Question No : 1 You are the project manager for a project.

While reviewing the cost estimates fo r the project you notice that one of the cost estimates for an element in the WB S is 20% higher than the previous project for very similar work. What should you do next? A. B. C. D. Accept the estimate Ask the person responsible about the difference Ignore it Reduce the estimate

Answer : B Explanations : Best option is ask the person responsible about the difference and create the mo st accurate estimate that is practical. Question No : 2 You are a project manager of ABC Company and your project is currently in an exe cution phase. The customer has requested you for additional work. This work will affect the budget but not the schedule of the project. What should you do next? A. B. C. D. add the additional requirements to the project plan. Ignore the request Explain the change procedure and ask to submit a request for change. Discuss with the project team about the change.

Answer : C Explanations : Explain the change procedure and ask to submit a request for change is the best choice. Question No : 3 Your company policy allows to gift exchange with customer within certain limit. By Mistake, you have given a gift to the customer's representative already which is beyond the limit mentioned in your company policy . What should you do? A. B. C. D. Forget it and don't tell anyone. Contact your company's senior management and ask for assistance. Ask your customer to return the gift Ask your customer to gift you which cost same.

Answer : B Explanations : Best option is Contact your company's senior management and ask for assistance. Question No : 4 Your company policy allows accepting gifts from customer within certain limit. Y our customer is giving you a gift which is beyond limit of your company policy. You have given a gift to the customer's representative already with of similar v alue. What should you do? A. B. C. D. Accept it and don't tell anyone. Contact your company's senior management and ask for assistance. Ask your customer to about company policy. Refuse it.

Answer : B Explanations : Best option is Contact your company's senior management and ask for assistance.

Question No : 5 You are a project manager of Software Product Company. After hired a person you got to know that many of this person's ideas were developed by the competing com pany. Are you going to implement the same ideas? A. Accept the new ideas. B. Ignore the ideas because it may be violation of code of conduct. C. Ask to sign NDA. D. Tell the person that he should not mention that the ideas came from another c ompany. Answer : A Explanations : Unless the employee signed the NDA with his or her previous organization, there is no obligation for him or her not to share knowledge that was gained while wor king for the competitor. Question No : 6 Which of the following processes involves measure project and product scope perf ormance and managing scope baseline changes ? A. B. C. D. Collect Requirements Define Scope Verify scope. Control scope

Answer : D Explanations : The control scope process involves measure project and product scope performance and managing scope baseline changes. Question No : 7 A planning phase for an engineering component generated 100 engineering componen ts. The QA team randomly selected 5 components for inspection. This exercise can best be described as example of: A. B. C. D. Statistical Sampling Flowcharting Inspection All of the above

Answer : A Explanations : entire process of random selection and inspecting a work product is known as Sta tistical Sampling. Question No : 8 You are a Project Manager and takes over a project currently in The Execution ph ase. Where you are going to find best source of information on the costs associa ted with each level of expertise needed for the project : A. B. C. D. Project Project Project Project Quality Management Plan Schedule Management Plan Staffing Management Plan Cost Management Plan

Answer : C Explanations :

Based on the PMBOK, this information would be available in Staffing plan. The Co st management plan would contain cost of scheduled activities. Question No : 9 In which type of organization , the project manager has total control of project s? A. B. C. D. Projectized organization Balanced Matrix organization Strong Matrix Weak Matrix organization

Answer : A Explanations : Projectized organization : The project manager has total control of projects. Pe rsonnel are assigned and report to a project manager. Question No : 10 At which stage, stakeholders have maximum influence on project? A. B. C. D. Initial stage Closing stage Execution stage Control stage

Answer : A Explanations : It is easy to make changes to project goals and approach at the initial stage. S take holders have maximum influence at Initial stage. Question No : 11 Which of the following is an output of Define Scope? A. B. C. D. Accepted deliverables Change Requests Project document updates. Project scope statement

Answer : D Explanations : Project scope statement is an output of Define Scope. Question No : 12 Reserve Analysis technique NOT used during __________. A. B. C. D. Control Costs Estimating Activity Duration Determine Budget Estimate Costs

Answer : A Explanations : Reserve analysis is used during Estimate Costs to calculate contingency buffers that apply to individual or group of activities. Reserve analysis is used during Determine Budget to calculate management contingency buffers that apply to the entire project. Reserve analysis is done during Activity Duration estimation in order to calculate duration buffers for individual or group of activities. Question No : 13 Project Cost Management Plan is created as a part of:

A. B. C. D.

Develop Project Management Plan process Control Costs process Determine Budget process Estimate Costs process

Answer : A Explanations : There is no separate process in the Project Cost Estimation knowledge area to de velop a cost management plan. It is devloped in Develop Project Management Plan process. Question No : 14 Analogous Estimate Costs is _________. A. B. C. D. Generally Accurate Generally less accurate Bottom-up estimating Top-up estimating

Answer : B Explanations : Analogous Estimate Costs is Generally less accurate . Analogous Estimate Costs U ses Expert Judgment . It is used when reference projects are similar . It is use ful in early phases of the project. Question No : 15 Which of the following Enterprises Environmental factors is not input for Develo p Human Resource Plan processes: A. B. C. D. Organizational Chart Tempates Reduced Training Funds Hiring Freeze Technical competencies of project staff

Answer : A Explanations : Enterprise Environmental Factors: The definition of project roles and responsibi lities is developed with an understanding of the ways that existing organization s will be involved and how the technical disciplines and people currently intera ct with one another. Inputs are Reduced Training Funds , Technical competencies of project staff and Hiring Freeze etc. Question No : 16 Which of the following is most important element of Project Management Plan that is useful in Develop A Human Resource Plan process: A. B. C. D. Risk Management activities Activity Resource requirements Budget Control activities Quality Assurance activities

Answer : B Explanations : Activity Resource requirements is a primary input to Develop Human Resource Plan process. Question No : 17 Which of the following is not used to document team member roles and responsibil ities ?

