AVERAGE LEAD OF 1 km

S.No. Kind of Materials Name of Quarry Lead Cost conveyance Total

1 Mortar Sand Arjuna River 23 115.00 114.50 229.50

2 Filling Sand Arjuna River 23 85.00 114.50 199.50

3 40 mm Metal Malaipatti 19 290.00 97.85 387.85

4 20 mm Metal Malaipatti 19 365.00 97.85 462.85

5 6 mm Metal Malaipatti 19 215.00 97.85 312.85

6 Rough Stone Malaipatti 19 160.00 97.85 257.85

7 Bond Stone Malaipatti 19 250.00 97.85 347.85

8 Country Bricks Gollapatti 29 1250.00 117.10 1250.00

9 Brick Jelly 20 mm Gollapatti 29 240.00 #REF! #REF!

10 Shell lime Virudhunagar 10 650.00 #REF! #REF!

11 Pressed Tiles Virudhunagar 10 3550.00 63.00 3550.00

12 Lime Stone Virudhunagar 10 320.00 #REF! #REF!

13 Steel Virudhunagar 10 16110.00 35.00 16110.00

14 Cement Virudhunagar 10 2600.00 35.00 2635.00


0 0
1 3.50
2 7
3
4 14
5 18
6 21
7 25
8 28
9 32
10 35
11 38

12
41
CEMENT
13 44
14 47
15 50
16 52
17 55
18 58
19 61
20 64
21 67
22 69
23 72
24 74
25 77
26 79
27 82
28 84
29 87
30 89
31 92
32 94
33 97
34 99
35 102
36 104
37 107
38 109
39 112
40 114
1 7.90
2 15.80
3 23.70
4 31.60
5 39.50
6 47.40
7 55.30
8 63.20
9 71.10
10 79.00
11 85.55
12 92.10
13 98.65
14 105.20
15 111.75
16 118.30
17 124.85
18 131.40
19 137.95
20 144.50
21 150-.15
22 155.80
23 161.45
24 167.10
25 172.75
26 178.40
27 184.05
28 189.70
29 195.35
30 201.00
31 206.65
32 212.30
33 217.95
34 223.60
35 229.25
36 234.90
37 240.55
38 246.20
39 251.85
40 257.50
1 6.80
2 13.60
3 20.40
4 27.20
5 34.00
6 40.80
7 47.60
8 54.40
9 61.20
10 68.00
11 73.40
12 78.80
13 84.20
14 89.60
15 95.00
16 100.40
17 105.80
18 111.20
19 116.60
20 122.00
21 126.45
22 130.90
23 135.35
24 139.80
25 144.25
26 148.70
27 153.15
28 157.60
29 162.05
30 166.50
31 170.95
32 175.40
33 179.85
34 184.30
35 188.75
36 193.20
37 197.65
38 202.10
39 206.55
40 211.00
1 6.30
2 12.60
3 18.90
4 25.20
5 31.50
6 37.80
7 44.10 Mangalore Tiles (2000 nos.) Machine Pressed Tiles
8 50.40
9 56.70
10 63.00
11 68.20
12 73.40
13 78.60
14 83.80
15 89.00
16 94.20
17 99.40
18 104.60
19 109.80
20 115.00
21 119.50
22 124.00
23 128.50
24 133.00
25 137.50
26 142.00
27 146.50
28 151.00
29 155..50
30 160.00
31 164.50
32 169.00
33 173.50
34 178.00
35 182.50
36 187.00
37 191.50
38 196.00
39 200.50
40 205.00
41-80 add 2.75 per km
Pressed Tiles
1 4.75
2 9.50
3 14.25
4 19.00
5 23.75
6 28.50
7 33.25 Country Bricks
8 38.00
9 42.75
10 47.50
11 51.40
12 55.30
13 59.20
14 63.10
15 67.00
16 70.90
17 74.80
18 78.70
19 82.60
20 86.50
21 89.90
22 93.30
23 96.70
24 100.10
25 103.50
26 106.90
27 110.30
28 113.70
29 117.10
30 120.50
31 123.90
32 127.30
33 130.70
34 134.10
35 137.50
36 140.90
37 144.30
38 147.70
39 151.10
40 154.50
41-80 add 2.00 per km
1 3.85
2 7.70
3 11.55
4 15.40
5 19.25 Lime Stone,Broken Stone Brick jelly Wood Work
6 23.10
7 26.95
8 30.80
9 34.65
10 38.50
11 41.70
12 44.90
13 48.10
14 51.30
15 54.50
16 57.70
17 60.90
18 64.10
19 67.30
20 70.50
21 73.25
22 76.00
23 78.75
24 81.50
25 84.25
26 87.00
27 89.75
28 92.50
29 95.25
30 98.00
31 100.75
32 103.50
33 106.25
34 109.00
35 111.75
36 114.50
37 117.25
38 120.00
39 122.75
40 125.50
41-80 add 1.65 per km
1 6
2 11
3 17
4 22
5 28
6 34
7 39 Rough Stone,Bond Stone,sand,Earth Broken Stone,Gr
8 45
9 50
10 56
11 61
12 65
13 70
14 75
15 79
16 84
17 89
18 93
19 98
20 103
21 107
22 111
23 115
24 119
25 123
26 127
27 131
28 135
29 139
30 143
31 147
32 151
33 155
34 159
35 162.50
36 166.50
37 170.50
38 174.50
39 178.50
40 182.50
41 185.70
42 188.90
43 192.10
44 195.30
45 198.50
46 201.70
47 204.90
48 208.10
49 211.30
50 214.50
51 217.70
52 220.90
53 224.10
54 227.30
55 230.50
56 233.70
57 236.90
58 240.10
59 243.30
60 246.50
61 249.70
62 252.90
63 256.10
64 259.30
65 262.50
66 265.70
67 268.90
68 272.10
69 275.30
70 278.50
71 281.70
72 284.90
73 288.10
74 291.30
75 294.50
76 297.70
77 300.90
78 304.10
79 307.30
80 310.50
h Broken Stone,Gravel,Surki
0 0
1 3.50
2 7.00
3 10.50
4 14.00
5 17.50
6 21.00
7 24.50
8 28.00
9 31.50
10 35.00
11 37.90
12 40.80

