Академический Документы
Профессиональный Документы
Культура Документы
Agenda
HTS Projects at AMSC HTS Project Objectives and Milestones Development Results of HTS Projects Conclusions
Cable Projects
- Transmission Voltage
LIPA 1 (BSCCO Wires) LIPA 2 (YBCO Wires)
- Distribution Voltage
Project Hydra Consolidated Edison
Projects Objectives
LIPA 1
Demonstrate a transmission voltage level HTS cable and outdoor terminations in an operational power transmission grid Demonstrate a 2G HTS transmission cable and a cable joint in an operational power transmission grid. Demonstrate an FCL cable technology and repairable cryostat. Demonstrate modular refrigeration system. Demonstrate HTS fault current limiting link between substations. Demonstrate feasibility of an underground installation of a fault current limiting HTS system in population condensed urban area Demonstrate standalone HTS fault current limiter based on 2G wires in an operational power transmission grid. Introduce HV into FCL
LIPA 2
Projects Specifications
LIPA 1
600m long using BSCCO wires
138kV/2400A, ~ 576 MVA Fault Current 51kA @ 12 line cycle (200ms) 600m long using YBCO wires 138kV/2400A, ~ 576 MVA Fault Current 51kA @ 12 line cycle (200ms)
LIPA 2
320m long using YBCO wires 13.8kV/4000A, ~ 96 MVA Fault Current 40kA @ 4 line cycle (67ms) 138kV/ 1200A Fault Current 63kA @ 4 line cycle (67ms) Fault Current reduction rate 36% (limit to 40kA)
Projects Timelines
Year LIPA 1
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
LIPA 2
HYDRA
FCL
Project Partners
Installation Site
Port Jefferson Shoreham
Wading River
Centereach
Superconductor
Holbrook Substation
10
Termination Design
- Qualify to 138 kV operation, 650 kV BIL - Safely manage voltage breakdown - Manage results from loss of cryostat vacuum
Worlds First Installation of a Transmission Voltage HTS Cable
11
Power
SCADA
Heat
HV Termination
Cold Termination
Return Redundant Cooling & Control
Supply
12
High Voltage Dielectric HTS-Shield Outer Cryostat Wall Copper Shield Stabilization Inner Cryostat Wall
13
Prototype Testing
A test program has been
defined together with the DOE review team based on existing standards
Tests included
- High voltage dielectric tests - High current tests - Hydraulic tests - Load cycles - Loss measurements
14
Pre-Construction
15
Installation - Terminations
Terminations were
installed with the cable phase in place
No issues identified
during termination work
16
Installation - Terminations
Terminations were
installed with the cable phase in place
No issues identified
during termination work
17
10000 9000
. theoritical curve total (coef f 0,24) therotical (rolls) theoritical (cable in PE pipe)
8000 7000
12000 10000 8000 6000 4000 2000 0 0 100 200 300 400 500 600 700 Distance [m]
Force (N)
6000 5000 4000 3000 2000 1000 0 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 HTS cable distance in the PE pipe (m)
18
Refrigeration substation
19
Predicted
Temperature (K)
200 175 150 125 100 75 50 0 48 96 Time (hours) 144 192 240
Actual
20
Cable Energization
AC-High Voltage test
completed successfully
- 1.5 Uo applied at each phase for one hour - PD measurement completed No partial discharge detected
21
22
7/2/08 12:00 PM
7/2/08 12:00 PM
7/3/08 12:00 AM
23
73
700
72 Return Temperature 71
LN2 Pressure (bara)
14.5
Temperature (K)
500
70
400
69
300
68 Inlet Temperature 67
12.5 200
66 7/2/08 12:00 AM
7/2/08 12:00 PM
7/3/08 12:00 AM
7/2/08 12:00 PM
24
Sound Issues
Several questions regarding
noise at the site (during operation)
Acoustical Louvers
- Lowered sound signature during operation to 38 db (modeled)
25
26
27
28
Cable Design
- Demonstrate field joint - Demonstrate field reparable cryostat
29
Heat
Replacement 2G Phase
Field Joint
Return Redundant Cooling & Control
Supply
30
31
LIPA 2 Wire
YBCO Coated Tapes
- Lower Tc, higher resistance substrate: Can be made to be current-limiting - Different dimensions and physical properties:
YBCO coated onto one side of buffered Ni-W substrate Brass laminated onto both sides
~ 0.3 mm thick, splices even thicker
32
Status
- Two different design options considered - First manufacturing trials (dummy cables) focus on one of the two designs
33
Only small force due to thermal contraction Small cross-section, stainless steel:
High resistance, good for current limitation - Requires some effort due to flexibility of former in the machine - Preferred design
34
Status:
- Updating of the cable connection is in progress with different new brazing alloys studied - Continuation of the development required now some LIPA 2 cable samples in order to achieved some connection and mechanical tests and improved the components
