Вы находитесь на странице: 1из 11

DISTRIBUTION TRAINING

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

SUBSTATION & OPERATION SYSTEM

SUBSTATION

Substation Fitter 1 (Maintenance) Asas Jurugegas Pencawang 1 (Senggaraan)

TT05/06

10

3-14

8-19

11-22

Substation Fitter 2 (Construction) Asas Jurugegas Pencawang 2 (Pembinaan) Transformer Operation & Maintenance up to 33kV & PPVR (Malim Nawar) Kendalian & Penyelenggaraan Alatubah setakat 33kV & PPVR (Malim Nawar) Earthing Installation of Distribution Substation Pemasangan Pembumian Pencawang Pembahagian Senggaraan Pencawang Substation Maintenance

TT05/06

10

24-5/10

19-30

1-12

TT07/08

19-23

18-22

TT07/08

18-19

12-13

17-18

TT07/08

1-5, 29-2/11

25-29

Senggaraan Pencawang (Malim Nawar) Substation Maintenance

TT07/08

04 - 08

08 - 12

10 - 14

Sistem Pembumian Earthing System Transformer Construction & Maintenance up to 33kV (Malim Nawar) Pembinaan & Penyelenggaraan Alatubah S t k t 33kV (Malim Setakat (M li Nawar) N ) Switchgear Installation and Maintenance up to 33kV Pemasangan dan Penyelenggaraan Alatsuis setakat 33kV Introduction to LV Capacitor Bank Pengenalan Pencawang Pembahagian Untuk Anggota Kerja Perjangkaan Introduction of Distribution Substation for Metering Staff Construction and Maintenance of Distribution Substation

TT09/14

22-23

26-27

29-30

TT09/14

8-12

7-11

15-19

TT09/14

29-2/11

3-7

10-14

10

TT11/12

22-24

12-14

21-23

11

TT09/14

18-20

13-15

20-22

12

E07/08/12/13 ET & Engineer

24-28

15-19,

5-9

17-21

1-5

3-7

13

Transformer & OLTC Maintenance up to 33kV for Executive

E07/08/12/13 ET & Engineer

26-29

14-17

6-9

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

OPERATION SYSTEM 11kV

14

Cable Fault Location Mencari Kerosakan Kabel

TT07/14

8-12

18-22

15

Sheath Fault Location Mencari Kerosakan Kabel 'Sheath' Substation Switching Operation up to 11kV (Malim Nawar) Kendalian Pencawang - Setakat 11kV (Malim Nawar) Switching Operation up to 1kV Kendalian (Switching Operation) - setakat 1kV (AP), Refresher Practical Substation Switching Operation up to 11kV BO (TNBD) Refresher Amali Kendalian Pencawang 11kV BO (TNBD) Switching Operation up to 11kV Kendalian Pencawang - Setakat 11kV

TT07/14

31/1-1/2

25-26

16

TT09/14

10-14, 24-28

08 - 12, 29 - 02/11

19-23

3-7

17

TT09/14

8-11,

29-31

14-17

8-11

18

TT09/14

19

E07/08/12/13 ET & Engineer

3-7

1-5, 15-19

5-9, 26-30

7-11

20

Cable Fault Location Mencari Kerosakan Kabel

E07-E15

1-5

14-18

21

Sheath Fault Location Mencari Kerosakan Kabel 'Sheath' Refresher Practical Substation Switching Operation up to 11kV BO (TNBG) Refresher Amali Kendalian Pencawang 11kV BO (TNBG) Practical Test Switching Operation BO (STTNBG) Ujian Amali Kendalian Pencawang BO (ST TNBG) Switching Operation up to 11kV Kendalian Pencawang - Setakat 11kV (TNBG only)

E07-E15

1-2

29-30

22

Non Exec Exec TNBG Only

23

Non Exec Exec TNBG Only

24

Non Exec Exec TNBG

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

OPERATION SYSTEM 33kV Switching Operation up to 33kV (Module 1 - Introduction to 33kV System) Kendalian Pencawang - Setakat 33kV (Modul 1 - Pengenalan Sistem 33KV) Switching Operation up to 33kV (Module 2 - System Operation 33kV) Kendalian Pencawang - Setakat 33kV (Modul 2 - Kendalian Sistem 33KV) Switching Operation up to 33kV (Module 1 - Introduction to 33kV System) Kendalian Pencawang - Setakat 33kV (Modul 1 - Pengenalan Sistem 33KV) Switching Operation up to 33kV (Module 2 - System Operation 33kV) Kendalian Pencawang - Setakat 33kV (Modul 2 - Kendalian Sistem 33KV)

