Bunderan HI Station
Tunneling 6800mm 6800mm mm
OUTLINE OF CP106
ClientPT. Mass Rapid Transit Jakarta ContractorSMCC-HK JO
SUMITOMO MITSUI CONSTRUCTION CO. CO., LTD. LTD. PT. PT.HUTAMA KARYA (PERSERO)
LOCATION
[MRT Location Plan]
Jakarta
OUTLINE OF CP106
Setiabudi Station Dukuh Atas Station Bunderan HI Station
PROCEDURE
Setiabudi Dukuh Atas
Bunderan Hi
Construct Underground Station (Diaphragm Walling, Earthwork, Concrete Work) Assemble TBM Tunneling (Bunderan Hi Dukuh Atas) Tunneling (Dukuh Atas Setiabudi Dismantle TBM Restore (Earthwork, Pavement, etc.)
PROPOSED SCHEDULE
year 2013 2014 2015 2016 2017 2018 month 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 7 1 5
Detail Design Utility Relocation King Post Road Decking Diaphragm Wall
Bunderan Hi L=440m
Road Decking Construct Structure 1st 2nd Shield Machine Temporary Machine Facilities Assemble
Detail Design Utility Relocation Slope Protection Diaphragm Wall King Post Temporary Facilities
Proposed Station
Public Space
Road
Road
24.5m 20750
Reduction of Environment impact by using Diaphragm wall as Permanent wall Conventional method
22.1m 22100
Excavated Soil Transport by Dump Truck SECANT PILE (Temporary) Using Cement & Rebar Disposal of Excavated Material, Slurry
24.5m 24550
1. Excavation width reduce Reduction of excavated soil volume Reduction of Environment impact Reduction of machine works for excavation & transport by dump truck 2. No Secant pile Reduction of Environment impact Cement & Rebar reduce Excavated material & Slurry reduce
24.5m
24550
24550
Reduced
Wall Height
DIAPHRAGM WALL
JOINT (Vertical)
1st Element
2nd Element
1st Element
Reduce to 1/18