A. B. C. D.

Text-oriented Format Functional Chart Hierarchical-type Organizational Chart Matrix-based Responsibility Chart

Answer : B Explanations : Functional Chart is not listed in PMBOK as a type of Organizational Chart Question No : 18 Which of the following is developing an approximation of the costs of the resour ces needed to complete project activities. A. B. C. D. Resource planning Estimate Costs Determine Budget Control Costs

Answer : B Explanations : Estimate Costs:Assessing how much it will cost the organization to provide the p roduct or service Question No : 19 Which of the following must be measured regularly to identify variances from the plan . A. B. C. D. Stakeholder requirements Project performance Control Schedule Project controls

Answer : B Explanations : Project performance must be measured regularly to identify variances from the pl an. Question No : 20 Which of the following is ensuring all features and functions are included in a product or service ? A. B. C. D. Project Project Project Product scope verification control scope

Answer : B Explanations : Project verification ensuring all features and functions are included in a produ ct or service Question No : 21 A process that is not part of Project Risk Management is: A. B. C. D. Identification Solicitation Quantification Response Development

Answer : B Explanations : All are part of Project Risk Management except Solicitation. Question No : 22 The work that must be done in order to deliver a product with the specified feat ures and functions is: A. B. C. D. Project Project Project Product scope verification control scope

Answer : A Explanations : Project Scope: The work that must be done in order to deliver a product with the specified features and functions. Question No : 23 With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____. A. B. C. D. 30.0 22.5 25.0 27.5

Answer : A Explanations : mean = (20+30+40)/3= 30 Question No : 24 The scope management provides: A. B. C. D. A basis for future decisions about the project. A baseline to accomplish verification measures. A baseline to evaluate potential scope changes. All of the above.

Answer : D Explanations : Project Scope Management is a group of processes required to ensure that the pro ject includes all the work required, and only the work required, to complete the project. Question No : 25 Lessons learned are most often based upon project historical records. Lessons le arned can be used to: A. B. C. D. See what mistakes others have made See how others have solved problems "Predict trends, highlight problems and identify alternatives" All of the above

Answer : D Explanations : All of the above Question No : 26 The major project scope management processes include:

A. B. C. D.

Change order control Initiation Program evaluation Scope statement

Answer : B Explanations : Initiation included in major project scope management processes Question No : 27 A graphic display of resource usage hours is: A. B. C. D. Organizational chart Responsibility matrix WBS Histogram

Answer : D Explanations : histogram that is useful in determining how much time is expected from the vario us team members and or functions. Question No : 28 Which of the following is an input to resource planning? A. B. C. D. Historical information Cost baseline Cost management plan Chart of accounts

Answer : A Explanations : Develop Human Resource Plan Inputs : Enterprise Environmental Factors, Historica l information, Organizational Process Assets and Project Management plan. Question No : 29 Which of the following tools or techniques are not used in Sequence Activities? A. B. C. D. Precedence diagramming method (PDM) Arrow diagramming method (ADM) Expert judgment Network templates

Answer : C Explanations : Expert judgment is not used in Sequence Activities. Sequence Activities : Identi fying and documenting interactivity logical relationships. Question No : 30 Name the ethical code you'll be required to adhere to as a PMP. A. B. C. D. Project Project Project Project Management Management Management Management Policy of Ethics Professional Standards Code of Professional Ethics and Standards Professional Code of Professional Conduct

Answer : D Explanations : The Project Management Professional Code of Professional Conduct is published by

PMI. Question No : 31 Which of the following ensures that project objectives are met by monitoring and measuring progress and taking corrective action when necessary. A. B. C. D. Project controls Controlling process Control logs Project chart

Answer : B Explanations : Controlling process ensures that project objectives are met by monitoring and me asuring progress and taking corrective action when necessary. Question No : 32 An example of a project is: A. B. C. D. Billing customers Managing an organization Constructing a building Providing technical support

Answer : C Explanations : An example of a project is Constructing a building. Question No : 33 Inputs to Team Development include all except A. B. C. D. Project staff Reward and recognition systems Performance reports Project plan

Answer : B Explanations : Inputs to Team Development include all except Reward and recognition systems. Question No : 34 In optimal organization structure , the project manager is: A. B. C. D. Functional Weak matrix Projectized Dedicated project team

Answer : D Explanations : Dedicated project team Question No : 35 Precedence diagramming method (PDM) uses which of the following dependencies A. B. C. D. Finish-to-start Start-to-start Finish-to-finish Start-to-finish

Answer : A Explanations : Finish-to-start An activity must finish before the next activity begins. Finishto-finish An activity must finish before the next activity can finish. Start-tostart An activity must start before the next activity can start. Start-to-finish An activity must start before the next activity can finish. Question No : 36 Which is not a tool or technique for Source Selection? A. B. C. D. Contract negotiation Weighting system Payment system Screening system

Answer : C Explanations : Payment system is not a tool or technique for Source Selection. Other options ar e . Question No : 37 Which of the following is not among the tools and techniques of Organizational P lanning? A. B. C. D. Staffing management plan Templates Human resource practices Organizational theory

Answer : A Explanations : Staffing management plan is not tools and techniques of Organizational Planning. Other options are true. Question No : 38 Control Costs is concerned with: A. B. C. D. Managing changes when they occur Resource rates Chart of accounts Organizational policies

Answer : A Explanations : Control Costs is concerned with Managing changes when they occur Question No : 39 The closing process scope includes: A. B. C. D. Contract closeout Final reporting Activity List Exit interview

Answer : A Explanations : closing process scope includes Contract closeout. Question No : 40 Collect Requirements is:

A. B. s C. D.

Developing a plan from major stakeholders Developing a written scope statement as the basis for future project decision Formalizing acceptance of the project scope Planning project milestones

Answer : B Explanations : Collect Requirements :Process of progressively elaborating and documenting the p roject work that produces the product of the project Question No : 41 Which of the following is not input to Define Activities : A. B. C. D. Work breakdown structure Product description Constraints Assumptions

Answer : B Explanations : Define Activities - Inputs : Work breakdown structure , Constraints , Assumption s and Organizational Process Assets . Question No : 42 When the project team directs staff assignments, what is not considered in the s election of a staff? A. B. C. D. Previous experience Staff age Availability Personal interest

Answer : B Explanations : Staff age is not considered in the selection of a staff Question No : 43 Which of the following involves estimating the cost of individual work items: A. B. C. D. Computerized Bottom up estimating Analogous estimating Square foot

Answer : B Explanations : Bottom-up estimating : Estimating the cost of individual work items and then rol ling up the costs to arrive at a project total , more accurate Question No : 44 The most rapid Estimate Costs technique is: A. B. C. D. Square foot estimating Template estimating Computerized estimating Analogous estimating

Answer : C

Explanations : Computerized estimating rapid Estimate Costs technique Question No : 45 Which of the following is another term for top down estimating. ? A. B. C. D. Analogous estimating Life-cycle costing Parametric modeling Bottom up estimating

Answer : A Explanations : Analogous estimating is also called top-down estimating and uses the actual cost of a previous, similar project as the basis for estimating the cost of the curr ent project. Question No : 46 In which of the following scope management processes is the scope management pla n prepared? A. B. C. D. Initiation Collect Requirements Define Scope Verify Scope

Answer : A Explanations : A Schedule Management Plan is developed as part of "Develop Project Management P lan". Question No : 47 _______ is the most accurate Estimate Costs technique. A. B. C. D. Parametric modelling Bottom up estimating Analogous estimating None

Answer : B Explanations : Bottom-up estimating : Estimating the cost of individual work items and then rol ling up the costs to arrive at a project total - more accurate Question No : 48 __________ involves using project characteristics in a mathematical model A. B. C. D. Analogous estimating Life-cycle costing Parametric modelling Bottom up estimating

Answer : C Explanations : Parametric modeling : Using project characteristics (or parameters) in a mathema tical model to predict costs (e.g., price per square foot). Question No : 49 Project risk is defined as the cumulative effect of chances of _____ which will adversely affect project objectives.

