Thursday, June 27, 2013 T&M8912-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N49-N50, 2-N88)

and a pipe (2-N85) due to the dewatering issue = 1 hour -cut sealing plates -burned holes with polyurethane behind the sheet pile -cored through the polyurethane with pipe -welded sealing frames Grouted polyurethane Re-sealed 2-N85 Used 1.5 resin, 0.5 accel, 0.5 packer T&M8913-Tieback Installation (Day) Installed pipe 2-N85 Started drilling tiebacks 2-N49-N50, 2-N88 Welded pipes on the wall. T&M8945-Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-N85, 2-N58) due to the dewatering issue = 1 hour -cut sealing plates Grouted polyurethane Re-sealed 2-N49-N50, 2-N88, 2-N85 Used 2 resin, 1 accel, 0.5 packer T&M8915-Tieback Installation (Night) Installed tieback 2-N49-N50, 2-N85, 2-N88 Drilled 2-N58 halfway. Welded pipes on the wall.

T&M8916-Tieback Night shift Premium Night shift premium between 3pm-1:30am (10.5 hours) for drilling tiebacks. T&M-Overtime Friday, June 28, 2013 T&M8917-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N67, 2-N82-N83, 2-N80) and a pipe (2-N64) due to the dewatering issue = 1 hour -cut sealing plates -burned holes with polyurethane behind the sheet pile -cored through the polyurethane with pipe -welded sealing frames -fabricated more sealing frames Grouted polyurethane Re-sealed 2-N67, 2-N82-N83, 2-N80, 2-N64 Used 2.5 resin, 1.5 accel, 1 packer

T&M8913-Tieback Installation (Day&Night) Installed pipe 2-N64 Installed tieback 2-N67, 2-N82-N83, 2-N80, 2-N58, 2-N43, 2-N45-N46, 2-N80-N81 Welded pipes on the wall. T&M8914-Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-N43, 2-N45-N46, 2-N80) due to the dewatering issue = 1 hour -cut sealing plates Grouted polyurethane Re-sealed 2-N43, 2-N45-N46, 2-N80-N81 Used 2 resin, 1 accel, 0.5 packer T&M8916-Tieback Night shift Premium Night shift premium between 3pm-1am (10 hours) for drilling tiebacks. T&M-Overtime

Saturday, June 29, 2013 T&M8932-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N61, 2-N64, 2-N78) due to the dewatering issue = 1 hour -cut sealing plates -burned holes with polyurethane behind the sheet pile -welded sealing frames Grouted polyurethane Re-sealed 2-N61 Used 1 resin, 0.5 accel,

T&M8933-Tieback Installation (Day) Installed tieback 2-N61 Started drilling 2-N64, 2-N78 Welded pipes on the wall. Welders Byron B5 Rodrigo stiffener for waler W211/214 And silvino Arturo guessets on waler 26/29 Geroge cutting and fitting for everyone T&M8950-Waler Installation Rodrigo stiffener for waler W211/214 T&M8934-Grouting Polyurethane (Night)

Additional hours lost trying to install tiebacks (2-N75, 2-S239-S240) due to the dewatering issue = 1 hour -cut sealing plates Grouted polyurethane Re-sealed 2-N64, 2-N78 Used 2 resin, 1 accel, 0.5 packer T&M8935-Tieback Installation (Night) Installed tieback 2-N64, 2-N78 Started drilling 2-N75, 2-S239-S240 Welded pipes on the wall. Tieback machine broke down and was serviced

T&M8936-Tieback Night shift Premium Night shift premium between 3pm-3am (12 hours) for drilling tiebacks, and servicing the tieback machine. T&M8936, 8951 Tieback Saturday Premium (Day & Night) Saturday premium time for drilling tiebacks, welding pipes. Serviced a tieback machine

Sunday, June 30, 2013 T&M8938-Grouting Polyurethane (Day) Additional hours lost trying to install a tieback (2-N72) due to the dewatering issue = 0.5 hour -cut sealing plates Grouted polyurethane Re-sealed 2-N75, 2-S239-S240 Used 1.5 resin, 0.5 accel, 0.5 packer T&M8939 Tieback Installation (Day) Installed tiebacks 2-N75, 2-S239-S240 Welded pipes on the wall One of the tieback machine broke down and it was serviced Started drilling 2-N72 Welders Byron on B5s (completed 10 between sat and sun) George cutting and fitting T&M8952-Waler Installation Carlos 26/29 gussets completed and worked on 211/214 waler onto the wall T&M8940-Grouting Polyurethane (Night) Additional hours lost trying to install a tieback (2-N70, 2-S250) due to the dewatering issue = 0.5 hours -cut sealing plates Grouted polyurethane Re-sealed 2-N72, 2-S250

Used 1.5 resin, 0.5 accel, 0.5 packer T&M8941 Tieback Installation (Night) Installed tiebacks 2-N72, 2-S250 Welded pipes on the wall One of the tieback machines broke down and it was serviced (9pm-5am) Started drilling 2-N70 T&M8943-Tieback Night shift Premium Night shift premium between 3pm-5am (14 hours) for drilling tiebacks, and servicing the tieback machine. T&M8942, 8949 Tieback Sunday Premium (Day & Night) Sunday premium time for drilling tiebacks, welding pipes, and servicing a tieback machine

