GOVERNMENT OF KERALA PUBLIC WORKS DEPARTMENT (ROADS AND BRIDGES), SOUTH CIRCLE, THIRUVANAHTHAPURAM S C H E D U L E TN154/SESC/2012-13

Name of Work: Construction of bridge at 10th mile stone across Killi riverconnecting Mulamukku to State Highway Thiruvananthapuram - Shenkotta road.
Sl. No. 1 No.or Qty. Description of work MDSS Figure APPENDIX. A. BRIDGE PROPER Providing rock bund with average height of 3.00 m above bed with 16 mm MS sheet piles driven through periphery of water side 1.00 m below and 0.60 m above bed level at 0.60 m c/c , water side protected with rock boulders 2.00 m bottom width and 0.60 m top width, inner side with a firm layer of sand bags laid with sufficent bonding 1.20 m wide and the gap between boulders and sand bags filled with a mixture of 50 % clay and 50 % local earth and consolidating in layers of 15 cm including maintaining the completion of the foundation work and removing the bund after completion of the work etc., complete as per the direction of deptl. officers at site. Bailing out water using 5 HP engine and pumpset including conveyance to the site and errection cost of fuel, lubricating oil pay of staff etc. complete as per the directions of the departmental officers at site. Words Unit Estimated Rate AMOUNT Rs. P

45 m

As per Spn.

1m

Rupees Twenty Three Thousand 23555.00 Five Hundred & Fifty Five Only

1059975.00

160 days

As per Spn.

1 day

2603.00

Rupees Two Thousand Six Hundred & Three Only

416480.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Earth work excavation in all clases of soil (exceept hard and medium rock which requires blasting) for foundation works and depositing the excess earth at a suitable place as directed by the departmental officer at site with all lead etc. complete As per Spn.

Words

3.1

280 m3

Initial lift upto 1.50m.

10 m3

2081.00

Rupees Two Thousand &Eighty One Only Rupees Two Thousand Two Hundred & Fifty Four Only

58268.00

3.2

245 m3

Fir Ist depth of 1.5m (upto 3m) Earthwork excavation in hard soil and depositing the spoil in convenient place with all leads as directed by departmental officers at site etc complete for foundation of the pier. Initial lift upto 1.50m.

As per Spn.

10 m3

2254.00

55223.00

4.1

140 m3

As per Spn.

10 m3

2374.00

Rupees Two Thousand Three Hundred & Seventy Four Only Rupees Two Thousand Five Hundred & Fourty Seven Only

33236.00

4.2

122 m3

For 1st depth of 1.5m (upto 3m)

As per Spn.

10 m3

2547.00

31073.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Excavating ordinary rock and depositing on bank with initial lead upto 50m and lift upto 4.5m including breaking clods, watering, ramming, sectioning of spoil bank etc. as directed by departmental officers at site. Boring through all classes of soil for cast-in-situ piles 900mm dia upto required depth using boring plant and equipment and by circulating bentonite slurry during boring installing casing pipe wherever necessary etc,complete and lifting and aligning welded reinforcement cage, lowering and placing in position assembling and lowering the trimie pipe for pouring cement concrete mix M30, lifting and removing the tremie pipe after completing the concreting and transfering and reinstalling the whole arrangement from one location to another etc., complete including all cost of materials required for concreting but excluding cost of reinforcement and depositing the mud with all leads and lifts. As per Spn.

Words Rupees Five Thousand Four Hundred & Thirty Only

70 m3

10 m3

5430.00

38010.00

176 m

As per Spn.

1m

9907.00

Rupees Nine Thousand Nine Hundred & Seven Only

1743632.00

80 m

Fabricating and driving down 900mm dia liner with 6mm thick MS plate fabricating to required bore size and As per driving down to depth of 5m without damaging the liner Spn. including all charges as directed by departmental officers at site etc complete.

1m

Rupees Ten Thousand Six 10633.00 Hundred & Thirty Three Only

850640.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Routine test on bored cast-in-situ piles having 900mm dia and with maximum load of 175.5t by arranging necessary equipments such as platform,load jacks,gange etc as per specification. As per Spn.