13
43.70
STEEL
14 46.60
15 49.50
16 52.40
17 55.30
18 58.20
19 61.10
20 64.00
21 66.50
22 69.00
23 71.50
24 74.00
25 76.50
26 79.00
27 81.50
28 84.00
29 86.50
30 89.00
31 91.50
32 94.00
33 96.50
34 99.00
35 101.50
36 104.00
37 106.50
38 109.00
39 111.50
40 114.00
Mazon I 160
Mazon II 145
Mazdoor I 100
Mazsdoor II 90
Fitter I 140
Fitter II 130
Painter I 130
Painter II 120
Carpenter I 160
Carpenter I I 145

Stocking charge
Metal 3.15
Gravel 3.05
Sand 3.05

Filling gravel 9.20


Filling Sand 8.20

Mixing CM 27.00
Mixing LM 38.00
Cleaning surface 1.80
Kind of Materials Rate
Mortar Sand 110
Filling Sand 110
40 mm Metal 490
20 mm Metal 685
12 mm Metal 630
10 mm Metal 465
6 mm Metal 315
Rough Stone 230
Bond Stone 315
Country Bricks 1470
Brick Jelly 20 mm 280
Shell lime 705
Pressed Tiles 4500
Lime Stone 345
Steel 31000
Cement 4300
Red Gravel 92
Well Gravel 82
Quarry Rubbish 51
Snowcem 30
Distember 60
Enemal paint 150

