Академический Документы
Профессиональный Документы
Культура Документы
Introduction to Project & Interface Management in Deep Offshore Oil & Gas Industry
Public Lecture ISTN 15 June 2013 Antonius Yunianto Offshore Project & Interface Management Professional Offshore-skills.com
offshore-skills.com
Agenda
I Introduction to Project Management in Oil and Gas Industry II
IV
Temporary endeavor with a beginning and an end Creates unique product, service or result Is progressively elaborated Distinguishing characteristics of each unique project progressively detailed as the project is better understood will be
Progressively means proceeding in steps, continuing steadily by increments, while elaborated means worked out with care and detail, developed thoroughly
Temporary endeavor with a beginning and an end Creates unique product, service or result Is progressively elaborated Distinguishing characteristics of each unique project progressively detailed as the project is better understood will be
Progressively means proceeding in steps, continuing steadily by increments, while elaborated means worked out with care and detail, developed thoroughly
A Project : Has a unique purpose Is temporary Is developed using progressive elaboration Requires resources, often from various areas Should have a primary customer or sponsor The project sponsor usually provides the direction and funding the project Involves uncertainty
Projects
To attain its objectives and terminate Create own charter, organization and goals Catalyst for change Unique product or services Heterogeneous teams Start and end dates
Examples Build LNG Plant Geotechnical Investigation Ground water well construction Opening a new shop Arrange for a conference
Operations
To sustain the business Semi permanent charter, organization and goals Maintain status quo Standard product or services Homogenous teams On going
Examples LNG Plant Production Writing a progress update memo Attending a conference Meeting with an employee Opening the shop
10
The Application of knowledge, skills, techniques and tools to project activities to meet project requirements.
Project management is accomplished through the application and integration of the process such as:
1. Initiating
2. Planning
3. Executing 4. Monitoring and Controlling 5. Closing
11
Scope What work will be done as part of the project? What unique product, service, or result does the customer or sponsor expect from the project as its deliverables? Cost What is the cost to complete the project? What is the project budget? Time How long it takes to complete the project? What is the project schedule?
12
Project managers are assigned by the performing organization to achieve the project objectives.
A project manager is in charge of all aspects of the project including, but not limited to: Developing the project management plan and all related component plans, Keeping the project on track in terms of schedule and budget, Identifying, monitoring, and responding to risk, and Providing accurate and timely reporting of project metrics.
The project manager is the lead person responsible for communicating with all stakeholders, particularly the project sponsor, project team, and other key stakeholders.
The project manager occupies the center of the interactions between stakeholders and the project itself.
13
14
15
I.10 Stakeholder
Reference : PMBOK
16
A Stakeholder are individuals and organizations that are actively involved in the Project, or whose interest may be positively or negatively affected as a result of project execution or project completion
17
18
Organizational structures range from functional to projectized, with a variety of matrix structures between them
19
Key Points: The organization is grouped by areas of specialization within different functional areas Projects generally occur within a single department Information required from other department will be routed through departmental heads Team members complete project work in addition to normal department work
Advantages: Easier management of specialists Team member reports to only one supervisor Similar resources are centralized, the company is grouped by specialties Clearly defined career paths in areas of work specialization
Disadvantages: People are more emphasis on their functional specialty to the detriment of the project No career path in project management Project Manager has little or no authority
20
Key Points: The Project Manager has control of projects Personnel are assigned and reports to a Project Manager Team members complete only project work and when it is over they dont have home Communication generally occurs only within project
Advantages: Efficient project organization Loyalty to project More effective communications than functional Disadvantages: No home when project is completed Lack of professionalism in discipline Duplication of facilities and job functions Less efficient use of resources
21
Key Points: Team members report to Functional Manager Team members do project work in addition to normal departmental work Power rest with the Functional Manager Project Manager plays a role of: Project Expeditor: Can not make any decision. Staff assistant and Communication Coordinator Project Coordinator: Similar to Project Expeditor except has some power to make decision.