25

TT09/14

10 - 12

30 - 1 Nov

3-5

29 - 31

24 - 26

26

TT09/14

1- 5

19 - 23

14 - 18

10 - 14

19 - 23

27

E07-E15

24 - 26

5-7

17 - 19

8 - 10

1-3

28

E07-E15

15 - 19

26 - 30

4-8

17 - 21

26 - 30

OVERHEAD LINES & CABLE

OVERHEAD LINES

29

Fault Finder Competency Kompetensi Pembaik Kerosakan

TT05

3-14

29/10-9/11

18 - 29

15 - 26

29Apr - 10

30

Low Voltage Live Line Work Kerja Talian Hidup Voltan Rendah Construction and Maintenance of Overhead Line Bare Conductor P Pemasangan dan d Penyelenggaraan P l Talian T li Atas Voltan Sederhana Tidak Bertebat Refresher For Fault Finder Ulangkaji Pembaik Kerosakan Low Voltage Live Line Work for Executives/Supervisors Kerja Talian Hidup Voltan Rendah Eksekutif/Penyelia Low Voltage Overhead Line for Executives Talian Atas Voltan Rendah Utk. Eksekutif Refresher Course for 33kV Overhead Line for Executives Ulangkaji Talian Atas 33kV Utk. Eksekutif Refresher for Low Voltage Live Line Ulangkaji Kerja Talian Hidup Voltan Rendah

TT05 - TT06

11-13

2-4

6-8

5-7

31

TT07/08

24-28 24 28

32

TT07/08

24-27

15-18

4-7

20 - 23

33

TT09-E12

34

ET & Jurutera O&M, Pembinaan (E07-E13) E07-E13 @ ET & Jurutera O&M 33kV (E07-E13) TT05 - 08

8-12

5-9

4-8

25 - 29

22 - 26

13 - 17

35

16-17 30 - 31

22 - 23 26 - 27

36

23-24

4 - 5,

12 - 13

37

Pembinaan dan Senggaraan Talian Atas VR

TT09/10 @ TT12

10-14

26-30

25-1/3

15-19

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

OVERHEAD LINES (MALIM NAWAR) High Voltage Overhead Line for Linesman (Malim Nawar) Asas Pemasang Talian Voltan Tinggi (Malim Nawar) Low Voltage Live Line Work (Malim Nawar) Kerja Talian Hidup Voltan Rendah (Malim Nawar) Low Voltage Overhead Line for Linesman Module 1 (Malim Nawar) Kompetensi Pemasang Talian VR Modul 1(Malim Nawar) Low Voltage Overhead Line for Linesman Module 2 Kompetensi Pemasang Talian VR Modul 2

38

TT05/07

20

5-30

39

TT05/06

5-7' 19-21

31 - 02/11

4-6

40

TT05/06

10

24 - 05/10

15 - 25

07 - 18

18 - 01/03

41

TT05/06

10

04 - 15/03, 18 - 29

01 - 12

06 - 17

42

MV ABC for Executive (Malim Nawar) Construction and Maintenance of MV ABC Cable (Malim Nawar) Pemasangan dan Penyelenggaraan Kabel MV ABC (Malim Nawar) Pengendalian & Penyelenggaraan Kren Auger (Malim Nawar) Operation & Maintenance of Crane - Auger (Malim Nawar) Vegetation Management (Malim Nawar)

E07-E14

31 - 01/02

17 - 18

43

Open

20 - 23, 27 - 31

44

TD05

10-14

8-12

22 - 26

45

29 - 30

15 - 16

46

Refresher for Low Voltage Live Line (Malim Nawar) Ulangkaji ji Kerja j Talian i Hidup i Voltan Rendah