0
Name of Work: Special Repairs to the cement concrete road at Mettu vadakarai.
LEAD STATEMENT

conv
Kind of Name of Lead
S.No. Unit Cost eyan Total
Materials Quarry in km
ce
1 Mortar Sand 29 1 cum 110.00 ### 248.50
2 Filling Sand 29 1 cum 110.00 ### 248.50
3 Cement 7 1 Mt 3600.00 24.50 3624.50
4 Steel 7 1 Mt ### 0.00 31000.00
5 40 mm Metal 3 1 cum 490.00 16.80 506.80
6 20 mm Metal 3 1 cum 685.00 16.80 701.80
7 12mm Metal 3 1 cum 630.00 16.80 646.80
8 10 mm Metal 3 1 cum 465.00 16.80 481.80
9 6 mm Metal 3 1 cum 315.00 16.80 331.80
10 Rough Stone 3 1 cum 230.00 16.80 246.80
11 Bond Stone 3 1 cum 315.00 16.80 331.80
Country Bricks (8 3/4x 4 1/4 x2)
12 2 1000 Nos1470.00 9.50 1470.00
13 Brick Jelly 20 mm 2 1 cum 280.00 7.70 287.70
14 Red Gravel 1 1 cum 92.00 5.60 97.60
15 Well Murambu 1 1 cum 82.00 5.60 87.60
16 Lime Stone 1 1 cum 345.00 3.85 348.85
17 Pressed Tiles (20 cm 20 cm*2cm)
12 1000 Nos4500.00 36.70 4536.70
18 Shell Lime 1 cum 705.00 705.00

Certified that the above leads and rates are shortest and correct to the best of my kno
s to the cement concrete road at Mettu vadakarai.

s are shortest and correct to the best of my knowledge.


SUB-DATA

Name of Materials
Cost of Materials
Mixing Ratio

CM 1:1 1/2 960


CMkgs
1:2 720
CM 1:3
kgs 480
CM 1:4
kgs 360
CM 1:5
kgs 288 kgs

Cement 3624.50 3479.52 2609.64 1739.76 1304.82 1043.86

Sand 248.50 248.50 248.50 248.50 248.50


Concrete Works
3728.02 2858.14 1988.26 1553.32 1292.36
Mixing charges
27.00 27.00 27.00 27.00 27.00 27.00
For Mortar Works
3755.02 2885.14 2015.26 1580.32 1319.36

Main Data

7.Earth work excavation in all clauses of soils with initial lead and lift except hard rock requiring
blasting etc., complete for foundation as per SS 20 B.

For Structure works Rs.26 x 2 = 52.00/ 1 cum.


For Drainage works Rs.26 x 1.5 = 39.00/ 1 cum.
For C.C pavement Rs.26x1 = 26.00/ 1 cum.

8. Filling with carted sand including cost and conveyance and all labour
charges such as watering and ramming etc., complete as per standard specification.

1.00 Cum Cost of Sand 248.50 1 Cum 248.50

1.00 Cum Filling 8.20 1 Cum 8.20


Charges
Total 256.70

Rs 256.70 /1CUM
SKM,SVPR.
5 288 kgs
Name of Work :-

Qty Unit Description of Work KM

Rate Per Amount


Applying tack coat over WBM
surface using 4Kg of Bitumen
per 10 sqm. Including cost of
Bitumen emulsion which will
be supplied departmentally at
section stores cost of which
will be recovered at the rates
as per special conditions
appended herewith including
conveyance of Bitumen
emulsion to actual workspot
handling charges including
labour charges for brushing,
cleaning and preparing the
surface for laying the tack coat
and labour for applying the
required quantity of bitumen
emulsion including, hire, fuel
and running charges for all
tools and plants employed for
the work including all other
incidental charges such as
barricading and providing
4.000 KG Cost of Biumen
danger lights, flages etc., 24700 MT 98.80
10 SQM Higher
completeCharges for Tools
as per and
standard 75.40 10 75.40
Plan
specification KM. sqm

10 Sqm Labour Charges 10


Sqm
Rate for 10 sqm 174.20

Rate for 1 sqm 17.42


Name of Work :-

Qty Unit Description of Work KM

Rate Per Amount


PROVIDING AND LAYING PREMIX CARPET WITH SEAL COAT TYPE - ‘A’