35
Status:
- Updating of the cable connection is in progress with different new brazing alloys studied - Continuation of the development required now some LIPA 2 cable samples in order to achieved some connection and mechanical tests and improved the components
36
Design of conductor connection Design of joint dielectric insulation Design of screen connection Design of joint cryostat
Cryostat for subscale test Cryostat for on site installation - Full prototype test of cable joint in the laboratory - Installation of a single cable joint on site
37
Prototypes for testing assembly procedures successfully prepared and tested with nominal current in LN2 (temperature measurement)
38
39
40
Status of work
- Vacuum barrier manufacturing techniques
41
42
43
44
45
ORNL
46
Installation Site
47
Program Structure
Currently Executing Planning
DHS/ HYDRA
48
Supply
Return
Refrigerator
HTS Cable
Return Line
49
Substation #2
138kV Transmission Bus
Reactor
50
Dielectric
Shield
51
A perspective 140 ms fault current of 44 kA was reduced to 29 kA The voltage developed due to the heating was 8-11 V/m over the 140
ms duration fault
This was comparable to the design fault of 300-m cable which results
in ~ 10 V/m
Measured temperature increase to 85-95 K Re-cooling time to 77 K is 9 min No change in temperature measured after a 9.1kA, 270ms through
fault test
53
54
Refrigerator Requirements
Refrigeration Cycle chosen is the Reverse-Brayton
- Best suited technology for high power applications (> 6 kW) - Best return on specific efficiency (We/Wc) vs. capital cost
Flexibility Requirement:
- 80% of time at 50% heat load on HTS cable
Reliability
- Redundancy accomplished at component level: compressors, pumps, expanders, electronics, instrumentation - No 1st order single point of failure allowed
Capacity Margin
- Current design has 50% safety margin to the expected losses
55
56
57
AMSC System Design Wire Development Wire Manufacturing Project Management Technical Oversight System Hardware Development
Siemens FCL Module and Accessory Design FCL Manufacturing FCL Module and Accessory Installation
HV Consulting
Air Liquide
58
Valley Substation
59
SCE Profile
50,000 Mile2 Service Territory 120 years of service $17 Billion T&D Assets
Distribution
85,000 Circuit Miles 690,000 Transformers
Customers
4.7 Million Meters 13 Million Customers 22,889 MW Load
Transmission
12,600 Circuit Miles 4,200 Transformers
60
SCE has unique experience with HTS FCL technology and this program extends this to transmission voltage levels
61
62
Virtual Switch
Superconductor
Under normal conditions, power flows through superconductor with virtually no impedance and system is Physical Switch electrically invisible Shortly after fault clears, power resumes flow through superconductor
Reactor Physical switch opens to protect FCL system; reactor maintains current Load Bus
63
Basic Specifications
Requirement
Nominal Voltage Insulation Class Nominal Current Maximum Site Unlimited Fault Current Site Limited Current Trip Current
Prototype System
115kV rms 138kV 1,200A 63kA
Production Units
115-138kV 138kV
Opening Switch
Reactor
Sized to Limiting Requirements
Load
>2,000A >80kA
Source
Switch Control
40kA
As required by customer
Protection and DAQ System Refrigeration System
Power Heat
1.6pu
As required by customer
64
Solution
- Operate FCL in sub-cooled LN2 with nominal operating temperature lower than design point.
FCL design at temperature 74K@5bar(a), but operate at temperature 72K@5bara Power Temperature margin determines the number of faults the system can absorb before system is off-line to re-cool 2K margin allows LN2 to absorb 57MJ energy (~6 faults) 5 bar pressure will allow LN2 in coil vicinity absorb fault energy without bubbling
FCL operates at high pressure sub-cooled LN2 temperature
Refrigeration System
Heat
65
Value (W)
850 200 900 350 1950
Terminations
Pressure
Level
4250 6000
Simplified, COTS based system Significant margin planned for prototype system
Refrigeration based on experience at LIPA and other AMSC utility HTS systems
66
115 kV
67
Alternating current directions between adjacent turns of bifilar coils cancel most magnetic fields Regions stressed by BIL tests, numbering see next slide
(1)
68
69
10
20
71
Summary
AMSC is currently advancing the state of the art in
HTS power products
- Worlds First Transmission Voltage HTS Cable in Operation - Worlds First Fault Current Limiting Cable for use in a distribution grid under development - Transmission Voltage Fault Current Limiter under development
72