EDITION NO.

9, December 20, 2008

1st Steel Structure Erection

L ast December 10, 2008, the 1st Steel Structure Erection Ceremony for # 1
Boiler Building was held. In attendance were KEPCO, KSPC, SPC and Doosan
Executives and Officers and as well as some of the workers.

The steel structure erection is one of the major project milestones that have
been successfully implemented due to the collective efforts of KSPC and
Doosan. (originally scheduled to be erected in the 2nd week of January 2009)

1st Boiler Steel Structure Erection Ceremony


(December 10, 2008)

1
1st Steel Structure Erection (Cont’d.)

K SPC and Doosan made it possible to have the erection done earlier due to
continuous improvement of the construction planning strategy as well as
incorporating KSPC’s commitment to provide services to its customers by 2011.

Steel structure is composed of beams and girders used to make the steel frame
of the boiler building. These steel frames will hold the boiler building steam
drum, pipings and auxiliary equipments.

The steel structure completion will take 10 months. Next will be the lifting of
the steam drum to be installed inside the boiler building. Others boiler parts
will also be installed. Boiler parts include boiler water and steam tubes,
superheaters and reheaters, headers, waterwalls and economizers.

1st Boiler Steel Structure Erection Ceremony


(December 10, 2008)

2
Construction Power

O ne of the basic requirements in every construction is electricity. It is


needed to run welding machines, electric drills and other construction tools
necessary for construction. It is also being utilized to power up temporary site
offices of contractors’ facilities and warehouses. After a lenghty deliberations
study and review, VECO was contracted for the supply of construction power.

The Construction Power Facility is being constructed by Jusung Electric


Construction Company. The facility is adopting the latest technology with
strict compliance of the latest electrical codes and standards of the Philippines
with utmost consideration for the Health, Safety & Environment.

With the energization of the costruction power facility last, it boosted the
erection of steel structure activities and would enable to parallel other
construction works to achieve our goal to be on-line in February 2011 & May
2011 for Units 1 and 2, respectively.

Construction Power Substation


(December 9, 2008)

3
Control Building Construction

T he Control Building, come commercial operations on 2011, will house


the Control Room necessary for the operation and monitoring of the 2x100 MW
Cebu Power Plant. This building will serve as the plant’s Central Nervous
System as all the control systems are found in this building.

The Control Building presently is undergoing water proofing system, adopting


the asphalt shingle system. Excavation has been achieved at 100% with lean
concrete done. It is located between two (2) Boiler Building structures.

Embedded below the lean concrete are pre-casted reinforced concrete piles.
They are located and driven with each distinct coordinate. Such pile and its
locations were strategically placed and designed based on the principles of
Structural Engineering.

The reinforced steel bar installation will be commenced after the water proofing
is finished.

On-going foundation works for Control Building


(December 3, 2008)

4
Status of KSPC PSCs & ERC Approvals

1. ERC Approvals
[As of November 30, 2008]

Contract Contract Date


ECs ERC Approval
Quantity (Amendment)

Final Approval on amended PSC


NOCECO 10MW Feb 11, 08
last 21 August 2008.
CEBECO 1 7 MW Mar 29, 08
CEBECO 2 12 MW Mar 29, 08
NORECO 1 2.7 MW May 2, 08 Final approval on 8 December 2008
NORECO 2 12 MW June 17, 08
VRESCO 7 MW June 25, 08
CENECO 40 MW April 28, 08 Expecting on Jan 2009
IN2POWER 37 MW Sept 31, 08 Not requiring ERC approval
Total 127.7MW

2. Timetable for remaining volume

Remaining Volume
(42 MW, 25%)

• NORECO2 (Additional)

• MECO

• MEPZ

• ATLAS

• VECO

• Others

5
Project Progress

On-going Steel Structure Erection for Boiler Building Unit #1


(December 11, 2008)

On-going Steel Structure Erection for Boiler Building Unit #1


(December 16, 2008)

6
Project Progress

On–going rebar works for Boiler Building Unit #2


(November 24, 2008)

Anchor Bolt installation for Boiler Building Unit #2


(December 17, 2008)

7
Project Progress

On-going Re-bars and Frameworks for Administration Building


(December 17, 2008)

Concrete Pouring for the Administration Building


(December 19, 2008)

8
Project Progress

On-going construction of Warehouse


(December 17, 2008)

Opened EHS Training Center and Canteen


(December 17, 2008)

9
Project Progress

Manufacturing of HP Rotor by Fuji Electric in Japan


(November 30, 2008)

Manufacturing of IP/LP Rotor by Fuji Electric in Japan


(November 30, 2008)

10
Project Information

 PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC)


 CAPACITY : 100 MW x 2 Units
 PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed Combustion)
 LOCATION : Colon, City of Naga (20 Km from Cebu City)
 TARGET COMPLETION : Unit #1: February 2011; Unit #2: May 2011

Contact us

Mr. Bag Woon Choi


Mr. Beach Padogdog

Tel. No. (032) – 272 6290~91, 93


Fax No. (032) – 489 7010