A. B. C. D.

Likely events Complex activities Complex schedules Uncertain occurrences

Answer : D Explanations : Uncertain occurrences can affect project objective. Question No : 50 Which is generally the least accurate. A. B. C. D. Using stakeholders to predict cost Parametric modelling Analogous estimating Computerized estimating

Answer : C Explanations : Analogous estimating : Analogous estimating is also called top-down estimating a nd uses the actual cost of a previous, similar project as the basis for estimati ng the cost of the current project. Question No : 51 Contract close out contains: A. B. C. D. Contract documentation Procurement audits Formal acceptance and closure All of the above

Answer : D Explanations : Contract close out contains Contract documentation,Procurement audits and Formal acceptance and closure. Question No : 52 Which is not included in General Management : A. B. C. D. Finance and accounting Strategic planning Sales and marketing Developing a new product or service

Answer : D Explanations : Developing a new product or service is not included in General Management. Question No : 53 A program is defined in the PMBOK as: A. A program consists of a related group of projects and Program management is t he process of managing multiple on going projects B. A number of subprojects divided into manageable components enabling a project team to ensure the completion of a desired outcome C. A project plan developed by key management personnel to obtain a desired outc ome D. The means to subdivide the project into manageable segments

Answer : A Explanations : A program consists of a related group of projects and Program management is the process of managing multiple on going projects Question No : 54 Which of the following processes is not included in Project Time Management. ? A. B. C. D. Define Activities Sequence Activities Develop Schedule and Control Schedule Work breakdown structure (WBS)

Answer : D Explanations : Work breakdown structure (WBS) is not included in Project Time Management but al l other options provided in Project Time Management.3/7/2009 Question No : 55 Which of the following is not included in Performance improvements : A. B. C. D. Improvements Improvements Improvements Improvements in in in in amount of overtime worked individual skills team behaviours team capabilities

Answer : A Explanations : Improvements in amount of overtime worked is not included in Performance improve ments. Question No : 56 Which of the following describes how cost variances will be managed? A. B. C. D. Cost management plan Cost baseline Cost estimate Chart of accounts

Answer : A Explanations : Cost management plan describes how cost variances will be managed. Question No : 57 ___________ coordinates people and other resources to carry out the plan. A. B. C. D. Work Breakdown Structure Resource planning Resource leveling Executing process

Answer : D Explanations : Executing process coordinates people and other resources to carry out the plan. Question No : 58 The process of identifying and defining a product or service is called: A. Procurement planning B. Source selection

C. Contract administration D. Contract closeout Answer : A Explanations : Procurement planning : Determining what project needs can best be met by procuri ng products or services outside the organization Question No : 59 The Critical Path Method of scheduling is: A. A mathematical analysis technique for Develop Schedule B. A technique that uses weighted averages to calculate project duration C. A technique that uses sequential network logic for schedule D. A technique that allows for probabilistic treatment of both network logic and activity duration estimates Answer : C Explanations : Critical Path Method (CPM): Calculates a single, deterministic early and late st art and finish date for each activity, to be used to determine which activities must be completed on time to avoid impacting the finish date of the project Question No : 60 During ______ part of the Procurement Management process does procurement negoti ations happened. ? A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : B Explanations : In Conduct Procurements process negotiations occurs. Question No : 61 You are project manager and now in middle of creating RFP(Request for proposal). RFP(Request for proposal) is done in _______. A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : A Explanations : RFP(Request for proposal) is done in Plan Procurements process, Question No : 62 Create Procurement document is done in _______. A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : A Explanations : Create Procurement document is done in Plan Procurements process.

Question No : 63 You are project manager and now you are middle of comparing proposals received f rom sellers . Comparing proposals received from sellers done in _______ . A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : B Explanations : Comparing proposals received from sellers done in Conduct Procurements. Question No : 64 Make payment to seller is done in _______ . A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : C Explanations : Make payment to seller is done in Administer Procurements. Question No : 65 Complete final contract performance reporting and verify the product is done in _______ . A. B. C. D. Plan Procurements Conduct Procurements Administer Procurements Close Procurements

Answer : D Explanations : Complete final contract performance reporting and verify product is done in Clos e Procurements. Question No : 66 Which of the following is controlling changes to the budget. A. B. C. D. Control Costs Estimate Costs Determine Budget None

Answer : A Explanations : Control Costs is controlling changes to the budget. Question No : 67 Key Management skills include: A. B. C. D. Leading Communicating Negotiating All of the above

Answer : D Explanations : All options are key management skills. Question No : 68 Which of the following is not output from Control Schedule: A. B. C. D. Schedule updates Revisions Corrective action Lessons learned

Answer : B Explanations : Outputs of Control Schedule : Schedule updates, Corrective action and Lessons le arned Question No : 69 A resource pool description provides: A. B. C. D. The unit cost for each resource What are the resources are available, at what times and in what patterns Performance of the pool resources Duration of the project

Answer : B Explanations : A resource pool description : What are the resources are available, at what time s and in what patterns Question No : 70 Which of the following processes recognizes that a project or phase should begin and commits the organization. A. B. C. D. Initiating process Solicitation process Scoping process Planning process

Answer : A Explanations : Initiating process :recognizes that a project or phase should begin and commits the organization. Question No : 71 Which of the following is an output of Define Scope? A. B. C. D. Accepted deliverables Change Requests Project document updates. Project scope statement

Answer : D Explanations : Project scope statement is an output of Define Scope. Question No : 72 Risk event is the description of what may happen to the _____ of the project. A. Manager

B. harm C. Schedule D. Budget Answer : B Explanations : Risk event is the description of what may happen to the harm of the project. Question No : 73 A RAM is: A. B. C. D. Random access memory Rapid and movement Responsibilities and methods Responsibility assignment matrix

Answer : D Explanations : The Responsibility Assignment Matrix is used to give an overview of personnel re sponsibility for particular tasks. Question No : 74 Contingency planning is a means to _____ risks to the project through a formal p rocess and provides the resources to meet the risk events. A. B. C. D. Address Classify Assign Resolve

Answer : A Explanations : Contingency Planning:The development of a management plan that identifies altern ative strategies to be used to ensure project success if specified risk events o ccur. Question No : 75 Which of the following devises and maintains a worktable scheme to accomplish th e business need that the project was undertaken to address. A. B. C. D. Development process Scoping process Planning process Information development process

Answer : C Explanations : Planning process Question No : 76 Staffing requirements do not define: A. B. C. D. What What What What types of skills are required time frames kinds of individuals or groups type of resource planning is required

Answer : D Explanations : Staffing requirements do not define What type of resource planning is required.