22
Key Points: Two Bosses Team members report to Project Manager and Functional Manager Team members do project work in addition to normal departmental work Power is shared between the functional and project manager
23
24
The project processes are performed by the project team and generally fall into one of two major categories: Project management processes ensure the effective flow of the project throughout its existence. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas. Product-oriented processes specify and create the projects product. Product-oriented processes are typically defined by the project life cycle (as discussed in Section 1.9) and vary by application area.
25
The process flow diagram provides an overall summary of the basic flow and interactions among Process Groups and specific stakeholders. A Process Group includes the constituent project management processes that are linked by the respective inputs and outputs where the result or outcome of one process becomes the input to another. The Process Groups are not project phases.
26
27
28
29
Link : EVM
30
1. 2. 3. 4.
PTK-037 POD PTK-038 WP&B PTK-039 AFE All procurement activities are bound by BPMIGAS Regulation on Supply Chain Management for PSC No. 007-REVISI-2/PTK/I/2011 - Providing guideline on supply chain management, procurement of goods and services, asset management, custom, and project management in BPMIGAS/PSC/JOBTAC. In general, all purchases of goods and services are done by either tender or direct selection/direct appointment (with certain requirements) and with only suppliers which are registered locally. Highlights in the procurement (goods & services) regulation guidelines : - Tender Plan and Contract Award > $5M needs BPMIGAS approval
Non compliance to the procurement regulation will result to non-cost recovery and may lead to disciplinary action to the PSCs personnel.
31
32
33
It is an interaction of crossproject Delivery Team members necessary to exploit the synergy that is possible by having the right people engaged in communication. This dialogue is focused on ensuring that project identifies and implements the best solutions effectively.
34
35
Interface Management Cover s Nine Knowledge Areas Project Integration Management Project Scope Management Project Time Management Project Cost Management Project Quality Management
Project HR Management Project Communications Management Project Risk Management Project Procure Management
36
Internal Interfaces: Internal Interfaces Occur within work areas of Contractors responsibility. Allow flow of information, identify Receiving and Providing Occur between the disciplines, e.g., Engineering, Construction, Quality, Procurement, Project Services, Commissioning, etc.
PS : This includes Project Controls, Document Controls and any of Contractors suppliers / vendors.
37
Tangible or Hard Interfaces Have a physical connection such as a structural steel connection, pipe termination, or cable connection, Ex. TieIn Points. Intangible or soft interfaces Involve only the exchange of information such as design criteria, clearance requirements or utility needs between Delivery Teams or between a Delivery Team and an external party. Technical interfaces Are tangibles or hard interfaces that occur within structures, systems and equipment, Ex. TieIn Points. Execution interfaces Occur when different contractors conduct their scope of work in series with interfaces that are dependent on each other or simultaneous when concurrent activities impact each other. (Here Construction Manager is in lead). Organizational Interfaces Result in a significant loss/gain in schedule or capital to the originating Delivery Team or to the project in general. Critical interfaces Result in a significant loss/gain in schedule or capital, those not performing have potential to negatively impact project performance.
38
Ensures all interfaces between the various parties are identified and controlled to ensure integrity between the different elements associated with the project.
Maintains uptodate Interface Registers and forms bridge between various parties involved in the execution of the Project.
Defines precisely the interface requirements associated with each party involved in a particular interface.
Defines the responsibilities for the parties involved with the interface so that individuals can be assigned and made accountable to followup the required actions.
Monitors the transfer of information relating to interfaces between the relevant parties, including Risk Identification & Mitigation Management, and VEP (Value Engineering & Constructability) Programs. Monitors the status of the interface actions to enable active followup if necessary by the Project Management Team, including potential change requests, variation requests, etc. In short, creates an environment to minimize loss of revenue.