Monday, July 1, 2013 T&M8953-Grouting Polyurethane Grouted Polyurethane Re-sealed 2-N70 1 resin, 0.5 accelerator, T&M8954-Tieback Installation Installed tieback 2-N70 Welded pipes on the wall T&M8955-Tieback Holiday Premium Holiday premium time between 7am-3:30pm for drilling tiebacks and welding pipes

Tuesday, July 2, 2013 T&M8956-Grouting Polyurethane (Day) Additional hours lost trying to install tieback (2-S308, 2-S257) due to the dewatering issue = 0.5 hours. -cut sealing plates -welded sealing frames onto the pipes -welded sealing plates and teeth onto the pipes Grouted Polyurethane Worked on 2-N108, 2-N110, 112, 115 Re-Sealed 2-S308 5 resin, 1.5 accel, 2 coupler, 1 packer, 1 breakline

T&M8957-Tieback Installation (Day) Installed tiebacks 2-S308 Started drilling 2-S257 Welded pipes on the wall Welded threads onto the pipes Worked on brackets on SW wall. T&M8958-Waler Installation (Day) Worked on waler 2-S211 / 2-S214 T&M8959-Grouting Polyurethane (Night) Additional hours lost trying to install pipes (2-S319, 2-S322) due to the dewatering issue = 1 hour. -burn holes with polyurethane behind the sheet pile wall -cored through polyurethane with pipes -welded sealing frames onto the pipes Grouted Polyurethane Finished foaming 2-N108, 2-N110, 112, 115 Re-Sealed 2-S257 1.5 resin, 0.5 accel, 0.5 packer T&M8960-Tieback Installation (night) Installed tiebacks 2-S257 Installed pipes 2-S319, 2-S322 Welded pipes on the wall. T&M8962-Tieback Night Shift Premium Night shift premium between 3pm-11:30pm (8.5 hours) for drilling tieback, installing pipes, and welding pipes on the wall.

Wednesday, July 3, 2013 T&M8963-Grouting Polyurethane (Day) Additional hours lost trying to install tieback (2-S305) and pipes (2-S253, 2-S255, 2-S316, 2-S325, 2-S328, 2-S331) due to dewatering issue = 6 hours -cut sealing plates -welded sealing frames -burn holes with polyurethane behind the sheet pile wall -cored through polyurethane with pipes -was not able to install 2-S253 and 2-S255 due to high water pressure Grouting Polyurethane Re-sealed 2-S253, 2-S255, 2-S316, 2-S325, 2-S328 2 resin, 0.5 packer, 1 accel, 1 breakline T&M8961-Tieback Installation (Day) Installed pipes 2-S316, 2-S325, 2-S328

Welded pipes on the wall Started drilling 2-S305 Worked on brackets on the SW wall Fabricated B5 brackets T&M8964-Waler Installation (Day) Worked on walers 2-S211 / 2-S214, and 2-S233 / 2-S239-S240 T&M8965-Grouting Polyurethane (Night) Additional hours lost trying to install pipes (2-N132, 2-N134, 2-S334, 2-S337, 2-S338-S339) due to dewatering issue = 1.5 hours -welded sealing frames -burn holes with polyurethane behind the sheet pile wall -cored through polyurethane with pipes Grouted Polyurethane Re-sealed 2-N132, 2-N134, 2-S334, 2-S337, 2-S338-S339 1.5 resin 0.5 accel, 0.5 packer T&M8966-Tieback Installation (Night) Installed pipes 2-N132, 2-N134, 2-S334, 2-S337, 2-S338-S339 Welded pipes on the wall T&M8967-Tieback Night Shift Premium Night shift premium between 3pm-11pm (8 hours) for installing pipes, and welding pipes on the wall

Thursday July 4, 2013 T&M8968-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-S303, 2-N14, 2-N17) due to dewatering issue = 1 hour -cut sealing plates -welded sealing frames -welded sealing plates and teeth onto the pipes Grouted Polyurethane Worked on 2-N102, 2-N105 Re-sealed 2-S303, 2-N14 7 resin, 3 accel, 1 plug, 2 breakline, 2 coupler T&M8969-Tieback Installation (Day) Installed tiebacks 2-S303, 2-N14 Started drilling 2-N17 Welded pipes on the wall. Welded threads onto the pipes Worked on brackets on the SW wall (2-S211, 2-S214) T&M8970-Waler Installation (Day)

Worked on walers 2-S211 / 2-S214, and 2-S233 / 2-S239-S240 T&M8971-Grouting Polyurethane (Night) Additional hours lost trying to install pipes (2-N112, 2-N115, 2-N128, 2-N341, 2-N343, 2-N346) due to dewatering issue = 1.5 hour -cut sealing plates -welded sealing frames -burn holes with polyurethane behind the sheet pile wall -cored through polyurethane with pipes Grouted Polyurethane Resealed 2-N112, 2-N115, 2-N128, 2-N341, 2-N343, 2-N346 3 resin, 1.5 accel, 1 packer T&M8972-Tieback Installation (Night) Installed pipes 2-N112, 2-N115, 2-N128, 2-N341, 2-N343, 2-N346 Welded pipe on the wall Installed tieback 2-N17 T&M8973-Tieback Night Shift Premium Night shift premium between 3pm-11pm (8 hours) for installing pipes, and welding pipes on the wall