Question No : 77 A major assumption of all network scheduling methods is that activity durations must be _____. A. B. C. D. Statistically dependent Variance distributed Statistically independent Deterministic

Answer : C Explanations : Statistically independent Question No : 78 Constraints do not include: A. B. C. D. Impacts of weather Organizational structure of the performing organization Collective bargaining Expected staff assignments

Answer : A Explanations : Impacts of weather Question No : 79 Which of the following is not the tools and techniques used in Contract Administ ration: A. B. C. D. Contract change control system Contract negotiation Payment system Performance rating

Answer : B Explanations : Contract negotiation is not the tools and techniques used in Contract Administra tion. Question No : 80 Which of the following documents the characteristics of the product or service t hat the project was undertaken to build. A. B. C. D. Resource plan Project charter Project description Scope statement

Answer : C Explanations : Project description documents the characteristics of the product or service that the project was undertaken to build. Question No : 81 A _______ is a series of actions bringing about a result. A. Project plan B. Process C. Schedule

D. Flowchart Answer : B Explanations : Process Question No : 82 Which of the following involves determining what quantities are to be used to pe rform project activities. A. B. C. D. Resource planning Estimate Costs Determine Budget Control Costs

Answer : A Explanations : Resource planning :Planning, identifying, documenting, and assigning project rol es, responsibilities, and reporting relationships to individuals or groups. Question No : 83 Which of the following is the Estimate Costs technique used most frequently in t he early stages of a project. A. B. C. D. Analogous estimating Life-cycle costing Parametric modeling Bottom up estimating

Answer : A Explanations : Analogous estimating : Analogous estimating is also called top-down estimating a nd uses the actual cost of a previous, similar project as the basis for estimati ng the cost of the current project. Question No : 84 A Project Manager is at the project kick-off meeting. He confidently states the vision and mission for the project. This PM is exhibiting the following leadersh ip style: A. B. C. D. Hierarchal Authoritarian Charismatic Associative

Answer : C Explanations : No Expl 0 Question No : 85 You are responsible of developing a new product for a bank. Your quality metrics is based on the 80th percentile of each of the last three products developed. T his is an example of: A. B. C. D. Statistical sampling Metrics Benchmarking Operational definitions

Answer : B

Explanations : No Expl 1 Question No : 86 The two closing procedures are called: A. B. C. D. Contract close out and Verify Scope Contract close out and administrative closure Project closure and product verification Project closure and lessons learned

Answer : B Explanations : No Expl 2 Question No : 87 Scoring models, comparative approaches and benefit contribution are all part of: A. B. C. D. Constrained optimization models for selecting a project Benefit measurement models for selecting a project Quality measurement techniques Distribute Information tools

Answer : B Explanations : No Expl 3 Question No : 88 During the Develop Schedule process the Project Manager may have to go through s everal iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process: A. B. C. D. Critical Path Method, GERT, Resource Requirements Resource Levelling Heuristics, Mathematical Analysis, Calendars Duration compression, Resource Leveling Heuristics, PERT GERT, PERT, Leads and Lags

Answer : C Explanations : No Expl 4 Question No : 89 Which of the following models of conflict resolution allows a cooling off period , but seldom resolves the issue in the long term? A. B. C. D. Problem solving Withdrawal Forcing Smoothing

Answer : C Explanations : No Expl 5 Question No : 90 The "To Complete Performance Index" (TCPI) is calculated by: A. Subtracting the actual costs to date from the estimate at completion B. Dividing the budgeted cost of the remaining work by the difference between th e estimate at completion and actual costs to date

C. Multiplying the estimate at completion by the cumulative cost performance ind ex D. Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index Answer : B Explanations : No Expl 6 Question No : 91 A complex project will fit best in what type of organization? A. B. C. D. Functional Cross-functional Matrix Balanced

Answer : C Explanations : No Expl 7 Question No : 92 Which of the following could be an appropriate WBS code for a work package at th e fourth level in a WBS where the top level code is 1.0? A. B. C. D. 1.4 1.1.1.1 1.2.3.4 b and c

Answer : D Explanations : No Expl 8 Question No : 93 Which of the following Project Scope Management processes involves subdividing t he major project deliverables into smaller, more manageable components? A. B. C. D. Collect Requirements Initiation Scope Change Control Define Scope

Answer : D Explanations : No Expl 9 Question No : 94 The review of key deliverables and project performance at the conclusion of a pr oject phase is called: A. B. C. D. phase exit kill point stage gate all of the above

Answer : D Explanations : No Expl 10

Question No : 95 Which of the following is a common characteristic of most project life cycle des criptions? A. Cost and staffing are low at the start, higher towards the end, and drop rapi dly as the project nears completion. B. The probability of successfully completing the project is highest at the star t of the project. C. Stakeholders have the most influence on the final characteristics of the prod uct at the end of the project. D. All of the above Answer : A Explanations : No Expl 11 Question No : 96 Project scope is: A. The work that must be done in order to deliver a product with the specified f eatures and functions. B. The features and functions that are to be included in a product or service. C. A narrative description of work to be performed under contract. D. All of the above Answer : A Explanations : No Expl 12 Question No : 97 What is the purpose of the WBS? A. To show which work elements have been assigned to organizational units. B. To ensure that all work within a project is identified and defined within a c ommon framework. C. To show the organizational structure of a program. D. all of the above Answer : B Explanations : No Expl 13 Question No : 98 The unique identifiers assigned to each item of a WBS are often known collective ly as: A. B. C. D. The The The The work package codes project identifiers code of accounts element accounts

Answer : C Explanations : No Expl 14 Question No : 99 Change requests can occur due to: A. An external event such as a change in government regulation. B. An error or omission in defining the scope of the product.

