Purpose Use this procedure to change budget documents when need to correcting. Very often you have a large number of original documents, of both a technical and an accounting nature, for your planned investments. You want to manage these documents for appropriation requests and their variants as centrally as possible. Therefore, the documents can be stored digitally in a document management system. Trigger Perform this procedure when need to change Budget Documents. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Project System > Financials > Budgeting > Document > CJ3A - Change
1/11
Work Instruction
Screen Flow
2/11
Work Instruction
Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access
2. Double-click the Accounting node 3. Double-click the Project System node 4. Double-click the Financials node 5. Double-click the Budgeting node 6. Click the Scroll - down button . . .
. .
3/11
Work Instruction
7. Double-click the Document node 8. Double-click the CJ3A - Change node " and click Enter " transaction. Change Document: Initial Screen
4/11
Work Instruction
A key that R/O/C identifies each document in a company code in a specific fiscal year. Field Example: 0100000102 R Document number
Description
5/11
Work Instruction
6/11
Work Instruction
Contains R/O/C an explanato ry text on the line item. Field Example: Distribute budget from WBS level 1 to lower level R Text Change Document
Description
7/11
Work Instruction
8/11
Work Instruction
9/11
Work Instruction
10/11
Work Instruction
Scenario Instructions In this simulation you are required to: Change Budget Documents in SAP ECC 6.0
Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. Distribute budget from WBS level 1 to lower level Field Text 0100000102 Document number Value
11/11