

0.000

-1.60 kN-m

0.069 L-Section
=

1.65 m from Supp.


333.306 x 1.650 -

26.160 x

2.000 x

2.0
2.0

13.500

1.650

475.36 kN-m

0.133 L-Section
=

3.150 m from Supp.


333.306 x 3.150 -

26.160 x

3.500 x

3.5
2.0

13.500

3.150

847.16 kN-m

0.145 L-Section
=

3.444 m from Supp.


333.306 x 3.444 -

26.160 x

3.794 x

3.794
2.0

13.500

3.444

913.08 kN-m

0.250 L-Section
=

5.938 m from Supp.


333.306 x 5.938 -

26.160 x

6.288 x

6.288
2.0

13.500

5.938

1381.76 kN-m

0.375 L-Section
=

8.906 m from Supp.


333.306 x 8.906 -

26.160 x

9.256 x

9.256
2.0

13.500

8.906

1727.60 kN-m

0.500 L-Section
=

11.875 m from Left Supp.


333.306 x 11.875 - 26.160 x

12.225 x

12.225
2.0

13.500 x

11.875

1842.88 kN-m

0.625 L-Section
=

8.906 m from Right Supp.


333.306 x 8.906 26.160 x

9.256 x

9.256
2.0

13.500

8.906

1727.60 kN-m

0.750 L-Section
=

5.938 m from Right Supp.


333.306 x 5.938 26.160 x

6.288 x

6.288
2.0

13.500

5.938

1381.76 kN-m

0.855 L-Section
=

3.444 m from Right Supp.


333.306 x 3.444 26.160 x

3.794 x

3.794
2.0

13.500

3.444

913.08 kN-m

0.867 L-Section
=

3.150 m from Right Supp.


333.306 x 3.150 26.160 x

3.500 x

3.500
2.0

13.500

3.150

847.16 kN-m

0.931 L-Section
=

1.650 m from Right Supp.


333.306 x 1.650 26.160 x

2.000 x

2.000
2.0

13.500

1.650

475.36 kN-m

1.000 L-Section
=

0.000 m from Right Supp.


333.306 x 0.000 26.160 x

0.350 x

0.350
2.0

13.500

0.000

-1.60 kN-m

Shear Force at Various Sections of Precast Girder due to Green Weight of Slab Concrete
a)

At 0.00 L Sec

0.00 m from Left Supp. =

333.306

26.16 x

0.350

13.500

310.650 kN

b)

At 0.07 L Sec

1.65 m from Left Supp. =

333.306

26.16 x

2.000

13.500

267.486 kN

c)

At 0.13 L Sec

3.15 m from Left Supp. =

333.306

26.16 x

3.500

13.500

228.246 kN

d)

At 0.15 L Sec

3.44 m from Left Supp. =

333.306

26.16 x

3.794

13.500

220.562 kN

e)

At 0.25 L Sec

5.94 m from Left Supp. =

333.306

26.16 x

6.288

13.500

155.325 kN

f)

At 0.38 L Sec

8.91 m from Left Supp. =

333.306

26.16 x

9.256

13.500

77.663 kN

g)

At 0.50 L Sec

11.88 m from Left Supp. =

h)

At 0.63 L Sec

8.91 m from Right Supp. =

333.306

26.16 x

12.225

13.500

0.000 kN

333.306

26.16 x

9.256

13.500

77.663 kN

i)

At 0.75 L Sec

5.94 m from Right Supp. =

333.306

26.16 x

6.288

13.500

155.325 kN

j)

At 0.86 L Sec

3.44 m from Right Supp. =

333.306

26.16 x

3.794

13.500

220.562 kN

k)

At 0.87 L Sec

3.15 m from Right Supp. =

333.306

26.16 x

3.500

13.500

228.246 kN

l)

At 0.93 L Sec

1.65 m from Right Supp. =

333.306

26.16 x

2.000

13.500

267.486 kN

m)

At 1.00 L Sec

0.00 m from Right Supp. =

333.306

26.16 x

0.350

13.500

310.650 kN

(6)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

Summary of B.M. & S.F. for Long.-Girder (Without Composite)


Section
w.r.t. to left
Support

Distance of due to Wt. of Green Conc. of Slab+Diaphragm+Temp. LL

Due to weight of Slab+ Diaphragm during Service

Section from

Bending

Shear

Stress at

Stress at

Bending

Shear

Stress at

Left Face of

Moment

Force

Top of Gir

Bottom of Gir.

Moment

Force

Top of Gir

I-Girder

kN-m

kN

(MPa)

(MPa)

kN-m

kN

(MPa)

Stress at

For Normal of Deck in Service

Bottom of Gir. Weight =

25.500 kN/m

(MPa)

0.000 L Sec

0.200 m

-1.602

310.650

-0.005

0.005

-1.562

461.630

-0.005

0.005

0.069 L Sec

1.850 m

475.360

267.486

1.384

-1.496

463.367

397.488

1.349

-1.459

0.133 L Sec

3.350 m

847.159

228.246

2.985

-3.128

825.786

339.177

2.909

-3.049

0.145 L Sec

3.644 m

913.078

220.562

3.217

-3.371

890.041

327.757

3.136

-3.286

0.250 L Sec

6.138 m

1381.761

155.325

4.868

-5.101

1346.900

230.815

4.745

-4.973

0.375 L Sec

9.106 m

1727.602

77.663

6.087

-6.378

1684.016

115.408

5.933

-6.217

0.500 L Sec

12.075 m

1842.882

0.000

6.493

-6.804

1796.387

0.000

6.329

-6.632

0.625 L Sec

15.044 m

1727.602

77.663

6.087

-6.378

1684.016

115.408

5.933

-6.217

0.750 L Sec

18.013 m

1381.761

155.325

4.868

-5.101

1346.900

230.815

4.745

-4.973

0.855 L Sec

20.506 m

913.078

220.562

3.217

-3.371

890.041

327.757

3.136

-3.286

0.867 L Sec

20.800 m

847.159

228.246

2.985

-3.128

825.786

339.177

2.909

-3.049

0.931 L Sec

22.300 m

475.360

267.486

1.384

-1.496

463.367

397.488

1.349

-1.459

1.000 L Sec

23.950 m

-1.602

310.650

-0.005

0.005

-1.562

461.630

-0.005

0.005

Summary of Design B. M. & S. F. at Different Sections for Long. Girder (With Composite)
EFFECTIVE SPAN =

(+ve) sign indicates Sagging Bending Moment


(-ve) sign indicates Hogging Bending Moment
Section
w.r.t. to left

Distance of
Section from
Left Permanant

Support

Node No.
from
Grillage

Support
(metre)

0.000 L Sec

0.00

54

23.75 m

Effect of SDL1 (SIDL Excluding Surfacing)


Bending
Moment
MZ

Shear
Force
FY

Stress in Composite Section


Stress at
Stress at
Stress at
Top of Deck
Top of Gir Bottom of Gir.

Effect of SDL2 (Dead Load of Surfacing (Wearing Coat))


Bending
Moment
MZ

Shear
Force
FY

Stress in Composite Section


Stress at
Stress at
Stress at
Top of Deck Top of Gir Bottom of Gir.

(kN-m)

(kN)

(MPa)

(MPa)

(MPa)

(kN-m)

(kN)

(MPa)

(MPa)

(MPa)

0.000

23.000

0.000

0.000

0.000

0.000

73.000

0.000

0.000

0.000

0.069 L Sec

1.65

55

45.000

23.000

0.051

0.034

-0.087

117.000

70.000

0.133

0.089

-0.227

0.133 L Sec

3.15

56

80.000

23.000

0.092

0.057

-0.200

209.000

60.000

0.241

0.149

-0.522

86.850

23.316

0.100

0.062

-0.217

222.700

58.314

0.257

0.159

-0.556

57

145.000

26.000

0.168

0.104

-0.362

339.000

44.000

0.392

0.242

-0.846

0.145 L Sec

3.44

0.250 L Sec

5.94

0.375 L Sec

8.91

58

221.000

29.000

0.255

0.158

-0.551

421.000

25.000

0.486

0.301

-1.051

0.500 L Sec

11.88

59

305.000

29.000

0.352

0.218

-0.761

450.000

5.000

0.520

0.321

-1.123

0.625 L Sec

14.84

60

221.000

29.000

0.255

0.158

-0.551

421.000

25.000

0.486

0.301

-1.051

0.750 L Sec

17.81

61

145.000

26.000

0.168

0.104

-0.362

339.000

44.000

0.392

0.242

-0.846

86.850

23.316

0.100

0.062

-0.217

222.700

58.314

0.257

0.159

-0.556

62

80.000

23.000

0.092

0.057

-0.200

209.000

60.000

0.241

0.149

-0.522

0.855 L Sec

20.31

0.867 L Sec

20.60

0.931 L Sec

22.10

63

45.000

23.000

0.051

0.034

-0.087

117.000

70.000

0.133

0.089

-0.227

1.000 L Sec

23.75

64

0.000

23.000

0.000

0.000

0.000

0.000

73.000

0.000

0.000

0.000

Section

Distance of

Node No.

w.r.t. to left

Section from

from

Bending

Shear

Bending

Shear

Left Permanant

Grillage

Moment

Force

Stress at

Stress at

Stress at

Moment

Force

Stress at

MZ

FY

Top of Deck

Top of Gir

Bottom of Gir.

MZ

FY

Top of Deck

Support

Support
(metre)

0.000 L Sec

0.00

54

Effect of Shifting of Support

Due to Footpath Live Load

Stress in Composite Section

Stress in Composite Section


Stress at

Stress at

Top of Gir Bottom of Gir.

(kN-m)

(kN)

(MPa)

(MPa)

(MPa)

(kN-m)

(kN)

(MPa)

(MPa)

(MPa)

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.069 L Sec

1.65

55

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.133 L Sec

3.15

56

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

57

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.145 L Sec

3.44

0.250 L Sec

5.94

0.375 L Sec

8.91

58

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.500 L Sec

11.88

59

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.625 L Sec

14.84

60

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.750 L Sec

17.81

61

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

62

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.855 L Sec

20.31

0.867 L Sec

20.60

0.931 L Sec

22.10

63

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

1.000 L Sec

23.75

64

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

(7)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

DESIGN OF INNER LONG. GIRDER (LG2)

SUMMARY OF DESIGN MOMENT & SHEAR FORCE DUE TO CWLL for Long. Girder (COMPOSITE)
CWLL responses are without impact (STAAD OUTPUT)
Section

Distance of

w.r.t. to left Section from


permanant Left Permanant
Support
Support

Node No.
from
Grillage

(metre)

Class-A (2-Lanes)

Class 70R Wheeled

Maximum Corresponding Maximum


Bending
Moment
MZ

Shear
Force
FY

(kN-m)

(kN)

Lane Reduction Fac. = 1.00

Bending
Moment
MZ

Corresponding
Shear
Force
FY

(kN-m)

(kN)

Lane Reduction Fac. = 1.00

Class-A (3-Lanes) Cl.70R Wheeled +Cl.A (1L)


Maximum Corresponding Maximum Corresponding
Bending
Moment
MZ

Shear
Force
FY

(kN-m)

(kN)

Lane Reduction Fac. = 0.90

Bending
Moment
MZ

Shear
Force
FY

(kN-m)

(kN)

Lane Reduction Fac. = 0.90

0.000 L Sec

0.00

54

0.000

264.000

0.000

376.000

0.000

0.000

0.000

0.000

0.069 L Sec

1.65

55

426.000

252.000

556.000

341.000

0.000

0.000

0.000

0.000

0.133 L Sec

3.15

56

0.145 L Sec

3.44

737.000

233.000

919.000

293.000

0.000

0.000

0.000

0.000

778.309

225.939

961.363

284.359

0.000

0.000

0.000

0.000

0.250 L Sec

5.94

57

1129.000

166.000

1321.000

211.000

0.000

0.000

0.000

0.000

0.375 L Sec

8.91

58

1283.000

114.000

1437.000

129.000

0.000

0.000

0.000

0.000

0.500 L Sec

11.88

59

1283.000

58.000

1437.000

80.000

0.000

0.000

0.000

0.000

0.625 L Sec

14.84

60

1283.000

114.000

1437.000

129.000

0.000

0.000

0.000

0.000

0.750 L Sec

17.81

61

1129.000

166.000

1321.000

211.000

0.000

0.000

0.000

0.000

0.855 L Sec

20.31

778.309

225.939

961.363

284.359

0.000

0.000

0.000

0.000

0.867 L Sec

20.60

62

737.000

233.000

919.000

293.000

0.000

0.000

0.000

0.000

0.931 L Sec

22.10

63

426.000

252.000

556.000

341.000

0.000

0.000

0.000

0.000

1.000 L Sec

23.75

64

0.000

264.000

0.000

376.000

0.000

0.000

0.000

0.000

Section
Distance of
w.r.t. to left Section from
permanant Left Permanant
Support
Support

Node No.
from
Grillage

(metre)

Class-A (2-Lanes)
Maximum Corresponding
Shear
Force
FY

Bending
Moment
MZ

(kN)

(kN-m)

Lane Reduction Fac. = 1.00

Class 70R Wheeled


Maximum
Shear
Force
FY

Corres.
Bending
Moment
MZ

(kN)

(kN-m)

Lane Reduction Fac. = 1.00

Class-A (3-Lanes) Cl.70R Wheeled +Cl.A (1L)


Maximum Corresponding Maximum
Corres.
Shear
Force
FY

Bending
Moment
MZ

(kN)

(kN-m)

Lane Reduction Fac. = 0.90

Shear
Force
FY

Bending
Moment
MZ

(kN)

(kN-m)

Lane Reduction Fac. = 0.90

0.000 L Sec

0.00

54

264.000

0.000

376.000

0.000

0.000

0.000

0.000

0.000

0.069 L Sec

1.65

55

252.000

426.000

341.000

556.000

0.000

0.000

0.000

0.000

0.133 L Sec

3.15

56

233.000

737.000

293.000

919.000

0.000

0.000

0.000

0.000

0.145 L Sec

3.44

225.939

778.309

284.359

961.363

0.000

0.000

0.000

0.000

0.250 L Sec

5.94

57

166.000

1129.000

211.000

1321.000

0.000

0.000

0.000

0.000

0.375 L Sec

8.91

58

114.000

1283.000

129.000

1437.000

0.000

0.000

0.000

0.000

0.500 L Sec

11.88

59

58.000

1283.000

80.000

1437.000

0.000

0.000

0.000

0.000

0.625 L Sec

14.84

60

114.000

1283.000

129.000

1437.000

0.000

0.000

0.000

0.000

0.750 L Sec

17.81

61

166.000

1129.000

211.000

1321.000

0.000

0.000

0.000

0.000

225.939

778.309

284.359

961.363

0.000

0.000

0.000

0.000

62

233.000

737.000

293.000

919.000

0.000

0.000

0.000

0.000

0.855 L Sec

20.31

0.867 L Sec

20.60

0.931 L Sec

22.10

63

252.000

426.000

341.000

556.000

0.000

0.000

0.000

0.000

1.000 L Sec

23.75

64

264.000

0.000

376.000

0.000

0.000

0.000

0.000

0.000

CWLL Responses with Impact


(+ve) sign indicates Sagging Bending Moment (-ve) sign indicates Hogging Bending Moment

Section

Distance of

Node No.

w.r.t. to left

Section from

from

CWLL B.M.

Corres. S.F.

Left Permanant

Grillage

with Impact

with Impact

Stress at

Stress at

Support

Ml

Vl

Top of Deck

(metre)

(kN-m)

(kN)

(MPa)

Support

Governing Bending Moment due to CWLL


Stress in Composite Section

Governing S.F.
CWLL S.F.

Corres. B.M.

Stress at

with Impact

with Impact

Top of Gir

Bottom of Gir.

Vl

Ml

(MPa)

(MPa)

(kN)

(kN-m)

0.000 L Sec

0.00

54

0.000

432.874

0.000

0.000

0.000

432.874

0.000

0.069 L Sec

1.65

55

640.101

392.580

0.726

0.488

-1.240

392.580

640.101

0.133 L Sec

3.15

56

1058.008

337.319

1.222

0.755

-2.640

337.319

1058.008

0.145 L Sec

3.44

1106.780

327.371

1.279

0.790

-2.762

327.371

1106.780

0.250 L Sec

5.94

57

1520.815

242.916

1.757

1.086

-3.795

242.916

1520.815

0.375 L Sec

8.91

58

1654.361

148.513

1.911

1.181

-4.128

148.513

1654.361

0.500 L Sec

11.88

59

1654.361

92.101

1.911

1.181

-4.128

92.101

1654.361

0.625 L Sec

14.84

60

1654.361

148.513

1.911

1.181

-4.128

148.513

1654.361

0.750 L Sec

17.81

61

1520.815

242.916

1.757

1.086

-3.795

242.916

1520.815

0.855 L Sec

20.31

1106.780

327.371

1.279

0.790

-2.762

327.371

1106.780

0.867 L Sec

20.60

62

1058.008

337.319

1.222

0.755

-2.640

337.319

1058.008

0.931 L Sec

22.10

63

640.101

392.580

0.726

0.488

-1.240

392.580

640.101

1.000 L Sec

23.75

64

0.000

432.874

0.000

0.000

0.000

432.874

0.000

1.151

1.151

Impact Factor for Class A Loading

Impact Factor for Cl. 70R(W) Loading

(8)

S. Rastogi

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

LONGITUDINAL TEMPERATURE ANALYSIS


(fck)

characteristic strength of Concrete

45.000 N/mm^2

Ec

Modulus of elasticity of conc.

34000.000 N/mm^2

Coefficient of Thermal Expansion


Moment of Inertia of Section

Icg

0.49852 m^4

1.383 m^2

Sectional Area of Composite Section

1.17E-05 / deg.Celsius

Overall Depth of the Comp. Section

1.820 m

Distance of c.g. from Deck Top

Yna

0.576 m

Equivalent Idealized Section of Long. Girder


Segment-I
seg-I

d1

seg-II

d2

Area of Segment

Depth of Segment

0.220 m

Equivalent Length of Seg

3.000 m

0.6600 m^2

Segment-II

seg-III

d3
seg-IV

Area of Segment

0.1500 m^2

Depth of Segment

0.150 m

Equivalent Length of Seg

1.000 m

=
=
=

0.0638 m^2
0.100 m
0.637 m

=
=
=

0.2613 m^2
0.950 m
0.275 m

=
=
=

0.0731 m^2
0.150 m
0.488 m

=
=
=

0.1750 m^2
0.250 m
0.700 m

Segment-III

cg. of Section
d4

Area of Segment
Depth of Segment
Equivalent Length of Seg

Segment-IV

Area of Segment
Depth of Segment
Equivalent Length of Seg

Segment-V

d5

seg-V

Area of Segment
Depth of Segment
Equivalent Length of Seg

Segment-VI
seg-VI

Dimension
H

d6

Area of Segment
Depth of Segment
Equivalent Length of Seg

Width of Sec-1 Depth of Sec-1 Width of Sec-2 Depth of Sec-2 Width of Sec-4 Depth of Sec-3 Width of Sec-4 Depth of Sec-4 Width of Sec-5 Depth of Sec-5 Width of Sec-6 Depth of Sec-6
W4
d4
W5
d5
W6
d6
W1
d1
W2
d2
W3
d3

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

(in m)

1.820

3.000

0.220

1.000

0.150

0.637

0.100

0.275

0.950

0.488

0.150

0.700

0.250

CASE-1 Positive Temperature Difference Case


Refer Fig. 10 of IRC:6-2010 for Temterature Gradient throughout the Depth
h1 =

0.3 x h

0.3 x h

h1 =
(

0.3 x h

I
II
III
IV
V
VI

T1

0.150 m
h1

i.e.

0.546

T2

or

0.250 m
h2

i.e.

0.250 m
0.546

or

0.150 m

{ Whichever is smaller }

h3 =
T1
T2
T3

Segment Segment Segment Segment Segment Segment -

or

0.150 m

h2 =

HENCE

SEGMENT

{ Whichever is smaller }

HENCE
h3

0.546

{ Whichever is smaller }

HENCE
h2

i.e.

0.150 m

=
=
=

17.8 degC
4.0 degC
2.1 degC

Width

Depth

Cum. Depth

in metre

in metre

in metre

3.000
1.000
0.637
0.275
0.488
0.700

0.220
0.150
0.100
0.950
0.150
0.250

0.220
0.370
0.470
1.420
1.570
1.820

Temperature Strain at any fiber


Stresses at any fiber

fy

h3
T3
Positive Temperature Difference

x
x

Ec

Total Temperature Stress at a depth Y from Top


(+ve) for compression
(-ve) for tension

fy

Ft / A

(Y - Yna) x

(9)

Mt / Icg

Segment
of Temp
Gradient

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

DESIGN OF INNER LONG. GIRDER (LG2)


Cum.Depth Cum.Depth Value of
Value of
With reference to Top Fiber
at top of
at bottom Temp. at Top Temp. at Bottom
of the Section
Segment
of Segment
of Segment
of Segment
Y-start
f1
Y-end

0.150
0.250
1.270
0.150

deg C

in metre

Mpa

in metre

Mpa

in metre

MPa

0.000
0.150
0.400
1.670

0.150
0.400
1.670
1.820

17.800
4.000
0.000
0.000

4.000
0.000
0.000
2.100

0.000
0.150
0.400
1.670

7.081
1.591
0.000
0.000

0.150
0.400
1.670
1.820

1.591
0.000
0.000
0.835

0.150
0.250
1.270
0.150

-5.490
-1.591
0.000
0.835

Depth of
Fiber from
Top
Y

Temp.
Stress at
Depth Y
fy

Average
Temp.
Stress
fy avg

Depth of
the Strip

Width of
the Strip

(MPa)

(m)

(m)

II

(m)

(MPa)

7.0808

0.150

1.5912

0.220
0.220

1.1457
1.1457

0.370
0.370

0.1909
0.1909

0.400

0.0000

Segment - IV
upto cg. of section
Segment - IV
Below cg. of section
V

0.470
0.470

0.0000
0.0000

0.576
0.576

0.0000
0.0000

1.420
1.420

0.0000
0.0000

1.570
1.570

0.0000
0.0000

1.670

0.0000

Ft / A

(kN-m)

3.0000

1951.21

0.0592

-0.5168

-1008.387

1.3684

0.0700

3.0000

287.37

0.1831

-0.3929

-112.901

(MPa)

-1.072
-1.363
-1.363
0.1500

1.0000

100.2456

0.2771

-0.2988

-29.957
-1.987
-1.987

0.0955

0.0300

0.6375

1.83

0.0000

0.0700

0.6375

0.00

0.3800

-0.1960

-0.358
-2.112
-1.958
-1.958

0.1060

0.2750

0.0000
-1.724
-1.724

0.0000

= 2384.509

(m)

0.1500

0.0000

1.820

(m)

Moment due Total Temp.


to temp. Stress at a
stress
depth Y
Mt

4.3360

0.8440

0.2750

0.0000
0.137
0.137

0.0000

Segment - VI

Yt - Yna

-36.598
-6.365
0.000
5.569

4.087

0.6683

Segment - III

Force due Depth of Ft


to temp.
from Top
stress
Ft
Yt
(kN)

df
dY

f2

deg C

0.000

S. Rastogi

Stress
df

in metre

Segment - I

Segment -

dY

in metre

SEGMENT

Segment -

Project
Client

0.1500

0.4875

0.0000
0.468
0.468

0.0000

0.1000

0.7000

0.00

0.4177

0.1500

0.7000

43.86

Sum

2384.5087

0.688
1.7700

1.1940

52.367

0.8354

1.854

Mt / Icg =

1724.001 kN/m^2

1.383

-1099.235

-1099.235

-2204.981 kN/m^3

0.499

CASE-2 Reverse Temperature Difference Case


Refer Fig. 10 of IRC:6-2010 for Temterature Gradient throughout the Depth
h1 =

0.2 x h

or h4
HENCE
h2 =
or h3
HENCE

i.e.

0.364

or

T1

0.250 m

h1

{ Whichever is smaller }

h1 =

h4

0.25 x h

=
i.e.

0.250 m
0.455

or

0.250 m
T2

{ Whichever is smaller }

h2 =

h3

0.250 m

T1
T2
T3
T4

=
=
=
=

-10.6
-0.7
-0.8
-6.6

h2

degC
degC
degC
degC

Width

Depth

Cum. Depth

in metre

in metre

in metre

Segment - I

3.000

0.220

0.220

Segment - II
Segment - III
Segment - IV

1.000
0.637
0.275

0.150
0.100
0.950

0.370
0.470
1.420

Segment - V
Segment - VI

0.488
0.700

0.150
0.250

1.570
1.820

Temperature Strain at any fiber


Stresses at any fiber

h3
T3

h4

x
x

T4
Reverse Temperature Difference
Ec

(10)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

Total Temperature Stress at a depth Y from Top


fy

(+ve) for compression


(-ve) for tension
Segment

Cum.Depth Cum.Depth

Value of

Ft / A

Value of

(Y - Yna) x

Mt / Icg

With reference to Top Fiber

Temp. at Top Temp. at Bottom

of the Section

dY

Stress

df

df

dY

of Temp

at top of

at bottom

Gradient

Segment

of Segment

of Segment

of Segment

Y-start

f1

Y-end

f2

in metre

in metre

deg C

deg C

in metre

Mpa

in metre

Mpa

in metre

MPa

0.250

0.000

0.250

-10.600

-0.700

0.000

-4.217

0.250

-0.278

0.250

3.938

0.250

0.250

0.500

-0.700

0.000

0.250

-0.278

0.500

0.000

0.250

0.278

1.114

0.820

0.500

1.320

0.000

0.000

0.500

0.000

1.320

0.000

0.820

0.000

0.000

15.753

0.250

1.320

1.570

0.000

-0.800

1.320

0.000

1.570

-0.318

0.250

-0.318

-1.273

0.250

1.570

1.820

-0.800

-6.600

1.570

-0.318

1.820

-2.625

0.250

-2.307

-9.229

SEGMENT

Segment -

Segment -

Segment Segment -

Depth of

Temp.