C. An error or omission in defining the scope of the project. D. all of the above Answer : D Explanations : No Expl 15 Question No : 102 Which of the following are outputs of the Scope Change Control Process? A. B. C. D. Scope changes Corrective action Lessons learned All of the above

Answer : D Explanations : No Expl 18 Question No : 103 Who should contribute to the development of the project plan? A. B. C. D. Project manager Entire project team including project manager Senior management Just the planning department

Answer : B Explanations : No Expl 19 Question No : 105 Which of the following tools and techniques are commonly used in the Define Scop e Process? A. B. C. D. Benefit/cost analysis Decomposition Inspection b and d

Answer : D Explanations : No Expl 21 Question No : 106 Which of the following is NOT an example of a type of schedule report? A. B. C. D. Gantt chart Milestone chart fishbone diagram network diagram

Answer : C Explanations : No Expl 22 Question No : 107 Which of the following is the primary purpose of a milestone chart? A. To show task dependencies.

B. To show resource constraints. C. To show significant events in the project such as completion of key deliverab les. D. To highlight the critical path. Answer : C Explanations : No Expl 23 Question No : 108 When should the project manager be assigned? A. B. C. D. As early in the project as feasible. Preferably before much project planning has been done. At least prior to the start of project plan execution. All of the above.

Answer : D Explanations : No Expl 24 Question No : 109 In which type of organization(s) is the project manager's role most likely parttime? A. B. C. D. Functional Balanced Matrix Weak Matrix Functional and Weak Matrix

Answer : D Explanations : No Expl 25 Question No : 110 A document which describes how project scope will be managed and how scope chang es will be integrated into the project is: (choose the best answer) A. B. C. D. A A A A project plan risk analysis scope management plan scope statement

Answer : C Explanations : No Expl 26 Question No : 112 During what Time Management Process are the specific activities that must be per formed to produce the deliverables in the WBS identified and documented? A. B. C. D. Sequence Activities Define Activities Develop Schedule Estimate Activity Durations

Answer : B Explanations : No Expl 28 Question No : 113

A period of time in work weeks which includes non-working days is called: A. B. C. D. Elapsed Time Duration Effort Earned Time

Answer : A Explanations : No Expl 29 Question No : 114 The amount of time that an activity can be delayed from its early start without delaying the project end date is called: A. B. C. D. Negative Float Total Float Float c and b

Answer : D Explanations : No Expl 30 Question No : 115 What are you likely to see as a project progresses in a schedule with must fix d ates and little or no slack? A. B. C. D. Lots of free float Idle resources Negative float Positive float

Answer : B Explanations : No Expl 31 Question No : 116 Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most l ikely 6 days, what is the PERT weighted average? A. B. C. D. 6 4 6.3 6.1

Answer : C Explanations : No Expl 32 Question No : 117 What is the standard deviation for the estimates in the above problem? A. B. C. D. 0.6 2 1.5 0.5

Answer : A Explanations :

No Expl 33 Question No : 118 In crashing the schedule, you would focus on: A. B. C. D. Accelerating as many tasks as possible Accelerating just the non-critical tasks Accelerating the performance of tasks on the critical path None of the above

Answer : C Explanations : No Expl 34 Question No : 119 To calculate the late start and late finish dates for a set of tasks , you must do : A. B. C. D. An analysis of the critical path A forwards pass A backwards pass All of the above

Answer : C Explanations : No Expl 35 Question No : 120 An activity that consumes no time or resources and shows only that a dependency exists between two activities is called: A. B. C. D. A milestone A hammock A dummy activity All of the above

Answer : C Explanations : No Expl 36 Question No : 121 A modification of a logical relationship that allows an acceleration of the succ essor task is represented by: A. B. C. D. Lead time Lag time Negative Lag Lead time or Negative Lag

Answer : D Explanations : No Expl 37 Question No : 122 Assuming a PERT weighted average computation, what is the probability of complet ing the project within plus-or-minus 3 standard deviations of the mean? A. 68% B. 99.74% C. 95%

D. 75% Answer : B Explanations : No Expl 38 Question No : 123 Activity Resource Requirements is an input to ____________ : A. B. C. D. Estimate Activity Durations Control Schedule Sequence Activities Estimate Activity Resources

Answer : A Explanations : Activity Resource Requirements is an input to Estimate Activity Durations. Question No : 124 Dummy relationships or dummy activities can be used in which Sequence Activities techniques ? A. B. C. D. Arrow Diagramming Method [ADM] Precedence Diagramming Method [PDM] Fragment Network All of the above

Answer : A Explanations : Dummy activities are used to show complete relationships between tasks, and the fact that ADM uses only finish-to-start dependences. Question No : 125 Which of the following relationships is used in Arrow Diagramming Method [ADM] : A. B. C. D. Start-to-Finish Finish-to-Start Start-to-Start Finish-to-Finish

Answer : B Explanations : Dummy activities are used to show complete relationships between tasks, and the fact that ADM uses only finish-to-start dependences. Question No : 126 Which of the following is NOT a technique for Sequence Activities ? A. B. C. D. Rolling Wave Planning Mandatory Dependencies Arrow Diagramming Method [ADM Precedence Diagramming Method [PDM]

Answer : A Explanations : Rolling wave planning is a technique for Define Activities. Other options are te chnique for Sequence Activities. Question No : 127 Which of the following is a technique used to Define Activities ?

A. B. C. D.

Rolling Wave Planning Mandatory Dependencies Arrow Diagramming Method [ADM Precedence Diagramming Method [PDM]

Answer : A Explanations : Rolling wave planning is a technique for Define Activities. Other options are te chnique for Sequence Activities. Question No : 128 Reserve Analysis is a technique for: A. B. C. D. Estimate Activity Durations Estimate Activity Resources Sequence Activities Define Activities

Answer : A Explanations : Reserve Analysis ( Contingency ): Project teams may choose to incorporate an add itional time frame, called time reserve, contingency or buffer, that can be adde d to the activity duration or elsewhere in the schedule as recognition of schedu le risk. Question No : 129 Resource Leveling is a technique for: A. B. C. D. Develop Schedule Estimate Activity Durations Estimate Activity Resources Sequence Activities

Answer : A Explanations : Resource Levelling Heuristics: Allocate scare resources to critical path activit ies first etc. Tools and Techniques for Develop Schedule are : Mathematical anal ysis, Duration compression, Simulation,Resource-leveling ,Project management sof tware, Adjusting Leads and Lags and Coding structure. Question No : 130 Adjusting Leads and Lags is a technique for: A. B. C. D. Develop Schedule Estimate Activity Durations Estimate Activity Resources Sequence Activities