Words

2 Nos.

1 Each

Rupees Four Lakh Sixty Thousand Five 460522.00 Hundred & Twenty Two Only Rupees Five Thousand Eight Hundred & Twenty Seven Only

921044.00

20 m3

Vibrated plain Cement Concrete 1:3:6 using 40mm broken stone including mixing cost of all materials,form works, labour charges, hire charges of machinery, As per watering, curing for levelling course under pile cap etc. Spn. complete. Chipping and removing the excess length of RCC bored piles 900mm dia without damaging the pile including reusing the reinforcement conveying the cutpits of piles As per and disposal of debris within all leads and lifts etc. Spn. complete as per direction of departmental officers at site. Vibrated reinforced cement concrete in mix M 25 using 20mm broke stone including cost of materials form work, As per watering curing etc., complete for pile cap excluding Spn. cost of reinforcement. Chiselling in hard rock where blasting is prohibited (measured in solids) and stacking serviceable materials As per for measurments and disposal of un serviceale materials Spn. including all lift and lead as directed by the dept. officers at site etc complete.

1 m3

5827.00

116540.00

10

10200 dm3

10 dm3

75.85

Rupees Seventy Five - Paise Eighty Five Only

77367.00

11

126000 dm3

10 dm3

86.75

Rupees Eighty Six Paise Seventy Five Only

1093050.00

12

48 m3

10 m3

Rupees Twelve Thousand Seven 12732.00 Hundred & Thirty Two Only

61114.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Providing dowel bars of size 25mmdia 2.5 mtr long at about 100 cm c/c at bottom of abutment keeping 1.00 mtr into rock and 1.5 length within cement concrete after As per drilling holes in granite rock including all cost and Spn. conveyance of materials cuting rods withthe required length and fixing rods in position with cement ground 1:2 etc. as directed by the department Officers. Vibrated reinforced cement concrete M20 for the footings of pier using 20mm broken stone including all cost of materials formwork labour charges watering curing etc.complete but excluding cost of reinforcement. Vibrated reinforced cement concrete M20 using 20mm broken stone for the abutment and wing wall including all cost of materials formwork labour charges watering curing etc.complete but excluding cost of reinforcement. Vibrated reinforced cement concrete M20 using 20mm broken stone including all cost of materials, labour, form work, watering curing etc. complete for Pier but excluding cost of reinforcement. Supplying and fixing 63mm PVC down water pipe of length 30 cm at suitable intervals in deck slab as weap hole including all cost and conveyance of materials and labour charges etc. complete as directed by departmental officers at site.

Words

13

48 Nos.

1 Each

795.00

Rupees Seven Hundred & Ninety Five Only

38160.00

14

214830 dm3

As per Spn.

10 dm3

88.00

Rupees Eighty Eight Only

1890504.00

15

75400 dm3

As per Spn.

10 dm3

97.20

Rupees Ninety Seven - Paise Twenty Only

732888.00

16

49250 dm3

As per Spn.

10 dm3

115.60

Rupees One Hundred & Fifteen Paise Sixty Only

569330.00

17

20 Nos.

As per Spn.

1 Each

52.00

Rupees Fifty Two Only

1040.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Vibrated reinforced cement concrete in 1:1:2 ( M 25)using 20mm hard broken stone including cost of materials and labour charges for formwork, watering, curing etc. complete for abutment cap,Pier cap, dirt wall and cantilever wing wall but excluding cost of reinforcement Vibrated reinforced cement concrete in mix M 25 using 20mm hard broken stone including cost of materials, labour charges form work, watering, curing etc. complete for beam and deck slab but excluding cost of reinforcement. Supplying and fixing Elastomeric bearing of size 630x220x61 mm in position etc.complete as directed by departmental officers at site. Welding 'V' cut ends of MS rods after cleaning the V cut ends including cutting charges, electrodes current charges, hire for tools and plants including labour for welding etc.complete. 250 Nos. for 36mm dia bar As per Spn. 1 Each 447.00

Words Rupees One Hundred & Fourteen - Paise Fifty Five Only Rupees Two Hundred & Thirty One - Paise Thirty Five Only

18

29950 dm3

As per Spn.

10 dm3

114.55

343077.00

19

117600 dm3

As per Spn.

10 dm3

231.35

2720676.00

20

12 Nos.

As per Spn.

1 Each

Rupees Seventeen Thousand Eight 17825.00 Hundred & Twenty Five Only

213900.00

21

21.1

Rupees Four Hundred & Fourty Seven Only Rupees Three Hundred & Fifty Nine Only

111750.00

21.2

100 Nos.

for 32mm dia bar

As per Spn.