Friday July 5, 2013 T&M8974-Grouting Polyurethane (Day) Additional hours lost trying to install a tieback (2-S316) due to dewatering issue = 0.5 hour -cut sealing plates -welded sealing frames -welded sealing plates and teeth onto the pipes Grouted Polyurethane Worked on 2-N143/144, 2-N146, 2-N147-N148, 2-N149-N150 6 resin, 3 accel, 2 packer T&M8975-Tieback Installation Started tieback 2-S316. Welded pipes on the wall Worked on brackets on the SW wall T&M8976-Waler Installation (Day) Worked on walers 2-N14/2-N17, 2-S211 / 2-S214, and 2-S233 / 2-S239-S240 T&M9201-Grouting Polyurethane (Night) Additional hours lost trying to install pipes (2-N124, 2-N130, 2-N136, 2-N140) due to dewatering issue = 2 hours -burn holes with polyurethane behind the sheet pile wall

-cored through polyurethane with pipes Grouted Polyurethane Re-sealed 2-S316, 2-N124, 2-N130, 2-N136, 2-N140 2 resin, 1 accel, 0.5 packer T&M9202-Tieback Installation (Night) Installed tieback 2-S316. Installed pipes 2-N124, 2-N130, 2-N136, 2-N140 Welded pipes on the wall T&M9203-Tieback Night Shift Premium Night shift premium between 3pm-11pm (8 hours) for installing tiebacks, pipes, and welding pipes on the wall

Saturday July 6, 2013 T&M9204-Grouting Polyurethane


Grouted Polyurethane Worked on 2-N146, 2-N147-N148, 2-N149-N150 3.5 resin, 1.5 accel, 1.5 packer used

Welded sealing plates and teeth onto the pipes Fabricated and welded sealing frames T&M9205-Tieback Installation Welded brackets 2-S217, 2-S220 Prepared B5 brackets Welded pipes on the wall Welded threads onto the pipes T&M9206-Waler Installation Worked on walers and stiffeners on 2-N14/2-N17, 2-N38/2-N43, 2-N46/2-N47 T&M9207-Saturday Premium Saturday premium time between 7am-3pm (8 hours) for welding brackets and walers on the West walls.

Monday July 8, 2013 T&M9208-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-S319, 2-S322) and pipes (2-N100, 2-N102, 2-N108) due to dewatering issue = 3 hours -cut sealing plates -welded sealing frames -welded sealing plates and teeth onto the pipes -burned holes with polyurethane behind the sheet pile wall

-was not able to install pipe 2-N100 due to too much water pressure Grouted Polyurethane Completed 2-N20, 2-N23/24 2-N143/144, 2-N146, 2-N147-N148, 2-N149-N150 Worked on 2-N152, 2-N154 Re-sealed 2-S319 6 resin, 2 accel, 2 packer T&M9209-Tieback Installation (Day) Installed tieback 2-S319 Started drilling 2-S322 Installed pipes on 2-N102, 2-N108 Welded pipes on the wall Welded threads onto the pipes Worked on B5 brackets T&M9210-Waler Installation (Day) Worked on walers 2-N38/2-N43, 2-N46/2-N47 T&M9214-Grouting Polyurethane (Night) Grouted Polyurethane Re-sealed 2-S322, 2-N108 T&M9211-Tieback Installation (Night) Finished drilling 2-S322 Welded pipes on the wall. T&M9212-Waler Installation (Night) Worked on walers 2-N38/2-N43, 2-N46/2-N47 T&M9213-Tieback Night Shift Premium Night shift premium between 3pm-7pm (4 hours) for installing tiebacks, pipes, and welding pipes on the wall

Monday July 15, 2013 T&M9215-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-S325, 2-N140) and pipes (2-N91, 2-N100, 2-N105) due to dewatering issue = 1.5 hours -cut sealing plates -weld sealing frames -burn holes with the polyurethane behind the sheet pile -cored through polyurethane with pipes -welded sealing plates and teeth onto the pipes Grouted Polyurethane Completed 2-N151, 2-N152

Re-sealed 2-S325, 2-N91, 2-N100, 2-N105 5 resin, 2 accel, 1.5 packer, 1 breakline T&M9216-Tieback Installation (Day) Installed tieback 2-S325 Started drilling 2-N140 Installed pipes 2-N91, 2-N100, 2-N105 Welded pipes on the wall Welded threads onto the pipes T&M9217-Waler Installation (Day) Worked on walers 2-N38/2-N43 2-N45-N46/2-N49-N50 2-S233/2-S239-S240 T&M9218-Grouting Polyurethane (Night) Additional hours lost trying to install pipes (2-N94, 2-N97, 2-N143-N144, 146, 147-148, 149-150, 152, 154) due to the dewatering issue = 2 hours -burned holes with polyurethane behind the sheet pile wall -cored through polyurethane with the pipes Grouted Polyurethane Re-sealed 2-N94, 2-N97 1 resin, 0.5 accel, 0.5 packer used T&M9219-Tieback Installation (Night) Installed pipes 2-N94, 2-N97, 2-N143-N144, 146, 147-148, 149-150, 152, 154 Welded brackets on the NW wall Welded pipes on the wall T&M9220-Waler Installation (Night) Worked on walers 2-N38/2-N43 2-N45-N46/2-N49-N50 T&M9259-Tieback Overtime (Night) Overtime between 11:30pm-12am (0.5 hours) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers

T&M9221-Tieback Night Shift Premium Night shift premium between 3pm-12am (9 hours) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers

Tuesday July 16, 2013

T&M9225 - Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-N134, 2-N136) and a pipe (2-N119-N120) due to the dewatering issue = 1 hour -cut sealing plate -burned holes with polyurethane behind the sheet pile wall -cored through polyurethane with the pipes Grouted Polyurethane Re-sealed 2-N134, 2-N136, and 2-N119-N120 1.5 resin, 0.5 accel, 0.5 packer used T&M9226-Tieback Installation (Night) Installed tieback 2-N134 and 2-N136 Installed a pipe 2-N119-N120 Welded pipes on the wall Welded brackets on the NW and SW wall Machine broke down and was serviced (R2) T&M9227-Waler Installation (Night) Worked on walers 2-N38/2-N43 2-S233/2-S239-S240 T&M9260-Tieback Overtime (Night) Overtime between 11:30pm-12am (0.5 hours) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers.

T&M9228-Tieback Night Shift Premium Night shift premium between 3pm-12am (9 hours) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers.

Wednesday July 17, 2013 T&M9236 - Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-S341, 2-S343, 2-N102) due to the dewatering issue = 1 hour -cut sealing plate -burned holes with polyurethane behind the sheet pile wall -cored through polyurethane with the pipes Grouted Polyurethane Re-sealed 2-S341, 2-S343

1.5 resin, 0.5 accel, 0.5 packer used T&M9237-Tieback Installation (Day) Installed tiebacks 2-S341 and 2-S343 Started drilling 2-N102 Welded pipes on the wall Welded brackets on the NW and SW wall (2-N14/2-N17, 2-S233/2-S239-S240)

T&M9238-Waler Installation (Day) Worked on walers 2-N14/2-N17 2-S233/2-S239-S240 T&M9239 - Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-S346, 2-N149-N150) and pipes (2-N118, 2-N121, 2N125-N126, 2-N137-N138, 2-N139-N140, 2-N142) due to the dewatering issue = 2 hours -burned holes with polyurethane behind the sheet pile wall -cored through polyurethane with the pipes Grouted Polyurethane Re-sealed 2-S346, 2-N149-N150 1.5 resin, 0.5 accel, 0.5 packer used T&M9240-Tieback Installation (Night) Installed tieback 2-S346, 2-N149-N150 Installed pipes 2-N118, 2-N121, 2-N125-N126, 2-N137-N138, 2-N139-N140, 2-N142 Welded pipes on the wall Welded brackets on the NW and SW wall Machine broke down and was serviced (R2) T&M9241-Waler Installation (Night) Worked on walers 2-N14/2-N17 2-S233/2-S239-S240 T&M9261-Tieback Overtime (Night) Overtime between 11:30pm-12:30am (1 hour) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers. T&M9242-Tieback Night Shift Premium Night shift premium between 3pm-12:30am (9.5 hours) for installing tiebacks, pipes, welding pipes on the wall, welding brackets and walers.

Thursday July 18, 2013

T&M9243-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N138-N139, 2-N139-N140) and pipes (2-N20, 2-S255, 2N223-N224) due to the dewatering issue = 1.5 hour -cut sealing plate -burned holes with polyurethane behind the sheet pile wall -cored through polyurethane with the pipes Grouted Polyurethane Re-sealed 2-N138-N139, 2-N139-N140, 2-N20, 2-S255, 2-N223-N224 2 resin, 1 accel, 0.5 packer used T&M9244-Tieback Installation (Day) Installed tiebacks 2-N138-N139, 2-N139-N140 Installed pipes 2-N20, 2-S255, 2-N223-N224 Welded pipes on the wall Welded brackets on the NW and SW wall (2-N14/2-N17, 2-S233/2-S239-S240)

T&M9245-Waler Installation (Day) Worked on walers 2-N14/2-N17 2-N38/2-N43 2-S233/2-S239-S240 T&M9246 - Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-N20, 2-N23-N24) due to the dewatering issue = 1 hour -cut sealing plates Grouted Polyurethane Re-sealed 2-N20, 2-N23-N24, 2-N105 1.5 resin, 1 accel, 0.5 packer used T&M9247-Tieback Installation (Night) Installed tieback 2-N20, 2-N23-N24, 2-N105 Fixed pipe 2-N142 Welded pipes on the wall Welded brackets on the NW and SW wall Machine broke down and was serviced (R2) T&M9248-Waler Installation (Night) Worked on walers 2-N14/2-N17 2-N38/2-N43 T&M9262-Tieback Overtime (Night) Overtime between 11:30pm-2am (2.5 hrs) for installing tiebacks, welding brackets and walers