Answer : A Explanations : Adjusting Leads and Lags: Since the improper use of leads or lags can distort th e project schedule, the leads or lags are adjusted during schedule network analy sis to develop a viable project schedule. Tools and Techniques for Develop Sched ule are : Mathematical analysis,Duration compression,Simulation,Resource-levelin g ,Project management software,Adjusting Leads and Lags and Coding structure. Question No : 131 Parametric Estimating is done as a part of which process:

A. B. C. D.

Develop Schedule Estimate Activity Durations Sequence Activities Estimate Activity Resources

Answer : B Explanations : Tools and Techniques for Estimate Activity Durations are : Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis. Question No : 132 Three-Point Estimates includes _________. A. B. C. D. Most likely Optimistic Pessimistic All of the above

Answer : D Explanations : Three-Point Estimates includes Most likely, Optimistic and Pessimistic. Question No : 133 Identification of Mandatory Dependencies is done during which process: A. B. C. D. Sequence Activities Develop Schedule Define Activities Estimate Activity Durations

Answer : A Explanations : Sequence Activities : Identifying and documenting interactivity logical relation ships Question No : 134 A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? A. B. C. D. Cost Variance Management Overhead Management Contingency Reserve Schedule Variance

Answer : C Explanations : The difference between the Cost Baseline and Funding requirement at Project comp letion is Management Contingency Reserve. BAC represents the revised Cost baseli ne for the project. So C is true. Question No : 135 Project Cost Management Plan is created as a part of: A. B. C. D. Estimate Costs process Determine Budget process Control Costs process None

Answer : A Explanations :

Cost management plan : Describes how cost variances will be managed and Part of the overall project plan. Output of Estimate Costs process is : Cost estimates a nd Cost management plan Question No : 136 Which of the following is NOT a part of the project cost baseline but is include d in the project budget? A. B. C. D. Management Contingency Reserve Management Overheads Project Management Planing Activity Cost Contingency Reserve

Answer : A Explanations : The difference between the Cost Baseline and Funding requirement at Project comp letion is Management Contingency Reserve. Management Contingency Reserve is not part of project cost baseline. Question No : 137 Which of the following is NOT part of the Earned Value calculations ? A. B. C. D. Unknown Unknowns Project Budget Known Unknowns Amount of work completed

Answer : A Explanations : Unknown Unknowns is not part of the Earned Value calculations. Question No : 138 Resource reallocation from non critical to critical activities is an example of ________ Project Scheduling technique: A. B. C. D. Resource Leveling Schedule Compression Critical Path Method What if Analysis

Answer : A Explanations : Resource Leveling :Allocate scare resources to critical path activities first . Question No : 139 Trend Analysis is best described as: A. B. C. D. Examining project performance over time Calculating Earned Value Calculating Cost Variance Analyzing performance of similar projects over time

Answer : A Explanations : Trend Analysis is Examining project performance time by time Question No : 140 Which of the following is the lowest level in a work breakdown structure? A. Project task

B. Work package C. SOW D. RBS Answer : B Explanations : A work package is the lowest level of a work breakdown structure. Question No : 141 Knowledge of best practices in a particular area is most likely to give rise to which of the following dependencies: A. B. C. D. Finish-to-Start dependency External dependency Mandatory dependency Soft Logic

Answer : D Explanations : This kind of dependency is also known as Soft Logic, Preferential Logic, or Pref erred Logic Question No : 142 Reserve Analysis involves: A. Estimating by multiplying the quantity of work by productivity rate B. Adding resource reserves to the activity resource estimates C. Developing project schedule with contingency reserves as a recognition of the schedule risk D. Incorporating time buffers into the activity duration estimates Answer : D Explanations : Reserve Analysis ( Contingency ): Project teams may choose to incorporate an add itional time frame, called time reserve, contingency or buffer, that can be adde d to the activity duration or elsewhere in the schedule as recognition of schedu le risk. Question No : 143 Reserve Analysis technique NOT used during __________. A. B. C. D. Control Costs Estimating Activity Duration Determine Budget Estimate Costs

Answer : A Explanations : Reserve analysis is used during Estimate Costs to calculate contingency buffers that apply to individual or group of activities. Reserve analysis is used during Determine Budget to calculate management contingency buffers that apply to the entire project. Reserve analysis is done during Activity Duration estimation in order to calculate duration buffers for individual or group of activities. Question No : 144 Which of the following is NOT true about Resource Leveling: A. Project's Critical path may be altered B. Reverse resource allocation scheduling C. Resource based scheduling method

D. All of the above Answer : D Explanations : All are true about Resource Levelling. Resource Levelling is another tool in Dev elop Schedule. Resource Levelling removes the peaks and valleys of resource allo cation. This technique also examines resource over allocation and critical resou rce allocation. This technique lets the schedule and cost slip. Question No : 145 If you are project manager , After a change request has been denied, you should: A. B. C. D. Record it and save it. Pass on to the project team. Forget it All of the above

Answer : A Explanations : You have to keep track of all change requests. Question No : 146 Change requests are made against the ____________? A. B. C. D. Project baseline SOW Charter Executive summary

Answer : A Explanations : All change requests are made against a project plan that has the project baselin e. Question No : 147 Change requests should be ______ ? A. B. C. D. Formal Interesting Short None

Answer : A Explanations : Record of changes request should be maintained. Question No : 148 The Change Control Board should be _______? A. B. C. D. flexible Include the project manager appropriate authority All of the above

Answer : D Explanations : CCB should have all the mentioned characteristics. Question No : 149 The work that must be done in order to deliver a product with the specified feat

ures and functions included in the __________? A. B. C. D. Execution Plan Project Scope Product scope Statement of work.