Average

Depth of

Width of

Fiber from

Stress at

Temp.

the Strip

the Strip

Top

Depth Y

Stress

fy

fy avg

Ft

Yt

(MPa)

(m)

(m)

(kN)

(m)

Segment -

1.0284

0.220

-0.7510

1.0284

0.250

-0.2785

(m)

(kN-m)

(MPa)

0.2200

3.0000

-1639.350

0.0844

-0.4916

805.831

-0.5148

0.0300

1.0000

-15.443

0.2327

-0.3433

5.301

-0.2116

0.1200

1.0000

-25.396

0.3037

-0.2723

6.915

1.4705

0.370

-0.1448

1.4824

0.370

-0.1448

1.4824

0.470

-0.0334

1.4924

0.470

-0.0334

1.4924

0.500

0.0000

0.1000

0.6375

-5.681

-0.0167

0.0300

0.2750

-0.138

0.0000

0.0760

0.2750

0.000

0.4096

0.4800

-0.1664

-0.0960

0.945

0.013
1.4953

0.576

0.0000

1.4183

0.576

0.0000

1.4183

1.320

0.0000

0.0000

0.7440

0.2750

0.000

-0.0636

0.1000

0.2750

-1.750

0.6634
1.3867

0.8107

-1.419

1.420

-0.1273

0.4346

1.420

-0.1273

0.4346

1.570

-0.3182

= -1961.622

depth Y

Mt

-0.7510

-0.2228

0.1500

0.4875

-16.290

-0.3182

0.0000

0.4875

0.000

1.5057

0.9297

-15.145
0.0915

1.570

-0.3182

0.0915

1.570

-0.3182

0.0915

1.820

-2.6255

-1.4719

Ft / A

stress

-2.2140

-0.0891

VI

Stress at a

0.220

below cg. of section

Segment -

Yt - Yna

Total Temp.

to temp.

(MPa)

II

IV

stress

Moment due

-4.2167

upto cg. of section

Segment -

from Top

(m)

-2.4839

IV

to temp.

0.000
I

II

Force due Depth of Ft

0.2500

0.7000

-257.576

Sum

-1961.622

1.7277

1.1517

-296.645
-2.4694

Mt / Icg =

-1418.254 kN/m^2

1.383

505.796

505.796
0.499

(11)

1014.587 kN/m^3

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)

Calculation for Differential Shrinkage Effect (Modified by Creep)

The differential shrinkage strain between th cast-insitu deck slab and precast girder causes the stresses in the precast girder & deck slab. The equivalent
force, that causes the stresses in the girder, is calculated from the basic principles. The force is equal to product of modulus of concrete, area of
flange and differential strain. The shrinkage strains for deck slab and precast girder have been worked out and modified with creep of concrete
Eslab =

Modulus of Elast. of Conc.

34000.00 N/mm^2

=
( ,t0) =

Differential shrinkage strain


Creep Coefficient

Adi =

Effective Area of Deck Slab

-6.2E-05

( At

35 days ) When in-situ deck is cast on the girder

2.1E+00

Creep Reduction Factor

(1 - e(- ))/

4.235E-01

Refer Cl. 6.3.5 of IRC:112-2011

0.660 m^2

Moment of Inertia of Composite Sec.

Icg

5.0E+11 mm^4

Area of Composite Section

Ac

1.4E+06 mm^2

Total Depth of the Section

1820.0 mm

Thickness of Deck Slab

Ds

220.0 mm

Distance of top of slab from cg. of Section

575.975 mm

Distance of Bottom of slab from cg of Section

355.975 mm

Distance of Bottom of girder from cg of Section

1244.025 mm

Stresses in Outer Girder due to Differential Shrinkage Effect:


Step(1) Calculate Restrained Shrinkage Stress

Restraining Force F = Eslab x A x

( acting at the cg. of Deck Slab )

Restraining Force for Girder


Fo =

34000.00

660000 -x

0.00006

0.423

-588484.61 N

Restraining Moment for Girder


-588485

fo_r =

34000.00

(
x

576

110.00

-6.2E-05

-2.105 MPa

Direct Stress + Bending Stress

Icg

Balancing Stress at Top of Deck Slab

0.742 MPa

Balancing Stress at Bottom of Deck Slab

0.621 MPa

Balancing Stress at Top of Girder

0.621 MPa

Balancing Stress at N.A.

0.425 MPa

Balancing Stress at Bottom of Girder

-0.259 MPa

Step(3) Calculate Final Stresses at Various Levels of Section


Total Stress at Top of Deck Slab

-2.74E+08 N-mm

Step(2) Calculate Balancing Stresses Balancing Stress at any Section =


Fo
Mo
fo_b =
+
x y
Ae

-2.105 +

0.742

-1.363 MPa

Total Stress at Bottom of Deck Slab

-2.105 +

0.621

-1.484 MPa

Total Stress at Top of Girder

0.000 +

0.621

0.621 MPa

Total Stress at N.A.

0.000 +

0.425

0.425 MPa

Total Stress at Bottom of Girder

0.000 +

-0.259

-0.259 MPa

-1.363

1800

-1.484

1600

Height from Soffit (mm)

Mo =

0.00
0.621

1400
1200

0.425

1000
800
600
400
200

-0.259

-3

0.00

Height from Soffit (mm)

1820

1820

1600

-1
0
1
2
(MPa)
1600Final Stresses
1244
0

Final Stresses

0.00

-1.363

-1.484

0.621

(MPa)

(12)

-2

0.425

-0.259

3
0
0.00

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

DESIGN OF INNER LONG. GIRDER (LG2)

Section Properties
1.

Properties of non-composite section: Precast Girder Only

1a

Area of Precast Girder

m2

1.171

1.171

1.171

0.723

0.723

0.723

0.723

0.723

0.723

0.723

0.723

0.723

1.171

1.171

1.171

1b

c.g. of girder from Top of girder

Yt

0.769

0.769

0.769

0.781

0.781

0.781

0.781

0.781

0.781

0.781

0.781

0.781

0.769

0.769

0.769
0.831

1c

c.g. of girder from soffit of girder Yb

0.831

0.831

0.831

0.819

0.819

0.819

0.819

0.819

0.819

0.819

0.819

0.819

0.831

0.831

1d

Overall Depth of Girder

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1.60

1e

Moment of Inertia of Section

Iz

m4

0.2640

0.2640

0.2640

0.2218

0.2218

0.2218

0.2218

0.2218

0.2218

0.2218

0.2218

0.2218

0.2640

0.2640

0.2640

1f

Section Modulus of Top

Zt

m3

0.3435

0.3435

0.3435

0.2838

0.2838

0.2838

0.2838

0.2838

0.2838

0.2838

0.2838

0.2838

0.3435

0.3435

0.3435

1g

Section Modulus of Bottom

Zb

m3

0.3177

0.3177

0.3177

0.2709

0.2709

0.2709

0.2709

0.2709

0.2709

0.2709

0.2709

0.2709

0.3177

0.3177

0.3177

m3

0.0903

0.0903

0.0903

0.0542

0.0542

0.0542

0.0542

0.0542

0.0542

0.0542

0.0542

0.0542

0.0903

0.0903

0.0903

kN/m

29.28

29.28

29.28

18.08

18.08

18.08

18.08

18.08

18.08

18.08

18.08

18.08

29.28

29.28

29.28

mm

457

457

457

255

255

255

255

255

255

255

255

255

457

457

457

0.711

0.711

0.711

0.795

0.795

0.795

0.795

0.795

0.795

0.795

0.795

0.795

0.711

0.711

0.711

1h

First moment of area above and about


N.A of Composite Section

1i

Weight of Girder per metre

1j.

Notional size (mm) of the Cross Section

wg

1k.

Coeff. depending on notional size for Shrinkage kh

h0

2.

Properties of Composite Section: Precast Girder + Deck Slab

2a

Area of Composite Section

m2

1.831

1.831

1.831

1.383

1.383

1.383

1.383

1.383

1.383

1.383

1.383

1.383

1.831

1.831

1.831

2b

c.g. of Section from Top of Deck Slab Yt

0.672

0.672

0.672

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.672

0.672

0.672

Yb

1.148

1.148

1.148

1.244

1.244

1.244

1.244

1.244

1.244

1.244

1.244

1.244

1.148

1.148

1.148

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

1.82

m4

0.5927

0.5927

0.5927

0.4985

0.4985

0.4985

0.4985

0.4985

0.4985

0.4985

0.4985

0.4985

0.5927

0.5927

0.5927

2c

c.g. of Section from soffit

2d

Overall Depth of the Section

2e

Moment of Inertia of Section

Iz

2f

Section Modulus at Top of Slab

Zts

m3

0.8819

0.8819

0.8819

0.8655

0.8655

0.8655

0.8655

0.8655

0.8655

0.8655

0.8655

0.8655

0.8819

0.8819

0.8819

2g

Sec. Modulus at Bottom of Slab

Zbs

m3

1.3111

1.3111

1.3111

1.4004

1.4004

1.4004

1.4004

1.4004

1.4004

1.4004

1.4004

1.4004

1.3111

1.3111

1.3111

2h

Sec.Modulus of Bottom of Section

Zb

2i

First moment of area of Composite Sec.

2j.

Notional size (mm) of the Cross Section

1k.

Coeff. depending on notional size for Shrinkage kh

0.5163

0.5163

0.5163

0.4007

0.4007

0.4007

0.4007

0.4007

0.4007

0.4007

0.4007

0.4007

0.5163

0.5163

0.5163

0.4612

0.4612

0.4612

0.3618

0.3618

0.3618

0.3618

0.3618

0.3618

0.3618

0.3618

0.3618

0.4612

0.4612

0.4612

above & about N.A of Composite Section

h0

mm

582

582

582

405

405

405

405

405

405

405

405

405

582

582

582

0.700

0.700

0.700

0.724

0.724

0.724

0.724

0.724

0.724

0.724

0.724

0.724

0.700

0.700

0.700

(13)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Summary of Bending Moment & Shear Force due to Different Loadings (Exculding Prestress)
1.

Due to Self Weight of Girder

1a
1b

Bending Moment (M)


Shear Force
(V)

Diaphragm (Applied on Non-Composite Section)


kN-m
kN

0.000
0.000

-1.793
243.895

360.775
195.582

2.

Due to Weight of Shuttering (Applied on Non-Composite Section)

2a
2b

Bending Moment (M)


Shear Force
(V)

kN-m
kN

0.000
0.000

-0.028
5.344

8.177
4.601

625.409
160.064

671.648
154.753

1001.35
109.671

1247.27
56.001

1333.86
2.332

1247.27
56.001

1001.35
109.671

671.648
154.753

625.409
160.064

360.775
195.582

-1.793
243.895

0.000
0.000

14.573
3.926

15.707
3.794

23.769
2.672

29.718
1.336

31.701
0.000

29.718
1.336

23.769
2.672

15.707
3.794

14.573
3.926

8.177
4.601

-0.028
5.344

0.000
0.000

3.

Due to Removal of Shuttering (Applied on Composite Section when structure is continuous on temporary bearings)

3a
3b

Bending Moment (M)


Shear Force
(V)

kN-m
kN

0.000
0.000

0.028
-5.344

-8.177
-4.601

-14.573
-3.926

-15.707
-3.794

4.

Due to Wt. of Green Conc. of Slab+Temporary Live Load (Applied on Non-Composite Section)

4a
4b

Bending Moment (M)


Shear Force
(V)

kN-m
kN

0.000
0.000

-1.602
310.650

475.360
267.486

475.360
267.486

-1.602
310.650

0.000
0.000

847.159
228.246

913.078
220.562

1381.761
155.325

1727.602
77.663

1842.882
0.000

1727.602
77.663

1381.761
155.325

913.078
220.562

847.159
228.246

475.360
267.486

-1.602
310.650

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

80.000
23.000

86.850
23.316

145.000
26.000

221.000
29.000

305.000
29.000

221.000
29.000

145.000
26.000

86.850
23.316

80.000
23.000

45.000
23.000

0.000
23.000

0.000
0.000

117.000
70.000

209.000
60.000

222.700
58.314

339.000
44.000

421.000
25.000

450.000
5.000

421.000
25.000

339.000
44.000

222.700
58.314

209.000
60.000

117.000
70.000

0.000
73.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

475.360
267.486

0.000
0.000

7.

Due to Super Imposed Dead Load SDL1(Applied on Composite Section)


Bending Moment (M)
Shear Force
(V)

45.000
23.000

8.

Due to Super Imposed Dead Load SDL2(Applied on Composite Section)

8a
8b

Bending Moment (M)


Shear Force
(V)

kN-m
kN

0.000
0.000

0.000
73.000

9.

Due to Footpath Live Load (Applied on Composite Section)

9a
9b

Bending Moment (M)


Shear Force
(V)

kN-m
kN

0.000
0.000

0.000
0.000

0.000
0.000

847.159
228.246

7a
7b

0.000
23.000

0.028
-5.344

913.08
220.562

Due to Shifting of Supports (Applied on Continuous Composite Section)

0.000
0.000

-8.177
-4.601

1381.76
155.325

Bending Moment (M)


Shear Force
(V)

kN-m
kN

-14.573
-3.926

1727.60
77.663

6.

0.000
0.000

-15.707
-3.794

1842.88
0.000

6a
6b

0.000
0.000

-23.769
-2.672

1727.60
77.663

Due to Wt. of Slab during Service (Applied on Non-Composite Section)

kN-m
kN

-29.718
-1.336

1381.76
155.325

Bending Moment (M)


Shear Force
(V)

-1.602
310.650

-31.701
0.000

913.08
220.562

5.

0.000
0.000

-29.718
-1.336

847.159
228.246

5a
5b

kN-m
kN

-23.769
-2.672

10.

Due to Carriageway Live Load (with Impact) (Applied on Composite Section)

10a

Governing Sagging Moment (M)

kN-m

0.000

0.000

640.101

1058.008

1106.78

1520.82

1654.36

1654.36

1654.36

1520.82

1106.780

1058.008

640.101

0.000

0.000

10b

Corresponding Shear Force (V)

kN

0.000

432.874

392.580

337.319

327.371

242.916

148.513

92.101

148.513

242.916

327.371

337.319

392.580

432.874

0.000

10c

Governing Shear Force

(V)

kN-m

0.000

432.874

392.580

337.319

327.37

242.92

148.51

92.10

148.51

242.92

327.371

337.319

392.580

432.874

0.000

10d

Corresponding Moment

(M)

kN

0.000

0.000

640.101

1058.008

1106.780

1520.815

1654.361

1654.361

1654.361

1520.815

1106.780

1058.008

640.101

0.000

0.000

(14)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Summary of Prestress Forces after Friction and Slip


0.000 L Sec

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

Dist. of Section from cL of Left Permanent Supports

-0.200 m
Col.- 1

0.000 m
Col.- 2

1.650 m
Col.- 3

3.150 m
Col.- 4

3.444 m
Col.- 5

5.938 m
Col.- 6

8.906 m
Col.- 7

11.875 m
Col.- 8

14.844 m
Col.- 9

17.813 m
Col.- 10

20.306 m
Col.- 11

20.600 m
Col.- 12

22.100 m
Col.- 13

23.750 m
Col.- 14

23.950 m
Col.- 15

0.83
987
0.509
1.237
1.231
0.118
0.627

0.83
987
0.379
1.245
1.241
0.097
0.470

0.83
987
0.357
1.246
1.243
0.093
0.443

0.83
987
0.207
1.260
1.259
0.057
0.261

0.83
987
0.125
1.276
1.276
0.013
0.159

0.83
987
0.120
1.286
1.286
0.000
0.154

0.83
987
0.125
1.296
1.296
-0.014
0.162

0.83
987
0.207
1.295
1.293
-0.059
0.268

0.83
987
0.357
1.282
1.278
-0.095
0.456

0.83
987
0.379
1.280
1.276
-0.099
0.484

0.83
987
0.509
1.273
1.267
-0.121
0.645

0.83
987
0.679
1.266
1.259
-0.133
0.855

0.83
987
0.700
1.266
1.259
-0.133
0.881

Sl. No.

Description

Units

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

Jaking End

Dist. of Section 'X' from Left Side Jacking End

Section under consideration

Tendon Details and Forces after Friction and Slip: For Stage-I Tendons
Cable No. 3

1
1a
1b
1c
1d
1e
1f
1g

No. of Cables
Area of Cables
c.g. of Cables from soffit of Girder ( Y-ord.)
Prestress Force at Sec. after (friction+slip)
H-Comp. of Prestress Force ( Ps . cos )
V-Comp. of Prestress Force ( Ps . sin )
( Ps . cos ) x ( Y-ord. )

3
3a
3b
3c
3d
3e
3f
3g

No. of Cables
Area of Cables
c.g. of Cables from soffit of Girder ( Y-ord.)
Prestress Force at Sec. after (friction+slip)
H-Comp. of Prestress Force ( Ps . cos )
V-Comp. of Prestress Force ( Ps . sin )
( Ps . cos ) x ( Y-ord. )

Cable No. 5

STRESSED FROM LEFT END


Nos.
mm2
m
MN
MN
MN
MN-m

0.83
987
0.700
1.229
1.222
0.129
0.856

0.83
987
0.679
1.230
1.223
0.129
0.830

STRESSED FROM LEFT END


Nos.
mm2
m
MN
MN
MN
MN-m

0.58
691
1.300
0.850
0.840
0.131
1.092

0.58
691
1.269
0.850
0.840
0.131
1.066

0.58
691
1.017
0.856
0.848
0.120
0.862

0.58
691
0.824
0.863
0.857
0.099
0.707

0.58
691
0.791
0.864
0.859
0.095
0.680

0.58
691
0.570
0.876
0.874
0.059
0.498

0.58
691
0.447
0.890
0.890
0.014
0.398

0.58
691
0.440
0.898
0.898
0.000
0.395

0.58
691
0.447
0.905
0.905
-0.014
0.405

0.58
691
0.570
0.895
0.893
-0.060
0.509

0.58
691
0.791
0.884
0.879
-0.097
0.695

0.58
691
0.824
0.883
0.877
-0.101
0.723

0.58
691
1.017
0.877
0.868
-0.123
0.883

0.58
691
1.269
0.872
0.861
-0.135
1.092

0.58
691
1.300
0.871
0.861
-0.135
1.119

Nos.
mm2

1.417
1678
2.079
2.062
0.260
0.944

1.417
1678
2.080
2.063
0.260
0.919

1.417
1678
2.093
2.079
0.238
0.716

1.417
1678
2.108
2.098
0.196
0.561

1.417
1678
2.111
2.102
0.187
0.534

1.417
1678
2.136
2.133
0.116
0.356

1.417
1678
2.165
2.165
0.027
0.257

1.417
1678
2.183
2.183
0.000
0.252

1.417
1678
2.201
2.201
-0.028
0.257

1.417
1678
2.190
2.187
-0.118
0.355

1.417
1678
2.166
2.157
-0.192
0.534

1.417
1678
2.163
2.154
-0.201
0.560

1.417
1678
2.149
2.135
-0.244
0.716

1.417
1678
2.138
2.120
-0.267
0.918

1.417
1678
2.137
2.120
-0.267
0.944

-0.113
1.183
0.498

-0.088
1.110
0.577

0.115
0.519
1.216

0.258
0.475
2.335

0.285
0.380
2.433

0.463
-0.248
3.092

0.562
-0.596
3.456

0.567
-0.615
3.477

0.562
-0.595
3.456

0.463
-0.250
3.094

0.285
0.378
2.435

0.258
0.473
2.337

0.116
0.517
1.218

-0.087
1.108
0.579

-0.112
1.181
0.500

0.204
0.315
0.391
0.940

0.229
0.287
0.372
0.989

0.432
0.057
0.217
1.382

0.683
-0.066
0.235
2.428

0.710
-0.097
0.216
2.494

0.888
-0.303
0.089
2.939

0.987
-0.417
0.018
3.186

0.992
-0.424
0.014
3.200

0.987
-0.417
0.018
3.186

0.889
-0.304
0.088
2.941

0.710
-0.098
0.216
2.496

0.684
-0.067
0.235
2.429

0.432
0.056
0.216
1.383

0.230
0.286
0.371
0.991

0.204
0.314
0.390
0.942

Total Effect of Stage-I Cables


Total Nos. of Cables
Total Area of Prestress
Total Prestress Force after (friction+slip)
( Ps . cos )
( Ps . sin )
cg of Stage-I cables from soffit (Y-ord)
For Non-Composite Section
Ecc. of Cables for Non-Composite Sec.

MN
MN
MN
m

Prestressing Factor (Top)= (1/A - e/Zt)


Prestressing Factor (Bottom)= (1/A+e/Zb)

For Composite Section


Ecc. of Cables for Composite Section
Pres. Factor (Slab Top)= (1/A - e/Zts)
Pres. Factor (Girder Top)= (1/A - e/Zbs)
Prestressing Factor (Bottom)= (1/A+e/Zb)

(15)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Tendon Details and Forces after Friction and Slip: For Stage-II Tendons
4
4a
4b
4c
4d
4e
4f
4g
2
2a
2b
2c
2d
2e
2f
2g
5
5a
5b
5c
5d

Cable No. 1
No. of Cables
Area of Cables
c.g. of Cables from soffit of Girder ( Y-ord.)
Prestress Force at Sec. after (friction+slip)
H-Comp. of Prestress Force ( Ps . cos )
V-Comp. of Prestress Force ( Ps . sin )
( Ps . cos ) x ( Y-ord. )

Cable No. 2
No. of Cables
Area of Cables
c.g. of Cables from soffit of Girder ( Y-ord.)
Prestress Force at Sec. after (friction+slip)
H-Comp. of Prestress Force ( Ps . cos )
V-Comp. of Prestress Force ( Ps . sin )
( Ps . cos ) x ( Y-ord. )

Cable No. 4
No. of Cables
Area of Cables
c.g. of Cables from soffit of Girder ( Y-ord.)

5e
5f

Prestress Force at Sec. after (friction+slip)


H-Comp. of Prestress Force ( Ps . cos )
V-Comp. of Prestress Force ( Ps . sin )

5g

( Ps . cos ) x ( Y-ord. )

STRESSED FROM LEFT END


Nos.
2
mm
m
MN

0.92
1086
0.300
1.363

0.92
1086
0.287
1.364

0.92
1086
0.186
1.373

0.92
1086
0.132
1.384

0.92
1086
0.127
1.387

0.92
1086
0.120
1.398

0.92
1086
0.120
1.407

0.92
1086
0.120
1.415

0.92
1086
0.120
1.424

0.92
1086
0.120
1.433

0.92
1086
0.127
1.434

0.92
1086
0.132
1.432

0.92
1086
0.186
1.420

0.92
1086
0.287
1.412

0.92
1086
0.300
1.411

MN
MN
MN-m

1.360
0.089
0.408

1.361
0.089
0.390

1.371
0.068
0.255

1.384
0.030
0.183

1.386
0.022
0.176

1.398
0.000
0.168

1.407
0.000
0.169

1.415
0.000
0.170

1.424
0.000
0.171

1.433
0.000
0.172

1.434
-0.023
0.182

1.431
-0.031
0.189

1.419
-0.070
0.263

1.409
-0.092
0.404

1.408
-0.092
0.423

STRESSED FROM LEFT END


Nos.
2
mm
m
MN
MN
MN
MN-m

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

0.92

1086
0.300
1.363
1.360
0.089
0.408

1086
0.287
1.364
1.361
0.089
0.390

1086
0.186
1.373
1.371
0.068
0.255

1086
0.132
1.384
1.384
0.030
0.183

1086
0.127
1.387
1.386
0.022
0.176

1086
0.120
1.398
1.398
0.000
0.168

1086
0.120
1.407
1.407
0.000
0.169

1086
0.120
1.415
1.415
0.000
0.170

1086
0.120
1.424
1.424
0.000
0.171

1086
0.120
1.433
1.433
0.000
0.172

1086
0.127
1.434
1.434
-0.023
0.182

1086
0.132
1.432
1.431
-0.031
0.189

1086
0.186
1.420
1.419
-0.070
0.263

1086
0.287
1.412
1.409
-0.092
0.404

1086
0.300
1.411
1.408
-0.092
0.423

STRESSED FROM LEFT END


Nos.
mm2
m
MN

1.00
1184
1.000
1.466

1.00
1184
0.974
1.467

1.00
1184
0.763
1.475

1.00
1184
0.602
1.486

1.00
1184
0.574
1.489

1.00
1184
0.389
1.507

1.00
1184
0.286
1.528

1.00
1184
0.280
1.541

1.00
1184
0.286
1.553

1.00
1184
0.389
1.544

1.00
1184
0.574
1.527

1.00
1184
0.602
1.525

1.00
1184
0.763
1.515

1.00
1184
0.974
1.507

1.00
1184
1.000
1.506

MN
MN

1.454
0.190

1.454
0.190

1.465
0.174

1.479
0.143

1.482
0.137

1.504
0.085

1.528
0.020

1.541
0.000

1.553
-0.020

1.542
-0.087

1.521
-0.141

1.518
-0.147

1.504
-0.178

1.494
-0.196

1.493
-0.196

MN-m

1.454

1.416

1.118

0.890

0.851

0.584

0.437

0.431

0.444

0.599

0.873

0.913

1.148

1.455

1.493

Nos.
mm2
MN
MN
MN
m

2.833
3356
4.192
4.174
0.368
0.544

2.833
3356
4.194
4.176
0.368
0.526

2.833
3356
4.221
4.207
0.310
0.387

2.833
3356
4.255
4.247
0.203
0.296

2.833
3356
4.262
4.255
0.181
0.283

2.833
3356
4.303
4.300
0.085
0.214

2.833
3356
4.341
4.341
0.020
0.178

2.833
3356
4.372
4.372
0.000
0.176

2.833
3356
4.402
4.402
-0.020
0.179

2.833
3356
4.410
4.407
-0.087
0.214

2.833
3356
4.394
4.388
-0.186
0.282

2.833
3356
4.388
4.380
-0.208
0.295

2.833
3356
4.356
4.342
-0.319
0.386

2.833
3356
4.331
4.312
-0.380
0.525

2.833
3356
4.329
4.310
-0.380
0.543

0.287
0.017
1.759

0.305
-0.034
1.814

0.444
-0.440
2.253

0.523
-0.459
3.313

0.536
-0.506
3.362

0.605
-0.748
3.616

0.640
-0.873
3.747

0.642
-0.880
3.754

0.640
-0.873
3.747

0.605
-0.748
3.616

0.537
-0.509
3.365

0.524
-0.462
3.317

0.446
-0.443
2.256

0.306
-0.038
1.818

0.289
0.013
1.763

0.604
-0.139
0.085
1.716

0.622
-0.159
0.072
1.750

0.761
-0.317
-0.034
2.020

0.948
-0.373
0.046
3.089

0.961
-0.388
0.036
3.122

1.030
-0.467
-0.013
3.294

1.066
-0.508
-0.038
3.382

1.068
-0.511
-0.039
3.387

1.066
-0.508
-0.038
3.382

1.030
-0.467
-0.013
3.294

0.962
-0.389
0.036
3.124

0.949
-0.373
0.045
3.091

0.762
-0.318
-0.035
2.022

0.623
-0.160
0.071
1.753

0.605
-0.140
0.084
1.719

Total Effect of Stage-II Cables


Total Nos. of Cables
Total Area of Prestress
Total Prestress Force after (friction+slip)
( Ps . cos )
( Ps . sin )
cg of Stage-I cables from soffit (Y-ord)
For Non-Composite Section
Ecc. of Cables for Non-Composite Sec.
Prestressing Factor (Top)= (1/A - e/Zt)
Prestressing Factor (Bottom)= (1/A+e/Zb)