10 - 11, 13 - 14

21 - 22

18 - 19, 25 - 26

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

CABLE

47

LV Jointing Practices Amalan Pencantuman Kabel Voltan Rendah

TT05/06

3-11

1-9

1-9

31/1-8/2

7-15

13-21

3-11

22-30

48

11kV Jointing Practices Amalan Pencantuman Kabel hingga 11 kV

TT05/06/07

20-28

11-19

29 - 7/12

14-22

6-14 17-25 27/6-5/7

27/6-5/7

19-27

49

33kV Jointing Practices Amalan Pencantuman Kabel hingga 33 kV ST Cable Jointing Level 1 (LV) Percantuman Kabel Tahap 1 (Voltan Rendah) TNBD / Open ST Cable Jointing Level 2 (LV) Percantuman Kabel Tahap 2 (11kV) - TNBD / Open Cable Laying Practices up to 33kV (Supervisor) Amalan Rentang Kabel hingga 33kV (Penyelia TNB) ST Cable Jointing Level 3 (33kV) Percantuman Kabel Tahap 3 (33kV) - TNBD / Open

TT07/08

22-26

6-10 17

13-

1-5

19-23

50

TT05/06

12

4-19

7-22

18/3-2/4

18/3-2/4

13-28

51

TT05/06/07

10

18/2-1/3

18/2-1/3 18-29

1-12

52

TT05-10

4-5

8-9

20-21

25-26

4-5

53

TT07/08

10

21-31

54

Cable Fault Post Mortem (Exec & NonExec)

TT09 -14 E07-E14

55

Cable Laying & Jointing

TT09-14

1-3

5-7

17-19

22-24

1-3

56

Condition Based Maintenance - Cable CPD

E07/08 - E14

15-17

5-7

17-19

57

U/G Distribution Cables CPD

E07/08- E14 ET & Engineer

17-19

4-6

27-29

58

22kV Jointing Practices Amalan Pencantuman Kabel hingga 22 kV

TT05/06/07

59

11kV Jointing Practices (Refresher) Amalan Percantuman Kabel 11kV (Refresher) Cable Laying Practices up to 33kV (Contractor) Amalan Rentang Kabel Hingga 33kV (Kontraktor)

TT05-08

60

Contractor

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

SAFETY & ENVIRONMENT (OSHE & CORPORATE TRAINING) Technician's Safety Module (Modul Keselamatan Juruteknik) -Electric Safety Rules (Aturan Keselamatan Elektrik) -Safety training Guideline (Panduan Latihan Keselamatan) TNBD Engineer's Safety Module I (Modul Keselamatan Jurutera Pembahagian I) -Electric Safety Rules (Aturan Keselamatan Elektrik) -Safety training Guideline (Panduan Latihan Keselamatan) TNBD Engineer's Safety Module II (Modul Keselamatan Jurutera Pembahagian II) -NIOSH-TNB Safety Passport -SEMS Awareness BEM Engineering Management Practice

61

TT09/10 (TNBD Only)

Upon Request

62

E11/12/13 (TNBD Only)

3-6

7-10

4-7 18-21

11-14

63

E11/12/13 (TNBD Only)

17-18

21-22

1-2

15-16

6-7

64

Engineer ** (Open)

22-23

3-4 6-7

7-8 10-11

18-19

14-15

1-2 18-19

27-28

65

BEM Safety & Health

Engineer ** (Open)

22-23

29-30

6-7

13-14

10-11 21-22

21-22

18-19

8-9

6-7

66

BEM Code of Ethics and Regulations

Engineer ** (Open)

29-30

3-4

13-14

7-8

21-22

18-19

11-12

25-26

11-12

20-21

PROTECTION (ENGINEERING SERVICES TRAINING)

67

Distribution Network Power System Protection 33/11KkV /

E12 - 13 (Post-PEP) ( )

21-23

26-28

19-21

23-25

28-30

68

Earth Fault Indication (EFI) Installation Operation & Maintenance

E07 - 15

6-7 27-28

12-13

15-16

19-20

69

Earth Fault Indication (EFI) Installation Operation & Maintenance Distribution System Protection 33/11kV (Basic) Perlindungan Sistem Pembahagian 33/11kV (Asas) Distribution System Protection 33/11kV (Intermediate) Perlindungan Sistem Pembahagian 33/11kV (Pertengahan) Distribution System Protection 33/11kV (Advance) Perlindungan Sistem Pembahagian 33/11kV (Lanjutan) Advanced Power System Protection (Analysis & Protection of Power System - APPS)