T&M9249-Tieback Night Shift Premium Night shift premium between 3pm-2am (11 hours) for installing tiebacks, welding brackets and walers Friday July 19, 2013 T&M9250-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N142, 2-N143-N144, 2-S255) due to the dewatering issue = 1.5 hour -cut sealing plate Grouted Polyurethane Re-sealed 2-N142, 2-N143-N144, 2-S255 3 resin, 1 accel, 0.5 packer 4 break line used T&M9251-Tieback Installation (Day) Installed tiebacks 2-N142, 2-N143-N144, 2-S255 Welded pipes on the wall Welded brackets on the NW wall (2-N38/2-N43, 2-N45-N46/2-N49-N50)

T&M9252-Waler Installation (Day) Worked on walers 2-N45-N46/2-N49-N50 2-S233/2-S239-S240 T&M9253-Tieback Installation (Night) Drilled 2-S253, 2-N146 to the rock Welded pipes on the wall Welded brackets on the NW T&M9254-Waler Installation (Night) Worked on walers 2-N20/2-N23-N24 2-N45-N46/2-N49-N50 T&M9255-Tieback Night Shift Premium Night shift premium between 3pm-7pm (4 hours) for installing tiebacks, welding brackets and walers Saturday July 20, 2013 T&M9256-Tieback Installation (Day) Welded brackets 2-N38, 2-N40, 2-N43 Welded pipes on the wall T&M9257-Waler Installation (Day) Worked on walers 2-N20/2-N23-N24

2-N45-N46/2-N49-N50 2-S247/2-S250 T&M9258-Saturday Premium Saturday premium time for welding brackets and walers on the NW and SW wall. Monday July 22, 2013 T&M9263-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N146. 2-N147-N148, 2-N152, 2-N159, 2-S253, 2-N108) due to dewatering issues = 2hrs. -cut sealing plates Grouted Polyurethane Worked on 2-N121 Re-sealed 2-S253, 2-N146, 2-N147-N14, 2-N152, 2-N159, 2-N108 T&M9264-Tieback Installation (Day) Installed tiebacks 2-N146, 2-N147 N148, 2-N152, 2-N159, 2-S253. Welded brackets on the west side Stressed tiebacks on the west side T&M9265-Waler Installation (Day) Worked on walers 2-N20/ 2-N23-N24, 2-S247/2-S250 T&M9275 Grouting Polyurethane (Night) Additional hours lost trying to install a tieback 2-N155-N156 due to the dewatering issue = 0.5 hours -cut sealing plate Grouted polyurethane Re-sealed 2-N155-N156, 2-N108, 2-N143-N144, 2-N152, 2-N154 Used 3 resin, 1.5 accel, 0.5 packer used T&M9276 Tieback Installation (Night) Installed tiebacks 2-N108, 2-N155-N156 Worked on brackets on the West side T&M9277 Waler Installation (Night) Worked on walers 2-N137-N138 2-N143-N144 T&M9278 Night Shift Premium Night Shift Premium between 3pm-11:30pm (8.5 hours) for installing tiebacks, welding brackets and walers.

Tuesday July 23, 2013

T&M9266-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N110, 2-S328, 2-N158, 2-N132) due to the dewatering issue = 1.5hrs -cut sealing plates Grouted Polyurethane Re-sealed 2-N110, 2-N158, 2-S328 Worked on 2-N163, 2-N166, 2-N168 T&M9267-Tieback Installation (Day) Installed tiebacks 2-N110, 2-S328, 2-N158, 2-N132 Worked on brackets on the west side T&M9268-Waler Installation (Day) Worked on walers 2-N20/ 2-N23-N24, 2-S247/2-S250, 2-S241/2-S244 T&M9279 Grouting Polyurethane (Night) Additional hours lost trying to install tiebacks (2-N125-N126, 2-N128) due to the dewatering issue = 1 hour. -cut sealing plates Grouted polyurethane Re-sealed 2-N132, 2-N125-N126, 2-N160 T&M9280 Tieback Installation (Night) Installed tieback 2-N125-N126 Started drilling 2-N128 Worked on brackets on the NW wall T&M9281 Waler Installation (Night) Worked on walers 2-S247/2-S250 2-S241/2-S244 T&M9282 Night Shift Premium Night Shift Premium between 3pm-11:30pm (8.5 hours) for installing tiebacks, welding brackets and walers.

Wednesday July 24, 2013 T&M9269-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N128, 2-N130, 2-N124, 2-N97) and pipes (2-N160, 2-N163, 2-N167, 2-N168) due to the dewatering issue = 2hrs -cut sealing plates -burn holes on the sheet pile with polyurethane behind -cored through polyurethane

Grouted Polyurethane Re-sealed 2-N128, 2-N130, 124, 97, 160, 163,167, 168 T&M9270-Tieback Installation (Day) Installed tiebacks 2-N128, 2-N130, 2-N124, 2-N97 Installed pipes 2-N160, 2-N163, 2-N167, 2-N168 Welded brackets on the west side Welded pipes on the NE wall Cut tieback stick out T&M9271-Waler Installation (Day) Worked on walers 2-S241/2-S244, 2-S229/2-232 T&M9283-Grouting Polyurethane (Night) Additional hours lost trying to install a tieback (2-N168) due to the dewatering issue = 0.5 hours -cut sealing plate Grouted Polyurethane Re-sealed 2-N168, 2-N96, 2-N160 Used 2 resin, 1 accel, 0.5 packer T&M9284 Tieback Installation (Night) Installed a tieback 2-N168 Worked on worked on brackets 2-S241, 2-S244, 2-N45-N46, 2-N49-N50 T&M9285 Waler Installation (Night) Worked on waler 2-S241 / 2-S244 T&M9286 Night Shift Premium Night Shift Premium between 1pm-12:30pm (11.5 hours) for installing tiebacks, welding brackets and walers.