Providing and laying P.C. with


seal coat type A for 20mm
thickness using 0.18 cum of
13.20 MM IRC and 0.09 Cum of
11.2 mm IRC. Machine crushed
metal with 14.60 Kg of
Bitumen for Green mixing 10
Sqm of premix carpet and 0.09
cum of 6.70mm IRC machine
crusher metal with 9.80 kgs of
bitumen for seal coat type A
per 10 sqm including cost and
conveyance of materials to the
work sight and stacking them
to the departmental metric
guage for pre measurement
hating bitumen boiler heating
0.180 Cum the aggregates
Cost of 13.2 mm andIRCmixing
HBG 657 1 cum 118.22
them with
machine bitumen in mini hot
metal
0.090 Cum mix plaint for
Cost of 11.2mm premixIRC
rollerHBG
for 512 1 Cum 46.06
rolling to
machine mix for pre mix
metal
0.090 Cum carpeter and
Cost of 6.70mm seals
IRC coats
HBG 383 1 Cum 34.45
separately
machine metal including labour
charges for spreading seals
24.40 KG Cost of packed Bitumen 26500 1 Mt 646.60
cost charges for mini hot mix
0
plant bitumen boiler power
10 Sqm Hire
roller charges for Tools
and all other tools and
and 266.25 10 266.25
plant
plants employed to Sqm
10 Sqm Labour Chargesas per standard
accommodate 10
specification KM. Sqm
Rate for 10 Sqm 1111.57

Rate for 1 Sqm 111.16


Name of Work :-
WBM – I Layer Using Grade II Metal (90mm to 22.4mm) size metal

Qty Unit Description Rate Per Amount


0.050 Cum Cost of 90mm IRC HBG Metal 221.75 1 cum 11.09
0.450 Cum Cost of 63mm IRC HBG Metal 358.75 1cum 161.44
0.425 Cum Cost of 53mm IRC HBG metal 433.75 1 cum 184.34
0.050 Cum Cost of 45mm IRC HBG metal 509.75 1 cum 25.49
0.025 Cum Cost of 22.4 mm IRC HBG metal 710.75 1 cum 17.77
0.24 Cum Cost of Red Gravel 100.65 1 cum 24.16
10.00 Sqm Higher Charges for Tolls & Plant 169.17 10 Sqm 169.17

10.00 Sqm Labour Charges


- Rate for 10 Sqm 593.45
- Rate for 1 Cum 791.27

Name of Work :-
WBM – II Layer Using Grade III Metal (63mm to 22.4mm) size metal

Qty Unit Description Rate Per Amount


0.025 Cum Cost of 63mm IRC HBG Metal 358.75 1 cum 8.97
0.200 Cum Cost of 53mm IRC HBG metal 433.75 1 cum 86.75
0.725 Cum Cost of 45mm IRC HBG metal 509.75 1 cum 369.57
0.025 Cum Cost of 22.4 mm IRC HBG metal 710.75 1 cum 17.77
0.025 Cum Cost of 11.20 mm IRC HBG 511.75 1 cum 12.79
metal
0.24 Cum Cost of Red Gravel 100.65 1 cum 24.16
10 Sqm Higher Charges for Tolls & Plant 169.17 10 Sqm 169.17

10 Sqm Labour Charges


- Rate for 10 Sqm 689.18
- Rate for 1 Cum 918.91
Name of Work :-
LEAD PARTICULARS

Sl. KIND OF MATERIALS NAME OF QUARRY LEAD IN KM COST CONVEY STAC TOTAL
No ANCE KING

No. 1 90MM IRC HBG METAL 1 213.00 5.60 3.15 221.75

2 63 MM IRC HBG METAL 1 350.00 5.60 3.15 358.75

3 53MM IRC HBG METAL 1 425.00 5.60 3.15 433.75

4 45 MM IRC HBG METAL 1 501.00 5.60 3.15 509.75

5 26.5 MM IRC HBG METAL 1 550.00 5.60 3.15 558.75

6 22.4 MM IRC HBG METAL 1 702.00 5.60 3.15 710.75

7 13.2MM IRC Machine Crusher 1 648.00 5.60 3.15 656.75


Metal
8 11.2MM IRC Machine Crusher 1 503.00 5.60 3.15 511.75
Metal
9 6.7MM IRC Machine Crusher 1 374.00 5.60 3.15 382.75
Metal
10 Red Gravel 1 92.00 5.60 3.05 100.65

