CKME - JPN - Released Planned Price

Purpose Use this procedure to update the valid future price (in the various currencies and valuations) as the current standard price or valuation price. Trigger Perform this transaction when you need to release planned price. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Controlling > Actual Costing/Material > Ledger Material Ledger > Set Prices > CKME - Release Planned Prices .

Transaction Code CKME

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

1/14

Work Instruction

CKME - JPN - Released Planned Price

Screen Flow

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

2/14

Work Instruction

CKME - JPN - Released Planned Price

Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access

2. Double-click the Accounting node 3. Double-click the Controlling node

. .

4. Double-click the Product Cost Controlling node . 5. Double-click the Actual Costing/Material Ledger node .
Tuesday, July 14, 2009 CO_CKME_JPN_Released Planned Price.udc 3/14

Work Instruction

CKME - JPN - Released Planned Price

6. Double-click the Material Ledger node

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

4/14

Work Instruction

CKME - JPN - Released Planned Price

7. Double-click the Set Prices node

8. Double-click the CKME - Release Planned Prices node . Release Planned Price Changes

9. Click the Material edit field

10 As required, complete/review the following fields: . The goods R/O/C Description

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

5/14

Work Instruction

CKME - JPN - Released Planned Price

that are the subject of business activity. The material can be traded, used in manufact ure, consumed , or produced. Field Example: 62039004 R Material

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

6/14

Work Instruction

CKME - JPN - Released Planned Price

11 Click the Plant edit field .

12 As required, complete/review the following fields: . A plant is R/O/C an organizati onal unit for dividing an enterprise according to productio n, procurem ent, maintena nce, and materials planning. It is a place where materials are produced, or goods and services are provided. Field Description

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

7/14

Work Instruction

CKME - JPN - Released Planned Price

Example: 9000 R Plant 13 Click the Ignore threshold values check box . . 14 Click the Test run check box . 15 Click the Execute button . . .

Release Planned Price Changes

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

8/14

Work Instruction

CKME - JPN - Released Planned Price

16 Click the Back button .

Release Planned Price Changes

17 Click the Test run check box . 18 Click the Execute button . .

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

9/14

Work Instruction

CKME - JPN - Released Planned Price

Release Planned Price Changes

19 Click the Message List button .

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

10/14

Work Instruction

CKME - JPN - Released Planned Price

Release Planned Price Changes

20 Click the Display Information Message button .

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

11/14

Work Instruction

CKME - JPN - Released Planned Price

Release Planned Price Changes

21 Click the Exit button .

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

12/14

Work Instruction

CKME - JPN - Released Planned Price

Result You have successfully released planned price of a material.

Tuesday, July 14, 2009

CO_CKME_JPN_Released Planned Price.udc

13/14

Work Instruction

CKME - JPN - Released Planned Price

Scenario Instructions In this simulation you are required to: Release Planned Price in SAP ECC 6.0.

Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. 9000 Field Plant 62039004 Material Value