JOBSAFETY ANALYSIS FOR BATHYMETRIC SURVEY

COMMON COOLING SEAWATER SYSTEM PHASE 2


SEQUANCE OF BASIC HAZARD 1.0 Utilization of survey vessel POTENTIAL HAZARD 1.1 Failure of vessel and equipment HAZARD CONTROL 1.1.1 The vessel must be certified and approved by QP approved third party 1.1.2 Operator of the vessel must have valid licence and must be certified by QP approved third party 1.1.3 Radio communication facility must be available between vessel and relevant control room at shore and one dedicated supervisor shall be monitored the activity at shore 1.1.4 Rescue team with vessel to be available to attend any undue event 1.2 Fall of material and 1.2.1 The crew members must be trained and should wear personnel in to sea life jacket 1.2.2 First Aid Facility to be available in the vessel 1.2.3 Equipments, tools, and materials to be secured properly to prevent falling RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Page : 1 of 3

JOBSAFETY ANALYSIS FOR BATHYMETRIC SURVEY


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF BASIC HAZARD POTENTIAL HAZARD HAZARD CONTROL 1.2.4 All personnel should be inducted with details of activity and sea survival training 1.2.5 Vessel shall be equipped with rescue buoys and rope 1.2.6 Good house keeping to be maintained on deck and platform all time and spillage of fuel,grease and oil to be cleaned properly and disposed 1.3 Local Marine traffic 2.0 General safety 2.1 Personnel injury and health hazard 1.3.1 Communication with RLIC port control room to be established prior to start of survey 2.1.1 Each member of the crew member to be phisically fit and in good health 2.1.2 Safe entrance and exit platform with ladder to be provided for sailors. 2.2 Fire 2.2.1 Flammable materials shall not be stored in the vessel if required it shall stored in a purpose designed container 2.2.2 Appropriate fire extinguishers shall be provided in the vessel RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Page : 2 of 3

JOBSAFETY ANALYSIS FOR BATHYMETRIC SURVEY


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF BASIC HAZARD 3.0 Weather POTENTIAL HAZARD 3.1 High tide 3.2 Exposure to extreme weather 3.3 Sun Burn 3.4 Heat stress and dehydration HAZARD CONTROL 3.1.1 Tide table shall be evaluated before sailing 3.2.1 Weather forecast must be followed 3.3.1 Adequate shelter to be provided for workers to take rest 3.4.1 Sufficient quantity of cool drinking water to be made available RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Notes: 1- Prior to start any work it to be made sure that personnel are safety inducted 2- Prior to start any work Tool Box Talk to be carried out 3- Personnel shall wear all applicable PPE 4- Adequate First Aid facility to be provided Prepared By : M.P Gupta ( Civil Engineer ) Reviewed By: Solayappan ( HSE Officer )