11 Well Murambu 1 82.00 5.60 3.05 90.65

12 Bitumen (packed) 60/70 26500. 26500.0


00 0
13 Emulsion Bitumen 24700. 24700.0
00 0

Certified that the Lead particulars furnished above are correct to the best of my knowledge
9.Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and
conveyance and all labour charges etc., Complete for 10 Cum

9.00 Cum Cost of 40mm metal 506.80 1 Cum 4561.20


4.50 Cum Cost of CM 1:4 1553.32 1 Cum 6989.94
1.80 Nos Mason II Class 145.00 Each 261.00
17.70 Nos Mazdoor I Class 100.00 Each 1770.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S. Sundries L.S 0.06
For 10 cum 14851.20

Rs. 1485.12 /1 cum

Brick work in CM 1:5 mix using country bricks of size 8½” x 4½” x 2” including all
cost and conveyance of all materials and all labour charges etc., Complete for 10 Cum.

6570.00 Nos Cost of country bricks 1470.00 1000 Nos 9657.90


3.00 Cum Cost of Sand 248.50 1Cum 745.50
860.00 Kgs Cost of Cement 3624.50 1Mt 3117.07
3.50 Nos Mason I Class 160.00 Each 560.00
7.10 Nos Mason II Class 145.00 Each 1029.50
7.10 Nos Mazdoor I Class 100.00 Each 710.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S Sundries L.S 0.03
Rate for 10 Cum 17089.00

Rs. 1708.90 / 1 cum

Plastering with Cm 1:5 mix using to 12 mm thick including all cost and
conveyance of all Materials and all labour charges etc., Complete for 10 Sqm.

0.14 Cum Cost of CM 1:5 1319.36 1Cum 184.71


1.10 Nos Mason I Class 160.00 Each 176.00
0.50 Nos Mazdoor I Class 100.00 Each 50.00
1.10 Nos Mazdoor II Class 90.00 Each 99.00
L.S Sundries L.S 0.09
For 10 sqm 509.80

Rs 50.98 /1 sqm

Random Rubble Masonry in CM 1:5 mix using required Bond stone simultaneous
pointing including all cost conveyance and all labour charges etc, Complete.

10.00 Cum Cost of Rough stone 246.80 1Cum 2468.00


1.00 Cum Cost of Bond stone 331.80 1Cum 331.80
3.40 Nos Cost of CM 1:5 1553.32 1Cum 5281.29
7.10 Nos Mason I Class 160.00 Each 1136.00
10.60 Nos Mason II Class 145.00 Each 1537.00
14.10 Nos Mazdoor I Class 100.00 Each 1410.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S Sundries L.S 0.01
For 10 cum 13433.10

Rs. 1343.31 / 1 cum


Plastering with CM 1:5 mix using to 20 MM thick including all cost
conveyance etc., Complete.

0.22 Cum Cost of CM 1:5 1319.36 1 Cum 290.26


2.20 Nos Mason I Class 160.00 Each 352.00
0.50 Nos Mazdoor I Class 100.00 Each 50.00
3.20 Nos Mazdoor II Class 90.00 Each 288.00
L.S Sundries L.S 0.04
For 10 sqm 980.30

Rs. 98.03 /1 sqm

CC 1: 2: 4 Mix using 20mm ISS HBG metal including all cost


and conveyance and all labour charges etc., Complete.

9.00 Cum Cost of 20mm Iss 701.80 1Cum 6316.20


HBG metal
4.50 Cum Cement Mortar 1:2 2858.14 1Cum 12861.63
1.80 1Nos Mason II Class 145.00 1Cum 261.00
17.70 Nos Mazdoor I Class 100.00 Each 1770.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S Sundries L.S 0.07
Rate for 10 cum 22477.90

Rs. 2247.79 / 1 cum

Supplying and fabrication of steel for RCC works including all cost
and conveyance etc., complete

1.00 Qtl Cost of steel 31000.00 1Mt 3100.00


0.01 Qtl Cost of binding wire 33.00 1 kg 33.00
3.50 Nos Fitter I Class 140.00 Each 490.00
For 1 qtl 3623.00

Rs. 3623.00 /qtl

RCC 1:11/2:3 mix using using 20mm size of HBG metal including all cost
and conveyance etc., complete