For Composite Section


Ecc. of Cables for Composite Section
Pres. Factor (Slab Top)= (1/A - e/Zts)
Pres. Factor (Girder Top)= (1/A - e/Zbs)
Prestressing Factor (Bottom)= (1/A+e/Zb)

(16)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

SHRINKAGE MODEL (microstrain)


Total Shrinkage Strain
cs
Drying Shrinkage Strain
Basic Drying Shrinkage Strain

cd.0 =

259.8

cd =

ds t,ts x kh x cd.0

Autogenous Shrinkage Strain


Total Shrinkage Strain cs
Coeff. for drying SH strain

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

ca
Where,

(Refer eq. 6.14)

cd
ca
ts

ds1

ds2

RH

Girder+Slab Autogenous Shrinkage Strain


Total Shrinkage Strain cs
Coeff. for drying SH strain

Girder+Slab Autogenous Shrinkage Strain


Total Shrinkage Strain cs
Coeff. for drying SH strain

Girder+Slab Autogenous Shrinkage Strain


Total Shrinkage Strain cs
Coeff. for drying SH strain

Girder+Slab Autogenous Shrinkage Strain


Total Shrinkage Strain cs

Girder+Slab Autogenous Shrinkage Strain


cs

Col.- 7

Col.- 8

Col.- 9

Col.- 10

Col.- 11

Col.- 12

Col.- 14

Col.- 15

Col.- 16

ds(t,ts)

0.0071

0.0071

0.0071

0.0121

0.0121

0.0121

0.0121

0.0121

0.0121

0.0121

0.0121

0.0121

0.0071

0.0071

0.0071

as(t,ts)

1.3
0.41

1.3
0.41

1.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

2.3
0.41

1.3
0.41

1.3
0.41

1.3
0.41

26.71

26.71

26.71

26.71

26.71

26.71

26.71

26.71

ds(t,ts)

27.99
0.0426

27.99
0.0426

27.99
0.0426

28.99
0.0713

28.99
0.0713

28.99
0.0713

28.99
0.0713

28.99
0.0713

26.71
28.99
0.0713

26.71
28.99
0.0713

26.71
28.99
0.0713

26.71
28.99
0.0713

26.71
27.99
0.0426

26.71
27.99
0.0426

26.71
27.99
0.0426

as(t,ts)

7.8
0.65

7.8
0.65

7.8
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

13.4
0.65

7.8
0.65

7.8
0.65

7.8
0.65

ds(t,ts)

42.44
50.19
0.0539

42.44
50.19
0.0539

42.44
50.19
0.0539

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
55.86
0.0895

42.44
50.19
0.0539

42.44
50.19
0.0539

42.44
50.19
0.0539

16.8
0.69

16.8
0.69

16.8
0.69

16.8
0.69

9.8
0.69

9.8
0.69

9.8
0.69

45.09
61.93
0.1238

45.09
61.93
0.1238

45.09
61.93
0.1238

45.09
61.93
0.1238

45.09
54.90
0.0757

45.09
54.90
0.0757

45.09
54.90
0.0757

23.3
0.75

23.3
0.75

23.3
0.75

23.3
0.75

13.8
0.75

13.8
0.75

13.8
0.75

9.8

9.8

9.8

16.8

16.8

16.8

16.8

16.8

0.69
45.09

0.69
45.09

0.69
45.09

0.69
45.09

0.69
45.09

0.69
45.09

0.69
45.09

0.69
45.09

as(t,ts)

54.90
0.0757
13.8
0.75

54.90
0.0757
13.8
0.75

54.90
0.0757
13.8
0.75

61.93
0.1238
23.3
0.75

61.93
0.1238
23.3
0.75

61.93
0.1238
23.3
0.75

61.93
0.1238
23.3
0.75

61.93
0.1238
23.3
0.75

ds(t,ts)

48.97
62.74
0.0965

48.97
62.74
0.0965

48.97
62.74
0.0965

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
72.26
0.1556

48.97
62.74
0.0965

48.97
62.74
0.0965

48.97
62.74
0.0965

as(t,ts)

17.6
0.80

17.6
0.80

17.6
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

29.3
0.80

17.6
0.80

17.6
0.80

17.6
0.80

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

51.71

ds(t,ts)

69.27
1.0

69.27
1.0

69.27
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

80.98
1.0

69.27
1.0

69.27
1.0

69.27
1.0

as(t,ts)

181.9
1.0

181.9
1.0

181.9
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

188.1
1.0

181.9
1.0

181.9
1.0

181.9
1.0

ca

ca

Right Anchor

Col.- 6

ca

Infinite days Coeff. for autogenous SH strain

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec
Col.- 5

ds(t,ts)

Coeff. for drying SH strain


Drying Shrinkage Strain cd

Age of concrete (in days) at start of Drying after Curing


coefficient which depends on the type of cement
coefficient which depends on the type of cement
(Refer Eq. A2-27)

Col.- 4

ca

At age t Drying Shrinkage Strain cd


( 63 days ) Coeff. for autogenous SH strain

Drying Shrinkage Strain


Autogenous Shrinkage Strain

Col.- 3

as(t,ts)

At age t Drying Shrinkage Strain cd


( 49 days ) Coeff. for autogenous SH strain

Col.- 2

ca

At age t Drying Shrinkage Strain cd


( 35 days ) Coeff. for autogenous SH strain

3
4.00
0.12
0.896

Col.- 1

ca

At age t Drying Shrinkage Strain cd


( 28 days ) Coeff. for autogenous SH strain

Total Shrinkage Strain

3.644 m

as t,ts x ca( )
Unit

At age t Drying Shrinkage Strain cd


( 7 days ) Coeff. for autogenous SH strain

At age t

3.350 m

Left Anchor. 0.000 L Sec

Description
Coeff. for drying SH strain

Girder only

1.850 m

(Refer Cl: 6.4.2.6 of IRC:112-2011)

Section under consideration

Item. No.

0.200 m

+
cd
(Refer Annexue A2.6 of IRC:112-2011)
cd.0

ca =

Right Anchor

0.000 m

Autogenous Shrinkage Strain

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

65.00

246.88

246.88

246.88

253.08

253.08

253.08

253.08

253.08

253.08

253.08

253.08

253.08

246.88

246.88

246.88

(17)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit
Differential Shrinkage Strain
Differential Shrinkage Strain
Differential Shrinkage Strain
Differential Shrinkage Strain
Differential Shrinkage Strain

( upto 7 days )
( from 7 to 28 days )
( from 28 to 35 days )
( from 35 to 49 days )
( from 49 to 63 days )
( from 63 to infinity )

Differential Shrinkage Strain

CREEP MODEL (microstrain)


Total Creep Strain
Type of Cement Used

t =
t0 =
t - t0 =

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

27.99
22.20
4.70
7.85
6.53

27.99
22.20
4.70
7.85
6.53

27.99
22.20
4.70
7.85
6.53

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

28.99
26.87
6.07
10.33
8.72

27.99
22.20
4.70
7.85
6.53

27.99
22.20
4.70
7.85
6.53

27.99
22.20
4.70
7.85
6.53

177.61

177.61

177.61

172.09

172.09

172.09

172.09

172.09

172.09

172.09

172.09

172.09

177.61

177.61

177.61

(Refer Cl: 6.4.2.7 of IRC:112-2011)


=

0.00

coefficient which depends on the type of cement

0.852

coefficient (Refer eq. A2-24 of IRC:112-2011)

0.955

coefficient (Refer eq. A2-24 of IRC:112-2011)

0.892

coefficient (Refer eq. A2-24 of IRC:112-2011)

(fcm)

2.532

Factor to allow for the effect of concrete strength on the


notional creep coefficient (Refer eq. A2-18 of IRC:1122011)

(Refer Annexue A2.5 of IRC:112-2011)

Age of the conc. in days at the moment considered


Age of the concrete at loading in days
Non adjusted duration of loading in days

Section under consideration

Item. No.

0.200 m

cc
t,t0

Right Anchor

0.000 m

Normal Portland Cement

Creep Coefficient
Where,

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Left Anchor. 0.000 L Sec

Description

Unit

In eq. A2-22 & Eq. A2-23 fck will be changed to 45 MPa

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Col.- 1

Col.- 2

Col.- 3

Col.- 4

Col.- 5

Col.- 6

Col.- 7

Col.- 8

Col.- 9

Col.- 10

Col.- 11

Col.- 12

Col.- 14

Col.- 15

Right Anchor
Col.- 16

Girder Only coefficient (Refer eq. A2-16 & 17)

RH

1.30

1.30

1.30

1.34

1.34

1.34

1.34

1.34

1.34

1.34

1.34

1.34

1.30

1.30

1.30

From age t coefficient (Refer eq. A2-22 & 23)


( 7 days ) Temperature adjusted Conc. Age
Age of Concrete at Loading
to
Infinity Factor (Refer eq. A2-19)

1253.93

1253.93

1253.93

947.96

947.96

947.96

947.96

947.96

947.96

947.96

947.96

947.96

1253.93

1253.93

1253.93

Creep Coefficient
Creep Coefficient, (t,t0)

t0,T

days

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

t0

days

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

8.79

(t0)

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

0.6081

( ,t0)

2.001

2.001

2.001

2.061

2.061

2.061

2.061

2.061

2.061

2.061

2.061

2.061

2.001

2.001

2.001

0.584

0.584
0.005

0.584
0.040

0.653
0.038

0.653
0.008

0.653
0.067

0.653
0.080

0.653
0.080

0.653
0.080

0.653
0.080

0.653
0.067

0.653
0.008

0.584
0.038

0.584
0.040

0.584
0.005

0.635
0.005

0.635
0.043

0.710
0.042

0.710
0.009

0.710
0.073

0.710
0.087

0.710
0.087

0.710
0.087

0.710
0.087

0.710
0.073

0.710
0.009

0.635
0.042

0.635
0.043

0.635
0.005

0.715
0.006

0.715
0.049

0.798
0.047

0.798
0.010

0.798
0.082

0.798
0.098

0.798
0.098

0.798
0.098

0.798
0.098

0.798
0.082

0.798
0.010

0.715
0.047

0.715
0.049

0.715
0.006

for ( (t,t0) from 7 to 28 days)

Refer eq. A2-21

0.638

Weighted Value of Creep Coefficient, (t,t0)


Creep Coefficient, (t,t0)

for ( (t,t0) from 7 to 35 days)

Refer eq. A2-21

0.635

Refer eq. A2-21

0.694
0.715

Refer eq. A2-21

0.781
0.777

Weighted Value of Creep Coefficient, (t,t0)


Creep Coefficient, (t,t0)

for ( (t,t0) from 7 to 49 days)

Weighted Value of Creep Coefficient, (t,t0)


Creep Coefficient, (t,t0)

for ( (t,t0) from 7 to 63 days)

Weighted Value of Creep Coefficient, (t,t0)


Creep Coefficient, (t,t0)

for ( (t,t0)

from 7 to Infinity) Refer eq. A2-21

Weighted Value of Creep Coefficient, (t,t0)

0.848
2.001

0.777

0.777

0.867

0.867

0.867

0.867

0.867

0.867

0.867

0.867

0.867

0.777

0.777

0.777

0.006

0.053

0.051

0.011

0.090

0.107

0.107

0.107

0.107

0.090

0.011

0.051

0.053

0.006

2.001
0.017

2.001
0.137

2.061
0.126

2.061
0.025

2.061
0.213

2.061
0.253

2.061
0.253

2.061
0.253

2.061
0.253

2.061
0.213

2.061
0.025

2.001
0.126

2.001
0.137

2.001
0.017

2.048

(18)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CALCULATION OF LOSS OF PRESTRESS


Elastic Shortening Loss
fcg_avg.

Fp_ES

0.5 x (Ep / Ecm(t)) fcg_avg x Ap

Ap
Ep

Avg. conc. stresses at the center of gravity of prestressing tendons due to

Ecm(t)

prestressing force and the self weight of the member. (MPa)


Left Anchorage 0.000 L Sec

Section under consideration


Dist. of Section 'X' from Left Side Jacking End

Description

Units

1678 mm^2 (Area of prestressing steel)


195000 MPa (modulus of elasticity of prestressing steel)
31543 MPa (Secant modulus of elasticity of concrete at 7 Days )

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

Col.- 1

Col.- 2

Col.- 3

Col.- 4

Col.- 5

Col.- 6

Col.- 7

Col.- 8

Col.- 9

Col.- 10

Col.- 11

Col.- 12

Col.- 14

Col.- 15

Col.- 16

DETAILS OF STAGE-I PRESTRESS BEFORE INSTANTANEOUS LOSS

( At

7 days )

Stresses due to Pres. after Friction+Slip


ft_girder
At Top of Precast Girder
fb_girder
At Bottom of Precast Gir.

MPa

2.440

2.290

1.079

0.996

0.800

-0.529

-1.290

-1.344

-1.311

-0.546

0.816

1.018

1.104

2.349

2.504

MPa

1.026

1.191

2.527

4.899

5.115

6.593

7.484

7.592

7.608

6.764

5.254

5.033

2.600

1.228

1.060

Stress due to Self Weight of Girder Only Ist Stage


ft_girder
fb_girder
At Bott. of Precast Gir.

MPa

0.000

-0.005

1.050

2.203

2.366

3.528

4.394

4.699

4.394

3.528

2.366

2.203

1.050

-0.005

0.000

MPa

0.000

0.006

-1.136

-2.309

-2.480

-3.697

-4.605

-4.925

-4.605

-3.697

-2.480

-2.309

-1.136

0.006

0.000

At Top of Precast Girder

Stress due to Pres. after Friction+Slip + Self Weight of Girder


ft_girder
MPa
fb_girder
At Bott. of Precast Gir.
MPa

2.440

2.284

2.129

3.199

3.166

2.999

3.104

3.356

3.084

2.982

3.183

3.221

2.155

2.344

2.504

1.026

1.196

1.391

2.590

2.635

2.896

2.879

2.667

3.003

3.067

2.774

2.724

1.464

1.234

1.060

Stress at cg. of Stage-I Cables

1.861

1.821

1.722

2.804

2.813

2.919

2.915

2.775

3.016

3.048

2.910

2.898

1.773

1.871

1.911

0.356

0.373

0.308

0.035

0.145

0.124

0.016

0.630 %

0.634 %

0.642 %

0.643 %

0.649 %

0.654 %

0.654 %

At Top of Precast Girder

MPa

Maximum Stress at cg. of Stage-I Cables

fcgp

3.048

MPa

Avg. Stress at cg. of Stage-I Cables

0.015

MPa

0.121

0.141

0.034

0.296

0.359

Fp_ES

0.50

195000

x 2.672

x 1677.9

0.672 %

0.672 %

0.667 %

0.350

2.672

fcg_avg
MPa
LOSS OF PRESTRESS DUE TO ELASTIC SHORTENING STAGE-I CABLES
13858.7 N

0.014 MN

31543

% of Elastic Shortening Loss

Stress due to Elastic Shortening Loss of Stage-I Cables


ft_girder
At Top of Precast Girder
MPa
fb_girder
At Bott. of Precast Gir.
MPa

0.660 %

0.659 %

0.650 %

0.640 %

0.635 %

-0.016

-0.015

-0.007

-0.007

-0.005

0.003

0.008

0.009

0.008

0.003

-0.005

-0.007

-0.007

-0.015

-0.016

-0.007

-0.008

-0.017

-0.032

-0.034

-0.043

-0.048

-0.048

-0.048

-0.043

-0.034

-0.032

-0.017

-0.008

-0.007

Stress due to Pres. after Friction+Slip + Elastic Shortening from Stage-I Cables
ft_girder
MPa
2.424
2.274
fb_girder
At Bott. of Precast Gir.
MPa
1.020
1.183

1.072

0.989

0.794

-0.525

-1.282

-1.335

-1.302

-0.542

0.811

1.011

1.097

2.333

2.487

2.510

4.867

5.081

6.551

7.436

7.544

7.560

6.722

5.220

5.000

2.583

1.220

1.053

At Top of Precast Girder

(19)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

DETAILS OF STAGE-I PRESTRESS AFTER INSTANTANEOUS LOSS

( At

7 days )

Net Stress in Girder after Losses due to Friction+Slip + Elastic Shortening of Stage-I Cables
ft_girder
At Top of Precast Girder
MPa
2.424
2.269
2.122
fb_girder
At Bott. of Precast Gir.
MPa
1.020
1.188
1.375

3.193

3.161

3.003

3.112

3.364

3.092

2.986

3.178

3.215

2.147

2.328

2.487

2.558

2.602

2.854

2.831

2.619

2.955

3.025

2.740

2.691

1.447

1.226

1.053

Stress at cg. of Stage-I Cables

2.780

2.788

2.887

2.876

2.736

2.977

3.016

2.886

2.875

1.760

1.859

1.899

0.351

0.368

0.305

0.035

0.144

0.124

0.016

2.187

2.173

2.143

2.140

2.121

2.107

2.106

1.848

MPa

Maximum Stress at cg. of Stage-I Cables

fcgp

MPa

fcg_avg

MPa

Pres. Force of Stage-I Cables after (F+S+ES) Loss

MN

Avg. Stress at cg. of Stage-I Cables

as a fraction of U.T.S.

( UTS

1.809

1.709

3.016
0.015

MPa

0.120

0.139

0.034

0.293

0.354

0.345

2.643

= 2.203 MN )

2.048

2.049

0.656 UTS

0.657 UTS

1.955 %

1.958 %

2.065

2.084

0.662 UTS 0.668 UTS

2.088
0.669 UTS

2.119

2.151

2.170

0.679 UTS 0.689 UTS 0.695 UTS 0.701 UTS 0.696 UTS 0.687 UTS 0.686 UTS 0.680 UTS 0.675 UTS 0.675 UTS

For Low Relaxation Steel (As per Table 6.2 of IRC: 112-2011)
1000 hr. relaxation Loss Stage-I Pres. Force

(1)

LOSS OF PRESTRESS

From 7 days to

28 days

2.020 %

2.099 %

2.114 %

2.236 %

2.367 %

2.440 %

2.518 %

2.452 %

2.335 %

2.321 %

2.245 %

2.188 %

2.184 %

FOR STAGE-I PRESTRESS

SHRINKAGE LOSS IN PRESTRESS


Differential Shrinkage Strain

0.00005

( upto 28 days )

cs

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between

( upto 28 days )

0.00005

0.00006

0.00006

0.00006

0.00006

0.00006

0.00006

0.00006

0.00006

0.00006

0.00005

0.00005

MN

0.016

0.016

0.00005

0.016

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.016

0.016

0.00005
0.016

0.802 %

0.801 %

0.795 %

0.877 %

0.875 %

0.863 %

0.850 %

0.842 %

0.836 %

0.841 %

0.853 %

0.854 %

0.774 %

0.780 %

0.780 %

CREEP LOSS IN PRESTRESS


Weighted Value of Creep Coefficient, (t,t0)

( at 28 days )

Eff. Elastic Modulus of Concrete, Ec,eff

( at 28 days )

Stress Loss due to Creep

Creep Loss between

( 7 day to 28 day )

0.638
Ecm

(t,t0) x

Stress Loss due to Creep


34000 MPa

Avg. Stress at cg. of Prestress cp

(Ep / Ec,eff) x

cp x Ap

2.560 MPa

MN

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.767 %

0.767 %

0.761 %

0.754 %

0.753 %

0.742 %

0.731 %

0.724 %

0.719 %

0.723 %

0.733 %

0.735 %

0.741 %

0.746 %

0.746 %

500 hrs as % of 1000 hrs relax..loss

90.0%
100.0%

LOSS DUE TO RELAXATION OF STEEL

For
Stage-I
Cables

Age of concrete between


7 day &
28 day
Time in hours after transfer of prestress
Relaxation Loss as % of loss at 1000 hrs.

=
=
=

21 days
504 hrs.
90.08 %

Relax. Loss for


Relax. Loss for

1000 hrs as % of 1000 hrs relax..loss

(Refer Table 6.3 of IRC: 112-2011)

% Relaxation Loss

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

Relaxation Loss

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

Relaxation Loss between

( 7 day to 28 day )

1.761 %

1.764 %

1.819 %

1.891 %

1.904 %

2.014 %

2.132 %

2.198 %

2.268 %

2.209 %

2.103 %

2.090 %

2.022 %

1.971 %

1.968 %

MN

0.036

0.036

0.038

0.039

0.040

0.043

0.046

0.048

0.050

0.048

0.045

0.045

0.043

0.042

0.041

3.330 %

3.332 %

3.376 %

3.521 %

3.532 %

3.619 %

3.712 %

3.765 %

3.822 %

3.774 %

3.689 %

3.679 %

3.538 %

3.496 %

3.494 %

MN

0.068

0.068

0.070

0.073

0.074

0.077

0.080

0.082

0.084

0.082

0.079

0.079

0.075

0.074

0.074

TOTAL PRESTRESS LOSS


TOTAL PRESTRESS LOSS ( 7 day to 28 day )
(SH + CR + RLEX)

(20)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Stress due to Total (S + C + R) Loss between


At Top of Precast Girder
ft_girder
At Bott. of Precast Gir.
fb_girder

NET STRESS IN GIRDER


At Top of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

fb_girder

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

-0.076
-0.039

-0.036
-0.085

-0.035
-0.171

-0.028
-0.179

0.019
-0.237

0.048
-0.276

0.050
-0.284

0.050
-0.289

0.020
-0.254

-0.030
-0.193

-0.037
-0.184

-0.039
-0.091

-0.082
-0.043

-0.087
-0.037

JUST BEFORE STAGE-II PRESTRESS


0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

2.343
0.986

2.193
1.149

2.086
1.290

3.158
2.386

3.133
2.422

3.022
2.617

3.160
2.555

3.415
2.335

3.142
2.666

3.006
2.771

3.148
2.548

3.178
2.507

2.109
1.356

2.247
1.183

2.400
1.016

1.787

1.749

1.646

2.657

2.659

2.707

2.652

2.505

2.742

2.823

2.748

2.742

1.693

1.794

1.832

0.015

0.116

0.134

0.032

0.277

0.329

0.317

0.323

0.342

0.288

0.033

0.138

0.119

0.015

1.492

1.482

2.529

2.548

2.671

2.622

2.454

2.719

2.802

2.653

2.631

1.537

1.532

1.485

0.012

0.102

0.125

0.031

0.269

0.325

0.312

0.318

0.339

0.282

0.032

0.129

0.105

0.012

2.477
1.447

2.394

MPa

NET STRESS IN GIRDER


( At 28 days )
Stresses due to Stage-II Prestress. after Friction+Slip
ft_slab
At Top of Deck Slab
MPa
ft_girder
At Top of Precast Girder
MPa
At Bott. of Precast Gir.

0.200 m

MPa

Stress at cg. of Stage-II Cables

MPa

Right Anchor

0.000 m

( 7 day to 28 day )
MPa
-0.081
MPa
-0.034

( At 28 days )
ft_slab
MPa
ft_girder
MPa
fb_girder
MPa

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

JUST AFTER PRESTRESSING OF STAGE-II CABLES & JUST BEFORE ES LOSS OF STAGE-II
0.000
0.071

0.000
-0.144

0.000
-1.852

0.000
-1.951

0.000
-2.153

0.000
-3.216

0.000
-3.791

0.000
-3.848

0.000
-3.841

0.000
-3.296

0.000
-2.233

0.000
-2.025

0.000
-1.925

0.000
-0.164

0.000
0.057

7.341

7.576

9.479

14.074

14.307

15.549

16.267

16.413

16.491

15.936

14.766

14.528

9.796

7.840

7.597
0.000

Net Stress in Girder just before ES Loss of Stage-II Prestress


At Top of Deck Slab

ft_slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

At Top of Precast Girder

ft_girder
fb_girder

MPa

2.414

2.049

0.233

1.207

0.979

-0.195

-0.631

-0.433

-0.699

-0.290

0.915

1.152

0.184

2.083

2.458

MPa

8.326

8.725

10.769

16.460

16.729

18.165

18.822

18.748

19.157

18.706

17.314

17.035

11.152

9.023

8.613

Stress at cg. of Stage-I Cables

MPa

4.836

4.890

6.053

11.112

11.471

14.082

15.697

15.732

15.965

14.487

11.844

11.473

6.247

5.039

4.983

Avg. Stress at cg. of Stage-I Cables

MPa

0.040

0.374

0.533

0.137

1.319

1.830

1.932

1.948

1.872

1.360

0.142

0.550

0.386

0.041

At Bott. of Precast Gir.

fcg_avg

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

12.465

MPa

Stress at cg. of Stage-II Cables

6.317

6.530

8.222

13.640

13.948

15.711

16.654

16.633

16.941

16.167

14.426

14.107

8.508

6.746

6.526

0.053

0.504

0.679

0.168

1.531

1.989

2.046

2.064

2.035

1.580

0.174

0.702

0.521

0.055

14.100

MPa

Increase in Average Stress at cg. of Stage-I Cables

MPa

9.987

Increase in Average Stress at cg. of Stage-II Cables

MPa

11.707

(21)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

4.366 %

4.395 %

4.455 %

4.463 %

4.502 %

4.532 %

4.534 %

ADDN. LOSS OF PRESTRESS DUE TO ELASTIC SHORTENING FROM STAGE-I CABLES


Fp_ES

1.00

195000

x 9.987

x 1677.9

34000

Elastic Shortening Loss due to Stage-I Cables

96108.9 N
Ec,eff

4.660 %

4.658 %

4.624 %

=
=

4.580 %

0.096 MN
Ecm / (1 + )

4.572 %

4.507 %

34000 MPa
4.439 %

4.402 %

Stress due to Stage-I Pres. after Additional Elastic Shortening from Stage-II
At Top of Deck Slab

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

At Top of Precast Girder

-0.037

0.024

0.057

0.059

0.057

0.024

-0.036

-0.045

-0.050

-0.106

-0.114

-0.234

-0.297

-0.332

-0.334

-0.332

-0.297

-0.234

-0.225

-0.117

-0.056

-0.048

2.577 %

2.559 %

2.556 %

2.568 %

2.572 %

2.595 %

2.613 %

2.614 %

ft_slab
MPa
0.000
0.000
0.000
0.000
ft_girder
MPa
-0.114
-0.107
-0.050
-0.046
fb_girder
At Bott. of Precast Gir.
MPa
-0.048
-0.055
-0.117
-0.224
LOSS OF PRESTRESS DUE TO ELASTIC SHORTENING FROM STAGE-II CABLES
Fp_ES

0.50

195000

x 11.707

x 3355.8

2.699 %

2.698 %

2.678 %

112655.0 N

0.113 MN

34000

Elastic Shortening Loss due to Stage-II Cables

Stress due to Stage-II Pres. after Elastic Shortening Loss due to Stage-II Cables
ft_slab
At Top of Deck Slab
MPa
0.000
0.000
ft_girder
At Top of Precast Girder
MPa
-0.002
0.004
fb_girder
At Bott. of Precast Gir.
MPa
-0.198
-0.204

2.652 %

2.648 %

2.620 %

2.595 %

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.050

0.052

0.057

0.084

0.098

0.099

0.098

0.084

0.057

0.052

0.050

0.004

-0.001

-0.254

-0.373

-0.379

-0.407

-0.422

-0.423

-0.422

-0.407

-0.379

-0.374

-0.254

-0.205

-0.199

0.000

NET STRESS IN GIRDER


( At 28 days )
JUST AFTER PRESTRESSING OF STAGE-II CABLES & JUST AFTER ES LOSS OF STAGE-II
Net Stress in Girder after Losses due to Friction+Slip + Elastic Shortening of Stage-II Cables
ft_slab
At Top of Deck Slab
MPa
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
ft_girder
At Top of Precast Girder
MPa
2.298
1.946
0.233
1.213
1.000
-0.086
-0.475
-0.275
fb_girder
At Bott. of Precast Gir.
MPa
8.080
8.465
10.398
15.862
16.117
17.461
18.068
17.991
Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

Pres. Force of Stage-II Cables after (F+S+ES) Loss


as a fraction of U.T.S.