Thursday July 25, 2013 T&M9272-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-N160, 2-N163, 2-N166) due to the dewatering issue = 1.5hrs -cut sealing plates Grouted Polyurethane Re-sealed 2-N163, 2-N166, 2-N168 T&M9273-Tieback Installation (Day) Installed tiebacks 2-N163, 2-N166, 2-N168 Re-installed 2-N112 Welded brackets on the west side

T&M9274-Waler Installation (Day) Worked on walers 2-S229/2-S232, 2-S253/2-S257, 2-N51/2-N55 T&M9287-Grouting Polyurethane (Night) Additional hours lost trying to install a tieback (2-N118) due to the dewatering issue = 0.5 hours -cut sealing plate Grouted Polyurethane Re-sealed 2-N166, 2-N118 Used 1.5 resin, 1 accel, 0.5 packer T&M9288 Tieback Installation (Night) Installed a tieback 2-N118 Worked on brackets 2-N20, 2-N23-N24, 2-S229, 2-S232 T&M9289 Waler Installation (Night) Worked on waler 2-N51/2-N55 2-S253/2-S257 T&M9290 Night Shift Premium Night Shift Premium between 1pm-12:30am (11.5 hours) for installing tiebacks, welding brackets and walers. Friday July 26, 2013 T&M9291-Grouting Polyurethane (Day) Additional hours lost trying to install tiebacks (2-S331, 2-S334, 2-S337, 2-S338-S339, 2-N119-N120, 2N115) due to the dewatering issue = 2 hours -cut sealing plates Grouted Polyurethane Re-sealed 2-N58, 2-N61, 2-N64, 2-N67, 2-S253, 2-S255, 2-N119-N120 Used 5 resin, 2 accel, 1 packer, 2 coupler T&M9292 Tieback Installation (Day) Installed a tieback a 2-N58, 2-N61, 2-N64, 2-N67, 2-S253, 2-S255, 2-N119-N120 T&M9293 Waler Installation (Day) Worked on walers 2-S229 / 2-S232 2-N45-N46/2-N49-N50 2-N52/2-N55 2-N58/2-N61 2-N64/2-N67

T&M9294-Grouting Polyurethane (Night) Additional hours lost trying to install a tieback (2-N115, 2-S339-S340) due to the dewatering issue = 0.5 hours -cut sealing plate Grouted Polyurethane Re-sealed 2-N166, 2-N118 Used 1.5 resin, 1 accel, 0.5 packer T&M9295 Tieback Installation (Night) Installed a tieback a 2-N118 Worked on brackets 2-N45-N46, 2-N49-N50, 2-N52, 2-N55, 2-N58, 2-N61

T&M9296 Waler Installation (Night) Worked on waler 2-N58/2-N61 2-N64/2-N67

T&M9297 Night Shift Premium Night Shift Premium between 1pm-12:30pm (11.5 hours) for installing tiebacks, welding brackets and walers.

Saturday July 27, 2013 T&M9298 Grouting Polyurethane Grouted Polyurethane Re-sealed 2-N168 Used 2 resin, 1 accel, 0.5 packer T&M9299 Tieback Installation Welded pipes on the NE wall Worked on brackets 2-N58, 2-N67, 2-N161 T&M9300 Waler Installation Worked on walers 2-S252 / w-S257 2-N64-N67 2-N52/2-N55 2-N58/2-N61 Monday July 29, 2013 T&M9380-Grouting Polyurethane (Day)

Additional hours lost trying to install tiebacks (2-N121, 2-N94) due to the dewatering issue = 1 hour. -cut sealing plates Grouted Polyurethane Re-sealed 2-N121 Used 1.5 resin, 0.5 accelerator, 0.5 packer T&M9381-Tieback Installation (Day) Installed tieback 2-N121 Started drilling 2-N94 Worked on brackets 2-N70, 2-N72, 2-N64, 2-N67, 2-N58, 2-N61 T&M9382 - Waler Installation (Day) Worked on walers 2-N58 / 1-N61 2-N64 / 2-N67 2-N70 / 2-N72 T&M9383-Tieback Installation (Night) Worked on brackets 2-N217, 2-N219, 2-S253, 2-N70, 2-N72 T&M9384-Waler Installation (Night) Worked on walers 2-N70 / 2-N72 T&M9385-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers under the CN Bridge. OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Tuesday July 30, 2013 T&M9386-Grouting Polyurethane (Day) Additional hours lost trying to install a tieback ( -cut sealing plates Grouted Polyurethane Re-sealed ( ) Used 1.5 resin, 0.5 accelerator, 0.5 packer T&M9387-Tieback Installation (Day) Installed tieback 2-N94, ( ) Worked on brackets 2-N70, 2-N72, 75, 78, 80 Stressed tiebacks 2-N20, 2-N26, 29, 49-50, 52, 55, 58, 61, 64, 67, 2-S250 T&M9388 - Waler Installation (Day)

) due to the dewatering issue = 0.5 hour.

