SECTION 01040 COORDINATION PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Coordination of Work of Contract.

1.02 RELATED REQUIREMENTS A. B. C. D. E. F. Section 01200 Section 01220 Section 01600 Section 01630 section 01700 Section 01701 - Project Meetings. - Progress Meetings. - Material and Equipment. - Product Options and Substitutions. - Contract Closeout. - Contract Closeout Procedures.

1.03 DESCRIPTION A. Co-ordinate scheduling, submittals, and work of the various sections of Specifications to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items to be installed later. Co-ordinate Work under direction of Architect/ Engineer.

B.

1.04 MEETINGS A. In addition to progress meetings specified in sections 01200 and 01220, hold coordination coatings and pre-installation conferences with personnel and subcontractors to assure co-ordination of Work.

1.05 COORDTNATZON OF SUEI4ITTALS A. B. C. Schedule and coordinate submittals specified in Sections 01300 and 01340. Co-ordinate work of various sections having interdependent responsibilities for installing connecting to, and placing in service, such equipment Co-ordinate requests for substitutions to assure compatibility of space, of operating elements and effect on work of other sections.

1.06 CO-ORDINATION OF SPACE A. Co-ordinate use of Project Space and sequence of installation of mechanical, and electrical work which is indicated diagrammatically on Drawings. Follow routings shown for pipes, ducts, and conduits as closely as practicable, with due allowance for available physical space; make runs parallel with lines of building.

Al Qassim University

01040 - 1

Coordination

Utilize space efficiently to maximize accessibility for other installations, for maintenance, and for repairs. B. In finished areas except as otherwise shown conceal pipes, ducts, and wiring in the construction Co-ordinate locations of fixtures and outlets with finish elements.

1.07 CO-ORDINATION OF CONTRACT PACKAGES A. Each service terminating at a contract package boundary shall be appropriated ended and marked as described in the contract document.

1.08 CO-ORDINATION OF CONTRACT CLOSEOUT A. B. Co-ordinate completion and cleanup of Work of separate sections in preparation for Substantial completion. Assemble and co-ordinate closeout submittals specified in Sections 01700 and 01701.

PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used PART 4 - MEASUREMENT 4.01 CO-ORDINATION A. Co-ordination shall be described as an item.

PART 5 - PAYMENT 5.01 PAYMENT A. The work shall be measured and payment shall be made in accordance with the requirements stated in bill no. 1 - Preliminaries and General Requirements . END OF SECTION

Al Qassim University

01040 - 2

Coordination