( UTS

4.720

5.848

10.726

11.070

13.558

15.088

0.039

0.361

0.515

0.133

1.272

1.761

6.115

MN

0.000

0.000

0.000

0.000

0.936

1.159

0.184

1.980

2.343

15.119

18.403
15.357

18.002
13.963

16.701
11.443

16.437
11.086

10.781
6.042

8.763
4.870

8.367
4.814

1.857

1.873

1.802

1.312

0.137

0.532

0.373

0.040

6.321

7.941

13.154

13.447

15.115

16.001

15.977

16.289

15.571

13.924

13.620

8.226

6.538

6.324

0.051

0.487

0.655

0.162

1.475

1.913

1.966

1.983

1.958

1.523

0.168

0.678

0.504

0.053

4.289

4.295

4.275

4.268

4.229

4.199

4.198

13.576

MPa

= 2.203 MN )

0.000
-0.182

12.005

MPa

Stress at cg. of Stage-II Cables

fcg_avg

4.667

0.000
-0.544

4.061

4.063

0.651 UTS

0.651 UTS

1.883 %

1.887 %

4.095

4.135

0.656 UTS 0.662 UTS

4.142
0.664 UTS

4.188

4.229

4.259

0.671 UTS 0.677 UTS 0.682 UTS 0.687 UTS 0.688 UTS 0.685 UTS 0.684 UTS 0.678 UTS 0.673 UTS 0.672 UTS

For Low Relaxation Steel (As per Table 6.2 of IRC: 112-2011)
1000 hr. relaxation Loss Stage-II Pres. Force

1.950 %

2.030 %

2.046 %

2.136 %

(22)

2.218 %

2.279 %

2.339 %

2.350 %

2.311 %

2.297 %

2.219 %

2.160 %

2.156 %

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

(2)

LOSS OF PRESTRESS

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.000005

From 28 days to

FOR STAGE-I & STAGE-II PRESTRESS

35 days

SHRINKAGE LOSS IN PRESTRESS


FOR STAGE-1 CABLES
Differential Shrinkage Strain cs

( from 28 to 35 days )

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between


FOR STAGE-2 CABLES

( from 28 to 35 days )

Differential Shrinkage Strain cs

0.000005

0.000005

0.000005

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000005

0.000005

MN

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.075 %

0.075 %

0.075 %

0.095 %

0.095 %

0.094 %

0.092 %

0.092 %

0.091 %

0.091 %

0.093 %

0.093 %

0.073 %

0.073 %

0.073 %

( from 28 to 35 days )

0.000005

0.000005

0.000005

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000006

0.000005

0.000005

0.000005

MN
%

0.003
0.076 %

0.003
0.076 %

0.003
0.075 %

0.004
0.096 %

0.004
0.096 %

0.004
0.095 %

0.004
0.094 %

0.004
0.093 %

0.004
0.093 %

0.004
0.092 %

0.004
0.093 %

0.004
0.093 %

0.003
0.073 %

0.003
0.073 %

0.003
0.073 %

Weighted Value of Creep Coefficient, (t2,t0) ( at 35 days )

0.694

Stress Loss due to Creep = { (t2,t0) - (t1,t0) } x (Ep / Ec,eff) x

Weighted Value of Creep Coefficient, (t1,t0) ( at 28 days )

0.638

Avg. Stress at cg. of Prestress of Stage-1 cp1

11.868 MPa

( at 35 days )

Avg. Stress at cg. of Prestress of Stage-2 cp2

13.415 MPa

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between

( from 28 to 35 days )

CREEP LOSS IN PRESTRESS

Eff. Elastic Modulus of Concrete, Ec,eff

FOR STAGE-1 CABLES

Stress Loss due to Creep for Stage-I Cables

Creep Loss between


FOR STAGE-2 CABLES

( from 28 to 35 days )

Stress Loss due to Creep for Stage-II Cables

Creep Loss between

( from to days )

Ecm

34000 MPa

cp x Ap

(Ap : Area of Prestress)

MN

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.313 %

0.312 %

0.310 %

0.307 %

0.307 %

0.302 %

0.298 %

0.295 %

0.293 %

0.295 %

0.299 %

0.299 %

0.302 %

0.304 %

0.304 %

MN

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.356 %

0.356 %

0.354 %

0.350 %

0.349 %

0.346 %

0.342 %

0.340 %

0.338 %

0.337 %

0.339 %

0.339 %

0.342 %

0.345 %

0.345 %

35 day

LOSS DUE TO RELAXATION OF STEEL


Age of concrete between

For
Stage-I
Cables

7 day &

Time in hours after transfer of prestress

Relaxation Loss as % of loss at 1000 hrs.

93.44 %

Relax. Loss for

500 hrs as % of 1000 hrs relax..loss

90.0%

Relax. Loss for

1000 hrs as % of 1000 hrs relax..loss

100.0%

(Refer Table 6.3 of IRC: 112-2011)

Relaxation Loss between

28 day &

35 day

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 28 day to 35 day )
For Stage-I Cables
Age of concrete between

For
Stage-II
Cables

28 days
672 hrs.

28 day &

93.44 %

-90.08 %

3.36 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

0.066 %

0.066 %

0.068 %

0.071 %

0.071 %

0.075 %

0.080 %

0.082 %

0.085 %

0.082 %

0.078 %

0.078 %

0.075 %

0.074 %

0.073 %

MN

0.001

0.001

0.001

0.001

0.001

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

35 day

Time in hours after transfer of prestress

Relaxation Loss as % of loss at 1000 hrs.

7 days
168 hrs.
76.76 %

Relax. Loss for

100 hrs as % of 1000 hrs relax..loss

72.0%

Relax. Loss for

200 hrs as % of 1000 hrs relax..loss

79.0%

(Refer Table 6.3 of IRC: 112-2011)

% Relaxation Loss

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

Relaxation Loss

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

Relaxation Loss between


( 28 day to 35 day )
For Stage-II Cables

1.445 %

1.448 %

1.497 %

1.559 %

1.570 %

1.640 %

1.703 %

1.750 %

1.796 %

1.804 %

1.774 %

1.763 %

1.704 %

1.658 %

1.655 %

MN

0.059

0.059

0.061

0.064

0.065

0.069

0.072

0.075

0.077

0.077

0.076

0.075

0.072

0.070

0.069

(23)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.451 %

TOTAL PRESTRESS LOSS (Shrinkage + Creep + Relaxation)


TOTAL PRESTRESS LOSS ( 28 day to 35 day )
For Stage-I Cables

TOTAL PRESTRESS LOSS ( 28 day to 35 day )


For Stage-II Cables

Stress due to Total (S + C + R) Loss between


ft_slab
At Top of Deck Slab
ft_girder
At Top of Precast Girder
fb_girder
At Bott. of Precast Gir.
Stress in Girder due to Wt. of Shuttering on Girder
ft_girder
fb_girder

At Top of Precast Girder


At Bott. of Precast Gir.

NET STRESS IN GIRDER


At Top of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

0.453 %

0.453 %

0.453 %

0.473 %

0.473 %

0.471 %

0.469 %

0.469 %

0.468 %

0.469 %

0.470 %

0.470 %

0.450 %

0.451 %

MN

0.009

0.009

0.009

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.009

0.009

1.878 %

1.880 %

1.925 %

2.005 %

2.016 %

2.080 %

2.139 %

2.183 %

2.226 %

2.234 %

2.206 %

2.195 %

2.119 %

2.076 %

2.073 %

MN

0.076

0.076

0.079

0.083

0.083

0.087

0.090

0.093

0.095

0.096

0.094

0.094

0.090

0.087

0.087

( 28 day to 35 day )
MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

-0.012

-0.008

0.030

0.033

0.038

0.068

0.085

0.088

0.089

0.074

0.044

0.039

0.035

-0.007

-0.012

MPa

-0.139

-0.144

-0.189

-0.298

-0.305

-0.346

-0.374

-0.384

-0.393

-0.378

-0.342

-0.334

-0.214

-0.164

-0.158

0.024
-0.026

0.051
-0.054

0.055
-0.058

0.084
-0.088

0.105
-0.110

0.112
-0.117

0.105
-0.110

0.084
-0.088

0.055
-0.058

0.051
-0.054

0.024
-0.026

0.000
0.000

0.000
0.000

0.000

( 28 day to 35 day )
MPa
MPa

( At 35 days )
ft_slab
MPa
ft_girder
MPa
fb_girder
MPa

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

JUST BEFORE CASTING OF DECK


0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

2.286

1.939

0.287

1.298

1.094

0.065

-0.286

-0.075

-0.350

-0.024

1.035

1.249

0.243

1.973

2.330

7.941

8.321

10.184

15.511

15.754

17.027

17.584

17.489

17.900

17.536

16.301

16.049

10.542

8.599

8.209

4.603

4.655

5.753

10.528

10.859

13.255

14.713

14.728

14.966

13.636

11.209

10.866

5.935

4.796

4.742

0.038

0.356

0.506

0.130

1.245

1.719

1.810

1.825

1.758

1.283

0.134

0.522

0.367

0.039

6.222

7.791

12.883

13.165

14.760

15.592

15.553

15.864

15.188

13.613

13.320

8.059

6.425

6.215

0.051

0.479

0.642

0.158

1.442

1.866

1.914

1.931

1.909

1.487

0.164

0.664

0.495

0.052

11.731
6.019

13.253

MPa

Stress in Girder due to Green Wt. of Deck Slab + Temporary Live Load
ft_girder
MPa
0.000
fb_girder
At Bott. of Precast Gir.
MPa
0.000
At Top of Precast Girder

NET STRESS IN GIRDER

0.000
0.000

MPa

Stress at cg. of Stage-II Cables

fcg_avg

0.000
0.000

At Top of Precast Girder

( At 35 days )
ft_girder
MPa

At Bott. of Precast Gir.

fb_girder

( At

35 days )

-0.005

1.384

2.985

3.217

4.868

6.087

6.493

6.087

4.868

3.217

2.985

1.384

-0.005

0.000

0.005

-1.496

-3.128

-3.371

-5.101

-6.378

-6.804

-6.378

-5.101

-3.371

-3.128

-1.496

0.005

0.000

JUST AFTER CASTING OF DECK SLAB


2.286

1.934

1.671

4.282

4.310

4.933

5.801

6.418

5.737

4.844

4.252

4.234

1.627

1.969

2.330

MPa

7.941

8.326

8.687

12.383

12.383

11.926

11.206

10.685

11.521

12.434

12.930

12.921

9.045

8.604

8.209

Stress at cg. of Stage-I Cables

MPa

4.603

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

5.546

9.543

9.688

10.371

10.338

10.014

10.591

10.748

10.035

9.879

5.727

4.795

4.742

0.348

0.469

0.117

1.036

1.273

1.251

1.267

1.312

1.073

0.121

0.485

0.359

0.039

6.224

6.991

10.885

10.957

10.991

10.604

10.215

10.876

11.419

11.402

11.319

7.257

6.427

6.215

0.051

0.451

0.555

0.133

1.133

1.327

1.280

1.296

1.370

1.178

0.138

0.577

0.467

0.052

9.188

MPa

Stress at cg. of Stage-II Cables

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

4.654
0.038

6.019

10.010

MPa

(24)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

(3)

LOSS OF PRESTRESS

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.000008

From 35 days to

BEFORE COMPOSITE ACTION

49 days

SHRINKAGE LOSS IN PRESTRESS


FOR STAGE-1 CABLES
Differential Shrinkage Strain cs

( from 35 to 49 days )

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between


FOR STAGE-2 CABLES

( from 35 to 49 days )

Differential Shrinkage Strain cs

0.000008

0.000008

0.000008

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000008

0.000008

MN

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.125 %

0.125 %

0.124 %

0.162 %

0.162 %

0.160 %

0.157 %

0.156 %

0.155 %

0.156 %

0.158 %

0.158 %

0.121 %

0.122 %

0.122 %

( from 35 to 49 days )

0.000008

0.000008

0.000008

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000010

0.000008

0.000008

0.000008

MN
%

0.005
0.126 %

0.005
0.126 %

0.005
0.125 %

0.007
0.164 %

0.007
0.163 %

0.007
0.161 %

0.007
0.160 %

0.007
0.159 %

0.007
0.158 %

0.007
0.157 %

0.007
0.158 %

0.007
0.158 %

0.005
0.121 %

0.005
0.122 %

0.005
0.122 %

Weighted Value of Creep Coefficient, (t2,t0) ( at 49 days )

0.781

Stress Loss due to Creep = { (t2,t0) - (t1,t0) } x (Ep / Ec,eff) x

Weighted Value of Creep Coefficient, (t1,t0) ( at 35 days )

0.694

Avg. Stress at cg. of Prestress of Stage-1 cp1

x 9.13

MPa

( at 49 days )

Avg. Stress at cg. of Prestress of Stage-2 cp2

x 9.94

MPa

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between

( from 35 to 49 days )

CREEP LOSS IN PRESTRESS

Eff. Elastic Modulus of Concrete, Ec,eff

FOR STAGE-1 CABLES

Stress Loss due to Creep for Stage-I Cables

Creep Loss between


FOR STAGE-2 CABLES

( from 35 to 49 days )

Stress Loss due to Creep for Stage-II Cables

Creep Loss between

( from 35 to 49 days )

Ecm

34000 MPa

cp x Ap

(Ap : Area of Prestress)

MN

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.008

0.371 %

0.371 %

0.368 %

0.365 %

0.364 %

0.359 %

0.354 %

0.351 %

0.348 %

0.350 %

0.355 %

0.355 %

0.359 %

0.361 %

0.361 %

MN

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.017

0.408 %

0.408 %

0.405 %

0.401 %

0.400 %

0.396 %

0.392 %

0.389 %

0.386 %

0.386 %

0.388 %

0.388 %

0.392 %

0.395 %

0.395 %

49 day

1000 hrs as % of 1000 hrs relax..loss

100.0%
100.0%

LOSS DUE TO RELAXATION OF STEEL


Age of concrete between

For
Stage-I
Cables

7 day &

Time in hours after transfer of prestress


Relaxation Loss as % of loss at 1000 hrs.

=
=

Relax. Loss for


Relax. Loss for

1000 hrs as % of 1000 hrs relax..loss

(Refer Table 6.3 of IRC: 112-2011)

Relaxation Loss between

35 day &

49 day

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 35 day to 49 day )
For Stage-I Cables
Age of concrete between

For
Stage-II
Cables

42 days
1008 hrs.
100.00 %

28 day &

100.00 %

-90.08 %

9.92 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

0.194 %

0.194 %

0.200 %

0.208 %

0.210 %

0.222 %

0.235 %

0.242 %

0.250 %

0.243 %

0.232 %

0.230 %

0.223 %

0.217 %

0.217 %

MN

0.004

0.004

0.004

0.004

0.004

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

49 day

Time in hours after transfer of prestress

Relaxation Loss as % of loss at 1000 hrs.

21 days
504 hrs.
90.08 %

Relax. Loss for

500 hrs as % of 1000 hrs relax..loss

90.0%

Relax. Loss for

1000 hrs as % of 1000 hrs relax..loss

100.0%

(Refer Table 6.3 of IRC: 112-2011)

Relaxation Loss between

35 day &

49 day

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 35 day to 49 day )
For Stage-II Cables

90.08 %

-76.76 %

13.32 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

0.251 %

0.251 %

0.260 %

0.270 %

0.272 %

0.285 %

0.295 %

0.304 %

0.312 %

0.313 %

0.308 %

0.306 %

0.296 %

0.288 %

0.287 %

MN

0.010

0.010

0.011

0.011

0.011

0.012

0.012

0.013

0.013

0.013

0.013

0.013

0.013

0.012

0.012

(25)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.700 %

TOTAL PRESTRESS LOSS (Shrinkage + Creep + Relaxation)


TOTAL PRESTRESS LOSS ( 35 day to 49 day )
For Stage-I Cables

TOTAL PRESTRESS LOSS ( 35 day to 49 day )


For Stage-II Cables

Stress due to Total (S + C + R) Loss between


ft_girder
fb_girder
At Bott. of Precast Gir.
At Top of Precast Girder

NET STRESS IN GIRDER


At Top of Precast Girder
At Bott. of Precast Gir.

0.691 %

0.691 %

0.693 %

0.735 %

0.736 %

0.740 %

0.746 %

0.748 %

0.752 %

0.749 %

0.744 %

0.744 %

0.702 %

0.700 %

MN

0.014

0.014

0.014

0.015

0.015

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.015

0.015

0.015

0.785 %

0.785 %

0.790 %

0.835 %

0.836 %

0.842 %

0.847 %

0.851 %

0.856 %

0.856 %

0.854 %

0.853 %

0.809 %

0.805 %

0.804 %

MN

0.032

0.032

0.032

0.035

0.035

0.035

0.036

0.036

0.037

0.037

0.036

0.036

0.034

0.034

0.034

( 35 day to 49 day )
MPa

-0.017

-0.015

0.007

0.009

0.012

0.030

0.041

0.042

0.042

0.032

0.013

0.009

0.007

-0.015

-0.018

MPa

-0.063

-0.066

-0.090

-0.150

-0.154

-0.176

-0.190

-0.193

-0.194

-0.183

-0.162

-0.158

-0.095

-0.070

-0.067

( At 49 days )
ft_girder
MPa
fb_girder
MPa

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

Stress in Composite Girder due to Removal of Shuttering


ft_slab
MPa
ft_girder
At Top of Precast Girder
MPa
fb_girder
At Bott. of Precast Gir.
MPa

NET STRESS IN GIRDER


At Top of Precast Girder
At Bott. of Precast Gir.

( At 49 days )
ft_slab
MPa
ft_girder
MPa
fb_girder
MPa

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

1.919

1.678

4.291

4.322

4.963

5.842

6.459

5.779

4.876

4.265

4.243

1.634

1.953

2.312

8.260

8.597

12.233

12.229

11.750

11.016

10.493

11.327

12.251

12.768

12.763

8.950

8.534

8.142

4.567

9.449

9.589

10.241

10.185

9.859

10.435

10.613

9.932

9.779

5.678

4.757

4.704

0.464

0.116

1.024

1.255

1.232

1.247

1.294

1.061

0.120

0.480

0.356

0.039

6.175

6.924

10.765

10.833

10.843

10.440

10.048

10.708

11.265

11.271

11.192

7.186

6.375

6.165

0.050

0.447

0.549

0.131

1.119

1.308

1.259

1.276

1.351

1.164

0.137

0.571

0.463

0.052

0.000

9.877

( At

49 days )

0.000

0.000

-0.009

-0.017

-0.018

-0.027

-0.034

-0.037

-0.034

-0.027

-0.018

-0.017

-0.009

0.000

0.000

0.000

-0.006

-0.010

-0.011

-0.017

-0.021

-0.023

-0.021

-0.017

-0.011

-0.010

-0.006

0.000

0.000

0.000

0.000

0.016

0.036

0.039

0.059

0.074

0.079

0.074

0.059

0.039

0.036

0.016

0.000

0.000

AFTER COMPOSITE ACTION & REMOVAL OF SHUTTERING


0.000

0.000

-0.009

-0.017

-0.018

-0.027

-0.034

-0.037

-0.034

-0.027

-0.018

-0.017

-0.009

0.000

0.000

2.268

1.919

1.671

4.280

4.311

4.946

5.821

6.437

5.757

4.859

4.253

4.232

1.628

1.954

2.312

7.878

8.260

8.613

12.269

12.268

11.809

11.090

10.572

11.401

12.310

12.807

12.800

8.966

8.534

8.142

4.567

4.618

5.505

9.469

9.611

10.283

10.244

9.922

10.494

10.655

9.954

9.799

5.684

4.757

4.704

0.038

0.346

0.465

0.116

1.027

1.262

1.239

1.255

1.300

1.064

0.120

0.481

0.357

0.039

9.109

MPa

Stress at cg. of Stage-II Cables

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

5.499
0.346

9.072
5.972

MPa

fcg_avg

4.618
0.038

MPa

At Top of Deck Slab

At Top of Deck Slab

2.268
7.878

MPa

Stress at cg. of Stage-II Cables

fcg_avg

JUST BEFORE COMPOSITE ACTION

5.972

6.175

6.935

10.792

10.863

10.892

10.503

10.116

10.772

11.314

11.301

11.220

7.197

6.375

6.165

0.050

0.448

0.551

0.132

1.123

1.315

1.267

1.284

1.357

1.168

0.137

0.572

0.464

0.052

9.919

MPa

(26)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

(3)

LOSS OF PRESTRESS

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.000007

From 49 days to

FOR STAGE-I & STAGE-II PRESTRESS

63 days

SHRINKAGE LOSS IN PRESTRESS


FOR STAGE-1 CABLES
Differential Shrinkage Strain cs

( from 49 to 63 days )

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between


FOR STAGE-2 CABLES

( from 49 to 63 days )

Differential Shrinkage Strain cs

0.000007

0.000007

0.000007

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000007

0.000007

MN

0.002

0.002

0.002

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.002

0.002

0.002

0.104 %

0.104 %

0.103 %

0.137 %

0.137 %

0.135 %

0.133 %

0.132 %

0.130 %

0.131 %

0.133 %

0.133 %

0.101 %

0.101 %

0.101 %
0.000007

( from 49 to 63 days )

0.000007

0.000007

0.000007

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000009

0.000007

0.000007

MN

0.004

0.004

0.004

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.004

0.004

0.004

0.105 %

0.105 %

0.104 %

0.138 %

0.138 %

0.136 %

0.135 %

0.134 %

0.133 %

0.133 %

0.134 %

0.134 %

0.101 %

0.102 %

0.102 %

Weighted Value of Creep Coefficient, (t2,t0) ( at 63 days )

0.848

Stress Loss due to Creep = { (t2,t0) - (t1,t0) } x (Ep / Ec,eff) x

Weighted Value of Creep Coefficient, (t1,t0) ( at 49 days )

0.781

Avg. Stress at cg. of Prestress of Stage-1 cp1

x 9.07

MPa

( at 63 days )

Avg. Stress at cg. of Prestress of Stage-2 cp2

x 9.88

MPa

Stress Loss due to Shrinkage

cs x Ep x Ap

Shrinkage Loss between

( from 49 to 63 days )

CREEP LOSS IN PRESTRESS

Eff. Elastic Modulus of Concrete, Ec,eff

FOR STAGE-1 CABLES

Stress Loss due to Creep for Stage-I Cables

Creep Loss between


FOR STAGE-2 CABLES

( from 49 to 63 days )

Stress Loss due to Creep for Stage-II Cables

Creep Loss between


( from 49 to 63 days )
LOSS DUE TO RELAXATION OF STEEL

For
Stage-I
Cables

Ecm

34000 MPa

(Ap : Area of Prestress)

MN

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.285 %

0.285 %

0.283 %

0.280 %

0.280 %

0.276 %

0.272 %

0.269 %

0.267 %

0.269 %

0.273 %

0.273 %

0.276 %

0.277 %

0.278 %

MN

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.313 %

0.313 %

0.311 %

0.308 %

0.307 %

0.304 %

0.301 %

0.299 %

0.297 %

0.296 %

0.298 %

0.298 %

0.301 %

0.303 %

0.303 %

1000 hrs as % of 1000 hrs relax..loss


1000 hrs as % of 1000 hrs relax..loss

100.0%
100.0%

Age of concrete between


7 day &
63 day
Time in hours after transfer of prestress
Relaxation Loss as % of loss at 1000 hrs.

=
=
=

56 days
1344 hrs.
100.00 %

Relax. Loss for


Relax. Loss for

(Refer Table 6.3 of IRC: 112-2011)

Relaxation Loss between

49 day &

63 day

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 49 day to 63 day )
For Stage-I Cables
Age of concrete between

For
Stage-II
Cables

cp x Ap

28 day &

100.00 %

-100.00 %

0.00 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

0.000 %

MN

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

63 day

0.157 %
0.007

0.158 %
0.007

0.155 %
0.007

0.154 %
0.007

0.149 %
0.006

0.145 %
0.006

0.145 %
0.006

Time in hours after transfer of prestress

Relaxation Loss as % of loss at 1000 hrs.

35 days
840 hrs.
96.80 %

Relax. Loss for

500 hrs as % of 1000 hrs relax..loss

90.0%

Relax. Loss for

1000 hrs as % of 1000 hrs relax..loss

100.0%

(Refer Table 6.3 of IRC: 112-2011)

Relaxation Loss between

49 day &

63 day

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 28 day to 63 day )
For Stage-II Cables

%
MN

96.80 %

-90.08 %

6.72 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

0.127 %
0.005

0.127 %
0.005

0.131 %
0.005

0.136 %
0.006

0.137 %
0.006

0.144 %
0.006

(27)

0.149 %
0.006

0.153 %
0.007

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.379 %

TOTAL PRESTRESS LOSS (Shrinkage + Creep + Relaxation)


TOTAL PRESTRESS LOSS ( 49 day to 63 day )
For Stage-I Cables

TOTAL PRESTRESS LOSS ( 49 day to 63 day )


For Stage-II Cables

Stress due to Total (S + C + R) Loss between


ft_slab
At Top of Deck Slab
ft_girder
At Top of Precast Girder
fb_girder
At Bott. of Precast Gir.