1 Each

359.00

35900.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure
21.3

Words Rupees Three Hundred & Fourty One Only Rupees Two Hundred & Fourty Four Only 85250.00

250 Nos.

for 25mm dia bar

As per Spn.

1 Each

341.00

21.4

250 Nos.

For 20mm dia bar

As per Spn.

1 Each

244.00

61000.00

22

28000 dm3

Vibrated CC M20 using 20mm hard granite broken stone for approach slab including cost of all materials, labour As per charges, watering, form work, curing etc. complete but Spn. excluding cost of reinforcement. Vibrated reinforced cement concrete M20 mix using 20mm broken stone for hand rails etc. including all cost As per and conveyance of materials, formwork, watering, curing Spn. etc. complete but excluding the cost of reiforcement. Vibrated reinforced cement concrete in 1:1:2 ( M 25)using 20mm hard broken stone including cost of materials and labour charges for formwork, watering, curing etc. complete for pre cast RCC slabs for the cable duct but excluding cost of reinforcement.

10 dm3

85.55

Rupees Eighty Five Paise Fifty Five Only

239540.00

23

7660 dm3

10 dm3

158.80

Rupees One Hundred & Fifty Eight - Paise Eighty Only

121641.00

24

6240 dm3

As per Spn.

10 dm3

92.00

Rupees Ninety Two Only

57408.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70mm, as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation etc. complete in all respects.

Words

25

34 m

As per Spn.

1m

Rupees Fifteen Thousand One 15125.00 Hundred & Twenty Five Only

514250.00

26

723 Qtl.

Reinforcement for RCC work bent, tied and place in position (Plain grill requiring bending cold) etc. including cost of reinforcement, binding wire, nails, conveyance As per and labour charges etc. complete (using TMT steel) as Spn. per dtirection of officers at site. Providing wearing coat using cement concrete M20 mix including cost and conveyance of materials watering curing cost of expansion pad labour charges etc.complete

1 Qtl.

7497.00

Rupees Seven Thousand Four Hundred & Ninety Seven Only

5420331.00

27

14710 dm3

As per Spn.

10 dm3

88.50

Rupees Eighty Eight - Paise Fifty Only

130184.00

28

380 m2

Painting with synthetic Enamel paint of approved quality two coat including one coat of primer after As per properly cleaning the surface etc complete as directed Spn. by departmental officers at site.

10 m2

1063.00

Rupees One Thousand &Sixty Three Only

40394.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Providing and fixing RCC guard stone 30cm dia 90cm long thick line dressed and side upto 60cm depth cut of total 90cm length of stone and three lines dressed for the top including painting fixing with cement concrete 1:4:8 As per using 40mm broken stone 50cmx50cmx45cm including Spn. earthwork excavation etc.complete but excluding cost of reinforcement as directed by departmental officers at site. APPENDIX.B. APPROACH ROAD AND PROTECTIVE WORKS Filling with contractors own good quality cut earth and compacting with power roller with all leads and lifts including speading in layers each layer not exceeding 25cm As per loose thickness consolidating at required OMC by watering Spn. and ramming properly as per the direction of deptl. Officers at site for forming embankment etc complete. Spreading, levelling and consolidating the depatmental cut earth by layers using power roller etc. as per specification and as directed by departmental officers at site. Earth work excavation in all clases of soil (exceept hard and medium rock which requires blasting) for removal of elevated berms and depositing the earth at a suitable place as directed by the departmental officer at site with all lead and lift etc. complete As per Spn.

Words

29

4 Nos.

1 Each

1297.00

Rupees One Thousand Two Hundred & Ninety Seven Only

5188.00

1.1

2600 m3

10 m3

3890.00

Rupees Three Thousand Eight Hundred & Ninety Only

1011400.00

1.2

207 m3

10 m3

100.00

Rupees One Hundred Only

2070.00

414 m3

As per Spn.

10 m3

2081.00

Rupees Two Thousand &Eighty One Only

86153.00

Signature of Tenderer with seal

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Earth work excavation in all clases of soil (exceept hard and medium rock which requires blasting) for foundation trenches of quadrant, protective wall, toe wall and depositing the earth at a suitable place as directed by the departmental officer at site with all lead and lift etc. complete. Demolishing old asphalt flooring and disposal of the debris within a distance of 150m away from site including all leads and lifts etc. compelte.

Words Rupees Two Thousand &Eighty One Only

920 m3

As per Spn.