Answer : B Explanations : Product scope - The features and functions that are to be included in a product or service. Project scope - The work that must be done in order to deliver a pro duct with the specified features and functions. Question No : 150 The outcome that must be produced to complete a part of a project or the project itself is called a _______ ? A. B. C. D. Deliverable Work Statement Project Plan WBS

Answer : A Explanations : The outcome that must be produced to complete a part of a project or the project itself is called a Deliverable. Question No : 151 Which of the following is a valid response to positive risks? A. B. C. D. Exploit Share Enhance All of the above

Answer : D Explanations : Risk mitigation is a response to negative risks and not positive risks. Positive risks may be responded by - "Exploit", "Enhance", "Share", "Accept". Question No : 152 Which of the following is a valid response to negative risks? A. B. C. D. Exploit Share Enhance mitigation

Answer : D Explanations : Risk mitigation is a response to negative risks and not positive risks. Positive risks may be responded by - "Exploit", "Enhance", "Share", "Accept". Question No : 153 Which of the following processes has risk register as the primary output? A. B. C. D. Perform Qualitative Risk Analysis Monitor and Control Risks Plan Risk Management Identify Risks

Answer : D Explanations : Process of Identify Risks has Risk register as the major output. Question No : 154 During which stage of Risk planning are risks prioritized based on probability a nd impact? A. B. C. D. Perform Quantitative Risk Analysis Monitor and Control Risks Plan Risk Management Identify Risks

Answer : A Explanations : Risk probability and impact are defined during Perform Qualitative Risk Analysis . Question No : 155 Which of the following compression techniques increases risk? A. B. C. D. Crashing Resource leveling Fast tracking Lead and lag

Answer : C Explanations : Fast tracking is a compression technique that increases risk and potentially cau ses rework Question No : 156 Which of the following performance measurements tells us how much more of the bu dget is required to finish the project? A. B. C. D. ETC EV EAC AC

Answer : A Explanations : Estimate to completion calculates how much more of the budget is needed to compl ete the project if everything continues at the current level of performance. Question No : 157 Project risk is characterized by three factors. What are they ? A. B. C. D. Severity of impact, duration of impact and cost of impact Identification, type of risk category and probability of impact Risk event, risk probability and the amount at stake Occurrence, frequency and cost

Answer : C Explanations : Risk event, risk probability and the amount at stake are the factors. Question No : 158 A project is defined in the PMBOK as:

A. B. C. D.

A A A A

process of considerable scope that implements a plan group of ideas managed in a coordinated way to obtain a desired outcome temporary endeavour undertaken to create a unique product or service collection of activities with a beginning and an end

Answer : C Explanations : A temporary endeavor undertaken to create a unique product or service Question No : 159 Which of the following is best for handling cross functional project needs for a large, complex project? A. B. C. D. A strong matrix organization A project coordinator A project expeditor Direct executive involvement

Answer : A Explanations : Strong Matrix: Power rest with Project Manager. Question No : 160 Project Stakeholders are defined as: A. Individuals and organizations who use the project's product B. Individuals and organizations whose interest may be positively or negatively affected as a result of project execution or successful project completion C. Individuals and organizations who provide the financial resources D. All of the above Answer : D Explanations : All of the above Question No : 161 The tools and techniques used in the initiation process are: A. B. C. D. Product analysis Project Develop Schedule Expert judgment Project budget

Answer : C Explanations : Expert judgment is required in the initiation process Question No : 162 Likely schedule durations for Estimate Activity Durations are available from his torical information that is derived from the following sources except: A. B. C. D. Commercial duration databases Project files Project team knowledge Outside consultants

Answer : D Explanations : All are inputs to Estimate Activity Durations except Outside consultants.

Question No Your spouse ny. You are ou are part A. B. C. D.

: 163 works for a vendor and the vendor bidding on a project at your compa not affiliated with the specific project team evaluating bids, but y of the executive project management team. What should you do?

Inform your company of the relationship Inform the vendor of the relationship Inform your company and vendor about the relationship Does not inform the vendor

Answer : C Explanations : It is your responsibility to disclose to both the vendor and your company . Question No : 164 Which of the following process involves measures project and product scope perfo rmance and managing scope baseline changes ? A. B. C. D. Collect Requirements Define Scope Verify scope. Control scope

Answer : D Explanations : Control scope process involves measures project and product scope performance an d managing scope baseline changes. Question No : 165 Which of the following is NOT one of the triple constraint of a project? A. B. C. D. Scope Time Cost Resources

Answer : D Explanations : Projects triple constraints are 1) Scope, 2)Time and 3)Cost Question No : 167 Which of the following organization is same as Functional organization? A. B. C. D. Projectized organization Balanced Matrix organization Strong Matrix Weak Matrix organization

Answer : D Explanations : Weak Matrix : Power reset with Functional Manager and Functional organization : Project Manager has least power and all management is taken care by functional m anager like marketing engineer, sales engineer etc. Question No : 168 A Schedule Management Plan is developed in which of the following knowledge area s: A. Develop Project Management Plan

B. Project Cost Management C. Project Scope Management D. Project Time Management Answer : A Explanations : A Schedule Management Plan is developed as part of "Develop Project Management P lan". Question No : 169 Define Activities is typically performed by which of the following: A. B. C. D. Project Manager who created the WBS Management Project Team Members responsible for the work package Project Stakeholder

Answer : B Explanations : Define Activities is typically performed by Project Team Members. identify the a ctivities that need to be done to complete the project. Question No : 170 Which of the following is not an activity attribute: A. B. C. D. Time when to perform the activity Location where to perform the activity Leads and Lags Person responsible for the activity

Answer : A Explanations : Activity attributes are an input for project Develop Schedule. The scheduling in formation is not a part of the activity attribute. Question No : 171 Which of the following does not create changes to the Project Scope Statement or Work Breakdown Structure ? A. B. C. D. Estimate Activity Durations Define Activities Estimate Activity Resources Sequence Activities

Answer : A Explanations : Estimate Activity Durations : Process of taking information on project scope and resources and then developing durations for input to schedules. Question No : 173 At which stage, project cost is maximum? A. B. C. D. Initial stage Closing stage Middle stage None of the above

Answer : C Explanations :

Middle stage : Execution stage has the resources and cost usage is maximum. Question No : 174 Which of the following is not correct about initial phase of a project? A. B. C. D. The cost associated at the initial phase of the project is highest. Stake holders have maximum influence during this phase The highest uncertainty is at this stage of the project. All of the above

Answer : A Explanations : minimum cost at the project initiation stage because minimum requirement of reso urces . Question No : 175 Process analysis is a function of ____________. A. B. C. D. Process Improvement Plan Quality Improvement Plan Quality Metrics Performance Analysis

Answer : A Explanations : process analysis is simply execution of the steps outlined in Process Improvemen t Plan. Question No : 176 Root Cause Analysis related to ________. A. B. C. D. Process Analysis Quality Audits Performance Measurements All of the above

Answer : A Explanations : Root Cause Analysis relates to Process Analysis. Question No : 177 Trend Analysis is performed using ______. A. B. C. D. Run Chart Scatter Diagram Pareto Chart Control Charts

Answer : A Explanations : Trend Analysis involves forecasting the future trend based on past performance. Run Chart shows the past pattern of variation. Question No : 178 A Pareto diagram can be best described as: A. B. C. D. Histogram Control Chart Scatter Chart Cause and Effect Diagram