NET STRESS IN GIRDER


At Top of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

0.390 %

0.389 %

0.387 %

0.417 %

0.417 %

0.411 %

0.404 %

0.401 %

0.398 %

0.400 %

0.406 %

0.407 %

0.376 %

0.379 %

MN

0.008

0.008

0.008

0.009

0.009

0.009

0.009

0.009

0.009

0.009

0.009

0.009

0.008

0.008

0.008

0.545 %

0.545 %

0.546 %

0.582 %

0.583 %

0.584 %

0.585 %

0.586 %

0.587 %

0.587 %

0.587 %

0.586 %

0.551 %

0.550 %

0.550 %

MN

0.022

0.022

0.022

0.024

0.024

0.024

0.025

0.025

0.025

0.025

0.025

0.025

0.023

0.023

0.023

( 49 day to 63 day )
MPa

0.001

0.001

0.007

0.010

0.010

0.014

0.016

0.016

0.016

0.014

0.011

0.010

0.007

0.001

0.001

MPa

-0.005

-0.005

-0.001

-0.003

-0.003

0.000

0.001

0.001

0.001

0.000

-0.003

-0.003

-0.001

-0.005

-0.005

MPa

-0.045

-0.047

-0.056

-0.096

-0.097

-0.106

-0.111

-0.112

-0.113

-0.109

-0.100

-0.098

-0.058

-0.048

-0.047

( At 63 days )
ft_slab
MPa
ft_girder
MPa
fb_girder
MPa

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

0.001

-0.003

-0.007

-0.008

-0.013

-0.018

-0.020

-0.018

-0.013

-0.008

-0.007

-0.002

0.001

0.001

1.915

1.670

4.277

4.308

4.946

5.821

6.438

5.758

4.858

4.251

4.229

1.627

1.949

2.307

7.833

8.213

8.556

12.174

12.171

11.703

10.979

10.460

11.288

12.202

12.707

12.701

8.907

8.485

8.095

4.546

4.595

5.474

9.405

9.546

10.200

10.150

9.827

10.399

10.571

9.887

9.734

5.651

4.733

4.681

0.038

0.344

0.462

0.115

1.020

1.251

1.228

1.243

1.289

1.056

0.119

0.478

0.355

0.039

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg
Stress in Composite Girder due to SIDL
ft_slab
ft_girder
At Top of Precast Girder
fb_girder
At Bott. of Precast Gir.

At Top of Deck Slab

( At

10.714

10.783

10.800

10.404

10.016

10.671

11.220

11.218

11.139

7.152

6.341

6.132

0.547

0.131

1.114

1.303

1.255

1.272

1.346

1.158

0.136

0.568

0.461

0.052

9.838

63 days )
0.000

0.000

0.051

0.092

0.100

0.168

0.255

0.352

0.255

0.168

0.100

0.092

0.051

0.000

0.000

0.000

0.000

0.034

0.057

0.062

0.104

0.158

0.218

0.158

0.104

0.062

0.057

0.034

0.000

0.000

MPa

0.000

0.000

-0.087

-0.200

-0.217

-0.362

-0.551

-0.761

-0.551

-0.362

-0.217

-0.200

-0.087

0.000

0.000

fb_girder

MPa
MPa

JUST AFTER SIDL PLACEMENT


0.001

0.001

0.048

0.085

0.092

0.154

0.237

0.332

0.237

0.154

0.093

0.086

0.049

0.001

0.001

2.263

1.915

1.705

4.334

4.370

5.049

5.979

6.655

5.916

4.962

4.313

4.286

1.661

1.949

2.307

7.833
4.546

8.213
4.595

8.469
5.441

11.974
9.296

11.954
9.422

11.341
9.942

10.428
9.713

9.698
9.220

10.737
9.962

11.840
10.312

12.490
9.763

12.502
9.624

8.820
5.618

8.485
4.733

8.095
4.681

0.038

0.343

0.458

0.114

1.000

1.208

1.164

1.179

1.246

1.036

0.118

0.473

0.354

0.039

MPa

8.769

MPa

Stress at cg. of Stage-II Cables

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

6.892
0.445

MPa

At Bott. of Precast Gir.

fcg_avg

6.142
0.050

MPa

At Top of Precast Girder

Avg. Stress at cg. of Stage-I Cables

5.940

MPa

( At 63 days )
ft_slab
MPa
ft_girder
MPa

Stress at cg. of Stage-I Cables

9.037

MPa

Stress at cg. of Stage-II Cables

NET STRESS IN GIRDER

0.001
2.263

MPa

fcg_avg

At Top of Deck Slab

JUST BEFORE SIDL PLACEMENT

5.940

6.142

6.834

10.562

10.615

10.500

9.932

9.363

10.199

10.920

11.050

10.987

7.094

6.341

6.132

0.050

0.443

0.540

0.129

1.090

1.256

1.186

1.202

1.298

1.134

0.134

0.562

0.459

0.052

9.535

MPa

(28)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

(4)

LOSS OF PRESTRESS

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.000178

From 63 days to

INFINITY

SHRINKAGE LOSS IN PRESTRESS


FOR STAGE-1 CABLES
Differential Shrinkage Strain cs ( from 63 to INFINITY days )
Stress Loss due to Shrinkage

cs x Ep x Ap

( from 63 to INFINITY days )


Shrinkage Loss between
FOR STAGE-2 CABLES

0.000178

0.000178

0.000178

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000178

0.000178

MN

0.058

0.058

0.058

0.056

0.056

0.056

0.056

0.056

0.056

0.056

0.056

0.056

0.058

0.058

0.058

2.837 %

2.836 %

2.815 %

2.701 %

2.696 %

2.658 %

2.617 %

2.595 %

2.574 %

2.592 %

2.627 %

2.631 %

2.740 %

2.759 %

2.760 %
0.000178

Differential Shrinkage Strain cs ( from 63 to INFINITY days )


Stress Loss due to Shrinkage

Shrinkage Loss between

cs x Ep x Ap

( from 63 to INFINITY days )

0.000178

0.000178

0.000178

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000172

0.000178

0.000178

MN

0.116

0.116

0.116

0.113

0.113

0.113

0.113

0.113

0.113

0.113

0.113

0.113

0.116

0.116

0.116

2.862 %

2.861 %

2.839 %

2.724 %

2.719 %

2.689 %

2.663 %

2.644 %

2.626 %

2.622 %

2.634 %

2.639 %

2.748 %

2.768 %

2.769 %

CREEP LOSS IN PRESTRESS


Weighted Value of Creep Coefficient, (t2,t0) ( at INFINITY )

2.048

Stress Loss due to Creep = { (t2,t0) - (t1,t0) } x (Ep / Ec,eff) x

Weighted Value of Creep Coefficient, (t1,t0)

( at 63 days )

0.848

Avg. Stress at cg. of Prestress of Stage-1 cp1

x 7.96

MPa

Eff. Elastic Modulus of Concrete, Ec,eff ( at INFINITY )

Avg. Stress at cg. of Prestress of Stage-2 cp2

x 8.62

MPa

Ecm

34000 MPa

cp x Ap

(Ap : Area of Prestress)

FOR STAGE-1 CABLES


Stress Loss due to Creep for Stage-I Cables

Creep Loss between

( from 63 to INFINITY )

MN

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

0.092

4.487 %

4.485 %

4.452 %

4.410 %

4.402 %

4.338 %

4.273 %

4.237 %

4.202 %

4.231 %

4.288 %

4.296 %

4.334 %

4.363 %

4.365 %

FOR STAGE-2 CABLES


Stress Loss due to Creep for Stage-II Cables

MN

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

0.199

4.902 %

4.900 %

4.862 %

4.815 %

4.806 %

4.754 %

4.708 %

4.675 %

4.642 %

4.636 %

4.657 %

4.665 %

4.708 %

4.741 %

4.743 %

Relax. Loss as % of loss at 1000 hrs.

At Infinity

x 100

Relaxation Loss between

INFINITY

4.733 %

4.880 %

5.035 %

4.904 %

4.670 %

4.641 %

4.490 %

4.375 %

4.368 %

0.102

0.106

0.110

0.107

0.100

0.099

0.095

0.092

0.092

Creep Loss between

( from 63 to INFINITY )

LOSS DUE TO RELAXATION OF STEEL

For
Stage-I
Cables

63 day &

% Relaxation Loss
Relaxation Loss

=
3.909 %

MN

0.080

Relax. Loss as % of loss at 1000 hrs.

At Infinity

Relaxation Loss between

INFINITY

Relaxation Loss between


( 63 day to INFINITY
For Stage-I Cables

For
Stage-II
Cables

=
=

63 day &

% Relaxation Loss
Relaxation Loss

Relaxation Loss between


( 63 day to INFINITY
For Stage-II Cables

3.0
300.00 %

-100.00 %

300.00 %
200.00 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100
( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss
3.917 %
4.039 %
4.198 %
4.228 %
4.472 %
0.080
3.0
300.00 %

0.083

0.087

x 100

-96.80 %

0.088

0.095

300.00 %
203.20 % of loss at 1000 hrs.

1000 hr. relaxation Loss x ( Relaxation Loss as % of loss at 1000 hrs.) /100

( % Relaxation Loss /100 ) x Prestress Force after (F + S + ES ) Loss

3.826 %

3.834 %

3.962 %

4.126 %

4.157 %

4.341 %

4.507 %

4.631 %

4.753 %

4.776 %

4.696 %

4.667 %

4.510 %

4.388 %

4.381 %

MN

0.155

0.156

0.162

0.171

0.172

0.182

0.191

0.197

0.204

0.205

0.201

0.199

0.191

0.184

0.184

(29)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

11.493 %

TOTAL PRESTRESS LOSS (Shrinkage + Creep + Relaxation)


TOTAL PRESTRESS LOSS ( 63 day to INFINITY
For Stage-I Cables

TOTAL PRESTRESS LOSS ( 63 day to INFINITY


For Stage-II Cables

Stress due to Total (S + C + R) Loss between


ft_slab
At Top of Deck Slab
ft_girder
At Top of Precast Girder
fb_girder
At Bott. of Precast Gir.

NET STRESS IN GIRDER


At Top of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

11.233 %

11.237 %

11.306 %

11.309 %

11.326 %

11.468 %

11.623 %

11.711 %

11.812 %

11.727 %

11.585 %

11.568 %

11.564 %

11.497 %

MN

0.230

0.230

0.233

0.236

0.237

0.243

0.250

0.254

0.258

0.255

0.248

0.248

0.245

0.242

0.242

11.590 %

11.594 %

11.663 %

11.664 %

11.681 %

11.784 %

11.879 %

11.950 %

12.021 %

12.034 %

11.988 %

11.971 %

11.966 %

11.897 %

11.893 %

MN

0.471

0.471

0.478

0.482

0.484

0.493

0.502

0.509

0.516

0.517

0.512

0.511

0.506

0.500

0.499

( 63 day to INFINITY
MPa

-0.007

0.009

0.138

0.195

0.211

0.304

0.360

0.367

0.370

0.319

0.224

0.207

0.147

0.011

-0.006

MPa

-0.130

-0.119

-0.034

-0.078

-0.069

-0.015

0.014

0.016

0.015

-0.016

-0.072

-0.081

-0.035

-0.125

-0.137

MPa

-1.024

-1.052

-1.288

-2.062

-2.101

-2.339

-2.496

-2.537

-2.567

-2.451

-2.221

-2.181

-1.363

-1.116

-1.086

-0.005

INFINITY days )
ft_slab
MPa
ft_girder
MPa
fb_girder
MPa

Stress at cg. of Stage-I Cables

MPa

Avg. Stress at cg. of Stage-I Cables

MPa

fcg_avg

-0.007

0.010

0.187

0.280

0.303

0.458

0.597

0.700

0.607

0.473

0.316

0.293

0.196

0.012

2.133

1.796

1.671

4.257

4.301

5.034

5.994

6.672

5.931

4.946

4.241

4.205

1.626

1.824

2.171

6.809

7.161

7.182

9.912

9.854

9.002

7.932

7.162

8.170

9.388

10.270

10.321

7.457

7.370

7.009

4.049

4.079

4.715

7.929

8.000

8.119

7.621

7.085

7.810

8.402

8.259

8.179

4.849

4.186

4.155

0.034

0.300

0.393

0.097

0.832

0.967

0.904

0.916

0.996

0.860

0.100

0.405

0.309

0.035

5.397

5.850

8.866

8.873

8.471

7.716

7.108

7.920

8.794

9.208

9.193

6.052

5.550

5.368

0.044

0.384

0.457

0.108

0.896

0.995

0.911

0.924

1.027

0.929

0.112

0.473

0.396

0.045

7.147

MPa

Stress at cg. of Stage-II Cables

MPa

Avg. Stress at cg. of Stage-II Cables

MPa

fcg_avg

5.220

7.702

MPa

(30)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

FINAL SUMMARY OF PRESTRESS LOSSES

FOR STAGE-I PRESTRESS

Left Anchor. 0.000 L Sec

Section under consideration

Item No.

Description

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

Col.- 1

Col.- 2

Col.- 3

Col.- 4

Col.- 5

Col.- 6

Col.- 7

Col.- 8

Col.- 9

Col.- 10

Col.- 11

Col.- 12

Col.- 14

Col.- 15

Col.- 16

MN
MN

2.341
2.079

2.341
2.080

2.341
2.093

2.341
2.108

2.341
2.111

2.341
2.136

2.341
2.165

2.341
2.183

2.341
2.201

2.341
2.190

2.341
2.166

2.341
2.163

2.341
2.149

2.341
2.138

2.341
2.137

%
MN

11.17 %
0.261

11.13 %
0.260

10.60 %
0.248

9.95 %
0.233

9.82 %
0.230

8.75 %
0.205

7.49 %
0.175

6.72 %
0.157

5.95 %
0.139

6.44 %
0.151

7.46 %
0.175

7.57 %
0.177

8.18 %
0.191

8.66 %
0.203

8.70 %
0.204
0.65 %

Units

LOSS OF PRESTRESS DUE TO FRICTION AND SLIP


Prestress Force applied at Jacks

Before Prestress Force at Sec. after (fric.+slip) 'Ps'


Transfer of Prestress Loss due to (Friction+Slip)
Prestress

LOSS OF PRESTRESS DUE TO ELASTIC SHORTENING, SHRINKAGE, CREEEP & RELAXATION OF STEEL
Elastic Shortening Loss

Between
7th Day Shrinkage Loss
and
28th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
28th Day Shrinkage Loss
and
35th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
35th Day Shrinkage Loss
and
49th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN

0.67 %

0.67 %

0.67 %

0.66 %

0.66 %

0.65 %

0.64 %

0.63 %

0.63 %

0.63 %

0.64 %

0.64 %

0.65 %

0.65 %

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.80 %

0.80 %

0.80 %

0.88 %

0.88 %

0.86 %

0.85 %

0.84 %

0.84 %

0.84 %

0.85 %

0.85 %

0.77 %

0.78 %

0.78 %

0.016

0.016

0.016

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.018

0.016

0.016

0.016

0.77 %

0.77 %

0.76 %

0.75 %

0.75 %

0.74 %

0.73 %

0.72 %

0.72 %

0.72 %

0.73 %

0.73 %

0.74 %

0.75 %

0.75 %

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

0.016

1.76 %

1.76 %

1.82 %

1.89 %

1.90 %

2.01 %

2.13 %

2.20 %

2.27 %

2.21 %

2.10 %

2.09 %

2.02 %

1.97 %

1.97 %

0.036

0.036

0.038

0.039

0.040

0.043

0.046

0.048

0.050

0.048

0.045

0.045

0.043

0.042

0.041

4.002 %
0.082

4.004 %
0.082

4.043 %
0.084

4.182 %
0.087

4.191 %
0.088

4.268 %
0.091

4.352 %
0.094

4.399 %
0.096

4.452 %
0.097

4.407 %
0.096

4.332 %
0.093

4.322 %
0.093

4.187 %
0.089

4.150 %
0.088

4.148 %
0.087

4.66 %

4.66 %

4.62 %

4.58 %

4.57 %

4.51 %

4.44 %

4.40 %

4.37 %

4.40 %

4.46 %

4.46 %

4.50 %

4.53 %

4.53 %

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.096

0.08 %

0.08 %

0.07 %

0.10 %

0.10 %

0.09 %

0.09 %

0.09 %

0.09 %

0.09 %

0.09 %

0.09 %

0.07 %

0.07 %

0.07 %

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.31 %

0.31 %

0.31 %

0.31 %

0.31 %

0.30 %

0.30 %

0.30 %

0.29 %

0.29 %

0.30 %

0.30 %

0.30 %

0.30 %

0.30 %

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.006

0.07 %

0.07 %

0.07 %

0.07 %

0.07 %

0.08 %

0.08 %

0.08 %

0.08 %

0.08 %

0.08 %

0.08 %

0.08 %

0.07 %

0.07 %

0.001

0.001

0.001

0.001

0.001

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

5.114 %
0.105

5.111 %
0.105

5.076 %
0.105

5.053 %
0.106

5.045 %
0.106

4.978 %
0.106

4.908 %
0.106

4.870 %
0.106

4.834 %
0.106

4.864 %
0.106

4.925 %
0.106

4.933 %
0.106

4.952 %
0.106

4.983 %
0.106

4.985 %
0.106

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.00
0.13 %

0.00
0.13 %

0.00
0.12 %

0.00
0.16 %

0.00
0.16 %

0.00
0.16 %

0.00
0.16 %

0.00
0.16 %

0.00
0.15 %

0.00
0.16 %

0.00
0.16 %

0.00
0.16 %

0.00
0.12 %

0.00
0.12 %

0.00
0.12 %

0.003
0.37 %
0.008
0.19 %
0.004

0.003
0.37 %
0.008
0.19 %
0.004

0.003
0.37 %
0.008
0.20 %
0.004

0.003
0.36 %
0.008
0.21 %
0.004

0.003
0.36 %
0.008
0.21 %
0.004

0.003
0.36 %
0.008
0.22 %
0.005

0.003
0.35 %
0.008
0.23 %
0.005

0.003
0.35 %
0.008
0.24 %
0.005

0.003
0.35 %
0.008
0.25 %
0.005

0.003
0.35 %
0.008
0.24 %
0.005

0.003
0.35 %
0.008
0.23 %
0.005

0.003
0.36 %
0.008
0.23 %
0.005

0.003
0.36 %
0.008
0.22 %
0.005

0.003
0.36 %
0.008
0.22 %
0.005

0.003
0.36 %
0.008
0.22 %
0.005

0.691 %
0.014

0.691 %
0.014

0.693 %
0.014

0.735 %
0.015

0.736 %
0.015

0.740 %
0.016

0.746 %
0.016

0.748 %
0.016

0.752 %
0.016

0.749 %
0.016

0.744 %
0.016

0.744 %
0.016

0.702 %
0.015

0.700 %
0.015

0.700 %
0.015

(31)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Elastic Shortening Loss

Between
49th Day Shrinkage Loss
and
63th Day Creep Loss
On Composite Relaxation Loss
Section

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
63th Day Shrinkage Loss
and
Infinity Creep Loss
(Service
Stage)

Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

TOTAL PRESTRESS LOSS ( 7 day to Infinity


For Stage-I Cables

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

0.0 %
0.00
0.10 %
0.002

0.0 %
0.00
0.10 %
0.002

0.0 %
0.00
0.10 %
0.002

0.0 %
0.00
0.14 %
0.003

0.0 %
0.00
0.14 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.13 %
0.003

0.0 %
0.00
0.10 %
0.002

0.0 %
0.00
0.10 %
0.002

0.0 %
0.00
0.10 %
0.002

0.29 %
0.006
0.00 %
0.000

0.29 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.27 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.28 %
0.006
0.00 %
0.000

0.390 %
0.008

0.389 %
0.008

0.387 %
0.008

0.417 %
0.009

0.417 %
0.009

0.411 %
0.009

0.404 %
0.009

0.401 %
0.009

0.398 %
0.009

0.400 %
0.009

0.406 %
0.009

0.407 %
0.009

0.376 %
0.008

0.379 %
0.008

0.379 %
0.008

0.0 %
0.00
2.84 %
0.058
4.49 %

0.0 %
0.00
2.84 %
0.058
4.49 %

0.0 %
0.00
2.81 %
0.058
4.45 %

0.0 %
0.00
2.70 %
0.056
4.41 %

0.0 %
0.00
2.70 %
0.056
4.40 %

0.0 %
0.00
2.66 %
0.056
4.34 %

0.0 %
0.00
2.62 %
0.056
4.27 %

0.0 %
0.00
2.60 %
0.056
4.24 %

0.0 %
0.00
2.57 %
0.056
4.20 %

0.0 %
0.00
2.59 %
0.056
4.23 %

0.0 %
0.00
2.63 %
0.056
4.29 %

0.0 %
0.00
2.63 %
0.056
4.30 %

0.0 %
0.00
2.74 %
0.058
4.33 %

0.0 %
0.00
2.76 %
0.058
4.36 %

0.0 %
0.00
2.76 %
0.058
4.36 %

0.092
3.91 %
0.080

0.092
3.92 %
0.080

0.092
4.04 %
0.083

0.092
4.20 %
0.087

0.092
4.23 %
0.088

0.092
4.47 %
0.095

0.092
4.73 %
0.102

0.092
4.88 %
0.106

0.092
5.04 %
0.110

0.092
4.90 %
0.107

0.092
4.67 %
0.100

0.092
4.64 %
0.099

0.092
4.49 %
0.095

0.092
4.38 %
0.092

0.092
4.37 %
0.092

%
MN

11.233 %
0.230

11.237 %
0.230

11.306 %
0.233

11.309 %
0.236

11.326 %
0.237

11.468 %
0.243

11.623 %
0.250

11.711 %
0.254

11.812 %
0.258

11.727 %
0.255

11.585 %
0.248

11.568 %
0.248

11.564 %
0.245

11.497 % 11.493 %
0.242
0.242

%
MN

21.43 %
0.440

21.43 %
0.440

21.50 %
0.445

21.70 %
0.453

21.71 %
0.454

21.87 %
0.464

22.03 %
0.475

22.13 %
0.481

22.25 %
0.487

22.15 %
0.482

21.99 %
0.472

21.97 %
0.471

21.78 %
0.463

21.71 %
0.458

%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN

21.70 %
0.458

FOR STAGE-II PRESTRESS


Section under consideration

Item No.

Description

Left Anchor. 0.000 L Sec

Units

Col.- 1

Col.- 2

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec Right Anchor

Col.- 3

Col.- 4

Col.- 5

Col.- 6

Col.- 7

Col.- 8

Col.- 9

Col.- 10

Col.- 11

Col.- 12

Col.- 14

Col.- 15

Col.- 16

LOSS OF PRESTRESS DUE TO FRICTION AND SLIP


Prestress Force applied at Jacks

Before Prestress Force at Sec. after (fric.+slip) 'Ps'


Transfer of Prestress Loss due to (Friction+Slip)
Prestress

MN

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

4.681

MN

4.192

4.194

4.221

4.255

4.262

4.303

4.341

4.372

4.402

4.410

4.394

4.388

4.356

4.331

4.329

%
MN

10.45 %
0.489

10.41 %
0.487

9.84 %
0.461

9.11 %
0.426

8.97 %
0.420

8.09 %
0.379

7.26 %
0.340

6.62 %
0.310

5.97 %
0.280

5.80 %
0.272

6.13 %
0.287

6.26 %
0.293

6.95 %
0.326

7.49 %
0.351

7.53 %
0.352

LOSS OF PRESTRESS DUE TO ELASTIC SHORTENING, SHRINKAGE, CREEEP & RELAXATION OF STEEL
Elastic Shortening Loss

Between
7th Day Shrinkage Loss
and
28th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

%
MN
%
MN
%
MN
%
MN
%
MN

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.0 %
0.00
0.0 %
0.00
0.0 %

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.00
0.0 %
0.00

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

0.000 %
0.000

(32)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Elastic Shortening Loss

Between
28th Day Shrinkage Loss
and
35th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
35th Day Shrinkage Loss
and
49th Day Creep Loss
Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
49th Day Shrinkage Loss
and
63th Day Creep Loss
On Composite Relaxation Loss
Section

TOTAL PRESTRESS LOSS


(ES + S + C + R)

Elastic Shortening Loss

Between
63th Day Shrinkage Loss
and
Infinity Creep Loss
(Service
Stage)

Relaxation Loss

TOTAL PRESTRESS LOSS


(ES + S + C + R)

TOTAL PRESTRESS LOSS ( 7 day to Infinity


For Stage-II Cables

%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN
%
MN

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

2.70 %
0.113
0.08 %
0.003

2.70 %
0.113
0.08 %
0.003

2.68 %
0.113
0.08 %
0.003

2.65 %
0.113
0.10 %
0.004

2.65 %
0.113
0.10 %
0.004

2.62 %
0.113
0.09 %
0.004

2.60 %
0.113
0.09 %
0.004

2.58 %
0.113
0.09 %
0.004

2.56 %
0.113
0.09 %
0.004

2.56 %
0.113
0.09 %
0.004

2.57 %
0.113
0.09 %
0.004

2.57 %
0.113
0.09 %
0.004

2.59 %
0.113
0.07 %
0.003

2.61 %
0.113
0.07 %
0.003

2.61 %
0.113
0.07 %
0.003

0.36 %
0.014
1.45 %
0.059

0.36 %
0.014
1.45 %
0.059

0.35 %
0.014
1.50 %
0.061

0.35 %
0.014
1.56 %
0.064

0.35 %
0.014
1.57 %
0.065

0.35 %
0.014
1.64 %
0.069

0.34 %
0.014
1.70 %
0.072

0.34 %
0.014
1.75 %
0.075

0.34 %
0.014
1.80 %
0.077

0.34 %
0.014
1.80 %
0.077

0.34 %
0.014
1.77 %
0.076

0.34 %
0.014
1.76 %
0.075

0.34 %
0.014
1.70 %
0.072

0.34 %
0.014
1.66 %
0.070

0.34 %
0.014
1.66 %
0.069

4.577 %
0.189

4.578 %
0.189

4.603 %
0.191

4.657 %
0.196

4.663 %
0.196

4.700 %
0.200

4.734 %
0.203

4.760 %
0.206

4.785 %
0.208

4.790 %
0.209

4.773 %
0.207

4.767 %
0.206

4.713 %
0.202

4.688 %
0.200

4.687 %
0.200

0.0 %
0.00
0.13 %
0.005
0.41 %
0.017

0.0 %
0.00
0.13 %
0.005
0.41 %
0.017

0.0 %
0.00
0.13 %
0.005
0.40 %
0.017

0.0 %
0.00
0.16 %
0.007
0.40 %
0.017

0.0 %
0.00
0.16 %
0.007
0.40 %
0.017

0.0 %
0.00
0.16 %
0.007
0.40 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.16 %
0.007
0.39 %
0.017

