0 Rev. No
25.09.09 Date
RSU Prepared by
KRK/TG Checked by
RKT Approved by
PROJECT
PLANT
JOB NO. QUANTITY SERVICE 1.0 1.1 : Fluid 1.2 : # Flow Rate (Rated), Kg/Hr 1.3 Design Margin 1.4 : Operating Pressure (Rated), Kg/Cm2 (g) 1.5 : Design Pressure, Kg/Cm2 (g) 1.6 : Operating Temperature (Rated), 0C 0 1.7 : Design Temperature, C 1.8 : Silencer Operation 1.9 : Position of the Silencer 1.10 Silencer Location : 1.11 Corrosion Allowance, mm : 1.12 Inlet Size/Rating/Type : 1.13 Silencer Type : 1.14 Silencer Bottom end : 1.15 Insulation on outer surface (by others) : 1.16 Rain hood with bird screen to be provided 2.0 MATERIAL OF CONSTRUCTION 2.1 : Inlet Pipe (Nozzle) 2.2 : Inlet Flange 2.3 : Shell 2.4 : Bottom Dished End 2.5 : Diffuser pipe 2.6 : Perforated Sheet for insulation and Bird Screen 2.7 : Rain Hood 2.8 : Sound Absorptive Packing Material 2.9 : Silencer Supports 2.10 Acceptable Noise Level, dBA (Max.) : 3.0 MANUFACTURERS DATA
3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.20 Manufacturers Name Size (Dia., mm & Overall Length, mm) Shell Thickness, mm Acoustic Insulation Material Acoustic Insulation Material Density, Kg/m3 Acoustic Insulation Surface area, m2 Acoustic Insulation Thickness, mm Silencer support (Type and no. of supports) Material of Construction Shell Dished end In let pipe In let pipe flange Diffuser pipe Drain details Drain valve External Insulation (To be provided by others) : : : : : : : : : : : : : : : : : * * * * * * * *
: DAHEJ PETRO CLIENT : OPAL CHEMICAL COMPLEX : Nitrogen gas and LOCATION : OUTDOOR Compressed Air System : 6987 ITEM NO. : : ITEM NAME : SILENCER : OPERATING AND DESIGN DATA
# as per process data sheet * Data to be furnished after award of order NOTES
1. Drain connection with a Globe Valve along with a Blind Flange shall be provided as per enclosed piping material specification attached elsewhere in the tender and as per P&ID.