TT09-TT14

5-6 27-28

16-17

7-8 28-29

25-26

70

TT05-TT06

10-12 25-27

9-11 22-24

6-8

71

TT07-TT08

20-22

4-6 17-19

72

TT09-TT14

15-17 29-31

13-15

73

Protection Engineer/Manager

10

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

SYSTEM AUTOMATION & SCADA (ENGINEERING SERVICES TRAINING)

74

SCADA System (M1) - Distribution @ Sistem SCADA (Modul 1)

TT09 (TNBD Only)

9-11

19-21

75

SCADA System(M3) - Distribution @ Sistem SCADA (Modul 3)

TT09 - E14 (TNBD Only)

2-4

7-9

76

RTU-Foxboro

TT09-TT14 (TNBD Only)

3-6

4-7

77

RTU- Dongfang

TT09-TT14 (TNBD Only)

6-9

8-11

78

RTU-Viscon Dua

TT09-TT14 (TNBD Only)

16-18

18-20

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

PLANNING (ENGINEERING SERVICES TRAINING)

79

LV Planning Guidelines for Non-executive (to be conducted together with MV Planning Guidelines for Non-exec) MV Planning Guidelines for Non-executive (to be conducted together with MV Planning Guidelines for Non-exec)

TT09/10

01-03

18-20

80

TT09/10

04-05

21-22

81

Basic PSS-Adept for Non-executive

TT11/12

22-24

19-21

05-07

82

Introduction to Power Quality for Executive

E07-12

18-19

10-11

83

LV Planning Guidelines for Executive

E07-13

15-17

25-27

84

MV Planning Guidelines for Executive

E07-13

11-14

30/10-02/11

19-22

85

Power Quality for O&M Executive

E12-15

14-16

04-06

04-06

86

Failure Analysis Methodology for MV VCBs

E07-15

11-13

27-29

87

Introduction to LV Planning (to be conducted together with Introduction to MV Planning)

E12

24-26

05-07

88

Introduction to MV Planning (to be conducted together with Introduction to LV Planning)

E12

27-28

08-09

89

Basic PSS-Adept for Executive

E12-13

01-03

07-09

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

METERING (ENGINEERING SERVICES TRAINING)

90

Installation and Testing of OPC Meters Pemasangan dan Pengujian Jangka OPC

TT05/06

15-17

91

Installation and Testing of LPC LV Meters Pemasangan dan Pengujian Jangka LPC LV

TT05/06

18-19

92

Inspection of OPC/LPC Meters Pemeriksaan Jangka OPC/LPC Installation and Testing of OPC and LPC Meters Pemasangan dan Pengujian Jangka OPC & LPC Inspection and Detection of LPC Metering Irregularities Pemeriksaan dan Mengesan Kejanggalan Jangka LPC Metering Wiring and Inspection

TT07/08

29/10 - 2/11

93

TT09/10

4-7

19-22

2-5

94

TT09/10

6-9

26-29

14-17

95

E07-13

21-23

25-27

96

Metering and Billing For Non Technical Executives

E07-13

Upon Request

97

Introduction to Metering & Supply Application

E12/13

26/2-1/3

23-26

98

High Voltage Metering

E12/13

17-21

CUSTOMER SERVICES CENTRE MODULE

99

METERINGSYSTEMFORPP&P - Meter types for all types of tariffs

FRONTLINER

27-28

27-28

METERINGSYSTEMFORMETERREADERSPS04/04 100 (New) - Meter types for all types of tariffs

PS 0304

18-19

15-16

ILSAS PROGRAM SCHEDULE FY2012/2013

DISTRIBUTION TRAINING

No

Course Title

Target Participant (Grade)

Duration (days)

Sept 12

Oct 12

Nov 12

Dec 12

Jan 13

Feb 13

Mac 13

Apr 13

May 13

Jun 13

Jul 13

Aug 13

AM MODULE

TECHNICAL

Fault Analysis & Troubleshooting 101 - Substation - Overhead Lines & Cable Metering 102 - Losses - Remote Meter Reading Planning 103 - Planning (1 day) - Power Quality (1 day)

E14/E15 E12/E13 E07/E08 E14/E15 E12/E13 E07/E08 E14/E15 E12/E13 E07/E08 E14/E15 E12/E13 E07/E08

21-22

3-4

19 (Planning), 20 (PQ)

104 Operational Safety & Switching

POST PEP

105

Distribution Network Power System Protection 33/11kV

E12-E13 (Post PEP)

21-23

26-28

19-21

23-25

28-30

Вам также может понравиться