0.0 %
0.00
0.12 %
0.005
0.39 %
0.017

0.0 %
0.00
0.12 %
0.005
0.39 %
0.017

0.0 %
0.00
0.12 %
0.005
0.39 %
0.017

0.25 %
0.010

0.25 %
0.010

0.26 %
0.011

0.27 %
0.011

0.27 %
0.011

0.28 %
0.012

0.30 %
0.012

0.30 %
0.013

0.31 %
0.013

0.31 %
0.013

0.31 %
0.013

0.31 %
0.013

0.30 %
0.013

0.29 %
0.012

0.29 %
0.012

0.785 %
0.032

0.785 %
0.032

0.790 %
0.032

0.835 %
0.035

0.836 %
0.035

0.842 %
0.035

0.847 %
0.036

0.851 %
0.036

0.856 %
0.037

0.856 %
0.037

0.854 %
0.036

0.853 %
0.036

0.809 %
0.034

0.805 %
0.034

0.804 %
0.034

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.00
0.11 %

0.00
0.11 %

0.00
0.10 %

0.00
0.14 %

0.00
0.14 %

0.00
0.14 %

0.00
0.14 %

0.00
0.13 %

0.00
0.13 %

0.00
0.13 %

0.00
0.13 %

0.00
0.13 %

0.00
0.10 %

0.00
0.10 %

0.00
0.10 %

0.004
0.31 %

0.004
0.31 %

0.004
0.31 %

0.006
0.31 %

0.006
0.31 %

0.006
0.30 %

0.006
0.30 %

0.006
0.30 %

0.006
0.30 %

0.006
0.30 %

0.006
0.30 %

0.006
0.30 %

0.004
0.30 %

0.004
0.30 %

0.004
0.30 %

0.013
0.13 %

0.013
0.13 %

0.013
0.13 %

0.013
0.14 %

0.013
0.14 %

0.013
0.14 %

0.013
0.15 %

0.013
0.15 %

0.013
0.16 %

0.013
0.16 %

0.013
0.16 %

0.013
0.15 %

0.013
0.15 %

0.013
0.15 %

0.013
0.14 %

0.005

0.005

0.005

0.006

0.006

0.006

0.006

0.007

0.007

0.007

0.007

0.007

0.006

0.006

0.006

0.545 %

0.545 %

0.546 %

0.582 %

0.583 %

0.584 %

0.585 %

0.586 %

0.587 %

0.587 %

0.587 %

0.586 %

0.551 %

0.550 %

0.550 %

0.022

0.022

0.022

0.024

0.024

0.024

0.025

0.025

0.025

0.025

0.025

0.025

0.023

0.023

0.023

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.0 %

0.00
2.86 %

0.00
2.86 %

0.00
2.84 %

0.00
2.72 %

0.00
2.72 %

0.00
2.69 %

0.00
2.66 %

0.00
2.64 %

0.00
2.63 %

0.00
2.62 %

0.00
2.63 %

0.00
2.64 %

0.00
2.75 %

0.00
2.77 %

0.00
2.77 %

0.116
4.90 %
0.199
3.83 %
0.155

0.116
4.90 %
0.199
3.83 %
0.156

0.116
4.86 %
0.199
3.96 %
0.162

0.113
4.82 %
0.199
4.13 %
0.171

0.113
4.81 %
0.199
4.16 %
0.172

0.113
4.75 %
0.199
4.34 %
0.182

0.113
4.71 %
0.199
4.51 %
0.191

0.113
4.67 %
0.199
4.63 %
0.197

0.113
4.64 %
0.199
4.75 %
0.204

0.113
4.64 %
0.199
4.78 %
0.205

0.113
4.66 %
0.199
4.70 %
0.201

0.113
4.67 %
0.199
4.67 %
0.199

0.116
4.71 %
0.199
4.51 %
0.191

0.116
4.74 %
0.199
4.39 %
0.184

0.116
4.74 %
0.199
4.38 %
0.184

11.590 %
0.471

11.594 %
0.471

11.663 %
0.478

11.664 %
0.482

11.681 %
0.484

11.784 %
0.493

11.879 %
0.502

11.950 %
0.509

12.021 %
0.516

12.034 %
0.517

11.988 %
0.512

11.971 %
0.511

11.966 %
0.506

17.497 %
0.714

17.503 % 17.602 % 17.739 % 17.763 % 17.910 % 18.045 % 18.147 % 18.249 % 18.268 % 18.201 % 18.177 % 18.039 % 17.940 % 17.93 %
0.714
0.724
0.736
0.739
0.753
0.766
0.776
0.786
0.787
0.781
0.779
0.766
0.756
0.756

(33)

11.897 % 11.893 %
0.500
0.499

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Classification of Characteristic Actions used for Superstructure Design


Permanent Action (G)
Symbol
G1

Symbol

DL : Dead Load of Structural Componenets

Accidental Action (A) / Seismic Action (AE)

Action Designation & Description


QL : Vehicular Live laod

A1
A2

G2

SDL1 : SIDL excluding Surfacing

Q2

Qim : Impact factor due to CWLL

SDL2 : Dead Load of Surfacing (Wearing Coat)

Q3

Fa : Tractive Effect of Vehicle

G4

GS : Snow Load
Wfill : Weight of the backfill

Q4

Fb : Braking Effect of the Vehicle

A3

Q5

Qs : Pedestrian Live Load

A4

G6

SE : Settlement Effect

Q6

G7

CR : Creep Effect

Q7

G8

SH : Shrinkage Effect

Q8

G9
G10

Fcf : Centrifugal Force of Vehicle


Fcp : Earth pressure surharge Effect due to Live Load
Fde : Temperature effects due to restraints to free structural
deformation

P : Prestressing Force
Q9

FS : Secondary Effect

W : Wind Load on the Structure

G11

Fep : Active Earth Pressure Effect due to Backfill

Q10

G12

DSH : Differential Shrinkage

Q11

Fwc : Water Current Force

Q12

Fwp : Wave Pressure

LOAD COMBINATIONS
DESCRIPTION OF COMBINATION

SLS : Service Limit State

STAGE

Symbol

Q1

G3
G5

(Marked in Red Colour)

Variable Action (Q)

Action Designation & Description

Right Anchor

0.000 m

Gb : Buoyancy Effect

Action Designation & Description


Vc : Vehicle collision on elements of bridge structure
Barge impact or impact due to floating
bodies in water current
Vehicular Impact on Crash Barriers.
AE : Seismic Action
i. Inertial loads due to self-mass
generated in bridge structure.
ii. Inertial loads due to mass of CWLL
iii. Hydrodynamic forces generated on
submerged part under water.
iv. Dynamic Earth Increment

ULS : Ultimate Limit State

DETAILS OF FORCES IN COMBINATION


Prestress(stage1) + DLgir

COMBINATIONS WITH LOAD FACTORS

PURPOSE OF CHECKING

AT TRANSFER (RARE)

SLS 1

RARE (CHARACTERISTIC)

SLS 2

Non-Composite

Prestress(Stage1 & 2) + DLgir

1.00 x G9 +

1.00 x G1

(At 28 days) Maximum Stresses

SLS 3

Non-Composite

Prestress(Stage1 & 2) + DLgir + DLslab (green wt.)

1.00 x G9 +

1.00 x G1

(At 35 days) Maximum Stresses

Non-Composite

1.00 x G9 +

1.00 x G1

( At 7 days ) Maximum Stresses

SLS 4

Composite

Prestress(Stage1 & 2) + DLgir + DLslab + DSH

1.00 x G9 +

1.00 x G1 +

SLS 5

Composite

Prestress + DLgir + DLslab + SDL1 + SDL2 + DSH + Q

1.00 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

1.00 x G12

(At 49 days) Maximum Stresses

0.60 x Q8

(At 63 days) Maximum Stresses

SLS 6

Composite

Final Prestress + DLgir + DLslab + SDL1 + SDL2 + DSH + Q

1.10 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

0.60 x Q8

(Long term) Max. Stresses with sup

SLS 7

Composite

Final Prestress + DLgir + DLslab + SDL1 + SDL2 + DSH + Q

0.90 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

0.60 x Q8

(Long term) Max. Stresses with inf

0.50 x Q8

FREQUENT

SLS 8

Composite

Final Prestress + DLgir + DLslab + SDL1 + SDL2 + DSH + Q

1.00 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 0.75 x Q1 + 0.75 x Q2 +

QUASI-PERMANENT

SLS 9

Composite

Final Prestress + DLgir + DLslab + SDL1 + SDL2 + DSH + Q

1.00 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 +

0.50 x Q8

(Long term) Deflection

ULTIMATE(BASIC)

ULS 1

Composite

Final

1.00 x G9 +

1.35 x G1 + 1.35 x G2 + 1.75 x G3 + 1.50 x Q1 +

1.50 x Q2

(Long term) Str. Strength Check in ULS

Prestress

+ factored (DLgir+DLslab+SDL1+SDL2+Q)

(34)

(Long term) Decompression,Crack Width

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Summary of Stresses in Concrete (Exculding Prestress Effect)


1.

Stress due to Self Weight of Girder Only (G1,1)

1a
1b
1c

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder

1d

At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

2.

Stress due to Lifting of Girder

2a
2b
2c
2d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa

0.000
0.000
0.000

0.000
0.000
-0.005

0.000
0.000
1.050

0.000
0.000
2.203

0.000
0.000
2.366

0.000
0.000
3.528

0.000
0.000
4.394

0.000
0.000
4.699

0.000
0.000
4.394

0.000
0.000
3.528

0.000
0.000
2.366

0.000
0.000
2.203

0.000
0.000
1.050

0.000
0.000
-0.005

0.000
0.000
0.000

MPa

0.000

0.006

-1.136

-2.309

-2.480

-3.697

-4.605

-4.925

-4.605

-3.697

-2.480

-2.309

-1.136

0.006

0.000

MPa

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

0.000
0.000
0.024
-0.026

0.000
0.000
0.051
-0.054

0.000
0.000
0.055
-0.058

0.000
0.000
0.084
-0.088

0.000
0.000
0.105
-0.110

0.000
0.000
0.112
-0.117

0.000
0.000
0.105
-0.110

0.000
0.000
0.084
-0.088

0.000
0.000
0.055
-0.058

0.000
0.000
0.051
-0.054

0.000
0.000
0.024
-0.026

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

MPa
MPa

MPa
MPa
MPa

3.

Stress due to Wt. of Shuttering on Girder

3a
3b
3c
3d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa
MPa
MPa
MPa

0.000
0.000
0.000
0.000

(G1,2)
0.000
0.000
0.000
0.000

4.

Stress due to Green Weight of Slab Concrete (G1,3)

4a

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

4b
4c
4d

At Top of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

At Bottom of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

0.000
0.000

-0.005
0.005

1.384
-1.496

2.985
-3.128

3.217
-3.371

4.868
-5.101

6.087
-6.378

6.493
-6.804

6.087
-6.378

4.868
-5.101

3.217
-3.371

2.985
-3.128

1.384
-1.496

-0.005
0.005

0.000
0.000

MPa

5.

Stress due to Removal of Shuttering (G1,2)

5a

At Top of Deck Slab

5b
5c

At Bottom of Deck Slab


At Top of Precast Girder

5d

At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa

0.000

0.000

-0.009

-0.017

-0.018

-0.027

-0.034

-0.037

-0.034

-0.027

-0.018

-0.017

-0.009

0.000

0.000

MPa
MPa

0.000
0.000

0.000
0.000

-0.006
-0.006

-0.010
-0.010

-0.011
-0.011

-0.017
-0.017

-0.021
-0.021

-0.023
-0.023

-0.021
-0.021

-0.017
-0.017

-0.011
-0.011

-0.010
-0.010

-0.006
-0.006

0.000
0.000

0.000
0.000

MPa

0.000

0.000

0.016

0.036

0.039

0.059

0.074

0.079

0.074

0.059

0.039

0.036

0.016

0.000

0.000

6.

Stress due to Shifting of Support

6a

ft_slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder Yft_girder
fb_girder
At Bott. of Precast Gir.

6b
6c
6d

At Top of Deck Slab

(G1,4)

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

MPa
MPa

(35)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

7.

Stresses due to Super Imposed Dead Load SDL1(Applied on Composite Section) (G2)

7a
7b

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

7c
7d

At Top of Deck Slab


At Bottom of Deck Slab

MPa
MPa
MPa
MPa

0.000
0.000

0.000
0.000

0.051
0.034

0.092
0.057

0.100
0.062

0.168
0.104

0.255
0.158

0.352
0.218

0.255
0.158

0.168
0.104

0.100
0.062

0.092
0.057

0.051
0.034

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.034
-0.087

0.057
-0.200

0.062
-0.217

0.104
-0.362

0.158
-0.551

0.218
-0.761

0.158
-0.551

0.104
-0.362

0.062
-0.217

0.057
-0.200

0.034
-0.087

0.000
0.000

0.000
0.000

0.257
0.159
0.159
-0.556

0.392
0.242
0.242
-0.846

0.486
0.301
0.301
-1.051

0.520
0.321
0.321
-1.123

0.486
0.301
0.301
-1.051

0.392
0.242
0.242
-0.846

0.257
0.159
0.159
-0.556

0.241
0.149
0.149
-0.522

0.133
0.089
0.089
-0.227

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

8.

Stresses due to Super Imposed Dead Load SDL2(Applied on Composite Section) (G3)

8a
8b
8c
8d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa
MPa
MPa
MPa

0.000
0.000
0.000
0.000

0.000
0.000
0.000
0.000

9.

Stress due to Governing CWLL on the Deck (With Impact)

9a
9b

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

9c
9d

At Top of Deck Slab


At Bottom of Deck Slab

0.133
0.089
0.089
-0.227

(Q1+Q2)

0.000
0.000

0.726
0.488

1.222
0.755

1.279
0.790

1.757
1.086

1.911
1.181

1.911
1.181

1.911
1.181

1.757
1.086

1.279
0.790

1.222
0.755

0.726
0.488

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.488
-1.240

0.755
-2.640

0.790
-2.762

1.086
-3.795

1.181
-4.128

1.181
-4.128

1.181
-4.128

1.086
-3.795

0.790
-2.762

0.755
-2.640

0.488
-1.240

0.000
0.000

0.000
0.000

MPa

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

0.000
0.000
0.000

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa
MPa
MPa

Stress due to FPLL on the Deck

10a
10b
10c

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder

10d

At Bott. of Precast Gir.

MPa
MPa

(Q5)

11.

Stresses due to Positive Temp. Difference (Case-1)

11a

11d

ft_slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

12.

Stresses due to Reverse Temp. Difference (Case-2)

11b
11c

At Top of Deck Slab

12a

At Top of Deck Slab

12b
12c

At Bottom of Deck Slab


At Top of Precast Girder

ft_slab
fb_slab
ft_girder
fb_girder

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

4.087

MPa
MPa

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

-1.363
-1.363

MPa

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

(Q8,2)

MPa

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

-2.214

MPa

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

1.028
1.028

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

-1.363
-1.484

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

0.621
-0.259

MPa

12d

At Bott. of Precast Gir.

Stresses due to Differential Shrinkage

13a
13b

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

13c
13d

(Q8,1)

MPa

13.

At Top of Deck Slab


At Bottom of Deck Slab

0.241
0.149
0.149
-0.522

0.000
0.000

MPa

10.

ft_slab
fb_slab
ft_girder
fb_girder

Right Anchor

0.000 m

MPa

MPa
MPa
MPa
MPa

(G12)

(36)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

1.00 x G9 +

1.00 x G1

STRESS LIMIT CHECK AT TRANSFER FOR SLS-1

( At

7 days )

14.

Stress due to Prestress at Transfer (JUST BEFORE INSTANTANEOUS LOSSES)

14a

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

14b
14c
14d

Right Anchor

0.000 m

At Top of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

At Bottom of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

2.440

2.290

1.079

0.996

0.800

-0.529

-1.290

-1.344

-1.311

-0.546

0.816

1.018

1.104

2.349

2.504

MPa

1.026

1.191

2.527

4.899

5.115

6.593

7.484

7.592

7.608

6.764

5.254

5.033

2.600

1.228

1.060

15.

Loss of Prestress

15a

ft_slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

16.

Eff. Prestress at Transfer (G9)

16a

At Top of Deck Slab

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

At Bottom of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

15b
15c
15d

16b
16c
16d

17.

due to Elastic Shortening of concrete from Stage-I Cables

At Top of Deck Slab

-0.016

-0.015

-0.007

-0.007

-0.005

0.003

0.008

0.009

0.008

0.003

-0.005

-0.007

-0.007

-0.015

-0.016

-0.007

-0.008

-0.017

-0.032

-0.034

-0.043

-0.048

-0.048

-0.048

-0.043

-0.034

-0.032

-0.017

-0.008

-0.007

MPa

2.424

2.274

1.072

0.989

0.794

-0.525

-1.282

-1.335

-1.302

-0.542

0.811

1.011

1.097

2.333

2.487

MPa

1.020

1.183

2.510

4.867

5.081

6.551

7.436

7.544

7.560

6.722

5.220

5.000

2.583

1.220

1.053

1.00 x G9 +

1.00 x G1,1

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

2.424
1.020

2.269
1.188

2.122
1.375

3.193
2.558

3.161
2.602

3.003
2.854

3.112
2.831

3.364
2.619

3.092
2.955

2.986
3.025

3.178
2.740

3.215
2.691

2.147
1.447

2.328
1.226

2.487
1.053

<
>

15.76 MPa
-2.57 MPa

Resultant Stresses in Girder.

ft_slab
fb_slab
17c
At Top of Precast Girder ft_girder
fb_girder
17d
At Bott. of Precast Gir.
For Precast Girder (Non-Composite)
17a
17b

MPa
MPa

At Top of Deck Slab


At Bottom of Deck Slab

Max. compressive stress


Min. compressive stress

=
=

MPa
MPa
MPa
MPa

3.364 MPa
1.020 MPa

(Allowable Compressive stress)


(Allowable Tensile stress)

HENCE O.K.
HENCE O.K.

(37)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

1.00 x G9 +

1.00 x G1

( At

28 days )

18.

Loss of Prestress

18a
18b

19.

ft_slab
MPa
0.000
0.000
fb_slab
MPa
0.000
0.000
At Top of Precast Girder ft_girder
MPa
-0.081
-0.076
fb_girder
At Bott. of Precast Gir.
MPa
-0.034
-0.039
Stresses due to Stage-II Prestress. after Friction+Slip

19a
19b
19c
19d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

due to Shrinkage+Creep+ Relaxation from Stage-I Cables

At Top of Deck Slab


At Bottom of Deck Slab

ft_slab
fb_slab
ft_girder
fb_girder

20

Loss of Prestress

20a

ft_slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

20b
20c
20d

MPa
MPa
MPa
MPa

0.000
0.000
0.071
7.341

0.000
0.000
-0.144
7.576

From 7 days to 28 days

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

-0.036
-0.085

-0.035
-0.171

-0.028
-0.179

0.019
-0.237

0.048
-0.276

0.050
-0.284

0.050
-0.289

0.020
-0.254

-0.030
-0.193

-0.037
-0.184

-0.039
-0.091

-0.082
-0.043

-0.087
-0.037

0.000
0.000
-1.852
9.479

0.000
0.000
-1.951
14.074

0.000
0.000
-2.153
14.307

0.000
0.000
-3.216
15.549

0.000
0.000
-3.791
16.267

0.000
0.000
-3.848
16.413

0.000
0.000
-3.841
16.491

0.000
0.000
-3.296
15.936

0.000
0.000
-2.233
14.766

0.000
0.000
-2.025
14.528

0.000
0.000
-1.925
9.796

0.000
0.000
-0.164
7.840

0.000
0.000
0.057
7.597

due to Elastic Shortening after Stage-II Prestress

At Top of Deck Slab

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

MPa

0.000
-0.116
-0.246

0.000
-0.103
-0.260

0.000
0.000
-0.371

0.000
0.006
-0.598

0.000
0.020
-0.613

0.000
0.108
-0.704

0.000
0.156
-0.754

0.000
0.158
-0.757

0.000
0.156
-0.754

0.000
0.108
-0.705

0.000
0.021
-0.613

0.000
0.007
-0.598

0.000
0.000
-0.371

0.000
-0.102
-0.261

0.000
-0.115
-0.247

0.000
0.000
1.952

0.000
0.000
-0.817

0.000
0.000
-0.991

0.000
0.000
-1.367

0.000
0.000
-3.614

0.000
0.000
-4.870

0.000
0.000
-4.974

0.000
0.000
-4.938

0.000
0.000
-3.710

0.000
0.000
-1.431

0.000
0.000
-1.044

0.000
0.000
-0.866

0.000
0.000
1.986

0.000
0.000
2.343

11.534

18.171

18.596

21.158

22.673

22.915

23.007

21.699

19.180

18.746

11.917

8.757

8.367

0.000
0.000
0.233
10.398

0.000
0.000
1.213
15.862

0.000
0.000
1.000
16.117

0.000
0.000
-0.086
17.461

0.000
0.000
-0.475
18.068

0.000
0.000
-0.275
17.991

0.000
0.000
-0.544
18.403

0.000
0.000
-0.182
18.002

0.000
0.000
0.936
16.701

0.000
0.000
1.159
16.437

0.000
0.000
0.184
10.781

0.000
0.000
1.980
8.763

0.000
0.000
2.343
8.367

MPa
MPa

21.

Eff. Prestress

(G9)

21a
21b
21c

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder

21d

At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

22.

Resultant Stresses in Girder.

22a
22b
22c
22d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

( At
MPa
MPa
MPa
MPa

MPa
MPa
MPa
MPa

28 days )
0.000
0.000
2.298
8.080

8.459

1.00 x G9 +

1.00 x G1,1

0.000
0.000
2.298
8.080

0.000
0.000
1.946
8.465

<
>

21.6 MPa
-3.3 MPa

For Precast Girder (Non-Composite)


Max. compressive stress
Min. compressive stress

=
=

Right Anchor

0.000 m

STRESS LIMIT CHECK FOR SLS-2

18c
18d

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

18.403 MPa
-0.544 MPa

(Allowable Compressive stress)


(Allowable Tensile stress)

HENCE O.K.
HENCE O.K.

(38)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Loss of Prestress

23a
23b
23c

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

1.00 x G9 +

1.00 x G1

23d

At Bott. of Precast Gir.

( At

MPa
MPa
MPa
MPa

24.

Eff. Prestress

24a
24b
24c
24d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa

25a
25b
25c
25d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

MPa

25.

35 days )

due to Shrinkage+Creep+ Relaxation from Stage-I & Stage-II Cables

ft_slab
fb_slab
ft_girder
fb_girder

(G9)

( At
MPa
MPa

Resultant Stresses in Girder

MPa

Right Anchor

0.000 m

STRESS LIMIT CHECK FOR SLS-3


23.

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

JUST AFTER CASTING OF DECK & WITH SHUTTERING ON GIRDER

From 28 days to 35 days

0.000
0.000
-0.012

0.000
0.000
-0.008

0.000
0.000
0.030

0.000
0.000
0.033

0.000
0.000
0.038

0.000
0.000
0.068

0.000
0.000
0.085

0.000
0.000
0.088

0.000
0.000
0.089

0.000
0.000
0.074

0.000
0.000
0.044

0.000
0.000
0.039

0.000
0.000
0.035

0.000
0.000
-0.007

0.000
0.000
-0.012

-0.139

-0.144

-0.189

-0.298

-0.305

-0.346

-0.374

-0.384

-0.393

-0.378

-0.342

-0.334

-0.214

-0.164

-0.158

0.000
0.000
1.944
8.315

0.000
0.000
-0.787
11.345

0.000
0.000
-0.957
17.874

0.000
0.000
-1.328
18.292

0.000
0.000
-3.547
20.812

0.000
0.000
-4.785
22.299

0.000
0.000
-4.886
22.531

0.000
0.000
-4.849
22.614

0.000
0.000
-3.635
21.320

0.000
0.000
-1.387
18.839

0.000
0.000
-1.006
18.412

0.000
0.000
-0.831
11.703

0.000
0.000
1.979
8.593

0.000
0.000
2.330
8.209

0.000
0.000
4.282
12.383

0.000
0.000
4.310
12.383

0.000
0.000
4.933
11.926

0.000
0.000
5.801
11.206

0.000
0.000
6.418
10.685

0.000
0.000
5.737
11.521

0.000
0.000
4.844
12.434

0.000
0.000
4.252
12.930

0.000
0.000
4.234
12.921

0.000
0.000
1.627
9.045

0.000
0.000
1.969
8.604

0.000
0.000
2.330
8.209

35 days )
0.000
0.000
2.286
7.941

1.00 x G9 + 1.00 x (G1,1 + G1,2 + G1,3)


MPa
MPa
MPa

0.000
0.000
2.286
7.941

0.000
0.000
1.934
8.326

0.000
0.000
1.671
8.687

For Precast Girder (Non-Composite)


Max. compressive stress

12.930 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

1.627 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

STRESS LIMIT CHECK FOR SLS-4


26.

Loss of Prestress

26a
26b

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

26c
26d

At Top of Deck Slab


At Bottom of Deck Slab

( At

MPa
MPa
MPa
MPa

Eff. Prestress

(G9)

27a
27b
27c

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder

27d

At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

28.

Resultant Stresses in Girder

ft_slab
At Top of Deck Slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
Min. compressive stress
For RCC Deck Slab

Min. stress

1.00 x G9 +

due to Shrinkage+Creep+ Relaxation from Stage-I & Stage-II

27.

25a
25b
25c
25d

49 days )

( At
MPa
MPa
MPa
MPa

MPa
MPa
MPa

=
=
=

1.00 x G12 JUST AFTER COMPOSITE ACTION & REMOVAL OF SHUTTERING

From 35 days to 49 days

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

0.000
0.000

-0.017
-0.063

-0.015
-0.066

0.007
-0.090

0.009
-0.150

0.012
-0.154

0.030
-0.176

0.041
-0.190

0.042
-0.193

0.042
-0.194

0.032
-0.183

0.013
-0.162

0.009
-0.158

0.007
-0.095

-0.015
-0.070

-0.018
-0.067

0.000
0.000
2.268

0.000
0.000
1.929

0.000
0.000
-0.781

0.000
0.000
-0.949

0.000
0.000
-1.316

0.000
0.000
-3.516

0.000
0.000
-4.744

0.000
0.000
-4.844

0.000
0.000
-4.807

0.000
0.000
-3.604

0.000
0.000
-1.374

0.000
0.000
-0.997

0.000
0.000
-0.824

0.000
0.000
1.963

0.000
0.000
2.312

7.878

8.249

11.255

17.724

18.138

20.636

22.109

22.338

22.420

21.137

18.677

18.254

11.608

8.523

8.142

-1.363
-1.484
6.969
10.351

-1.363
-1.363
-1.484
-1.484
6.295
5.413
11.178
12.080
HENCE O.K.
HENCE O.K.

-1.363
-1.484
4.830
12.567

-1.363
-1.484
4.813
12.558

-1.363
-1.484
2.232
8.717

-1.363
-1.484
2.575
8.275

0.000
0.000
2.312
8.142

49 days )

1.00 x G9 + 1.00 x (G1,1 + G1,2) + 1.00 x G12

MPa

1.00 x G1 +

0.000
-1.363
0.000
-1.484
2.268
2.541
7.878
8.001
12.567 MPa
2.232 MPa
-1.484 MPa

(Including Differential Shrinkage)

-1.363
-1.484
2.275
8.364
<
>

-1.363
-1.484
4.861
12.028
21.6 MPa
-3.3 MPa

-1.363
-1.363
-1.363
-1.484
-1.484
-1.484
4.888
5.501
6.358
12.028
11.579
10.867
(Allowable Compressive stress)
(Allowable Tensile stress)

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

(39)

HENCE O.K.