9.00 Cum Cost of 20mm Metal 701.80 1 Cum 6316.20


4.50 Cum Cost of Sand 248.50 1Cum 1118.25
4308.00 Kgs Cost of Cement 3624.50 1 Mt 15614.35
3.50 Nos Mason II Class 145.00 Each 507.50
21.20 Nos Mazdoor I Class 100.00 Each 2120.00
35.30 Nos Mazdoor II class 90.00 Each 3177.00
L.S Sundries L.S 0.00
For 10 cum 28853.30

Rs. 2885.33 /1 cum


Granolithic Cement Concrete 1:2:4 mix to 0.25m thick using 10mm to
12mm ISS size of HBG metal including all cost and conveyance of all materials
to work site and all labour charges etc., complete for 10 cum

9.00 Cum Cost of 10mm to 564.30 1 Cum 5078.70


12mm ISS HBG metal
4.50 Cum Cement Mortar 1:2 2858.14 1 Cum 12861.63
1.80 Nos Mason II Class 145.00 Each 261.00
17.70 Nos Mazdoor I Class 100.00 Each 1770.00
14.10 Nos Mazdoor II 90.00 Each 1269.00
L.S Sundries L.S 0.07
For 10 cum 21240.40

Rs. 2124.04 /1 cum


Pointing with CM 1:3 mix over pressed titles on terrace roofing including all cost
and conveyance of all materials and labour charges etc., Complete for 10 sqm

0.04 Cum Cost of CM 1: 3 2015.26 1 Cum 80.61


2.20 Nos Mason II Class 145.00 Each 319.00
0.50 Nos Mazdoor I Class 100.00 Each 50.00
1.10 Nos Mazdoor II Class 90.00 Each 99.00
L.S Sundries L.S 0.09
For 10 sqm 548.70

Rs. 54.87 /1 sqm

Brick jelly with lime concrete using 20mm size of brick jelly with no sand
to be add including all cost and conveyance and all labour charges etc., complete

12.80 Cum Cost of 20mm brick 287.70 1 Cum 3682.56


jelly
5.00 Cum Cost of lime Stone 348.85 1 Cum 1744.25
1.80 Nos Mason I Class 160.00 Each 288.00
17.70 Nos Mazdoor I Class 100.00 Each 1770.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S Sundries L.S 0.09
For 10 cum 8753.90

Rs. 875.39 / 1 cum

Weathering course concrete using brick jelly of size 20mm slacked lime
(no sand to be used) over the RCC roof slab brick jelly in lime being 32 : 12 ½ by volume
and top finished with one course of pressed tiles and pointing with CM 1:3 etc., complete.

250.00 Nos Cost of pressed tiles 4536.70 1000 Nos 1134.18


0.75 Cum Cost of brick jelly concrete 875.39 1 Cum 656.54

0.12 Cum Cost of CM 1:3 2015.26 1 Cum 241.83


5.80 Kgs Cost of Crude Oil 20.00 1 kg 116.00
10.00 Sqm Pointing with CM 1:3 54.87 1 Sqm 548.70
1.10 Nos Mason I Class 160.00 Each 176.00
2.10 Nos Mason II Class 145.00 Each 304.50
2.20 Nos Mazdoor I Class 100.00 Each 220.00
1.10 Nos Mazdoor II Class 90.00 Each 99.00
L.S Sundries L.S 0.05
For 10 sqm 3496.80

Rs. 349.68 / 1 sqm

White washing two coats with best shell lime including all cost and
conveyance and all materials and all labour charges etc., complete for 100 Sqm
0.07 Cum Cost of shell lime 705.00 1 Cum 49.35
1.60 Nos Mason II Class 145.00 Each 232.00
0.50 Nos Mazdoor I Class 100.00 Each 50.00
2.70 Nos Mazdoor II Class 90.00 Each 243.00
L.S Sundries for gum & L.S 2.05
conjee water
For 100 sqm 576.40

Rs. 5.76 / 1 sqm

Colour washing two coats including all cost conveyance and all labour
charges etc., complete