10 m3

2081.00

191452.00

150 m2

As per Spn.

10 m2

434.00

Rupees Four Hundred & Thirty Four Only Rupees Five Thousand Three Hundred & Ninety Four Only Rupees Seven Thousand Four Hundred & Seventy Eight Only Rupees One Thousand Six Hundred & Fifty Nine Only

6510.00

225 m3

880 m3

Cement concrete 1:4:8 using 40mm nominal size As per broken stone including cost and conveyance of Spn. materials , labour charges for mixing and laying , ramming,watering, curing etc. complete . Cement concrete 1:3:6 graded broken stone using 60% 40mm and 40% 20mm including all cost and As per conveyance of materials and labour charges watering Spn. curing and form work etc complete. Rough stone masonry packing on slopes and base on slopes for drain out water etc. including cost and conveyance of materials, labour charges etc. complete as directed by departmental officers at site. Turfing the slopes of embankment with sides including trimming, dressing, watering as required unit the turf not properly take roots and in any case for a period of nto less than1 month etc as directed by departmental officers at site.

1 m3

5394.00

1213650.00

1 m3

7478.00

6580640.00

36 m3

As per Spn.

1 m3

1659.00

59724.00

1000 m2

As per Spn.

10 m2

694.00

Rupees Six Hundred & Ninety Four Only

69400.00

Signature of Tenderer with seal

10

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure 9 1100 m2 Plastering with cement mortar 1:4, 15 mm . thick one As per coat after cleaning the surface, floated hard and Spn. trowelled smooth, watering, curing on top of RR masonry etc. complete. Reinforcement for RCC work bent, tied and placed in position (Plain grill requiring bending cold) etc. including cost of reinforcement, binding wire, nails, conveyance As per and labour charges etc. complete (using TMT steel) as Spn. per dtirection of officers at site. 10 m2 2234.00

Words Rupees Two Thousand Two Hundred & Thirty Four Only Rupees Seven Thousand Two Hundred & Fifty Three Only

245740.00

10

50 Qtl.

1 Qtl.

7253.00

362650.00

11

181 m3

Supplying and stacking graded metal (70% of 60mmbroken stone and 30% of 36mm broken stone by volume) in standard uniform heaps for measurements without hindrance to the traffic including cost and conveyance of all materials etc. complete. Supplying and stacking 36mm hard granite broken stone in standard heaps for measurements including all cost and conveyance of all materials and labour charges etc. complete. Supplying and stacking 22.4mm hard granite broken stone in standard heaps for measurements without hindrance to the traffic including cost and conveyance of all materials etc. complete.

As per Spn.

1 m3

1314.00

Rupees One Thousand Three Hundred & Fourteen Only Rupees One Thousand Four Hundred & Twenty One Only Rupees One Thousand Six Hundred & Thirty Nine Only

237834.00

12

181 m3

As per Spn.

1 m3

1421.00

257201.00

13

68 m3

As per Spn.

1 m3

1639.00

111452.00

Signature of Tenderer with seal

11

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Supplying and stacking 12mm hard granite broken stone in standard heaps for measurementswithout hindrance to the traffic including cost and conveyance of all materials etc. complete. Supplying and stacking 6mm hard granite broken stone in standard heaps for measurementswithout hindrance to the traffic including cost and conveyance of all materials etc. complete. As per Spn.

Words Rupees One Thousand Seven Hundred & Seventy Eight Only Rupees One Thousand Four Hundred & Thirty Eight Only Rupees Four Hundred & Fourty Seven Only

14

47 m3

1 m3

1778.00

83566.00

15

20 m3

As per Spn.

1 m3

1438.00

28760.00

16

64 m3

Supplying and stacking good quality gravelly red earth for blinding in standard heaps for measurement without As per hindrance to the traffic including cost and conveyance of Spn. all materials etc. complete.

1 m3

447.00

28608.00

Signature of Tenderer with seal

12

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure SUB BASE WORK;- Metalling the roadway 100mm spread thickness compacted to 75mm using departmental broken stone (graded in the ratio of 7:3 of 60mm and 36mm size) 1m3/10M2) and departmental blinding materials (0.2m3/10m2) bed rolling spreading broken stone to template rolling dry to compaction from sides to centre, until the movements of broken stone cease, watering profusely and rolling until the fines cream up and fill the voids of the stones, then spreading the red/gravelly earth and sweeping into the joints watering and rerolling until the red earth/gravely earth has worked into all the crevices and only a thin coat of slurry remain, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion.