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Loss of Prestress

29a

ft_slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

29b
29c
29d

At Top of Deck Slab

30.

Eff. Prestress

(G9)

30a
30b
30c
30d

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

( At

From 49 days to 63 days

0.010

0.010

0.014

0.016

0.016

0.016

0.014

0.011

0.010

0.007

0.001

0.001

MPa

-0.005

-0.005

-0.001

-0.003

-0.003

0.000

0.001

0.001

0.001

0.000

-0.003

-0.003

-0.001

-0.005

-0.005

MPa

-0.005

-0.005

-0.001

-0.003

-0.003

0.000

0.001

0.001

0.001

0.000

-0.003

-0.003

-0.001

-0.005

-0.005

MPa

-0.045

-0.047

-0.056

-0.096

-0.097

-0.106

-0.111

-0.112

-0.113

-0.109

-0.100

-0.098

-0.058

-0.048

-0.047

0.001
-0.005
1.925
8.203

0.007
-0.001
-0.782
11.199

0.010
-0.003
-0.952
17.628

0.010
-0.003
-1.319
18.041

0.014
0.000
-3.517
20.530

0.016
0.001
-4.743
21.998

0.016
0.001
-4.843
22.226

0.016
0.001
-4.806
22.307

0.014
0.000
-3.604
21.028

0.011
-0.003
-1.377
18.577

0.010
-0.003
-1.000
18.155

0.007
-0.001
-0.825
11.550

0.001
-0.005
1.959
8.475

0.001
-0.005
2.307
8.095

( At

63 days )

MPa

0.001
-0.005
2.263
7.833

MPa

0.001

1.090

1.279

1.432

1.457

1.662

1.847

1.978

1.847

1.663

1.457

1.433

1.280

1.090

0.001

MPa

-0.005

-2.307

-2.180

-2.099

-2.084

-1.957

-1.843

-1.762

-1.843

-1.957

-2.084

-2.099

-2.179

-2.307

-0.005

MPa
MPa
MPa

CASE-1

WITHOUT CWLL PLACEMENT & TEMPERATURE RISE CASE

MPa

2.263

1.718

1.580

4.246

4.288

5.028

6.000

6.691

5.936

4.941

4.231

4.198

1.536

1.752

2.307

MPa

7.833

9.067

9.106

12.324

12.271

11.378

10.266

9.467

10.576

11.876

12.807

12.851

9.457

9.339

8.095

12.851 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

1.536 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.307 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

32.

Resultant Stresses in Girder + Slab

32a

At Top of Deck Slab

CASE-2

WITHOUT CWLL PLACEMENT & TEMPERATURE FALL CASE

MPa

0.001

-2.690

-2.501

-2.348

-2.324

-2.118

-1.934

-1.803

-1.933

-2.118

-2.323

-2.348

-2.501

-2.690

0.001

MPa

-0.005

-0.872

-0.745

-0.664

-0.649

-0.522

-0.408

-0.327

-0.408

-0.522

-0.649

-0.664

-0.744

-0.872

-0.005

MPa

2.263

3.153

3.015

5.681

5.723

6.463

7.435

8.126

7.371

6.376

5.666

5.633

2.971

3.187

2.307

MPa

7.833

6.473

6.512

9.730

9.677

8.783

7.672

6.873

7.981

9.282

10.213

10.257

6.863

6.745

8.095

10.257 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

2.263 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.690 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

33.

Resultant Stresses in Girder

33a

At Top of Deck Slab

ft_slab
33b
fb_slab
At Bottom of Deck Slab
33c
At Top of Precast Girder ft_girder
33d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress

AT THE OPENING FOR TRAFFIC

0.007

Min. compressive stress

ft_slab
32b
fb_slab
At Bottom of Deck Slab
32c
At Top of Precast Girder ft_girder
32d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress

0.60 x Q8

0.001

Resultant Stresses in Girder

For RCC Deck Slab

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

0.001

At Top of Deck Slab

For RCC Deck Slab

1.00 x G9 +

MPa

31a

For RCC Deck Slab

63 days )

due to Shrinkage+Creep+ Relaxation from Stage-I & Stage-II

31.

ft_slab
31b
fb_slab
At Bottom of Deck Slab
31c
At Top of Precast Girder ft_girder
31d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress

Right Anchor

0.000 m

STRESS LIMIT CHECK FOR SLS-5


29.

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

CASE-3

WITH CWLL PLACEMENT & TEMPERATURE RISE CASE

MPa

0.001

1.090

2.005

2.655

2.736

3.419

3.758

3.889

3.758

3.420

2.736

2.655

2.005

1.090

0.001

MPa

-0.005

-2.307

-1.691

-1.343

-1.294

-0.871

-0.662

-0.581

-0.662

-0.871

-1.294

-1.343

-1.691

-2.307

-0.005

MPa

2.263

1.718

2.068

5.001

5.079

6.114

7.181

7.872

7.118

6.027

5.021

4.953

2.025

1.752

2.307

MPa

7.833

9.067

7.867

9.684

9.509

7.583

6.138

5.339

6.447

8.081

10.045

10.211

8.218

9.339

8.095

10.211 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

1.718 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.307 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

(40)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

34.

Resultant Stresses in Girder + Slab

34a

At Top of Deck Slab

ft_slab
34b
fb_slab
At Bottom of Deck Slab
34c
At Top of Precast Girder ft_girder
34d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
For RCC Deck Slab

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CASE-4

WITH CWLL PLACEMENT & TEMPERATURE FALL CASE

0.001

-2.690

-1.775

-1.126

-1.045

-0.361

-0.022

0.109

-0.022

-0.361

-1.045

-1.125

-1.775

-2.690

0.001

MPa

-0.005

-0.872

-0.256

0.092

0.141

0.564

0.773

0.854

0.773

0.564

0.141

0.092

-0.256

-0.872

-0.005

MPa

2.263

3.153

3.503

6.436

6.514

7.549

8.616

9.307

8.553

7.462

6.456

6.388

3.460

3.187

2.307

MPa

7.833

6.473

5.272

7.089

6.915

4.988

3.544

2.745

3.853

5.487

7.451

7.617

5.623

6.745

8.095

9.307 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.690 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

Eff. Prestress

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

ft_slab
fb_slab
ft_girder
fb_girder

(G9)
ft_slab
fb_slab
ft_girder
fb_girder

Long Term (At infinity days )

ft_slab
At Top of Deck Slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
Min. compressive stress
For RCC Deck Slab
Min. stress

MPa
MPa
MPa

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

0.60 x Q8

LONG TERM EFFECT

MPa

-0.007
-0.130
-0.130
-1.024

0.009
-0.119
-0.119
-1.052

0.138
-0.034
-0.034
-1.288

0.195
-0.078
-0.078
-2.062

0.211
-0.069
-0.069
-2.101

0.304
-0.015
-0.015
-2.339

0.360
0.014
0.014
-2.496

0.367
0.016
0.016
-2.537

0.370
0.015
0.015
-2.567

0.319
-0.016
-0.016
-2.451

0.224
-0.072
-0.072
-2.221

0.207
-0.081
-0.081
-2.181

0.147
-0.035
-0.035
-1.363

0.011
-0.125
-0.125
-1.116

-0.006
-0.137
-0.137
-1.086

0.010
-0.124
1.805
7.150

0.145
-0.035
-0.816
9.911

0.205
-0.081
-1.029
15.566

0.221
-0.072
-1.388
15.940

0.318
-0.016
-3.532
18.191

0.376
0.015
-4.728
19.502

0.384
0.017
-4.827
19.689

0.386
0.016
-4.791
19.741

0.333
-0.017
-3.620
18.577

0.234
-0.075
-1.449
16.356

0.217
-0.084
-1.081
15.975

0.154
-0.036
-0.860
10.187

0.012
-0.130
1.834
7.359

-0.005
-0.142
2.171
7.009

2.384
-1.744
6.225
8.899

2.255
2.015
-1.827
-1.975
5.472
4.563
9.983
11.282
HENCE O.K.
HENCE O.K.
HENCE O.K.

1.704
-2.163
4.014
12.222

1.662
-2.189
4.009
12.268

1.442
-2.218
1.415
9.113

1.102
-2.445
1.810
8.959

-0.006
-0.156
2.388
7.709

-1.397
-0.309
7.660
6.305

-1.525
-1.766
-0.392
-0.540
6.907
5.998
7.389
8.688
HENCE O.K.
HENCE O.K.
HENCE O.K.

-2.076
-0.728
5.449
9.628

-2.119
-0.754
5.444
9.674

-2.338
-0.783
2.850
6.519

-2.678
-1.010
3.245
6.365

-0.006
-0.156
2.388
7.709

(At infinity days )


MPa
MPa
MPa
MPa

-0.007
-0.135
2.133
6.809

CASE-1

MPa
MPa
MPa
MPa

=
=
=

Resultant Stresses in Girder + Slab

ft_slab
At Top of Deck Slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
Min. compressive stress
For RCC Deck Slab
Min. stress

1.10 x G9 +

with Superior value of Prestress ,sup


due to Shrinkage+Creep+ Relaxation from Stage-I & Stage-II
From 63 days to Infinity

Resultant Stresses in Girder

37a
37b
37c
37d

38a
38b
38c
38d

3.644 m

2.263 MPa

Loss of Prestress

38.

3.350 m

At Top of Deck Slab


At Bottom of Deck Slab
At Top of Precast Girder
At Bott. of Precast Gir.

37.

1.850 m

35a
35b
35c
35d
36a
36b
36c
36d

0.200 m

Min. compressive stress

35.

Right Anchor

0.000 m

MPa

STRESS LIMIT CHECK FOR SLS-6

36.

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

MPa
MPa
MPa
MPa

=
=
=

-0.007
1.100
-0.149
-2.438
2.347
1.779
7.489
8.730
12.268 MPa
1.415 MPa
-2.445 MPa

CASE-2
-0.007
-2.680
-0.149
-1.003
2.347
3.214
7.489
6.135
9.674 MPa
2.347 MPa
-2.680 MPa

WITHOUT CWLL PLACEMENT & TEMPERATURE RISE CASE


1.432
-2.217
1.464
8.810
<
>
>

1.648
-2.185
4.065
11.818
21.6 MPa
-3.3 MPa
-3.3 MPa

1.690
1.998
2.244
-2.160
-1.974
-1.827
4.081
4.659
5.541
11.765
10.857
9.721
(Allowable Compressive stress)
(Allowable Tensile stress)
(Allowable Tensile stress in deck conc.)

WITHOUT CWLL PLACEMENT & TEMPERATURE FALL CASE


-2.349
-0.782
2.899
6.216
<
>
>

-2.132
-0.750
5.500
9.224
21.6 MPa
-3.3 MPa
-3.3 MPa

-2.091
-1.782
-1.536
-0.725
-0.539
-0.392
5.516
6.094
6.976
9.170
8.263
7.127
(Allowable Compressive stress)
(Allowable Tensile stress)
(Allowable Tensile stress in deck conc.)

(41)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

39.

40.

MPa
MPa

=
=
=

MPa
MPa
MPa
MPa

=
=
=

STRESS LIMIT CHECK FOR SLS-7


41.

Loss of Prestress

41a

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

41d

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CASE-4
-0.007
-2.680
-0.149
-1.003
2.347
3.214
7.489
6.135
8.841 MPa
2.177 MPa
-2.680 MPa

WITH CWLL PLACEMENT & TEMPERATURE RISE CASE


2.158
-1.729
1.952
7.570
<
>
>

2.871
-1.429
4.821
9.178
21.6 MPa
-3.3 MPa
-3.3 MPa

2.968
3.755
4.155
-1.369
-0.888
-0.646
4.871
5.745
6.723
9.003
7.062
5.593
(Allowable Compressive stress)
(Allowable Tensile stress)
(Allowable Tensile stress in deck conc.)

4.295
-0.563
7.406
4.771

4.167
3.772
-0.645
-0.889
6.653
5.648
5.855
7.487
HENCE O.K.
HENCE O.K.
HENCE O.K.

2.983
-1.373
4.804
9.460

2.884
-1.433
4.764
9.628

2.168
-1.730
1.903
7.873

1.102
-2.445
1.810
8.959

-0.006
-0.156
2.388
7.709

0.514
0.872
8.841
2.177

0.386
-0.009
0.790
0.546
8.088
7.083
3.261
4.893
HENCE O.K.
HENCE O.K.
HENCE O.K.

-0.798
0.062
6.239
6.866

-0.896
0.002
6.199
7.034

-1.612
-0.295
3.338
5.279

-2.678
-1.010
3.245
6.365

-0.006
-0.156
2.388
7.709

WITH CWLL PLACEMENT & TEMPERATURE FALL CASE


-1.623
-0.294
3.387
4.976
<
>
>

-0.910
0.006
6.256
6.584
21.6 MPa
-3.3 MPa
-3.3 MPa

Long Term (At infinity days )

-0.812
-0.025
0.375
0.066
0.547
0.789
6.306
7.180
8.158
6.408
4.468
2.998
(Allowable Compressive stress)
(Allowable Tensile stress)
(Allowable Tensile stress in deck conc.)

0.90 x G9 +

1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 1.00 x Q1 + 1.00 x Q2 +

0.60 x Q8

LONG TERM EFFECT

with Inferior value of Prestress ,inf


due to Shrinkage+Creep+ Relaxation from Stage-I & Stage-II
From 63 days to Infinity
MPa

-0.007

0.009

0.138

0.195

0.211

0.304

0.360

0.367

0.370

0.319

0.224

0.207

0.147

0.011

MPa

-0.130

-0.119

-0.034

-0.078

-0.069

-0.015

0.014

0.016

0.015

-0.016

-0.072

-0.081

-0.035

-0.125

-0.137

MPa

-0.130

-0.119

-0.034

-0.078

-0.069

-0.015

0.014

0.016

0.015

-0.016

-0.072

-0.081

-0.035

-0.125

-0.137

MPa

-1.024

-1.052

-1.288

-2.062

-2.101

-2.339

-2.496

-2.537

-2.567

-2.451

-2.221

-2.181

-1.363

-1.116

-1.086

42a

ft_slab
fb_slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.

42c

6.138 m

At Bottom of Deck Slab

Eff. Prestress

42d

3.644 m

At Top of Deck Slab

42.
42b

3.350 m

Resultant Stresses in Girder + Slab

ft_slab
At Top of Deck Slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
Min. compressive stress
For RCC Deck Slab
Min. stress

41c

1.850 m

CASE-3
MPa

40a
40b
40c
40d

41b

0.200 m

-0.007
1.100
-0.149
-2.438
2.347
1.779
7.489
8.730
9.628 MPa
1.779 MPa
-2.445 MPa

MPa

Right Anchor

0.000 m

Resultant Stresses in Girder

ft_slab
At Top of Deck Slab
fb_slab
At Bottom of Deck Slab
At Top of Precast Girder ft_girder
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
Min. compressive stress
For RCC Deck Slab
Min. stress
39a
39b
39c
39d

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

(G9)

-0.006

(At infinity days )

At Top of Deck Slab

MPa

-0.007

0.010

0.145

0.205

0.221

0.318

0.376

0.384

0.386

0.333

0.234

0.217

0.154

0.012

-0.005

At Bottom of Deck Slab

MPa

-0.135

-0.124

-0.035

-0.081

-0.072

-0.016

0.015

0.017

0.016

-0.017

-0.075

-0.084

-0.036

-0.130

-0.142

MPa

2.133

1.805

-0.816

-1.029

-1.388

-3.532

-4.728

-4.827

-4.791

-3.620

-1.449

-1.081

-0.860

1.834

2.171

MPa

6.809

7.150

9.911

15.566

15.940

18.191

19.502

19.689

19.741

18.577

16.356

15.975

10.187

7.359

7.009

MPa

-0.006

1.098

1.403

1.607

1.645

1.935

2.169

2.307

2.178

1.948

1.657

1.618

1.411

1.100

-0.005

MPa

-0.122

-2.414

-2.210

-2.168

-2.145

-1.971

-1.830

-1.747

-1.830

-1.971

-2.148

-2.172

-2.211

-2.419

-0.127

43.

Resultant Stresses in Girder

43a

At Top of Deck Slab

ft_slab
43b
fb_slab
At Bottom of Deck Slab
43c
At Top of Precast Girder ft_girder
43d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
For RCC Deck Slab

CASE-1

WITHOUT CWLL PLACEMENT & TEMPERATURE RISE CASE

MPa

1.920

1.418

1.627

4.271

4.358

5.366

6.487

7.190

6.430

5.287

4.304

4.225

1.587

1.444

1.954

MPa

6.128

7.300

6.828

8.705

8.577

7.219

5.821

4.961

6.035

7.567

8.951

9.073

7.076

7.488

6.308

9.073 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

1.418 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.419 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

(42)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

44.

Resultant Stresses in Girder + Slab

44a

At Top of Deck Slab

ft_slab
44b
fb_slab
At Bottom of Deck Slab
44c
At Top of Precast Girder ft_girder
44d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
For RCC Deck Slab

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CASE-2

WITHOUT CWLL PLACEMENT & TEMPERATURE FALL CASE

-0.006

-2.682

-2.378

-2.173

-2.135

-1.846

-1.612

-1.474

-1.602

-1.832

-2.123

-2.162

-2.369

-2.680

-0.005

MPa

-0.122

-0.979

-0.775

-0.733

-0.710

-0.536

-0.395

-0.313

-0.395

-0.536

-0.713

-0.737

-0.776

-0.984

-0.127

MPa

1.920

2.853

3.062

5.706

5.793

6.801

7.922

8.625

7.865

6.722

5.739

5.660

3.022

2.879

1.954

MPa

6.128

4.705

4.233

6.111

5.982

4.625

3.226

2.367

3.441

4.973

6.357

6.479

4.482

4.893

6.308

8.625 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

1.920 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.682 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

Resultant Stresses in Girder

45a

At Top of Deck Slab

CASE-3

WITH CWLL PLACEMENT & TEMPERATURE RISE CASE

MPa

-0.006

1.098

2.129

2.830

2.924

3.692

4.080

4.218

4.090

3.705

2.936

2.841

2.137

1.100

-0.005

MPa

-0.122

-2.414

-1.722

-1.413

-1.355

-0.885

-0.649

-0.566

-0.648

-0.885

-1.358

-1.416

-1.723

-2.419

-0.127

MPa

1.920

1.418

2.115

5.027

5.149

6.452

7.668

8.371

7.612

6.373

5.094

4.980

2.075

1.444

1.954

MPa

6.128

7.300

5.588

6.065

5.815

3.424

1.692

0.833

1.907

3.772

6.189

6.433

5.836

7.488

6.308

8.371 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

0.833 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.419 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

46.

Resultant Stresses in Girder + Slab

46a

At Top of Deck Slab

ft_slab
46b
fb_slab
At Bottom of Deck Slab
46c
At Top of Precast Girder ft_girder
46d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress
For RCC Deck Slab

0.200 m

Min. compressive stress

ft_slab
45b
fb_slab
At Bottom of Deck Slab
45c
At Top of Precast Girder ft_girder
45d
fb_girder
At Bott. of Precast Gir.
For Precast Girder
Max. compressive stress

Right Anchor

0.000 m

MPa

45.

For RCC Deck Slab

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

CASE-4

WITH CWLL PLACEMENT & TEMPERATURE FALL CASE

MPa

-0.006

-2.682

-1.652

-0.951

-0.856

-0.089

0.300

0.438

0.309

-0.075

-0.845

-0.940

-1.643

-2.680

-0.005

MPa

-0.122

-0.979

-0.287

0.022

0.080

0.550

0.786

0.869

0.787

0.550

0.077

0.019

-0.288

-0.984

-0.127

MPa

1.920

2.853

3.550

6.462

6.584

7.887

9.103

9.806

9.047

7.808

6.529

6.415

3.510

2.879

1.954

MPa

6.128

4.705

2.994

3.471

3.220

0.830

-0.902

-1.761

-0.688

1.178

3.595

3.839

3.242

4.893

6.308

9.806 MPa

<

21.6 MPa

(Allowable Compressive stress)

HENCE O.K.

Min. compressive stress

-1.761 MPa

>

-3.3 MPa

(Allowable Tensile stress)

HENCE O.K.

Min. stress

-2.682 MPa

>

-3.3 MPa

(Allowable Tensile stress in deck conc.)

HENCE O.K.

(43)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

DECOMPRESSION LIMIT CHECK FOR SLS-8

Long Term (At infinity days )

(FOR FREQUENT LOAD COMBINATION)


Considering Outer Diameter of sheathing
Section under consideration

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

1.00 x G9 + 1.00 x G1 + 1.00 x G2 + 1.00 x G3 + 1.00 x G12 + 0.75 x Q1 + 0.75 x Q2 +

0.50 x Q8

Decompression requires requires that no tensile stresses occur within 100mm of the surface of the duct for bonded prestressing tendons.
=

80 mm (assumed)
Left Anchor. 0.000 L Sec

Section Properties of Composite Section

(Refer Cl: 12.3.2 of IRC:112-2011)


0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

c.g. of Section from Top of Deck Slab Yt

0.672

0.672

0.672

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.576

0.672

0.672

0.672

Moment of Inertia of Section


Overall Depth of the Section

m4
m
m
m
m

0.593
1.820
0.300
0.9880
0.1600
0.5999

0.593
1.820
0.287
1.0010
0.1469
0.5921

0.593
1.820
0.186
1.1023
0.0457
0.5377

0.499
1.820
0.132
1.2440
0.0000
0.4007

0.499
1.820
0.127
1.2440
0.0000
0.4007

0.499
1.820
0.120
1.2440
0.0000
0.4007

0.499
1.820
0.120
1.2440
0.0000
0.4007

0.499
1.820
0.120
1.2440
0.0000
0.4007

0.499
1.820
0.120
1.2440
0.0000
0.4007

0.499
1.820
0.120
1.2440
0.0000
0.4007

0.499
1.820
0.127
1.2440
0.0000
0.4007

0.499
1.820
0.132
1.2440
0.0000
0.4007

0.593
1.820
0.186
1.1023
0.0457
0.5377

0.593
1.820
0.287
1.0010
0.1469
0.5921

0.593
1.820
0.300
0.9880
0.1600
0.5999

(At infinity days )


fb,d
MPa

6.341

6.659

9.605

15.566

15.940

18.191

19.502

19.689

19.741

18.577

16.356

15.975

9.871

6.852

6.525

fb,d

MPa

0.000

0.009

-2.488

-5.437

-5.851

-8.798

-10.983

-11.729

-10.983

-8.798

-5.851

-5.437

-2.488

0.009

0.000

fb,d

MPa

0.000

0.000

-0.084

-0.200

-0.217

-0.362

-0.551

-0.761

-0.551

-0.362

-0.217

-0.200

-0.084

0.000

0.000

Stress at 100m below lowest tendon

fb,d

MPa

0.000

0.000

-0.218

-0.522

-0.556

-0.846

-1.051

-1.123

-1.051

-0.846

-0.556

-0.522

-0.218

0.000

0.000

Stress due to Differential Shrinkage

(G12)
MPa

0.000

-0.178

-0.234

-0.259

-0.259

-0.259

-0.259

-0.259

-0.259

-0.259

-0.259

-0.259

-0.234

-0.178

0.000

MPa

0.000

1.559

1.763

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.854

1.763

1.559

0.000

MPa

0.000

-2.148

-2.370

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.469

-2.370

-2.148

0.000

MPa

0.000

-1.190

-2.640

-2.762

-3.795

-4.128

-4.128

-4.128

-3.795

-2.762

-2.640

-1.190

0.000

0.000

6.745

7.824
9.239
HENCE O.K.

10.401

10.485

7.730

7.462

6.525

4.583

5.662

8.239

8.323

5.664

5.608

6.525

Iz
D

Height of Lowest tendon from Soffit of Girder


Depth of Section below cg reqd. for decompression
Depth of Section above soffit reqd. for decompression
Sec.Modulus of Sec. for Decompression Check Zb,d

Eff. Prestress

(G9)

Stress at 100m below lowest tendon

Stresses due to DL

(G1)

Stress at 100m below lowest tendon

Stresses due to SDL1

(G2)

Stress at 100m below lowest tendon

Stresses due to SDL2

m3

(G3)

Stress at 100m below lowest tendon

fb,d

Stress due to Temperature Rise

(Q8,1)

Stress at 100m below lowest tendon

fb,d

Stress due to Temperature Fall

(Q8,2)

Stress at 100m below lowest tendon

fb,d

Stress due to CWLL on deck

(Q1 + Q2)

Stress at 100m below lowest tendon

fb,d

Resultant Stresses at 100mm below Lowest Tendon


fb,d
Stress at 100m below lowest tendon
For Precast Girder
Min. compressive stress

MPa

6.341
7.270
6.341 MPa

Resultant Stresses at 100mm below Lowest Tendon


Stress at 100m below lowest tendon
fb,d
For Precast Girder
Min. compressive stress

MPa

MPa

MPa

CASE-3

6.341
7.270
3.649 MPa

Resultant Stresses at 100mm below Lowest Tendon


Stress at 100m below lowest tendon
fb,d
For Precast Girder
Min. compressive stress

CASE-2

6.341
5.416
4.583 MPa

Resultant Stresses at 100mm below Lowest Tendon


Stress at 100m below lowest tendon
fb,d
For Precast Girder
Min. compressive stress

0.000

CASE-1

CASE-4

6.341
5.416
1.487 MPa

WITHOUT CWLL PLACEMENT & TEMPERATURE RISE CASE


7.464
>

10.076
-3.3 MPa

9.985
8.853
(Allowable Tensile stress)

7.585

WITHOUT CWLL PLACEMENT & TEMPERATURE FALL CASE


5.397
>

7.914
-3.3 MPa

7.823
6.691
(Allowable Tensile stress)

5.424

7.077

HENCE O.K.

WITH CWLL PLACEMENT & TEMPERATURE RISE CASE


6.571
>

8.096
-3.3 MPa

7.914
6.006
(Allowable Tensile stress)

4.489

3.649

4.727
6.393
HENCE O.K.

8.330

8.505

6.837

7.462

6.525

1.487

2.565
4.231
HENCE O.K.

