Академический Документы
Профессиональный Документы
Культура Документы
L ast December 10, 2008, the 1st Steel Structure Erection Ceremony for # 1
Boiler Building was held. In attendance were KEPCO, KSPC, SPC and Doosan
Executives and Officers and as well as some of the workers.
The steel structure erection is one of the major project milestones that have
been successfully implemented due to the collective efforts of KSPC and
Doosan. (originally scheduled to be erected in the 2nd week of January 2009)
1
1st Steel Structure Erection (Cont’d.)
K SPC and Doosan made it possible to have the erection done earlier due to
continuous improvement of the construction planning strategy as well as
incorporating KSPC’s commitment to provide services to its customers by 2011.
Steel structure is composed of beams and girders used to make the steel frame
of the boiler building. These steel frames will hold the boiler building steam
drum, pipings and auxiliary equipments.
The steel structure completion will take 10 months. Next will be the lifting of
the steam drum to be installed inside the boiler building. Others boiler parts
will also be installed. Boiler parts include boiler water and steam tubes,
superheaters and reheaters, headers, waterwalls and economizers.
2
Construction Power
With the energization of the costruction power facility last, it boosted the
erection of steel structure activities and would enable to parallel other
construction works to achieve our goal to be on-line in February 2011 & May
2011 for Units 1 and 2, respectively.
3
Control Building Construction
Embedded below the lean concrete are pre-casted reinforced concrete piles.
They are located and driven with each distinct coordinate. Such pile and its
locations were strategically placed and designed based on the principles of
Structural Engineering.
The reinforced steel bar installation will be commenced after the water proofing
is finished.
4
Status of KSPC PSCs & ERC Approvals
1. ERC Approvals
[As of November 30, 2008]
Remaining Volume
(42 MW, 25%)
• NORECO2 (Additional)
• MECO
• MEPZ
• ATLAS
• VECO
• Others
5
Project Progress
6
Project Progress
7
Project Progress
8
Project Progress
9
Project Progress
10
Project Information
Contact us
11