Words

17

1810 m2

As per Spn.

10 m2

837.00

Rupees Eight Hundred & Thirty Seven Only

151497.00

Signature of Tenderer with seal

13

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure BASE WORK; - Metalling the roadway 100mm spread thickness compacted to 75mm using 36mm departmental broken stone (graded in the ratio of 7:3 of 60mm and 36mm size)(1m3/10M2) and departmental blinding materials (0.15m3/10m2) bed rolling spreading broken stone to template rolling dry to compaction from sides to centre, until the movements of broken stone cease, watering profusely and rolling until the fines cream up and fill the voids of the stones, then spreading the red/gravelly earth and sweeping into the joints watering and rerolling until the red earth/gravely earth has worked into all the crevices and only a thin coat of slurry remain, then take off the roller and allow to set to harden for 24 hours and rerolling next day until any deformity is rectified including fencing, lighting, watching and maintaining the surface free of ruts for 15 days after completion.

Words

18

1810 m2

As per Spn.

10 m2

837.00

Rupees Eight Hundred & Thirty Seven Only

151497.00

Signature of Tenderer with seal

14

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure Providing 40mm premixed bituminous maccadom over BT surface with departmental broken stone after thoroughly cleaning the base with wire brushes, bass brooms and applying priming coat of 2.50 kg of bitumen/10m2 and spreading the hot premix (formed of 0.32/m3 of departmental 24mm broken stone and 0.22m3 of 12mm metal and 22.08 kg of bitumen per 10m2) rolling to dense surface then spreading the seal coat (comprising of a hot premix of 0.09m3 of 6mm departmental broken stone and 8.64kg of bitumen/10m2) again rolling including the cost of bitumen, oils and fuel, hire of bass brooms, camber board roller and other machines, lighting watching and other charges etc. complete (Total usage of bitumen 33.22kg/10m2)

Words

19

2370 m2

As per Spn.

10 m2

2342.00

Rupees Two Thousand Three Hundred & Fourty Two Only

555054.00

20

200 Nos.

Moulding and fixing RCC guard stone size 20cmx20cmx100cm with RCC 1:2:4 using 20mm broken As per stone and fixing in correct lines and levels using CC Spn. 1:4:8 using 40mm broken stone etc as directed by departmental officers at site. Reinforced cement concrete for foot slab on drain top including cost and conveyance of materials labour charges, form work, curing etc. but excluding the cost of reinforcement. As per Spn.

1 Each

1227.00

Rupees One Thousand Two Hundred & Twenty Seven Only

245400.00

21

10800 dm3

10 dm3

94.20

Rupees Ninety Four Paise Twenty Only

101736.00

Signature of Tenderer with seal

15

Sd/Superintending Engineer

Sl. No.

No.or Qty.

Description of work MDSS

Unit

Estimated Rate

AMOUNT Rs. P

Figure 22 185 m2 Painting with synthetic Enamel paint of approved As per quality coat two coat including one coat of primer Spn. after properly cleaning the surface etc complete Painting with synthetic Enamel paint on road way using approved quality two coat including one coat As per of primer after properly cleaning the surface etc Spn. complete as directed by departmental officers at site. Providing and erecting direction and place identification
retro- reflectorised sign board as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 As per sqm supported on a mild steel angle iron post 75 mm x 75 Spn. mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing in all respects.

Words Rupees One Thousand &Thirty Eight Only Rupees One Thousand Two Hundred & Nineteen Only 19203.00

10 m2

1038.00

23

100 m2

10 m2

1219.00

12190.00

24

7 m2

1 m2

Rupees Twelve Thousand Eight 12847.00 Hundred & Fourty Seven Only

89929.00

25

75 m

Putting up ring bund of suitable size as required at site with contractor's own materials which is to be As per maintained till the completion of work and demolishing Spn. the same on completion of work. ESTMATE PAC Deduct Cost of Department Materials Net PAC

1m

9646.00

Rupees Nine Thousand Six Hundred & Fourty Six Only

723450.00 32514829.00 317815.00 32197014.00

Net estimated cost in Figures

Rupees Three Crore Twenty One Lakh Ninety Seven Thousand &Fourteen Only

Signature of Tenderer with seal

16

Sd/Superintending Engineer