6.168

6.343

4.771

5.608

6.525

WITH CWLL PLACEMENT & TEMPERATURE FALL CASE


4.505
>

5.934
-3.3 MPa

5.752
3.845
(Allowable Tensile stress)

(44)

2.327

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CHECK FOR ULTIMATE MOMENT


1.00 x G9 +
ULS MOMENT CHECK FOR ULS-1
(At infinity days )
(FOR BASIC LOAD COMBINATION)

Right Anchor

0.000 m

Considered as
Resistance

1.35 x G1 + 1.35 x G2 +

1.75 x G3 + 1.50 x Q1 +

fcd

cu3

Ac

di

Fcs1

Section under consideration

Acs1

1.50 x Q2

cs1

Long Term Assuming neutral axis lies within the top flange

Fc

Stress-Strain Relationship of Concrete at ULS :


c3
cu3

fcd

d2

Rectangular Stress Distribution

0.8

0.8

0.67
1
20.1

0.67
1
20.1

N/mm2

Compressive strain at peak stress for Rectangle Stress Distribution


Ultimate compressive strain for Rectangle Stress Distribution
Coefficient to convert to rectangular stress block
Coefficient to convert to rectangular stress block
Coefficient to convert the strength in test to strength in structral member
for age t >
Coefficient to convert the strength in test to strength in structral member
for age t <
Compressive design strength of concrete: fcd = ( c x fcu) / m for Basic and Seismic Combination

25.125

25.125

N/mm2

Compressive design strength of concrete: fcd = ( c x fcu) / m for Accidental Combination

0.0018
0.0035
1.0

Considering

0.0018
0.0035
1.0

Section under consideration

Left Anchor. 0.000 L Sec

Ultimate Design Flexural Moment

MEd

Overall Depth of the Section


Width of Web

As2

d1

As1
Section (s chematic)

28 days
28 days
for age t >
for age t >

s2

Fs2

s1

Fs1

Strain

Stres s

28 days
28 days

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

kN-m

0.000

-4.584

2354.434

4048.730

4306.520

6287.425

7532.721

7969.395

7532.721

6287.425

4306.520

4048.730

2354.434

-4.584

1820

1820

1820.0

1820

1820

1820

1820

1820

1820

1820

1820

1820

1820

1820

0.000
1820

mm

700.0

700

700.0

275.0

275.0

275.0

275.0

275.0

275.0

275.0

275.0

275.0

700.0

700.0

700.0

Width of Deck Slab

Bf

mm

3000.0

3000

3000

3000

3000

3000

3000

3000

3000

3000

3000

3000

3000

3000

3000.0

Thickness of Top Flange

Tf

mm

220.0

220

220

220

220

220

220

220

220

220

220

220

220

220

220.0

cg. of group of cables from Soffit

Ycab

mm

676

656

496

383

366

261

205

201

205

261

365

382

494

655

675

D - Ycab

mm

676

1164

1324

1437

1454

1559

1615

1619

1615

1559

1455

1438

1326

1165

675

mm

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

1184.400

fp,0.1k

MPa

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

1618

kN

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

mm

117

117

117

117

117

117

117

117

117

117

117

117

117

117

117

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

1300

1269

1017

824

791

570

447

440

447

570

791

824

1017

1269

1300

Eff. Depth to centroid of tendons Dp =

Area of one tendon

0.1 % proof-stress of prestressing steel


Tendon Force at Yield Fp =

x Ap x

fp,0.1k / m

Depth of Concrete Compression Block

(Assuming N.A. in flange)

x fcd)

x = Fp / ( bf x

Height of highest tendon from Soffit of Girder

Depth of highest tendon from Top of Deck

520

551

803

996

1029

1250

1373

1380

1373

1250

1029

996

803

551

520

MPa

0.009
1016.7

0.010
1017.1

0.016
1022.1

0.020
1027.7

0.021
1029.0

0.026
1037.3

0.029
1046.1

0.029
1052.6

0.029
1058.9

0.026
1058.9

0.021
1054.4

0.020
1053.3

0.016
1048.3

0.010
1043.8

0.009
1043.5

Conc. strain at level of highest tendons ( )

cu3*(d-x)/x

Effective Prestress in tendons

p,eff

Prestrain in tendons ( )

p,eff

s / (Ep)

Minimum strain in tendons


Yield strain of tendons

(fp,0.1k / m) / (Ep)

Moment capacity of Section

MRd

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.005

0.015

0.021

0.026

0.026

0.032

0.035

0.035

0.035

0.032

0.026

0.026

0.021

0.015

0.014

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

0.007

Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields. Tendon yields.

Check for Yielding of Tendons


MRd = Fp x (Dp - x/2)

0.005
0.014

kN-m

4373.9
> MEd

7828.0
> MEd

8964.1
> MEd

9759.0
> MEd

9884.4
> MEd

10626.7
> MEd

11026.4
> MEd

11048.5
> MEd

11024.9
> MEd

10627.7
> MEd

9891.4
> MEd

9766.3
> MEd

8972.9
> MEd

7838.4
> MEd

4363.4
> MEd

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

O.K.

(45)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

CHECK FOR ULTIMATE SHEAR


ULS SHEAR CHECK FOR ULS-1
(At infinity days )
(FOR BASIC LOAD COMBINATION)

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

1.00 x G9 + 1.35 x G1 + 1.35 x G2 +

1.75 x G3 + 1.50 x Q1 +

1.50 x Q2

Long Term Assuming neutral axis lies within the top flange
Nos. of Cables at most unfavourable level in the Section =

80 mm

Considering Outer Diameter of sheathing

Unit

Section under consideration

Left Anchor. 0.000 L Sec

Refer eq. 10.4 of IRC:112-2010 for calculating bw,nom = bw - 0.5

in case of Shear Check with Shear Reinf.)

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

Ultimate Design Shear Force

VEd

kN

1556.7

1556.7

1367.6

1166.2

1131.3

834.2

486.1

189.2

486.1

834.2

1131.3

1166.2

1367.6

1556.7

Co-existing ULS Flexural Moment

MEd

kN-m

0.0

-4.6

2354.4

4048.7

4306.5

6287.4

7532.7

7969.4

7532.7

6287.4

4306.5

4048.7

2354.4

-4.6

0.0

Nos.

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42

1.42
1679.3

Total Nos. of Effective Stage-1 Cables


Final Prestress Force in Stage-1 Cables Fp1
Total Nos. of Effective Stage-2 Cables
Final Prestress Force in Stage-2 Cables Fp2
Total Nos. of Effective Strands
Total Area of prestress steel

Ap

Co-existing Tendon force NEd = Fp = Fp1 + Fp2

Fp = s,inf x (Fp1 + Fp2)

1556.7

kN

1639.6

1640.3

1647.9

1654.8

1656.6

1671.8

1690.6

1702.6

1714.1

1708.0

1694.1

1692.5

1686.6

1679.9

Nos.

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

2.83

kN

3478.36

3479.67

3497.06

3518.54

3522.88

3549.64

3575.36

3595.86

3616.20

3622.21

3613.48

3609.49

3590.02

3574.45

3573.26

Nos.

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

4.25

mm2

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

5034

kN

5117.98

5119.94

5144.95

5173.35

5179.46

5221.48

5265.99

5298.47

5330.30

5330.21

5307.55

5301.97

5276.61

5254.35

5252.58

with ( s,inf = 1.00 )

Smallest width of cross-section in tensile area

mm

700.00

700.00

700.00

275.00

275.00

275.00

275.00

275.00

275.00

275.00

275.00

275.00

700.00

700.00

700.00

Eff. Depth to centroid of main R/f

mm

676.25

1163.90

1324.30

1436.52

1454.23

1559.03

1615.45

1618.58

1615.25

1559.17

1455.22

1437.55

1325.54

1165.37

674.76

Characteristic strength of concrete

fck

MPa

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

45.00

Design value of conc. compression Strength

fcd

MPa

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

20.10

cp

MPa

2.79

2.80

2.81

3.74

3.74

3.78

3.81

3.83

3.85

3.85

3.84

3.83

2.88

2.87

2.87

Mean Comp. Stress in Concrete at cg. of Sec.


cp = NEd / Ac < 0.2 fcd

Shear capacity without Design Shear Reinforcement


Shear Resistance without Shear Reinforcement VRd,c =
Allowance for size effect

1 = Asl /(bw x d) < 0.02

Long. Untensioned Reinf.(Asl)

x (fck)

^1/2

As per Eq. 10.1 of IRC;112-2011

+ 0.15 cp ] x bw x d

1.54

1.41

1.39

1.37

1.37

1.36

1.35

1.35

1.35

1.36

1.37

1.37

1.39

1.41

1.54

0.003

0.001

0.001

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.003

0.001

0.001

0.003

380.69

581.93

647.82

365.23

369.17

392.81

406.64

408.86

409.69

397.89

374.93

370.95

658.32

591.50

385.26

0.40

0.35

0.34

0.33

0.33

0.33

0.33

0.33

0.33

0.33

0.33

0.33

0.34

0.35

0.40

387.28

626.73

706.12

353.82

358.12

383.90

398.92

401.20

401.97

388.99

363.90

359.57

716.73

636.42

391.75

6 Nos.- 16 mm dia

VRd,c =
^3/2

0.33

K = 1 + (200/d) < 2.0

Reinforcement ratio

min = 0.031 (K)

Refer Cl. 10.3.2 of IRC: 112-2010

[ 0.12 K (80 x 1 x fck )^

kN

(ref. eq. 10.3 of IRC:112)

VRd,c(min)

kN

VRd,c(min) = ( min +0.15 x cp ) x bw x d


Hence, adopted for VRd,c for Checking VRd,c
Check for Requirement for Shear Reinforcement

kN

387.28

626.73

706.12

365.23

369.17

392.81

406.64

408.86

409.69

397.89

374.93

370.95

716.73

636.42

391.75

< VEd

< VEd

< VEd

< VEd

< VEd

< VEd

< VEd

> VEd

< VEd

< VEd

< VEd

< VEd

< VEd

< VEd

< VEd

Required

Required

Required

Required

Required

Required

Required

Not Reqd.

Required

Required

Required

Required

Required

Required

Required

(46)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

Shear Capacity with Design Shear Reinforcement

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Refer Cl. 10.3.2 of IRC: 112-2010

Smallest width of cross-section in tensile area b =bw - 0.5

mm

660.00

660.00

660.00

235.00

235.00

235.00

235.00

235.00

235.00

235.00

235.00

235.00

660.00

660.00

660.00

Depth of Precast Girder Alone

Dgir

mm

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1600.0

1148.0
2.64E+11

1148.0

1148.0

1244.0

1244.0

1244.0

1244.0

1244.0

1244.0

1244.0

1244.0

1244.0

1148.0

1148.0

1148.0

2.64E+11

2.64E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.22E+11

2.64E+11

2.64E+11

2.64E+11

c.g. of Composite Section from Soffit

Yb

mm

Second Moment of Area of Precast Sec. alone

Ip

mm4

Second Moment of Area of Composite Section

Ic

mm4

5.93E+11

5.93E+11

5.93E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

4.99E+11

5.93E+11

5.93E+11

5.93E+11

(Ay)p

mm3

9.03E+07

9.03E+07

9.03E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

5.42E+07

9.03E+07

9.03E+07

9.03E+07

First Moment of Area of Composite Section

(AY)c

mm3

4.61E+08

4.61E+08

4.61E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

3.62E+08

4.61E+08

4.61E+08

4.61E+08

Using Vertical Links for Shear Reinf.

Cot ( )

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

400.00

First Moment of Area of Precast Sec. alone


= /2

fywd

MPa

Characteristic Tensile Strength 5% fractile

fctk,0.05

MPa

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

2.30

Long term Verical Component of Prestress

VPd

kN

508.36

508.55

441.57

319.97

295.95

159.70

37.46

0.00

37.99

163.03

302.53

327.19

452.18

521.24

521.07

Shear Reinf. Design Strength

Design Shear on Precast Sec. before Composite

VEd,1

kN

748.635

748.635

625.142

524.218

506.675

357.744

180.446

3.148

180.446

357.744

506.675

524.218

625.142

748.635

748.635

Design Shear on Precast Sec. after Composite

VEd,2

kN

808.11

808.11

742.42

642.03

624.58

476.47

305.67

186.05

305.67

476.47

624.58

642.03

742.42

808.11

808.11

Design Mom. on Precast Sec. before Composite

MEd,1

kN-m

0.000

-4.584

1128.8

1988.0

2139.4

3217.2

4016.1

4288.6

4016.1

3217.2

2139.4

1988.0

1128.8

-4.6

0.0

Design Mom. on Precast Sec. after Composite

MEd,2

kN-m

0.00

0.0

1225.7

2060.8

2167.1

3070.2

3516.6

3680.8

3516.6

3070.2

2167.1

2060.8

1225.7

0.0

0.0

ft_gir
fb_gir
fcp

MPa

2.263

1.925

-0.782

-0.952

-1.319

-3.517

-4.743

-4.843

-4.806

-3.604

-1.377

-1.000

-0.825

1.959

2.307

MPa

7.833

8.203

11.199

17.628

18.041

20.530

21.998

22.226

22.307

21.028

18.577

18.155

11.550

8.475

8.095

MPa

3.837

3.699

2.603

3.182

2.988

1.833

1.206

1.179

1.226

1.876

3.063

3.262

2.671

3.800

3.942

MPa

0.000

Stress due to Prestress after all losses


At Top of Precast Girder
At Bott. of Precast Girder
Stress due to prestress at Centroidal axis
Stress due to ultimate Moment (MEd1)
Stress at top of precast girder due to MEd,1

ft_gir
fb_gir
fcp

0.000

-0.013

3.287

7.004

7.537

11.335

14.149

15.109

14.149

11.335

7.537

7.004

3.287

-0.013

MPa

0.000

0.014

-3.554

-7.340

-7.899

-11.878

-14.827

-15.834

-14.827

-11.878

-7.899

-7.340

-3.554

0.014

0.000

MPa

0.000

-0.005

1.354

3.813

4.103

6.170

7.702

8.225

7.702

6.170

4.103

3.813

1.354

-0.005

0.000

Stress at top of precast girder due to MEd,2

ft_gir

MPa

0.000

0.000

0.935

1.472

1.547

2.192

2.511

2.628

2.511

2.192

1.547

1.472

0.935

0.000

0.000

Stress at bottom of precast girder due to MEd,2

fb_gir

MPa

0.000

0.000

-2.374

-5.142

-5.408

-7.661

-8.775

-9.185

-8.775

-7.661

-5.408

-5.142

-2.374

0.000

0.000

fcp

MPa

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

ft_gir
fb_gir
fcp

MPa

2.263

1.912

3.440

7.524

7.766

10.010

11.917

12.894

11.854

9.923

7.708

7.476

3.396

1.946

2.307

MPa

7.833

8.217

5.271

5.146

4.734

0.991

-1.605

-2.793

-1.296

1.489

5.270

5.673

5.622

8.489

8.095

MPa

3.837

3.693

3.957

6.995

7.091

8.003

8.909

9.404

8.928

8.046

7.166

7.075

4.025

3.794

3.942

MPa

2.263

1.912

3.440

5.146

4.734

0.991

-1.605

-2.793

-1.296

1.489

5.270

5.673

3.396

1.946

2.307

fctd

MPa

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

-1.53

Cracked

Cracked

Stress at bottom of precast girder due to MEd,1


Stress due to MEd,1 at Centroidal axis
Stress due to ultimate Moment (MEd2)

Stress due to MEd,2 at Centroidal axis


Stress in Precast Beam due to (Prestress + MEd)
Resultant Stress at top of precast girder
Resultant Stress at bottom of precast girder
Resultant Stress at Centroidal axis
Check for tension crack in the Section
Tensile stress in the Section
Design value of conc. tensile strength (fctk,0.05/ m)

Section Type (Cracked/uncracked)

Uncracked.

Uncracked. Uncracked. Uncracked. Uncracked. Uncracked.

(47)

Uncracked. Uncracked. Uncracked. Uncracked. Uncracked. Uncracked. Uncracked.

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

Nos.

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

12
2 legged

Shear Reinforcement Provided


Dia of Shear Stirrups
Numbers of Legs of Link Reinf
Spacing of Link Reinf. Provided

mm
mm

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

@300 mm c/c

Area of Shear Reinforcement


Overall depth of Composite Girder
Depth of from comp. fiber

Asw
D
dt

mm2
mm

226

226

226

226

226

226

226

226

226

226

226

226

226

226

226

mm

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

1820
1752

Yield Strength of Shear Stirrups

fyv

MPa

500

500

500

500

500

500

500

500

500

500

500

500

500

500

500

0.51
0.51
1.14
1048.39
1576.80

0.51
0.51
1.14
1048.19
1576.80

0.51
0.51
1.14
926.00
1576.80

0.51
0.51
1.19
846.28
1576.80

0.51
0.51
1.19
835.30
1576.80

0.51
0.51
1.19
674.52
1576.80

0.51
0.51
1.19
448.66
1576.80

0.51
0.51
1.19
189.20
1576.80

0.51
0.51
1.19
448.12
1576.80

0.51
0.51
1.19
671.19
1576.80

0.51
0.51
1.19
828.72
1576.80

0.51
0.51
1.19
839.05
1576.80

0.51
0.51
1.14
915.38
1576.80

0.51
0.51
1.14
1035.50
1576.80

0.51
0.51
1.14
1035.68
1576.80

11.66

11.66

13.21

5.35

5.43

6.73

10.13

24.04

10.16

6.78

5.49

5.42

13.40

11.84

11.84

Strength Reduction Factor (ref eq 10.6 of IRC:112)


Strength Reduction Factor (Cl. 10.3.1 of IRC:112)
Allowance for the state of stress in compression chord
cw Using Eq. 10.9
Effective Design Shear Force
kN
VEd - VPd
Inner Lever Arm
mm
z
cot + tan Using Eq. 10.8
Consider Conc. Strut Angle be
cotmin/max
1
2.5
max / min
taking VRd,s
cot
equal to VRd,max
Hence,
is the smallest angle before
concrete crushing starts.
Hence,
deg.

VRd,max

kN

Check for ULS Shear Resistance

s,reqd

Required spacing of Shear Reinf.


s = Asw x z x fywd x cot

mm

@300 mm c/c @300 mm c/c

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

2.50

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

22.00

4216.73

1562.41

1564.69

1566.80

1568.34

1569.84

1569.84

1568.77

1568.50

4229.96

4227.72

4227.54

4214.02

4214.21

> Ved - VPd

> Ved - VPd

> Ved - VPd > Ved - VPd

1562.70
> Ved - VPd

> Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd > Ved - VPd

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

340.20

340.27

385.17

421.45

426.99

528.77

794.96

1885.12

795.90

531.39

430.38

425.08

389.63

344.44

344.38

0.0010

VEd - VPd) . Eq. 10.7

Requirement of MinimumShear Reinforcement


0.5

Min.Shear Reinf. Ratio (0.072 x (fck) /fyw)


Max.Spacing of Shear Reinf.=0.75d (1+cot )
Adopted Spacing for Shear Links

Using Eq. 10.20

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

0.0010

sl,max

mm

507.19

872.93

993.22

1077.39

1090.68

1169.27

1211.59

1213.93

1211.44

1169.38

1091.42

1078.16

994.15

874.03

506.07

mm

300.00

300.00

300.00

400.00

400.00

500.00

700.00

1200.00

700.00

500.00

400.00

400.00

300.00

300.00

300.00

Reqd..

Reqd..

Reqd..

Not Reqd.

Not Reqd.

Reqd..

Reqd..

Reqd..

Reqd..

Reqd..

Reqd..

Reqd..

w,min

Check for Web Shear Cracking for Uncracked Section (Refer Cl. 12.3.5 of IRC:112-2011)
Requirement of Check

Reqd..

Reqd..

Reqd..

a. Check at the Composite section Centroid


Direct stress at Section
Shear stress at Composite centroid due to VEd1
Using s1 = VEd1 x (Ay)p / (Ip x b)

c1

MPa

3.84

3.69

3.96

6.99

7.09

8.00

8.93

8.05

7.17

7.07

4.03

3.79

3.94

Ed1

MPa

0.366

0.366

0.305

0.466

0.451

0.318

0.160

0.318

0.451

0.466

0.305

0.366

0.366

Shear stress at Composite centroid due to VEd2


Using s2 = VEd2 x (Ay)c / (Ic x b)

Ed2

MPa

0.898

0.898

0.825

1.694

1.648

1.257

0.807

1.257

1.648

1.694

0.825

0.898

0.898

Total Shear Stress

Ed

MPa

c0

MPa

1.26
1.92
2.30

1.26
1.85
2.24

1.13
1.98
2.28

2.16
3.50
4.11

2.10
3.55
4.12

1.58
4.00
4.30

0.97
4.46
4.57

1.58
4.02
4.32

2.10
3.58
4.15

2.16
3.54
4.14

1.13
2.01
2.31

1.26
1.90
2.28

1.26
1.97
2.34

4.22
-0.38
2.13

4.08
-0.39
2.13

4.26
-0.30
2.13

7.61
-0.61
1.99

7.67
-0.57
1.99

8.30
-0.30
1.96

9.03
-0.10
1.93

8.34
-0.30
1.96

7.74
-0.57
1.98

7.68
-0.61
1.99

4.32
-0.30
2.12

4.18
-0.38
2.13

4.31
-0.37
2.12

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Not Reqd.

Ed1

From Mohr's Circle


sqrt[ Ed^2 + ( c1- c0)^2]

Ed2

center
radius

MPa

Larger Principal stress

3 = Min. of 0.6 fck &

c0

MPa

Smaller Principal stress

1 =

c0

MPa

Conc. tensile strength prior to cracking


f ctb = [ - 0.8 x ( 3 / fck) ] x fctk,0.05

fctb

Check for Min. Longitudinal Reinforcement in the Girder

MPa

(48)

Project

DESIGN CONSULTANCY SERVICES FOR 4-LANING OF KASHIPUR-SITARGANJ SEC. OF NH-74

Designed by:

Client

GALFAR ENGINEERING & CONTRACTING (INDIA) PVT. LTD. / NHAI

Checked by:

--------

Job Name

Design of PSC Precast Post-tensioned Girder & CIP Deck Slab Superstructure for (23.75m eff. Span)

Date & Rev.

25/05/2013 (R0)

S. Rastogi

DESIGN OF INNER LONG. GIRDER (LG2)


Section under consideration

Left Anchor. 0.000 L Sec

Dist. of Section 'X' from Left Side Jacking End (Anchorage)


Dist. of Section 'X' from cL of Left Support
Unit

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec

Right Anchor

0.000 m

0.200 m

1.850 m

3.350 m

3.644 m

6.138 m

9.106 m

12.075 m

15.044 m

18.013 m

20.506 m

20.800 m

22.300 m

23.950 m

24.150 m

-0.200 m

0.000 m

1.650 m

3.150 m

3.444 m

5.938 m

8.906 m

11.875 m

14.844 m

17.813 m

20.306 m

20.600 m

22.100 m

23.750 m

23.950 m

DESIGN OF SHEAR CONNECTORS for Interface Shear between Deck & Top Flange of Precast Girder
Shear Connectors between cast-in-situ deck slab and precast girder are designed to restrain the separation at the interface of two different
concrete. The size and spacing of Shear Connectors are evaluated for long. shear per unit length at the interface of precast girder and slab.
Left Anchor. 0.000 L Sec

Section under consideration

Description

Refer Cl. 10.3.4 of IRC:112-2011

0.069 L Sec 0.133 L Sec 0.145 L Sec 0.250 L Sec 0.375 L Sec 0.500 L Sec 0.625 L Sec 0.750 L Sec 0.855 L Sec 0.867 L Sec 0.931 L Sec 1.000 L Sec Right Anchor

Units

Effective Design Shear Force

VEd

(in kN)

1048.39

1048.19

926.00

846.28

835.30

674.52

448.66

189.20

448.12

671.19

828.72

839.05

915.38

1035.50

1035.68

Total Width of the Flange at Interface

bf

(in mm)

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

3000.00

Thickness of the Top Flange at Interface

hf

(in mm)

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

220.00

Design value of the shear stress at the interface


Width of the Girder Flange at Interface

bi

Lever arm of the composite Section z = (Dp- x/2)


Proportion of longitudinal tensile force carried in top slab

vEdi =

VEd / ( z x bi) . Cl. 10.3.4

(in mm)

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

1000.00

(in mm)

F1 / (F1+F2)

617.52
1.00

1105.17
1.00

1265.56
1.00

1377.79
1.00

1395.50
1.00

1500.30
1.00

1556.72
1.00

1559.85
1.00

1556.52
1.00

1500.44
1.00

1396.49
1.00

1378.82
1.00

1266.81
1.00

1106.64
1.00

616.03
1.00
7083

Where, Compression Force in Top Slab

F1

kN

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

7083

Where, Comp. Force in Precast Gir. above N.A.

F2

kN

vEdi

(N/mm^2)

1.70

0.95

0.73

0.61

0.60

0.45

0.29

0.12

0.29

0.45

0.59

0.61

0.72

0.94

1.68

Design value of interface shear stress


vEdi =

VEd / ( z bi) . Cl. 10.3.4

Design Shear Resistance at the Interface

vRdi =

Ai

Area of the interface


Angle of reinforcement to interface
minimum coexisting normal stress < 0.6 fcd

(mm^2/m)

fyd [ sin + cos ]

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

1000000.0

90.0

90.0

90.0

90.0

90.0

90.0

90.0

1000000.0 1000000.0
90.0

90.0

90.0

90.0

90.0

1000000.0 1000000.0
90.0

deg,

1000000.0
90.0

n)

N/mm^2

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

0.60

Factors dependent on interface roughness

90.0

Assuming smooth surface as per Cl. 10.3.4


Max. Value of Interface stress = 0.5 .

fcd

vRdi, max

N/mm^2

Check for Interface Shear Stress

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

5.2

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

> vEdi

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

O.K..

Dia of Shear Connectos crossing the Joint

mm

12

12

12

12

12

12

12

12

12

12

12

12

12

12

12

Numbers of Legs of Shear Connectors


Spacing of Shear Connectos Provided

Nos.

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

4 legged

s_provided

mm

@60 mm c/c

Area of Shear Connector crossing the joint

As

mm2

452

452

452

452

452

452

452

452

452

452

452

452

452

452

Equating VEdi to VRdi for minimum Reinf. Ratio (

vRdi

N/mm^2

1.70

0.95

0.73

0.61

0.60

0.45

0.29

0.12

0.29

0.45

0.59

0.61

0.72

0.94

1.68

vRdi =

,reqd)

0.007

0.004

0.003

0.003

0.002

0.002

0.001

0.001

0.001

0.002

0.002

0.003

0.003

0.004

0.007

fyd [ sin + cos ]

,min = 0.15% of interface area

Max. Spacing of Links using ( = As/Ai)

min,reqd)

s_reqd

mm

@110 mm c/c @140 mm c/c @170 mm c/c @180 mm c/c @240 mm c/c @300 mm c/c @300 mm c/c @300 mm c/c @240 mm c/c @180 mm c/c @170 mm c/c @150 mm c/c @110 mm c/c @60 mm c/c

452

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

63.95

114.48

148.39

176.76

181.39

241.50

301.59

301.59

301.59

242.71

182.96

178.42

150.26

116.03

64.58

(49)

Вам также может понравиться