Worked on walers 2-N82-N83 / 2-N85 T&M9389-Tieback Installation (Night) Worked on brackets 2-N75, 2-N78, 80, 82-83, 85 T&M9390-Waler Installation (Night) Worked on walers 2-N82-N83 / 2-N85 T&M9391-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers under the CN Bridge. OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Wednesday July 31, 2013 T&M9392-Tieback Installation (Day) Worked on brackets 2-N70, 2-N72, 75, 77-78 Stressed 2-S247, 2-S229, 2-S232 T&M9393 - Waler Installation (Day) Worked on walers 2-S289 / 2-S292 2-S284 / 2-S286-S287 2-S278 / 2-S281 T&M9394-Tieback Installation (Night) Worked on brackets 2-N82-N83, 2-N85 T&M9395-Waler Installation (Night) Worked on walers 2-S289 / 2-S292 2-S284 / 2-S286-S287 2-S278 / 2-S281 T&M9396-Night Shift Premium Night shift premium between 3pm-11:30pm (8.5 hours) for welding brackets and walers under the CN Bridge.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Thursday Aug 1, 2013

T&M9397-Tieback Installation (Day) Worked on brackets 2-N70, 2-N72, 2-N75, 78, 80, 82-83, 85 2-S277-S278, 2-S281, 284, 286-287, 289, 292 Stressed 2-N70, 2-S253, 2-S255, 2-S257 T&M9398 - Waler Installation (Day) Worked on walers 2-N88 / 2-N91 2-S289 / 2-S292 2-S284 / 2-S286-S287 2-S277-S278 / 2-S281

T&M9399-Tieback Installation (Night) Worked on B5 brackets on the SW wall 2-S258 ~ 2-S275 T&M9400-Waler Installation (Night) Worked on walers 2-S289 / 2-S292 2-S284 / 2-S286-S287 2-S278 / 2-S281 T&M9401-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers under the CN Bridge.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Friday Aug 2, 2013 T&M9402-Tieback Installation (Day) Worked on B5 brackets on the SW wall 2-S258 ~ 2-S275 Worked on brackets 2-S278, 2-S281, 284, 286-287, 289, 292 Stressed 2-N75, 78, 80, 82-83 T&M9403 - Waler Installation (Day) Worked on walers 2-S289 / 2-S292 2-S284 / 2-S286-S287 2-S277-S278 / 2-S281

T&M9404-Tieback Installation (Night) Worked on B5 brackets on the SW wall T&M9405-Waler Installation (Night)

Worked on walers 2-S284 / 2-S286-S287 T&M9406-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers under the CN Bridge. OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Saturday Aug 3, 2013 T&M9407-Tieback Installation Worked on B5 brackets on the SW wall 2-S258 ~ 2-S275 Worked on brackets 2-S277-S278, 2-S281, 284, 286-287, 289, 292 Stressed 2-S258 ~ 2-S275, 2-N23-N24, 2-N46-N47, 2-S241, 2-S244, T&M9408 Saturday Premium Saturday premium between 7am-6pm (11 hours) for welding brackets and walers, and stressing tiebacks.

Tuesday August 6, 2013 T&M9410-Tieback Installation (Day) Welded pipes on the East side Worked on brackets 2-N88, 2-N91, 2-N94, 1-N97 T&M9411-Waler Installation (Day) Worked on walers 2-S267-S268 / 2-S269-S270 2-S270-S271 / 2-S272-S273 T&M9412-Tieback Installation (Night) Worked on brackets 2-N88, 2-N91, 2-N94, 1-N97 T&M9413-Waler Installation (Night) Worked on walers 2-S267-S268 / 2-S269-S270 2-S270-S271 / 2-S272-S273

T&M9414-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

Wednesday August 7, 2013 T&M9415-Tieback Installation (Day) Worked on brackets 2-N88, 2-N91, 2-N94, 1-N97 T&M9416-Waler Installation (Day) Worked on walers 2-N94 / 2-N97 2-S295 / 2-S298 T&M9417-Tieback Installation (Night) Worked on brackets 2-N94, 1-N97

T&M9418-Waler Installation (Night) Worked on walers 2-N94 / 2-N97 2-S295 / 2-S298

T&M9419-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

Thursday August 8, 2013 T&M9420-Tieback Installation (Day) Worked on brackets 2-N94, 1-N97, 2-S295, 2-S298 T&M9421-Waler Installation (Day) Worked on walers 2-S295 / 2-S298 2-S301 / 2-S311 T&M9422-Tieback Installation (Night) Worked on brackets 2-S295, 2-S298, 2-S301, 2-S311 T&M9423-Waler Installation (Night) Worked on walers 2-S295 / 2-S298 2-S301 / 2-S311 T&M9424-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