10.00 Sqm Cost of white washing 5.76 1 Sqm 57.64


L.S and for colour pigments L.S 28.82
(50%
whitewash)
For 10 sqm 86.46
Rs. 8.65 / 1 sqm

Painting with ready mixed good quality of enamel paint two coats including
all cost and conveyance etc., complete for 10 Sqm Over new Iron works.
2.22 Lits Cost of enamel paint 150.00 1 Litter 333.00
1.10 Nos Painter Ist Class 130.00 Each 143.00
L.S Sundries L.S 0.00
For 10 sqm 476.00
Rs. 47.60 / 1 sqm

Plastering withs CM 1:3 10mm thick including all cost and conveyance and all
labour charges etc., complete.
0.10 Cum Cost of CM 1:3 2015.26 1Cum 201.53
1.10 Nos Mason I Class 160.00 Each 176.00
1.10 Nos Mazdoor I Class 100.00 Each 110.00
1.10 Nos Mazdoor II Class 90.00 Each 99.00
L.S Sundries L.S 0.07
For 10 sqm 586.60
Rs. 58.66 / 1 sqm
Distermpering two coats includidng all cost anad conv eyance and all labour charges
for 10 sqm.
1.34 Kgs Distember 60.00 1Kg 80.40
0.50 Nos Painter I grade 130.00 Each 65.00
0.50 No. Mazdoor I grade 100.00 Each 50.00
0.80 No. Mazdoor II grade 90.00 Each 72.00
Sundries L.S. 0.60
for 10 sqm 268.00
Rs. 26.80 / 1 sqm

Snowcem painting two coats with approved paint over cement plastered wall surface ceiling and other new
surface including cleaning preparing the surface and curing etc. complete for 10 sqm

10.00 sqm Cleaning plastered surface 1.80 1sqm 18.00


3.23 kgs snowcem paint 30.00 1Kg 96.90
0.50 No. Painter I class 130.00 Each 65.00
0.50 No. Mazdoor Igrade 100.00 Each 50.00
0.80 No. Mazdoor II Grade 90.00 Each 72.00
Sundries L.S. 0.10
for 10 sqm 302.00
Rs. 30.20 / 1 sqm

Brick work in CM1:3mix using country bricss including all cost and conveyance etc. complete.

6570.00 Nos Cost of country bricks 1470.00 1000 Nos 9657.90


3.00 Cum Cost of Sand 248.50 1Cum 745.50
1433.33 Kgs Cost of Cement 3624.50 1Mt 5195.10
3.50 Nos Mason I Class 160.00 Each 560.00
7.10 Nos Mason II Class 145.00 Each 1029.50
7.10 Nos Mazdoor I Class 100.00 Each 710.00
14.10 Nos Mazdoor II Class 90.00 Each 1269.00
L.S Sundries L.S 0.07
Rate for 10 Cum 19167.07

Rs. 1916.71 / 1 cum

Plastering with CM1:3,


1:520mm
mixthick
using to 20
including all MM thick including all cost
cost and
conveyance etc., Complete.

0.22 Cum Cost of CM 1:3 2015.26 1 Cum 443.36


2.20 Nos Mason I Class 160.00 Each 352.00
0.50 Nos Mazdoor I Class 100.00 Each 50.00
3.20 Nos Mazdoor II Class 90.00 Each 288.00
L.S Sundries L.S 0.04
For 10 sqm 1133.40

Rs. 113.34 /1 sqm


country bricss including all cost and conveyance etc. complete.
Rough stone Dry packing for approns and revetmante including Gravel
packing including all lapour Charges etc. complete

11.00 Cum Cost of Rough stone 1 Cum

3.50 Nos Wooder 105.00 Each 367.50

10.60 Nos Mazdoor I Class 100.00 Each 1060.00

7.10 Nos Mazdoor II Class 90.00 Each 639.00

11.60 Cum Cost. Red Gravel 97.60 Each 1132.16

7.10 Nos Mazdoor I Class 100.00 710.00

3.50 Nos Mazdoor II Class 90.00 315.00

L.S. Sundries L.S

For 10 cum

Rs. /1 cum