39
PART III SAMPLE CASE STUDY : CONCEPT SELECTION IN OFFSHORE DEEPWATER FIELD DEVELOPMENT
40
Well type
Vertical type
Cluster type
Offshore processing
None
Minim.Off. Treatment
None
Minim.Off. Treatment
Offshore structure
SWP
SWP
FPU
SWP
TLP
SWP
TLP
FPU
Existing plant
Existing plant
New offshore
Existing Plant
Existing plant
New offshore
40
41
41
SWP - NO condensate storage (Layout and safety constraints) - Longer infield flowline system
FPU - High capability for condensate storage - subsea layout more exposed to geohazards - More complex riser system - Larger deck area and load capacity permit easier expansion; - allows for storage of liquids
HSE
- Risks for personnel working offshore for long periods during hook up and commissioning activities (moreover possible SIMOPs)
- Flexible risers and umbilicals not protected from dropped objects - Flexible risers less protected from ship impact than SWP risers - Complex riser base for export line due to diameter limit on flexible riser (16 ID)
Subsea system Decommissioning Contractual scheme Schedule Operability/ piggability Constructability - 1000 days - Requires heavy decommissioning activities
- Residual value
- 800 days - Pigging of export line requires support vessel and subsea pig launcher because of complex riser base - Possible availability of existing FPU for reconversion
42
43
44
Professional Certifications in Project Management 1. IAMPI (Ikatan Ahli Manajemen Proyek Indonesia) IAMPI website: http://www.iampi.org/ 2. Project Management Institute (PMI) a. Certifies Associate in Project Management (CAPM)
A secondary degree (high school diploma or the global equivalent) AND At least 1,500 hours of project experience OR 23 hours of project management education by the time you sit for the exam.
45
46
47
48
49
50
51
52
53
G B
G B
54
1960 -1970
G B
55
56
Extra Deepwater
Extra Heavy Oil High Cost EOR Conventional E&P Development Field
57
Higher Risk
Algeria
57
58
58
59
59
60
Vico Ind., 15,236 PetroChina Jabung, 16,345 Mobil Cepu Ltd., 24,083
CICO, 26,910 ConocoPhillips Ind., 35,146 CNOOC SES, 36,331
39,7%
Chevron Pacific Ind. PERTAMINA Total E&P
PHE - ONWJ CNOOC SES ConocoPhillips Ind. CICO Mobil Cepu Ltd. PetroChina Jabung Vico Ind.
PERTAMINA, 120,798
41 KKKS Lainnya
7,8%
Sumber: SKK MIGAS
14,6%
60
61
PEAK 1977
1683 1631 1624 15891587 1506 1519 1445 1407 1373 1336 1305 1362 1338 1288 1387 1303
PEAK 1995
Plateau stage
1575 1539 16121624 1574 1557 1537 1535 1500 1491 13971404 1364 1327 13021302 1264 1214 1316 1415 1366 1341 1586 1522 1501 14681462 1499 14981496 15001500 1460 1375
1500
1408 1373
1240
MBOEPD
1082
1056 966
1096 1062 1006 977 100010101010 949 945 902 861 830 900
1000
889 853 773 797 847 904
954
742
744
585
500
466
266
153 74 52 57 57 51 53 59 109 91 99
0 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016
TAHUN
Minyak
61
62
PEAK 1977
1683 1631 1624 15891587 1506 1519 1445 1407 1373 1336 1305 1362 1338 1288 1387 1303
PEAK 1995
Plateau stage
1575 1539 16121624 1574 1557 1537 1535 1500 1491 13971404 1364 1327 13021302 1264 1214 1316 1415 1366 1341 1586 1522 1501 14681462 1499 14981496 15001500 1460 1375
1500
1408 1373
1240
MBOEPD
1082
1056 966
1096 1062 1006 977 100010101010 949 945 902 861 830 900
1000
889 853 773 797 847 904
954
742
744
585
500
466
266
153 74 52 57 57 51 53 59 109 91 99
0 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016
TAHUN
Minyak
62
IV.9 Model
Where do you apply the new model?
63
Existing Contracts
Expiring Contracts
63
64
Deepwater Challenges in Indonesia Exploration and Exploitation : subsurface uncertainties, difficulties in seismic, geological modeling, reservoir engineering, reserve calculation Procurement : Scarcity of seismic survey vessels, deepwater drilling rigs Development : Difficulties and uncertainties in development concept selection, design and technological approaches Commercial : Huge capital investment, Economics enhancement target of production Legal : Timing of evaluation and approvals of POD are critical relative to the expiration of the exploration period
64