Friday August 9, 2013 T&M9433-Grouting Polyurethane Grouted polyurethane Worked on 3-S267-S268, 3-S269-S270, 3-S270-S271, 3-S272-S273 Used 3 jugs, 1 accel, 0.5 packer T&M9425-Tieback Installation (Day) Worked on brackets 2-N100, 2-N102, 2-S301, 2-S311 T&M9426-Waler Installation (Day) Worked on walers 2-N100 / 2-N102 2-S301 / 2-S311

T&M9427-Tieback Installation (Night) Worked on brackets 2-N100, 2-N102, 2-S301, 2-S311

T&M9428-Waler Installation (Night) Worked on walers 2-S301 / 2-S311 T&M9429-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

Saturday August 10, 2013 T&M9434-Grouting Polyurethane Grouted polyurethane Worked on 3-S267-S268, 3-S269-S270, 3-S270-S271, 3-S272-S273 Used 7.5 jugs, 3 accel, 1 packer, 1 coupler T&M9430-Tieback Installation Welded pipes on the east side Worked on brackets 2-N100, 2-N102, 2-S301, 2-S305, 2-S308, 2-S311 T&M9431-Waler Installation Worked on walers 2-S301 / 2-S311

2-S313 / 2-S316 T&M9432-Saturday Premium Saturday premium tiem 7am-3pm (8 hours) For welding brackets and walers OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO

Monday August 12, 2013 T&M9435-Grouting Polyurethane (Day) Additional hours lost trying install a tieback 2-N113-N114 due to dewatering issue = 0.5 hours -cut sealing plate Grouted polyurethane T&M9436-Tieback Installation (Day) Worked on brackets 2-N94, 2-N97, 2-N100, 2-N102 T&M9437-Waler Installation (Day) Worked on walers 2-N100 / 2-N102 2-S301 / 2-S311 T&M9438-Tieback Installation (Night) Worked on brackets 2-N100, 2-N102 T&M9439-Waler Installation (Night) Worked on walers 2-N100 / 2-N102 2-S301 / 2-S311 T&M9440-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Tuesday August 13, 2013 T&M9441-Grouting Polyurethane (Day) Grouted polyurethane

T&M9442-Tieback Installation (Day) Worked on brackets 2-N100, 2-N102, 2-S301, 2-S305, 2-S308, 2-S311 T&M9443-Waler Installation (Day) Worked on walers 2-N100 / 2-N102 2-S301 / 2-S311 2-S313 / 2-S316 T&M9444-Tieback Installation (Night) Worked on brackets 2-N100, 2-N102, 2-S301, 2-S305 T&M9364-Waler Installation (Night) Worked on walers 2-S301 / 2-S311 T&M9365-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Wednesday August 14, 2013 T&M9366-Grouting Polyurethane (Day) Grouted polyurethane T&M9367-Tieback Installation (Day) Worked on brackets 2-N100, 2-N102, 2-S295, 2-S298, 2-S301, 2-S302-S303 2-S305 T&M9368-Waler Installation (Day) Worked on walers 2-N100 / 2-N102 2-S295 / 2-S298 2-S301 / 2-S305, 2-S313 / 2-S316 T&M9369-Tieback Installation (Night) Worked on brackets 2-N100, 2-N102, 2-S295, 2-S298, 2-S301, 2-S302-S303 2-S305 T&M9370-Waler Installation (Night) Worked on walers 2-N100 / 2-N102 2-S295 / 2-S298

T&M9371-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Thursday August 15, 2013 T&M9372-Grouting Polyurethane (Day) Additional hours lost trying to install pipe on 2-N72 due to the dewatering issue = 0.5 hours Grouted polyurethane Re-sealed 2-N72 Worked on 2-N58 and 2-N61 Used 6 resin, 3 accel, 1 packer T&M9373-Tieback Installation (Day) Worked on brackets

T&M9489-Waler Installation (Day) Worked on walers 2-N88 / 2-N91 2-N100 / 2-N102 2-S295 / 2-S298 2-S301 / 2-S305 2-S313 / 2-S316 T&M9490-Tieback Installation (Night) Worked on brackets 2-S301, 2-S305, 2-S313, 2-S316 T&M9491-Waler Installation (Night) Worked on walers 2-S301 / 2-S305, 2-S313 / 2-S316 T&M9492-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers.

OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Friday August 16, 2013 T&M9493-Grouting Polyurethane (Day) Grouted polyurethane

T&M9494-Tieback Installation (Day) Worked on brackets T&M9495-Waler Installation (Day) Worked on walers T&M9496-Tieback Installation (Night) Worked on brackets T&M9497-Waler Installation (Night) Worked on walers T&M9498-Night Shift Premium Night shift premium between 3pm-11:30pm (8 hours) for welding brackets and walers. OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO Saturday August 17, 2013 T&M9499-Grouting Polyurethane Grouted polyurethane T&M9500-Tieback Installation Worked on brackets T&M9501-Waler Installation Worked on walers T&M9502-Saturday Premium Saturday premium time 7am-3pm (8 hours) For welding brackets and walers