Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM SLNO 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 PLANT DETAILS OBJECTIVE PROPOSAL SERVICES REQUIRED SAFETY PERECAUTIONS EMERGENCY PROCEDURE STATE OF THE PLANT TEST METHOD COMPLETION CRITERIA APPENDICES a. LOG SHEET

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 2

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO 1.0 PLANT DETAILS: 1.1 Boiler Fill Pump & Associated System Boiler) (Main & Auxiliary

This system consists of 2 Nos of centrifugal pumps meant for initial filling of the Unit. These pumps are connected to 2 Nos of DM water storage tank and through its associated pipe line Boiler fill pump (Main) delivers DM water to Unit No 1 and 2 for boiler initial filling as well as deaerator initial filling. Boiler Fill pump meant for Auxiliary boiler delivers DM Water to Auxiliary boiler. Pump Parameter (Main Boiler) a) Capacity b) Pressure c) No. of Pumps 1.2 : 200 CUB. M/HR : 18 KSC (Design) : 2 Nos.

Boiler Fill Pumps (Main) are common for both Units. Pump parameter (Auxiliary Boiler) a) Capacity b) Pressure c) No. of Pumps : 20 CUB. M/Hr. : 10 KSC (Design) : 2 Nos.

DM make up pumps & Associated system. This system consists of 3 Nos of contrifugal Pumps meant for delivering DM water to a) b) c) d) e) Signatures NTPC BHEL Condenser - Hotwell make up Stator Cooling System make up ECW overhead Tank Hydrogen Plant Condensate Storage.

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 3

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO DM make up pumps are connected to 2 Nos of DM water storage tanks and through its associated pipe lines, delivers DM water to systems mentioned abve. DM water up pumps are common for both Units. Pump Parameters are a) Capacity b) Pressure c) No.of Pumps : 85 CUB.M/HR : 7 KSC (Design) : 3 Nos.

Refer to section 10.0 for lay-out of Boiler fill pump and DM make up pumps. 2.0 OBJECTIVE: To commission the Pumps and their associated pipe lines and make it available for the DM water requirements of Main and auxiliary Boiler. 3.0 PROPOSAL: It is proposed to commission the pumps and its system by a) Trial running the pumps under recirculation for 8 Hrs. b) Flushing the lines up to delivery points for a duration mutually agreed between BHEL and NTPC (Refer Section 1.0 for delivery points) 4.0 4.1 4.2 Signatures NTPC BHEL SERVICES REQUIRED: Availability of sufficient quantity of DM water. Availability of L.T. Power Supply

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 4

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO 4.3 4.4 4.5 5.0 Availability lighting, communication at working area. Availability of sufficient manpower with required tools & tackles for any pump maintanance. Availability of operating personnel for the activity. SAFETY PRECAUTIONS: Refer Procedure No. PS-DC-186-500-100/SIM/1/TS/2/100. 6.0 EMERGENCY PROCEDURES: Refer Procedure No. PS-DC-186-500-100/SIM/1/TS/2/100.

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 5

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO 7.0 7.1 7.2 STATE OF THE PLANT: Pump and motors are erected as per recommended drawings and check lists. Erection of the following are completed. a) 2 Nos DM water storage tank (Common for station) b) All associated suction and discharge lines of the pumps up to receiving point. 7.3 7.4 7.5 7.6 All permanent supports of systems of both Boiler fill pumps and DM make up pumps are erected as per drawing. Pump bearings are lubricated as per recommendation. Cleanliness of DM water storage tank ensured and DM water filled up to required level. Electrical connection to Motor is completed with recommended protections and the requited mock start / stop conducted satisfactorily under pump and motor in decoupled condition. Insulation Resistance of the motor measured and confirmed OK. All local and remote indication of pump and Tank are made ready. List of Indications, interlocks and protections required are made mutually by BHEL and NTPC. Sealing and cooling water lines (if applicable) are laid and connected to pumps.

7.7 7.8

7.9

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 6

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO 8.0 8.1 8.2 METHOD Under decoupled condition, start the motor and check direction of rotation. Motor started and 8 Hrs trial run completed. During the trial run, observations are made for normal vibration and bearing temperatures. Pump and motor coupled and the pump lined up from DM water storage tank back to tank through re-circulation line keeping the discharge valve closed. Pump started at local and put under 8 Hrs trial run through RC line. During the trial run, pump vibration, load current, bearing temperatures, suction and discharge pressures are logged. DM water line from the pump up to the delivery terminal are lined up and pump started and run for duration mutually agreed between BHEL & NTPC for flushing the lines one by one. For this flushing, a suitable opening to be made at the delivery terminal point for discharging flushed water.

8.3

8.4 8.5 8.6

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-150 NTPC Ref no SIM/0/TS/4/150

Sheet 7

of 8

Plant area: BOILER PROCEDURE FOR COMMISSIONING OF BOILER FILLING PUMP (FOR MAIN & AUXILIARY BOILER) / DM MAKE UP PUMPS AND ASSOCIATED SYSTEM STATUS SLNO 9.0 9.1 9.2 COMPLETION CRITERIA: All the pumps are run for 8 Hrs trial run satisfactorily under recirculation. DM water lines from DM storage tank up to all delivery terminals are flushed for duration mutually decided between BHEL & NTPC.

Signatures NTPC BHEL

SHEET 8 OF 8 10.0 APPENDICES: b) STATION : UNIT NO : ACTIVITY : BEARING TEMPERATURE DE NDE LOG SHEET

S.NO

PUMP LOADING (AMPS)

PRESSURE SUCTION DISCHARGE

Signatures NTPC BHEL