MV panel:

1. 2. 3. 4. 5. 6. In MV panel transformer feeder-5 trip circuit healthy indication not showing. In MV panels O/G feeder to cooling tower makeup pump-3 (feeder-14) spring charge motor problem. In MV panels spare transformer feeder-12 spring charging motor problem. Ammeter and Energy Meter not working in I/C-2. Panel illumination lamps not provided. In MV panel-2 REM615 Relay sent for repair.

LV panel:

7. For the following feeders provided OLR rating not matching with motor rated current v Air compressor for DAF (3.7kw) motor rated amperes 4.6A, OLR rating 7-10A [20F3]. v RO-CIP pumps(7.5KW) motor rated amperes 14.3A, OLR rating 16-24A [10F4,20F2] v SERVIECE AIR COMPRESSOR (5.5KW) motor rated amperes 7.5A,m OLR rating 12-18A [11F5,23R2 8. Hooter in LV panels is not working. 9. Public announcement system Commissioning is pending. 10. Illumination lamps not provided in MCC Panel. 11. Field ammeters of effluent pumps not taken into line 12. Approach not provided for EOT maintenance. 13. For Intake pump-3 one of three run cable (R& B- Phases) IR Values showing zero. 14. LPBS are to be replaced in outdoor areas with weather proof LPBS. 15. Control cable of Lubrication motor shorted in Intake area. LV PANEL MATERIAL SHORTAGE:

7 8 9

ION-XCHANGE Pending Jobs of CREEK RO plant


1. Operational& protection testing of circuit breaker in the VFD panel is not done. 2. VFD service engineer required for limiting noise generating from VFD. nd 3. Damaged exhaust fan in 2 VFD panel should be replaced. 4. Motor guards (canopy) should be provided for outdoor motors. 5. Erection of Centrifuge feed pump-1 pending. 6. Acid dosing and SBS dosing pump motors(0.37KW) taking more than rated amperes on no-load and tripping after some time, either the motors should be replaced or some appropriate solution should

Sterling & Wilson pending works in RO-PLANT


1. Control panel for AHU&A/C units erected. Commissioning not done. 2. Earthing to be done for AHU system.

MV SERVICE ENGINEER AVAILABLE AT SITE WILL BE COMPLETED SHORTLY.

completed cable to receive while handovering panel spares will be given cable to receive Mechanincal requirement ladder to be arranged in progress SEPL Shall carry out regular maintenance will be replaced

25f2,12f2

19F1

10R1

16F3

20F1,27F1,4R6,13R4, 24R3,26R5,29R4

4R5,6R2,22R3,30F2

14F3 1F4 27F3

BREAKER IS IN OPERATION FROM ONE YEAR, NOT REQUIRED VFD Noise level in limits only. waiting for spares agency to be finalized motor to receive for erection. taken up issue with supplier completed completed

Interposin g Relay IPR1 is not installed

ACB Operating rod (rack in/out) not available. Add-on Contact Block LADN04 not available.

Cable cord for B21Voltage Protection Relay (SEPAM)is not available Power fuses to be replaced(1 25A,160A, 35A,32A,6 3A,6A) material Control will be fuses to handover be ed during replaced(6 handoveri A) ng of mcc. Fuse link F65-6A is not available completed control transformer in progress operating knob is broken SFU got struck completed and not getting On and OFF.