Answer : A Explanations : Pareto diagram mainly helps the project management team to quantify and categori es the defects/issues according to sources ( engineering defects, setup problems , etc) Question No : 180 The process of Manage Stakeholder Expectations is part of which process? A. B. C. D. Planning Monitoring and Control Executing QA

Answer : B Explanations : Manage Stakeholder Expectations is part of Monitoring and Control process. Question No : 181 Which of the following is not an example of formal communication? A. B. C. D. Contract email Project status report Status meeting

Answer : B Explanations : Communication via email is not considered a formal communication. Question No : 182 Which of the following processes is not included in project communication knowle dge area? A. B. C. D. Communication Planning Documenting Project Closure Managing stakeholders Distribute Information

Answer : B Explanations : Document Project Closure is not a part in Project communication knowledge area. Question No : 183 You are the project manager of a project .You have just completed the Collect Re quirements and Define Scope. What should you do next? A. B. C. D. Create WBS Verify Scope Value analysis Control Scope

Answer : A Explanations : Create the WBS is the process that follows Collect Requirements and Define Scope . Question No : 184 Reserve Analysis a technique not used in:

A. B. C. D.

Estimate Costs Estimating Activity Duration Control Costs Determine Budget

Answer : C Explanations : Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs . Question No : 185 A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000? A. B. C. D. Cost Variance Management Overhead Management Contingency Reserve Schedule Variance

Answer : C Explanations : The difference between the Cost Baseline and Funding requirement at Project comp letion is Management Contingency Reserve. BAC represents the revised Cost baseli ne for the project. So C is true. Question No : 186 Project Cost Management Plan is created as a part of: A. B. C. D. Estimate Costs process Determine Budget process Control Costs process None

Answer : A Explanations : Cost management plan : Describes how cost variances will be managed and Part of the overall project plan. Output of Estimate Costs process is : Cost estimates a nd Cost management plan Question No : 187 Which of the following is not a part of the project cost baseline but is include d in the project budget? A. B. C. D. Management Contingency Reserve Management Overheads Project Management Planing Activity Cost Contingency Reserve

Answer : A Explanations : The difference between the Cost Baseline and Funding requirement at Project comp letion is Management Contingency Reserve. Management Contingency Reserve is not part of project cost baseline. Question No : 188 Which of the following is not part of the Earned Value calculations ? A. Unknown Unknowns B. Project Budget

C. Known Unknowns D. Amount of work completed Answer : A Explanations : Unknown Unknowns is not part of the Earned Value calculations. Question No : 189 If the Earned Value is equal to Actual Cost, What does it means: A. B. C. D. There is no cost variance There is no schedule variance Schedule Variance Index is 1 Project is on budget and on schedule

Answer : A Explanations : Cost Variance = EV - AC . Therefore if EV = AC, the Cost Variance is zero . Question No : 190 Trend Analysis is best described as: A. B. C. D. Examining project performance over time Calculating Earned Value Calculating Cost Variance Analyzing performance of similar projects over time

Answer : A Explanations : Trend Analysis is Examining project performance time by time Question No : 191 Which of the following is the lowest level in a work breakdown structure? A. B. C. D. Project task Work package SOW none

Answer : B Explanations : A work package is the lowest level of a work breakdown structure. Question No : 192 Which of the following is not part of Performance Measurements? A. B. C. D. Calculating Calculating Calculating Calculating Earned Value ETC Cost Variance Planned Value

Answer : A Explanations : Calculating Earned Value is not done as part of Performance Measurements. Question No : 193 Management Contingency Reserve is identified in which process: A. Determine Budget B. Estimate Activity Resources

C. Estimate Costs D. Estimate Activity Durations Answer : C Explanations : The difference between the Cost Baseline and Funding requirement at Project comp letion is Management Contingency Reserve. Management Contingency Reserve is iden tified in Estimate Costs process. Question No : 194 Resource Breakdown Structure is an example of: A. B. C. D. Text-oriented Format Functional Chart Hierarchical-type Organizational Chart Matrix-based Responsibility Chart

Answer : C Explanations : Resource Breakdown Structure is a type of hierarchical chart breaks down the pro ject by resource types so that the project manager can see quickly which resourc es can be grouped together. The RBS does not have to be only for human resources and may include materials, communication technologies, and other types of resou rces needed to execute the project Question No : 195 Which of the following types of Organizational Charts can be best used to track project costs : A. B. C. D. Organizational Breakdown Structure Responsibility Assignment Matrix Resource Breakdown Structure Hierarchical-type Organizational Chart

Answer : C Explanations : Resource Breakdown Structure is a type of hierarchical chart breaks down the pro ject by resource types so that the project manager can see quickly which resourc es can be grouped together. The RBS does not have to be only for human resources and may include materials, communication technologies, and other types of resou rces needed to execute the project. A RBS can be aligned with Organization's acc ounting system. Question No : 196 Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. B. C. D. Defines all people associated with each activity Defines responsibilities for each WBS component Text description of roles, responsibilities, authorities Defines what project member is responsible for each activity

Answer : C Explanations : The Responsibility Assignment Matrix (RAM) details the different tasks for the p eople listed in the matrix chart. Question No : 197 Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines all people associated with each activity

B. Defines responsibilities for each WBS component C. Defines what project member is responsible for each activity D. All of the above Answer : D Explanations : The Responsibility Assignment Matrix (RAM) details the different tasks for the p eople listed in the matrix chart. Question No : 198 War room creation during project deployment phase is an example of: A. B. C. D. Team Building activity General Management Skills Working together on Co-Location Establishing Ground Rules

Answer : C Explanations : War room : Working together on Co-Location Question No : 199 Building a virtual team for a project will limit the usability of which of the f ollowing tools and techniques for Team Development: A. B. C. D. Team Building Reward and Recognitions Working together on Co-Location Establishing Ground Rules

Answer : C Explanations : Virtual team for a project will limit the usability of Working together on Co-Lo cation. Question No : 200 A single source seller is ____________. A. B. C. D. There There There There is only one seller the company wants to do business with. is only one qualified seller. is only one seller in the market. are many seller in the market

Answer : A Explanations : A single source seller is only one seller the company wants to do business with. PMP 4th Edition Exam Simulator- window installer - 1400+ questions with explanat ions only for : 69$ $39 only for today

PMP 4th Edition Exam Simulator- window installer - 1000+ questions with explanat ions only for : 49$ $29 only for today

PMP 4th Edition Exam Simulator- window installer - 800+ questions with explanati ons only for : 39$ $19 only for today

CertChamp Certification Champion

Вам также может понравиться